Lack of information about the
market
66. A recurring theme in the evidence we received
was the limitation on competition imposed by the paucity of timely
and accurate information in the wholesale gas market. The main
problem was the lack of information about gas flows from the UKCS.
Until recently, even NGT was experiencing difficulties in obtaining
enough information to enable it easily to plan the balancing of
the system. As a result, over a period of several years,[176]
the DTI persuaded the production industry of the need to release
more information and negotiated with the industry a voluntary
agreement on the types of information to be supplied and the form
in which some of the information was to be released.[177]
67. The process has been a gradual one. In November
2003 the production companies agreed to standardise the information
about available gas supplies and planned and unplanned maintenance
shutdowns provided to NGT via the operators of the beach-head
terminals. In March 2004 they agreed to provide, on a confidential
basis, further operational and planning information to help NGT's
ten year planning process. More pertinently for our inquiry, they
also conceded that NGT should provide certain information to the
market in an aggregated form. This information falls into four
categories:
Category
1: physical flows of gas, close to real time
Category 2: forecast flows, ahead of
the day and hourly throughout the day
Category 3: deliverability of gas (reflecting
planned maintenance)
Category 4: sub-terminal 'after-the-day'
flows.
Information under Categories 3 and 4 is already available
on NGT's website; Category 2 is expected to become available on
15 March 2005; and Category 1 is expected to be available during
the third quarter of the year.[178]
NGT told us that the reason for the delay in publishing Category
1 and 2 information was the difficulty in devising the processes
and establishing IT systems robust enough to enable a large quantity
of data to be accessible in a comprehensible form.[179]
UKOOA and BP felt that, taken as a whole, the information to be
released "will address the market issues."[180]
68. Although all our witnesses welcomed the provision
of the extra information by the production companies, some argued
for further disclosure. energywatch advocated the model applied
to the electricity industry, under which anyone could obtain from
websites real time information on the amount of power being produced
by each generating station and the bids being made in the markets
for the power available. It wanted Transco to publish real time
information about sub-terminal gas pressure and planned maintenance,
and it warned that further measures might be necessary. energywatch
also disliked the voluntary nature of the current disclosure by
gas producers: it suggested that the licences for the offshore
industry should be revised to ensure the disclosure of information
to all market participants.[181]
energywatch's proposals were supported by the CIA, E.ON and Scottish
and Southern Energy (SSE).[182]
SSE argued that only if there was as much transparency in the
gas as in the electricity market would buyers of gas accept that
the prices they were being offered were fair.[183]
An alternative model, suggested by the CIA, was that provided
by the US Energy Information Administration.[184]
69. Centrica said that, as a producer, it was willing
to provide further informationafter all, within two years
its ability to supply 25 percent of its own needs from its production
facilities would have fallen to 20 percent, so it had an interest
as a purchaser of gas. It suggested that the type of extra information
likely to be most useful related to maintenance: it argued for
a fairly tight time period for reporting unplanned outages and
for a requirement to give some indication of how long they would
last, and was generally concerned that, under the recently agreed
arrangements, there was no requirement on producers to explain
why gas was not flowing.[185]
However, Centrica understood why other producers might be reluctant
to provide further information: if a company faced production
problems which made it difficult to honour contracts for the supply
of gas, it would want to be able to buy the replacement gas before
the market became aware of its difficulty and the price rose accordingly.
Centrica suggested that the key to providing extra information
was aggregation: if aggregation was feasible, then enough information
could be provided for market participants to be able to make rational
buying decisions, but without causing disadvantages to any specific
player.[186]
70. NGT said that there were practical difficulties
in supplying further information[187]
and it gave us a comprehensive explanation of why this was so.
The background was that in many cases NGT did not itself own the
flow meters at the beach-head terminals, and therefore did not
own the data provided by these meters. In essence, there were
two issues. The first was a statutory limitation on its right
to disclose information relating to individual companies that
it had obtained in the course of its activities as the operator
of the transmission system (section 105 of the Utilities Act 2000,
again). The second was the fact that the flow meters at the various
sub-terminals did not provide strictly comparable or easily interpreted
information, so release of such data in real timeand therefore
in raw formwould at best be costly for market participants
to analyse individually and at worst, if not properly interpreted,
could mislead the market. NGT's solution had been to aggregate
the data and provide it an hour in arrears, rather than in real
time.[188]
71. We asked why it had taken so long for the industry
to agree to supply the basic information now being made available;
and why there had been such a difference in transparency between
the gas and the electricity markets. UKOOA argued that the gas
wholesale market was still a young and developing market, whose
needs were gradually becoming apparent.[189]
Although the wholesale gas market is fairly young, it is a fundamental
principle of all markets that they cannot function properly without
all parties having roughly equal access to basic information.
More plausibly, NGT cited the genesis of the electricity wholesale
market from a nationalised industry, with the associated regulatory
regime when it was privatised; whereas the 'North Sea' was seen
as a functioning, competitive market from the start. While the
electricity industry is used to, and accepts, the need to provide
ample information to the regulator, systems operator and market
participants, this is a novel situation for the major oil companies.[190]
72. We understand
and accept NGT's explanation of why it is currently impossible
to provide real time information on gas flows. This may not be
very significant: information delayed by an hour represents a
huge increase in the transparency of this market, and is, we believe,
quite sufficient for the needs of customers. However, we suspect
that to restore market confidence there may be a need for still
more information about production outages, not least because of
the mistrust that has arisen over maintenance patterns in 2003.
It is too soon to make a firm judgement on this, but we recommend
that the DTI and Ofgem keep a watch on this area to see whether
further information is needed.
73. We note that
the Norwegian gas production companies have agreed to participate
in the arrangements for providing voluntary information.[191]
We welcome this. We consider that the advantages of receiving
information from all major parties, albeit on a voluntary basis,
outweigh any benefit from imposing any element of compulsion which
might lead the Norwegian companies to withdraw from the scheme
altogether.
96