Select Committee on Transport Written Evidence


Supplementary memorandum by the Department for Transport (DAR 01A)

EVIDENCE GIVEN BY THE SECRETARY OF STATE AND PERMANENT SECRETARY AT THE HEARING ON THE DEPARTMENTAL ANNUAL REPORT 2004

  This memorandum responds to the questions put to the Department following the oral evidence given by the Secretary of State and Permanent Secretary on 17 November 2004. These questions were set out in a letter dated 26 November from the Committee Secretariat to the Department's Parliamentary Clerk.

1.   The Secretary of State promised a note on the penalties and incentives for train manufactures. (Q59)

  Contracts for new trains usually include reliability conditions. Their form varies but the commonest types are:

    —  a "miles per casualty" target, that is, the distance the trains are expected to run between breakdowns. Figures vary from contract to contract, but a requirement that trains should achieve 20,000 to 30,000 miles per casualty on delivery, rising to between 40,000 and 60,000 within two years would be typical;

    —  an availability requirement, which may be applied where the manufacturer himself maintains the trains. The obligation is that he must provide a set number of trains, sufficient to run the service, from the maintenance depot each day.

  Failure to meet targets of either type will trigger contractual damages. These usually take one of two forms: liquidated damages; or the withholding of a performance bond which becomes payable to the manufacturer only once the relevant targets have been met.

  Details of the penalty clauses in individual contracts are commercially confidential. The importance of these provisions to manufacturers can, though, be gauged from the fact that, since 1995, there have been 48 orders for new trains (comprising 4527 vehicles) worth, in total, £4.2 billion. Of that, some £420 million is at risk if manufacturers fail to meet contractual performance targets.

2.   Mr Rowlands described the arrangements for agencies to give the Department their workbooks on a monthly basis. How long have these arrangements been in place? When does the Department expect to produce monthly accounts?(Q88)

  Agencies have provided the Department with monthly workbooks since the introduction of Resource Accounting and Budgeting in 2001-02 and with monthly cash-based information before then. These workbooks provide details of expenditure and full year forecasts against budgets.

  The Department already prepares monthly management accounts and expects balance sheet and cash flow information to be produced quarterly from June 2005 and monthly from December 2005.

3.   The Chairman asked about the Highways Agency's target on non-motorised crossing points. The Committee would like more information about why the target was missed. (Q112-113)

  The target was to survey all non-motorised crossing points on the core network and trunk road network for access, safety and convenience. A five-year programme of improvements based on the survey would be developed by 31 March 2003. The improvement programme to be completed by 31 March 2009 and monitored through the Highways Agency work programme.

  By 31 March 2003, the Highways Agency completed surveys of all non-motorised user crossing points on the trunk road network and drew up a provisional list of improvements, which would offer good value for money, for implementation by 31 March 2009. The list was not developed into a five-year programme because of funding pressures. As a result an in-year target was not set for 2003-04 and the Agency have since issued a correction to their annual report.

  Non-motorised user crossings are provided where justified as part of major schemes. In addition, small free-standing schemes are funded from the small schemes budget. Following the recent spending review settlement, the Highways Agency is developing its forward programme for small schemes, which also include high value-for-money safety schemes and junction improvements, as well as environmental improvement measures. The Agency is now unlikely to be able to implement all identified non-motorised user crossings by 31 March 2009 due to pressure on the small schemes budget. However, in developing its Business Plan for 2005-06 to 2007-08, consideration will be given to how best to meet the needs of non-motorised users within the budgets available.

  Non-motorised user crossing locations will be identified in the Highways Agency's Route Management Strategies, which provide a framework for considering all potential issues affecting the management and operation of a route in an integrated manner, so that forward programmes are developed on a comprehensive basis.

  Progress on delivery of non-motorised user crossing improvements will be monitored by the Agency.

4.   The Spending Review 2004 provided the Department with £1.7 billion to cover "immediate pressures" over 2005-06 and 2006-07. What are these "immediate pressures"?

  These pressures result predominantly from the rail industry—a peak in renewals expenditure by Network Rail following the Hatfield accident, as well as rising passenger franchise support costs. For future years, infrastructure costs will reduce, both as the current renewals peak passes and as Network Rail work towards the stretching efficiency target set by the Office of the Rail Regulator in the recent Interim Regulatory Review. Nevertheless, financial discipline across the railway will remain essential. The reforms set out in The Future of Rail (Cm 6233) and embodied in the Railways Bill currently before Parliament, will form an important element in the maintenance of future cost control

  In addition, changing assumptions about the Highways Agency's private finance programme have created further public spending pressures. At the time of the original 10 Year Plan in 2000, it was assumed that approximately a quarter of HA's total capital investment programme would be delivered through off-balance sheet Private Finance Initiative contracts, with these spread evenly across the years in proportion to conventionally-procured spending. The experience of HA's first phases of DBFO schemes has, however, shown that these are best suited to the larger investment projects. As these fall in the later years of HA's Targeted Programme of Improvements (TPI), this means that the public expenditure impact of delivering the TPI is higher than anticipated in the earlier years.

  Furthermore, the working assumption is now that most strategic roads PFI projects will be accounted for on the Government's balance sheet. Whilst this does not affect the overall economic cost of the projects, it brings forward the impact on DfT's Departmental Expenditure Limit, giving a further pressure on overall spending.

5.   Staff numbers at the DVLA increased by 22% between 2000-01 and 2003-04. Do you still expect to reduce DVLA staff by 500 by 2007-08? Will the DVLA be able to operate effectively with 500 less staff given its full work programme?

  The 22% increase in DVLA numbers in the four years 2001-02 to 2003-04 was a result of a mixture of volume growth, which averaged some 7% in each year over this period, and a range of new statutory and policy initiatives. During this period, the DVLA managed to achieve an improvement of 11.4% in efficiency. DVLA has undertaken a great deal of work over the last 12 months in terms of assessing the full positive impact on productivity of its introduction of new systems and processes, building in continuing growth assumptions and factoring in its planned resources to further policy and statutory changes. On this basis, as it has reported in its response to the Gershon Review, it is confident that it can continue to provide its services to existing standards with the estimated 500 less posts.

6.   The Committee would be grateful for a copy of the review of the bus subsidies referred to in the Department's memorandum on significant changes and developments since the publication of the Departmental Annual Report 2004.

  The review of bus subsidies started in April 2002 and the Department published a consultation paper at an early stage, in August 2002, to seek views from interested groups. The outcome of the review of bus subsidies was published on page 70 of the White Paper "The Future of Transport" (Cm 6234) in July 2004. Nothing else was published or issued by the Department as a result of this review. The key elements of the outcome of the review are:

    —  Guidance will be issued by the Department to help local authorities and bus operators assess whether Quality Contracts are appropriate in their area. The Department has already issued a draft of this guidance for consultation.

    —  The Department will streamline the statutory procedure for Quality Contracts by reducing the minimum period between making and implementing a scheme from the current 21 months to six months. The Department's guidance will make clear that use of the minimum period will only be appropriate for schemes with a limited impact on bus operators.

    —  The Department considered a number of options for replacing or modifying Bus Service Operators' Grant (BSOG), such as relating subsidies to the number of passengers carried or to the distance travelled. The Department concluded that the benefits to be gained from any change are not certain enough to justify the costs and disruption at a time when we want operators to focus all their energy on improving services for passengers.

    —  The Department will no longer pay BSOG, for any routes that are procured under a Quality Contract but instead transfer a parallel sum to the local authority for procurement of bus services.

    —  The Department will also consult Transport for London on implementing this change for the existing franchised service in London.

    —  The Department will review the case for a further round of funding for Kickstart projects, aimed at pump-priming patronage growth, in light of progress with the 18 pilots already being funded.

    —  Rural Bus Subsidy Grant will be retained beyond April 2006 to give continuing support to local authorities in promoting rural accessibility.

    —  The Department does not propose any changes to concessionary fares entitlement, but will look at streamlining the administration of concessionary fare schemes.

December 2004


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 10 March 2005