Select Committee on Transport Sixth Report


5  London Underground's powers

27. Transport for London and the current chief executive of London Underground Ltd were not involved in negotiating the PPP contracts. In his introduction to the TfL report on London Underground and PPP Mr O'Toole said "I have…been disappointed by the overly convoluted processes that the contracts require, the limitations on London Underground's rights and inadequacies of real-world technical planning analysis that went into the PPP."[37] Not only does LUL have to work with the infracos; it has also to deal with three separate PFIs for important services which were entered into before the PPP, and which were not taken into account when the PPP was negotiated. The Prestige PFI covers ticketing; the Power PFI with Seeboard Powerlink was entered into in connection with the decommissioning of the Underground's Lots Road power plant; the Connect PFI is for maintaining and the current radio system and delivering a new system. The PFIs and the PPPs are interdependent - the Connect PFI will, for example, only meet the deadline for introducing a new system if it shares engineering hours with the infracos and draws on their engineering trains, protection personnel and other assets.[38]

28. Unlike most PFI deals, the PPP does not contain a provision allowing for voluntary termination on a no fault basis. The NAO reported that :

    4.10 One of Transport for London's major concerns was over the absence of arrangements for voluntary termination on a no fault basis, which is usually found in PFI contracts. Ernst & Young in their report echoed this concern because the provision enforces a duty on the PFI contractor to mitigate costs in such an event. We find that the PPP's pervasive requirement for "economic & efficient" behaviour captures the duty to mitigate costs, but the absence of pre-agreed contract provisions leaves considerable room for argument.[39]

In 2002, London Underground said that it was decided not to include such a right, because the PPP bidders would have found it unacceptable, and the Department later told the National Audit Office that a decision was taken not to include such a provision since the bidders would have added a premium to their prices to reflect the greater political uncertainty.[40]

29. If the only ground for termination is that the companies are in default of their obligations, then it is clearly essential that those responsible for the assessing performance get the information they need. Yet LUL complained that the infracos were not providing satisfactory information about the planning and delivery of projects. By the time he gave evidence, Mr O'Toole told us that London Underground had reached agreement with the infracos about the information they would provide, although it was still not available "Because it has taken us the better part of the year to argue over what it is and what it should look like".[41] Tube Lines told us that they were not aware of the information that London Underground required until three months after the contract was signed. As the result of the PPP, London Underground is left with a plethora of different arrangements with private partners all responsible for different bits of the infrastructure. It has no public interest right to terminate the PPP contracts. It is responsible for the overall running of the Underground and for managing the performance of the infracos. It vital that it has the information it needs to do its job. It is astonishing that it took a year to negotiate access to the information London Underground needed.


37   TfL Report, p5 Back

38   TFL Report, p6 Back

39   HC(2003-04)645, p 37 Back

40   HC(2003-04)645, p 37 Back

41   Q 135 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 18 March 2005