Select Committee on Trade and Industry Written Evidence


APPENDIX 33

Supplementary memorandum by National Grid Transco

INTRODUCTION

  1.  National Grid Transco Group (NGT) gave oral evidence on 26 January. At that session NGT was asked to provide supplementary evidence on:

    —    the expected frequency of LNG tankers supplying LNG sites in Great Britain; and

    —    some of the issues to be addressed in order to provide greater information to the gas market.

LNG SUPPLY TO GB

  2.  The LNG supply chain usually consists of a large remote gas source, associated upstream facilities, liquefaction plant(s), LNG tankers to ship the gas and a re-gasification terminal(s). The total costs of a project can run into many $billions. Current total project costs are about $700 million per bcm per year of delivered gas, though it should be noted that there are numerous variables here notably the number of ships required and other upstream costs. The biggest cost items are usually the upstream facilities and liquefaction plant then ships then re-gasification terminals.

  3.  With investment of this magnitude it is essential that LNG is delivered to markets and any slippage in project timescales can impact break-even costs, hence LNG should be considered as a consistent supply, especially in terms of ships leaving the liquefaction plant(s). Where LNG can be considered a less consistent supply is in its ability to reach alternative destinations. This market opportunity is difficult to quantify but should not be discounted particularly given the relatively low cost of re-gasification terminals and the volatility of localised markets, notably the US. To some extent this should enhance UK security rather than undermine it as Europe has numerous LNG terminals and only the UK has a fully functioning gas market.

  4.  Making calculations according to some assumptions of what is known about the capacity of Milford Haven, the capacity that has been signalled is required and the current capacity of LNG ships, NGT would estimate that ships would arrive to unload LNG between every 1.5 to 4.5 days. At the Isle of Grain the initial shippers (BP/Sonatrach) have contracted for baseload capacity which, if utilised fully, would on average see around one ship per week unloading at the facility. If the terminal were to be expanded, as planned, the frequency of ships could increase to a maximum of one ship every two days.

ISSUES SURROUNDING GREATER INFORMATION PROVISION IN THE GAS MARKET

  5.  Transco played a leading role in the DTI's Information Initiative and continues to work with the wider industry to gain an understanding of what additional information provision might be considered beneficial to the market. The first two phases of the Information Initiative were completed by summer 2004 and it is expected that the third phase will be fully implemented by Q3 2005.

  6.  For clarity, the three phases cover:

    —    Phase 1—the improved provision of information (standardisation of Delivery Flow Notifications (DFN's) and Storage Flow Nominations (SFN's) from upstream parties to Transco.

    —    Phase 2—further provision of detailed planned maintenance and outage data by upstream parties to support Transco in refining its annual Transporting Britain's Energy (TBE) process.

    —    Phase 3—the four categories within stage 3 are:

    1.  Real Time flows into the NTS at sub-terminals—to be published from 1 July 2005.

    2.  Forecast flows into the NTS at sub-terminals—to be published from 18 March 2005.

    3.  Deliverability with respect to planned maintenance—published Q4 2004.

    4.  Sub-terminals "End of day" flow data—published Q4 2004.

  7.  During the development of phase three various confidentiality, data ownership and liability issues have arisen (explained below) which mean that category 1, 2 and 3 information will be published on an aggregated (North/South zone) basis. In addition, due to physical and operational limitations, agreement has been reached that Transco will publish category 1 and 2 data on an hourly, rather than "real time" frequency.

  8.  Concern relating to the publication of further information fall into two categories. The first area concerns data ownership, commercial confidentiality and liabilities whilst the second relates to the telemetry equipment, accuracy, timing and delivery of data. In order to release further information to the market, these issues will need to be resolved.

DATA OWNERSHIP, COMMERCIAL CONFIDENTIALITY AND LIABILITIES

  9.  Transco has access to instantaneous physical flow rate data, often via telemetry, at the majority of the sub-terminals. The Delivery Facility Operators (DFO's) generally own the metering equipment and provide the flow data to Transco for use in its operational control activities, on a non-contractual basis. Where Transco does not have access to flow data at a sub-terminal it utilises data derived from Transco owned equipment downstream of that point.

  10.  During the DTI Information Initiative, the position of Transco was discussed in respect of the ownership and publication of the sub-terminal flow data, and the following position was reached:

    —    where the terminal operator owns the metering equipment and provides Transco with access to the real-time flow data, this data belongs to the terminal operator and the ability by Transco to disclose that data to others is restricted by the provisions of Section 105 of the Utilities Act 2000 and the provisions of any relevant Network Entry Agreement;

    —    where Transco owns the metering or has installed duplicate metering, Transco would be utilising its own equipment to derive the data and would therefore, own the data. However, this data would still be covered by the terms of Section 105 (as it is information relating to the affairs of a particular business and was obtained by virtue of the Gas Transporter's Licence) and Transco would not be able to disclose that information to others except as set out in Section 105; and

    —    when Transco aggregates sub-terminal flow data it then has legal ownership of the aggregated figure. However, the provisions of Section 105 will still apply to that aggregated figure to the extent that information relating to a particular business entity could be identified from it.

  11.  Transco can only publish information consistent with relevant legislation and its Gas Transporters Licence. Transco took the view that publishing the sub-terminal flow data on an aggregated North/South basis would afford protection from any action under Section 105. This was agreed to by DTI, Ofgem and UKOOA as primary data owners will be protected from any risks pertaining to commercial confidentiality or liabilities.

METERING ARRANGEMENTS AND DATA ACCURACY

  12.  As explained earlier, Transco does not own the majority of measurement equipment that is used to monitor flow data. The measurement equipment used by producers is fit for purpose according to its particular situation so there is no consistency over the types of metering used, the parameters measured or the accuracy of the metering. In addition, certain metering can be inaccurate in real time. In order for market participants to correctly interpret the data it would be necessary to publish the various parameters associated with each specific meter eg the type of metering (instantaneous or integrated), pulse rates, quantities, meter accuracy and meter tolerances. Of further consideration is that several of these parameters can be affected by factors such as the physical operation of the pipeline or mechanical failure.

  13.  This currently makes the provision of real time information very difficult as flow data is not strictly comparable or easily interpreted. This coupled with the potential risk of inaccurate data in real time could provide misleading signals to the market and be costly for market participants to analyse individually. The problem is overcome through the aggregation of data and it is why data will be provided hourly, rather than in real time. Replacement and standardisation of metering and the associate telemetry would carry a cost.

February 2005





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 1 June 2005