Select Committee on Transport Written Evidence


Memorandum by Tube Lines (LU 01)

PERFORMANCE OF LONDON UNDERGROUND

1.  ABOUT TUBE LINES

  1.1  Tube Lines is the infrastructure and asset management company responsible for maintaining and upgrading the Jubilee, Northern and Piccadilly Lines, under a 30 year partnership with London Underground, which commenced on 31 December 2002.

  1.2 Tube Lines is responsible for 320 km of track, 251 trains, 100 stations, 2,395 bridges and structures, 71 lifts, 227 escalators and 2 passenger travellators.

2.  INVESTMENT PROJECTS

  2.1  Over 60% of Tube Lines' work is taken up by infrastructure projects: that is, upgrades to track, stations and other assets. The remaining 40% of our work is involved in maintenance of the current network.

  2.2  Over the first seven and a half years of our contract, Tube Lines is investing £2.2 billion in these projects, in line with our plans. We are currently investing approximately £30 million per month, a tripling on the rate of investment committed by London Underground prior to transfer. We are not under spending on our investment commitments.

  2.3  Progress with these projects is proceeding on time and to budget. Tangible results will begin to be seen in the near future, as outlined below.

  2.4  We are adding a 7th car to every Jubilee Line train and four additional trains to the fleet. The first "shells" of these trains have been completed, and they will all be put into service at the start of 2006.

  2.5  We have recently completed the first stage of testing of the equipment required to replace completely the signalling on the Jubilee and Northern Lines. The upgrade will be applied to the Jubilee Line by 2009 and the Northern Line by 2011 and work on this is ahead of schedule. The upgrade on the Jubilee Line, together with the additional cars and trains, will increase passenger capacity by over 40% and reduce average journey times by over 20% and the upgrade on the Northern Line will increase capacity by roughly 30% and reduce average journey times by about 18%. Both of these upgrades will allow speedier and more efficient transport of passengers by 2012 and are essential components of London's Olympic bid transport package.

  2.6  Our programme to modernise or refurbish 97 of the 100 stations is well under way with engineers on site at 15 stations. The first modernisation will be completed by the end of the year. In the new year we will start work on a new site every two weeks.

  2.7  In 2004-05, we are replacing or refurbishing 36km of track, a fourfold increase on the amount of track renewed in 2003-04.

  2.8  We are also on target with a number of additional projects. We are undertaking major works to increase the capacity at Wembley Park station so that it can accommodate 37,500 passengers an hour rather than the current 22,000. This is on track for completion in September 2005, well in advance of the reopening of the Stadium for the FA Cup Final in May 2006. We also completed the new eastern exit at Canary Wharf station earlier this year, two and a half months ahead of schedule and ahead of budget.

3.  MAINTENANCE OF THE PRESENT NETWORK

  3.1  Most of the focus of attention on Tube Lines in the first 22 months has, understandably, centred on the current network and how it is performing, although as noted above, this constitutes less than 40% of our work.

  3.2  There have been some misconceptions about current levels of performance. Current levels of performance are ahead of target (see below): the figures on missed targets widely reported in the media are not an indicator of our current performance, since they applied to the year to December 2003.

  3.3  In the first year, there were some considerable advances. Graffiti at stations and on trains has been almost completely eliminated and no train goes into service with graffiti. There has also been a 12-fold increase in the day-to-day cleaning of trains and the frequency of thorough, so-called "deep cleans" of trains has also increased.

  3.4  Performance has consistently increased during the course of 2004. The last quarter was the most successful since we took responsibility for the assets: we hit all four of our contractual targets. Broken down by four week period, we hit target on 10 counts out of a possible 12.

  3.5  On availability, a measure of reliability, we were ahead of target on all three lines in the last quarter and have seen significant progress since last year. Breaking results down by line and by four week period, we hit target seven out of nine times in the last quarter. In addition, we have had four successive periods of increasing availability.

  3.6  On the Northern Line, our most problematic line, the two most recent four week periods for which we have figures have seen dramatic improvements. It does, however, remain our single biggest challenge in achieving a consistent performance.

  3.7  The improvements in performance have been acknowledged by TfL and London Underground. In his report to the TfL Board on 27 October, Bob Kiley noted that "The most recent 4-week period has seen the best train service performance results for over seven years, with 96.3% of scheduled kilometres operated, together with the lowest excess journey time for six years."

4.  INNOVATION

  4.1  In addition to the investment in infrastructure projects, Tube Lines is investing in a variety of innovations to improve performance further.

  4.2  We are taking steps to reduce the time taken to refurbish escalators, by ensuring that more work is completed off site. The current time taken to a refurbish an escalator is 26 weeks, and we are seeking to reduce this to 10 weeks. This is being trialled at Green Park.

  4.3  We are seeking to increase the amount of work which is carried out during the day, as opposed to during night-time engineering hours, in order to reduce the amount of time needed to deliver improvements. We have agreed with London Underground a trial programme of work to carry out painting, cleaning and the provision of increased signage at Leicester Square station.

  4.4  We are also stepping up our programme of works to reduce delays on the Northern Line. These include the introduction of a dedicated team of engineers to replace essential components on the signalling equipment.

  4.5  As part of our strategy to ensure that we retain and recruit employees of the highest calibre, we are taking steps to tackle skill shortages in certain areas of the business. We are investing £7.5 million in constructing a training school in Stratford for signalling engineers and others. This will open during the course of 2005.

  4.6  We have invested £30 million in integrating hundreds of processes and IT systems which the company inherited from London Underground, to create a single system which facilitates more efficient asset management, business planning and maintenance of the network. This programme is almost complete.

5.  SAFETY

  5.1  Tube Lines is committed to building upon London Underground's existing safety record. We operate under London Underground's safety case, which has been accepted by the Health and Safety Executive and are investing in various initiatives to improve safety across the network.

  5.2  We are undertaking a £20 million programme to replace the axles and axle boxes on all of the carriages on the Piccadilly Line. This programme is roughly 60% complete.

  5.3  We are in the process of developing a vehicle which will enable us detect faults on the network ultrasonically much more quickly than the current system, where engineers walk along the track with a handheld device.

6.  CONCLUSION

  6.1  We believe that, through our improvements in performance, innovation and infrastructure enhancements, we are beginning to make the transformations necessary to reverse decades of under-investment and deliver a better railway for London.

  6.2  In addition, our 30 year contract allows us to take the type of long-term, fully-planned approach which has been impossible in the past. We are committed to embodying this long-term approach in all of our work: investment, innovation, safety, infrastructure upgrades and performance, and we believe that this will guarantee continuous improvements over the next three decades.

  6.3  We look forward to giving oral evidence to the Committee on 8 December.

November 2004





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 18 March 2005