APPENDIX 3
Memorandum by the Baku Ceyhan Campaign
Thank you for your letter of 23 July enclosing
the reply of Mr Weiss, Deputy Director of ECGD, to the Committee
Chair's letter requesting a written response to the concerns raised
over ECGD's support for the Baku-Tbilisi-Ceyhan (BTC) project.
Please find attached the Baku Ceyhan Campaign's
response to Mr Weiss's letter and accompanying documents. The
response is submitted collectively by Corner House, Friends of
the Earth (England, Wales and Northern Ireland), Kurdish Human
Rights Project and PLATFORM.
We have reviewed the documents sent to the Committee
by the ECGD and, on the evidence available to us, conclude:
The ECGD's due diligence of BTC was
insufficiently rigorous and that it relied to a compromising extent
on the project sponsor for information and reassurances over the
many detailed concerns that have been raised by independent parties;
The ECGD's monitoring procedures
failed to alert ECGD to a range of problems that should have been
picked up, notably the problems that have arisen with the field
joint coating system;
The human rights due diligence took
insufficient account of the context in which the project was being
implemented and the abuses that were likely to result;
The coating problem constitutedand
still constitutesa clear material threat to the project's
timing, safety and viability. The Minister's judgment that the
field coating problem was limited does not stand up to scrutiny.
In our view, BP was therefore in breach of its obligations by
not reporting the coatings failures.
The Baku Ceyhan Campaign recommends that:
Immediate steps should be taken to
address these institutional failures.
The project loans be suspended until
a full independent assessment of the project's safety has been
completed.
We hope that the submission assists the Committee
in its deliberations. Please do not hesitate to contact us if
there are points on which the Committee would like clarification
or further information.
Nicholas Hildyard
Corner House
Anders Lustgarten
Baku-Ceyhan Campaign
Greg Muttitt
PLATFORM
Hannah Ellis
Friends of the Earth England Wales and Northern Ireland
Kerim Yildiz,
Kurdish Human Rights Project
6 September 2004
INTRODUCTION
1. We have received from the Committee the
reply of Mr Weiss, Deputy Director of ECGD, to the Committee Chair's
letter requesting a written response to the concerns raised over
ECGD's support for the Baku-Tbilisi-Ceyhan (BTC) project. We have
now had an opportunity to review Mr Weiss's letter and the accompanying
documents.
2. We should point out that the WorleyParsons
Energy Services Redacted July 2004 Desktop Study which Mr Weiss
forwarded is not the same document as the "Parsons
report" referred to by ECGD in previous correspondence with
the Corner House, the Baku Ceyhan Campaign and, indeed, in evidence
to the Committee.[1]
This has been confirmed to us by ECGD.[2]
For the avoidance of doubt, we have therefore referred to the
July 2004 Desktop Study as the "WorleyParsons Report"
throughout this response, and to the March 2003 report from Parsons
Energy and Consulting as the "Parsons report".
3. We should add that we are gravely concerned
that the ECGD has sought to answer questions that have been posed
by parliamentarians arising from the 2003 Parsons Report by referring
to information in the 2004 WorleyParsons report without making
it clear that the two reports are different and are separated
by over a year. There should be no question of confusing the two
reports: the 2004 WorleyParsons report plainly states that it
was only "initiated after the 15 February 2004 London Sunday
Times article."[3]
We believe that the ECGD's elision of the two reports could have
the effect of misleading parliamentarians into believing that
the ECGD had undertaken certain due diligence issues prior
to approving its support for BTC, when this was not in fact the
case.[4]
4. Our detailed comments on Mr Weiss's evidence
are set out below. They seek to address eight questions, under
three headings:
(1) ECGD due diligence process
Did the ECGD undertake adequate due
diligence on the field joint coatings, both prior to and after
approving the BTC project?
Did BP withhold material information
relating to the safety of BTCin breach of the lending procedures
of the ECGD?
Does the ECGD rely too closely on
information provided by the Project Sponsor?
(2) Failures in coating selection process
and remediation
Is the ECGD justified in claiming
that the selection process, evaluation/testing and quality control
for the SPC 2888 coating were rigorous and effective?
Is ECGD justified in claiming that
the failures of the field joint coating system have been remedied?
Is ECGD right to claim that Derek
Mortimore's concerns have been dealt with?
(3) Broader issues and lessons
Are there other areas where ECGD's
due diligence was inadequate?
What policy lessons can be learned
from such inadequacies?
5. Before proceeding, we would like to make
an important clarification. There are two main problems with the
SPC 2888 coating material, both brought to light by Derek Mortimore
and by the Sunday Times. They have at times been conflated, but
are separate:
The first and major problem is that
the SPC coating does not properly adhere to polyethylene, which
is the main exterior layer for the BTC pipeline. Because the field
joint coating does not permanently stick to the pipe section coating,
it does not therefore provide full anti-corrosion protection.
As a result, the total coating system cannot be impervious to
water, as it needs to be to protect the pipeline from corrosion.
The SPC coating also cracks at cold
temperatures. Obviously, the cracks also let in water. This problem
is due to the chemistry of SPC 2888 itself, whereas the first
is due to its interaction with polyethylene.
Although the majority of the controversy over
the coating has focused on the cracking, that is actually much
the lesser of the two concerns. Methods can be used to mitigate
the cracking of the coating, at least temporarily. By contrast,
there is no way in which SPC 2888 can be guaranteed to adhere
to the polyethylene exterior of the pipeline for the estimated
design life of the pipeline (40 years), and it is therefore inevitable
that the pipeline will corrode, with all the potential for leakages.
Significantly, the WorleyParsons report, and
indeed all correspondence from ECGD on this subject, only acknowledges
the second problem, and not the first.
1. ECGD'S DUE
DILIGENCE PROCESS
A. Did ECGD undertake adequate technical
due diligence?
6. Column 2 of the following Timeline sets
out the due diligence (and lack of it) undertaken by ECGD on the
technical specifications of the BTC pipeline from October 2002
(shortly after the department became involved in negotiations)
to August 2004, as detailed by ECGD in correspondence with the
Committee, NGOs and in responses to parliamentary questions. Shaded
boxes cover actions taken prior to ECGD approving support for
the project. Column 3 details the evolving construction problems
on the pipeline.
7. Given that the ECGD was considering support
of US$150 million[5]
in taxpayers' money for the project (eventually reduced to $106
million[6]);
that the project involved major environmental risks in the event
of a leak of oil; that internal BP reports had questioned the
selection of the field joint coating; and on BP's own admission,
that the field joint system was entirely novel;[7]
the public might legitimately expect that the coating system merited
special due diligence on the part of the ECGD.[8]
8. From the timeline, it can be seen that
the ECGD undertook two technical investigations prior to the decision
to fund BTC: the 2003 Parsons report and the field investigations
undertaken by Mott MacDonald prior to November 2003.
9. Five questions arise:
10. Did these technical investigations include
an assessment of the concerns raised by Derek Mortimore, BP's
own consultant, in 2002?
Answer: No.
The ECGD was not informed by BTC of Mr Mortimore's
findings[9],
nor was Parsons Energy and Chemicals.[10]
TIMELINE OF
ECGD DUE DILIGENCE
ON COATING
Date | ECGD Due Diligence and Statements
| Emerging Construction Problems |
May 2002 | | BP senior managers, who had already raised their concerns internally, commissioned Derek Mortimore, a leading pipeline integrity consultant, to assess the viability of a proposed epoxy coating to protect the pipeline joints in Azerbaijan and Georgia
|
5 September 2002 |
| PEER Assist Review describes the chosen field joint system as "a step change in industry practice" [1]
|
October 2002 | "Interim reports from [Parsons Energy and Chemicals] made available to ECGD." [2] The Parsons Reports were commissioned to assess technical specifications for the project.
| |
10 November 2002 |
| Mortimore submitted report to BP, concluding that the field joint coating specification "is utterly inappropriate as it does not confirm a protective system that can be successfully applied in all the conditions under which this pipeline will be constructed, nor does it confirm the integrity of the protection for the design life of the pipeline."
|
March 2003 | "Final version of [2003 Parsons Report] was produced [2]
| |
August 2003 | |
BP's Frontiers magazine publishes article in which BP's engineering manager states that "This is the first time that such a system has been employed." [3]
|
24 September-
11 October 2003
| Mott MacDonald Pre-Financial Closure Site Visit. No further in situ checks on the integrity of any sections of the pipeline after November 2003 prior to financial close. [4]
| |
November 2003 |
| Early to Mid-November 2003, "cracking of the field joint coating was reported in both Azerbaijan and Georgia. BP/BTC assembled a team to investigate the cracking" [5]
|
17 December 2003 | ECGD agreed to provide cover for a line of credit facility to a value of US$150 million, subject to ECGD's prior approval of the Project's Environmental and Social Action Plan, the General Oil Spill Response Plan and the General Hydrostatic Testing Plan; and the establishment of final project documentation to the satisfaction of ECGD. [6]
| |
3 February 2004 | Project agreements signed by ECGD and Project Sponsors
| |
15 February 2004 | Sunday Times story published on problems with field joint coatings. ECGD first becomes aware of the coatings issue.
|
Unspecified date after
15 February 2004
| ECGD requests WorleyParsons Energy Services to "complete" [7] desktop review of the BTC field joint coatings.
| |
29 February-
24 March 2004 | First post-financial closure site visit undertaken by D'Appolonia on behalf of ECGD and lenders' group
| |
March 2004 | ECGD states that it has no specific information on use of SPC 2888 on other pipelines coated with a three layer, high-density, polyethylene coating [8]
| |
19 March 2004 | ECGD Minister states that Parsons Energy "scrutinised" choice of coating in 2003 Parsons Report [9]
| |
May 2004 | WorleyParsons "planned routine site visit" [10]
| |
June 2004 | D'Appolonia report published.
| |
August 2004 | ECGD responds to request for further information from Trade an Industry Committee by releasing redacted WorleyParsons desktop review
| |
| | |
Notes:
[1] WorleyParsons, p 8;
[2] Letter from ECGD to Corner House, 30 March 2004;
[3] BP, "Caspian Connection", Frontiers, August
2003, pp 18-25;
[4] Letter from ECGD to Corner House, 30 March 2004,
"ECGD has not itself carried out any in situ checks on the
integrity of any sections of the pipeline since November 2003";
[5] WorleyParsons 2004, p 4;
[6] ECGD, Note on BTC Decision, 17 December 2004. In
the event, the sum agreed was $106 million (see John Weiss, Letter
to Trade and Industry Committee, 19 July 2004);
[7] WorleyParsons 2004, p 2. The choice of the word "complete"
is highly misleading since it suggests that the 2003 Parsons Report
was incomplete. In fact, ECGD has confirmed that the 2003 Parsons
Report was a final report (see Letter from ECGD to Corner House,
30 March 2004;
[8] Letter from ECGD to Corner House, 30 March 2004:
". . . ECGD does not have this specific information . . .";
[9] Letter from Minister for Trade to Corner House and
others 17 March 2004;
[10] Worley Parsons, 2004. It is unknown when this visit took
place or what its findings were. The WorleyParsons report does
not discuss it further and refers to it in the future tense.
We find it profoundly unsatisfactory that ECGD did not make
it its business to ensure that BP supply it with all reports of
relevance to the selection of materials to be used on the pipeline,
which would have included the Mortimore report. We would recommend
that the ECGD's due diligence procedures be revised to require
that all technical reports are requested from the project sponsors
and investigated.
11. Given the experimental nature of the chosen field
joint system, did ECGD put in place special measures to investigate
its safety?
Answer: No.
From the outset BP has made it clear that the chosen field
joint system was novel:
BP's PEER Assist Team described the system as
"a step change in present industry practice."[11]
(For further discussion, see also paragraph 30 [iii] below);
In August 2003, prior to financial closure, Ian
Parker, BP's Engineering Manager stated in BP's in-house magazine
that, in the company's view: "This is the first time that
such a system has been employed."[12]
Nonetheless, despite the experimental nature of the field
joint coating system, the ECGD appears to have required no special
due diligence measures. In a letter to The Corner House, received
30 March 2004, the ECGD stated that "its consultants considered
the track record of the specified coatings as part of the technical
analysis."[13] However,
in the same letter, the ECGD also denied that it had any specific
information on other projects where SPC 2888 had been used on
a pipeline coated with a three layer, high-density, polyethylene,
like the BTC pipeline.[14]
At the very least, the ECGD's inability to provide such information
(despite the issue having supposedly been examined by its technical
consultants) raises serious questions as to the thoroughness of
its consultants' pre financial closure investigations.
Even now, after WorleyParsons has conducted a full desktop
study, the ECGD is unable to give a clear-cut and definitive response.
On the contrary, despite BP's admission that the coating system
used in BTC is entirely new, the WorleyParsons report is at best
equivocal on the issue:[15]
"the SPC coating material SPC 2888 may not
have been used on projects with 3-layer PE [polyethylene] coated
line pipe";[16]
"There is no best industry practice for field
joint coating on three-layer polyethylene, the industry is still
learning".[17]
ECGD makes no acknowledgement of this uncertainty in its
response to the committee. Instead, it continues to insistas
it has done since the Sunday Times' allegationsthat
SPC 2888 is widely used and has a good track record,[18]
failing to mention that this track record is on pipelines that
are materially different to BTC.
We believe this to be deliberately misleading. No-one has
suggested that the SPC product has never been used[19],
merely that it has no operational track record on pipelines coated
with polyethylene. This is a crucial distinction, as the most
important criticism of the SPC 2888 coating is that it does not
adhere to polyethylene. In other words, it will let in water,
and so not do its job as a corrosion protector.
We note that the same misleading interpretation has been
made by the Minister of State for Trade, Investment and Foreign
Affairs, Mike O'Brien, in answer to a Parliamentary Question on
the coating issue[20].
Given that this reply was made after WorleyParsons had undertaken
its desktop study, a key question is whether or not the Minister
was aware that his statement was misleading.
12. Did the ECGD adequately scrutinise the evaluation,
testing, selection and application of the field joint coating
system for Azerbaijan and Georgia prior to approving support for
the BTC project?
Answer: Disputedbut the evidence strongly suggests
that it did not.
The Minister for Trade has stated: "The choice of coating
was scrutinised and approved by Parsons E&C, the independent
engineering company operating on behalf of the project lenders
and ECAs."[21] The
ECGD has also stated that its consultants "examined the track
record of the specified coatings as part of the technical analysis".
However, in a February 2004 interview conducted by investigative
journalists Melissa Jones and Michael Gillard, Parsons reported
that the assessment made in its 2003 was not an in-depth study.
The reviewer was not a corrosion expert; he did no quality assurance
exercise; and there was no testing undertaken of SPC 2888, the
Canadian paint used as a coating.[22]
In our view, the conflict between the Minister's statement
and Parsons' can only be resolved through release of the 2003
Parsons report and the correspondence between ECGD, Parsons and
BTC on the coating. The Corner House and Friends of the Earth
(FOE) have both requested the Parsons Reportunder the Code
of Practice on Open Government and the Environmental Information
Regulations, respectivelybut have been refused on the grounds
of confidentiality. The ECGD has also claimed in correspondence
with FOE that it is not a "relevant person" under the
Environmental Information Regulations, a claim which, if true,
would mean either that the ECGD no longer acknowledges that it
is a government department or that it believes it has no environmental
responsibilities.
13. Did the ECGD undertake any steps to investigate the
integrity of the pipeline prior to financial closure?
Answer: No.
The only in-situ investigation was undertaken by Mott MacDonald
in September-October 2003. It was charged with verifying, "the
implementation of commitments established in the Environmental
and Social Action Plan", and its remit did not include checking
technical adequacy or pipeline integrity.
We find it of grave concern that no independent in-situ technical
investigation was undertaken of the integrity of the pipeline,
which was already well-advanced, prior to financial closure. We
would recommend that this be corrected for future projects.
14. Are the construction monitoring procedures put in
place by ECGD sufficiently rigorous to pick up materially significant
technical problems?
Answer: Not on the evidence to date.
The ECGD's monitoring regime did not detect the problems.
The ECGD only learned of them through the press.
In response to the Sunday Times' investigation into
the field joint coating problems, the Minister of Trade has stated:
"The problems with the application of the coating were detected
by the inspection regime in place on the pipelineevidence
that the monitoring regime is doing its job." However, he
is referring to BP's internal monitoring systems, not those of
the ECGD. That BP had picked them upbut failed to inform
ECGDonly reinforces the failure of the ECGD's monitoring
regime, which, if it is to be effective, clearly needs to act
independently of BP.
We note from the WorleyParsons report that there were major
failures in BP's processes of selection, evaluation and quality
control in relation to the coating, which we discuss in paragraphs
29-30 below. If ECGD had properly monitored the project, it should
have identified these systemic failings.
Even after the coatings issue came to public attention through
the media, ECGD did not properly scrutinise the problems or proposed
solutions, instead relying heavily on information it received
from BP (see paragraphs 21-28 below).
15. From the above (paragraphs 9-14), we would conclude
that:
ECGD failed to ensure that it was properly informed
on the issues surrounding the coating's suitability;
There is strong evidence to suggest that the 2003
Parsons Report was superficial in "scrutiny" of the
choice of coatingan issue that can only be resolved by
release of the report, which ECGD has refused;
The ECGD failed to undertake necessary in-situ
inspections prior to approving the project;
The ECGD's agreed post-financing monitoring procedures
are inadequate.
B. Did BP withhold material information relating to the
safety of BTCin breach of the lending procedures of the
ECGD?
16. ECGD's lending procedures require project sponsors
to inform them of all material issues that might affect a project.
17. The ECGD Minister has acknowledged that "BTC
Co did not inform the ECGD about the problems with the field joint
coating material."[23]
However, he claims that BTC Co was not obliged to do so, ostensibly
due to "the limited nature of the problem".[24]
This assessment was made prior to any independent investigation
of the problem and on the basis solely of information provided
by BP.[25]
18. We would strongly contest the Minister's views based
on both the content of the Mortimore report and the extent of
the problem as revealed by WorleyParsons:
(i) Mr Mortimore's report stated, inter alia, that
"Clearly the use of (this paint) is going to lead to a serious
problem . . . the cost for repairs could be astronomical. The
potential for claims against (BP) is open-ended."[26]
This statement cannot be described as immaterial. Even if BP disputed
the conclusions of the report, we believe that the company was
required to inform ECGD that the questions had been raised.
(ii) Following the publication of the WorleyParsons Redacted
Desktop Study, it is now clear that BP knew at the time of financial
closure that the coating problem was far from limited in nature.
In early February 2004, BP would have been aware that in Georgia
at least 26% of joints welded and coated by that time were known
to have developed problems.[27]
A known fail rate of 26% cannot reasonably be considered immaterial.
Moreover, the true proportion of joints with cracked coatings
is likely to be far higheralthough the full extent of the
problem is not known.[28]
(This issue is discussed in more detail in paragraph 35, below).
(iii) The WorleyParsons report reveals that BP is in dispute
with its contractors over the liability for costs incurred as
a result of the cracking problems, and that the cost to BTC Co
of the debacle is unknown until those liability questions are
resolved. Firstly, the fact that liability for costs is being
debated is a clear indication that the problems are material,
in any meaningful sense of the word: if they were not material,
there would be nothing to debate. Secondly, if the cost to BTC
Co is as yet unknown, the impact on ECGD's position, and hence
on the British taxpayer, is also unknown. For both reasons, BP's
failure to inform ECGD is indefensible.
19. We therefore do not accept the Minister's view that
BP was under no obligation to report either the original Mortimore
report or the cracking of the field joints in November 2003, and
are surprised that he made this statement solely on the basis
of information provided by the project sponsors without having
made independent investigations. In our view, the failure of BP
to inform ECGD constituted a clear breach of ECGD lending requirements,
the more so given that ECGD was still assessing the project.
20. We believe that BP should be held to account. We
further recommend that the ECGD lay down clear guidelines as to
what levels of failure they view as materially significant.
C. Does the ECGD rely too closely on information provided
by the project sponsor?
21. In our previous submission we made the case that
ECGD relies too heavily on information provided by the project
sponsorsrather than its own investigationsto "ground
truth" claims of the project's compliance with international
best practice. We also provided a number of examples, including
evidence that ECGD had refused to meet with ex-workers who have
reported major construction failures, including faulty welds being
passed as satisfactory.
22. In response to that criticism, ECGD has referred
the Committee to independent field assessments carried out on
behalf of the lenders' group.
23. In the case of the WorleyParsons report, all data
were acquired only from BP/BTC, and no external sources (including
Mr Mortimore) were consulted. As it admits in the introduction,
"this desktop study was prepared utilising documents and
information furnished by BP/BTC".[29]
Furthermore, no independent checks were made on the quality of
the data.[30] This is
alarming, given that the role of that report was to check on due
diligence. The report appears to accept BP's explanations without
scrutiny; for example:
"BTC indicated that no cracks were found
that were associated with application of the field joint coating
following these procedures. They indicated that the small cracks
that where (sic) found were caused by other reasons."
[31]
24. We would also point out that the studies commissioned
by ECGDthough of high qualityare of extremely limited
scope, monitor performance only within very narrow parameters,
and have no investigative remit.
For example, the 2003 Parsons Energy & Chemical report
did not identify problems with the choice of field joint coatingwhether
it actually scrutinised the selection and evaluation process is
not known, due to ECGD's continued refusal to disclose that report.
We have also noted that the lenders' construction-monitoring consultant
Mott MacDonald did not scrutinise the application method for field
joint coatings on its site visit in October 2003.
In addition, even after the field joint coatings problems
had become known to ECGD, the lenders' new environmental monitoring
consultant D'Appolonia did not investigate the issue on its field
visit in March/April 2004. In contrast to the 2004 WorleyParsons
report, which was based only on a desktop study, D'Appolonia was
on site and thus ought to have examined the implications of the
coatings problem for compliance with BTC's environmental commitments,
and whether or not the new coating procedures would ensure the
environmental safety of the pipeline. It did not; in fact, there
is not a single mention of field joint coatings in D'Appolonia's
report.[32]
25. With regard to ECGD's continuing refusal to meet
with Mr Derek Mortimore, whose original report first raised many
of the concerns about the coating, we wish to convey to the Committee
our extreme regret that ECGD should now seek to justify this refusal
by citing a passage in the WorleyParsons report which repeats
BP's reaction to his criticisms.[33]
We note that this passage is not backed by any evidence and that
neither WorleyParsons nor ECGD made any attempt to verify its
content with Mr Mortimore. That BP dismisses Mr Mortimore's concerns
by personal attack is disappointing; that WorleyParsons and ECGD
take BP's dismissal as grounds for not consulting him is wholly
unacceptable.[34]
26. It is of particular concern that ECGD made no independent
investigation of the allegation in the Sunday Times of
procurement fraud in the selection of the coating. Instead the
ECGD simply accepted the findings of the company's own internal
investigation,[35] the
thoroughness of which has been challenged.[36]
27. We note that, even beyond the WorleyParsons report,
the evidence strongly suggests that ECGD is too willing to accept
BP's word at face value, without subjecting it to the scrutiny
that due diligence requires. Whilst we accept that BP is a major
company with a reputation to protect, this does not justify ECGD's
failure to exercise independent and rigorous assessment, particularly
where wrongdoing has been alleged.
28. Indeed, in many cases, the company's desire to protect
its reputation serves not as the guarantor of high standards which
many have claimed, but as a motive to obscure and cover-up concerns
over its work before they have been appropriately resolved. This
factor can perhaps be seen in BP's failure to inform ECGD about
the cracking on the coating.
2. ENFAILURES IN
COATING SELECTION
PROCESS AND
REMEDIATION
A. Were the selection process, evaluation/testing and
quality control for the SPC 2888 Coating rigorous and effective?
29. While we are disappointed that ECGD has declined
once again to disclose the 2003 Parsons report, the 2004 WorleyParsons
report is nonetheless helpful in providing further information
to shed light on the events leading up to the selection of the
faulty SPC 2888 coating. We are therefore very grateful to the
committee for making this report available to us.
30. However, far from reassuring us that the coating
is reliable, appropriate and safe, some of the information provided
by WorleyParsons gives us further cause for concern: [37]
(i) Acknowledgement of the Experimental Nature of SPC
2888 on Polyethylene Pipes
As already noted (paragraph 11) WorleyParsons report
confirms that SPC 2888 may not have "may not have been used
on projects with 3-layer PE [polyethylene] coated line pipe"[38].
The particular concern relating to use on coated
pipelines is partially acknowledged in the WorleyParsons report:
"At low ambient temperatures cure over the
PE overlap may be slower than over steel and some post application
cure may be required."[39]
The report also acknowledges "limited adhesion"
to plastic (HDPE), but claims that the same problem exists for
other field joint coating systems.[40]
Where it discusses the specific tests on adhesion,[41]
WorleyParsons does not report or comment on the results relating
to the adequacy of the coating's adhesion to the polyethylene
pipe coating (except that it was improved by grit blasting and
worsened by use of primer), only to the bare steel and to the
epoxy "toe"[42][43]
(iii) Cutting Costs as a reason for the choice of SPC
2888
The WorleyParsons report also makes it clear that
the main reason for the innovation in choice of coating was to
reduce costs, by increasing the size (and hence reducing the cost
of the crush process) of the backfill material. The review that
led to the selection of SPC 2888 was part of BP's Pipeline Cost
Reduction Initiative; efficacy of the coating was only "an
additional driver"[44]implying
that it was a secondary concern. That this was a cost reduction
innovation is emphasised by BP's Upstream Technology Group: "The
selected liquid field joint coating system represents a step change
in present industry practice, both technically and commercially."[45]
We do not suggest that BP should not attempt to carry out
its projects cost-effectively. However, there is a clear tension
in some cases between cost reduction and achievement of a high
safety performance. This is especially the case when such great
store has been set by BP and others on finishing this project
on schedule. We contend that where cost-cutting innovations are
made, there must be a rigorous process to ensure that safety is
not compromised.
(iv) Irregularities in Testing and Approval Process
In light of the above, it is worrying that despite
the experimental nature of the coating selection, the testing
and approval process contained a number of irregularities, revealed
in the WorleyParsons report:
(a) The coating selection process[46]
evaluated the performance of the various coating options applied
on 36-inch pipe[47],
whereas the BTC pipeline has a diameter of 42 inches in Azerbaijan
and 46 inches in Georgia. That the tests were not performed on
pipe of the correct diameter is alarming, given that BP and the
project engineers had doubts about the efficacy of coatings on
pipes larger than 36 inches.[48]
(b) In the selection process, heat shrink sleeves,
the main alternative to a liquid coating such as SPC 2888, were
tested, but were not included in the ranking of coatings.[49]
(c) The second test[50]
examined the impact of 20 millimetre backfill material[51]
on the coatings, whereas the WorleyParsons report indicated that
the intention was to use larger, 22mm backfill material.[52]
Again, the use of the wrong size backfill material in the test
is very surprising, given that the primary reason for seeking
a new coating was to withstand damage from larger, 22mm, backfill.
(d) The only field test of the SPC coating was
on 34-inch pipeline, in Algeria[53]hardly
comparable conditions to Azerbaijan and Georgia. This pipeline
is still under constructionso there is no experience of
the coating's performance in operation.
(e) The only tests on the SPC coating's performance
in cold weather were in fact carried out or contracted by Speciality
Polymer Coatings Inc,[54]
the supplier of the coating. While there is no objection to a
company carrying out laboratory tests on its own products, the
WorleyParsons report lists these two studies as part of the "evaluation,
testing and selection process",[55]
which is clearly inappropriate, given the conflict of interest,
and the need to establish reliability in those conditions of the
previously unused coating.
Thus, far from the rigorous selection process claimed by
ECGD[56] and the Minister[57],
all of the major elements of the selection process were flawed
in some important way.
(v) Inadequate Quality Control
One might also have expected any reports of problems
to be thoroughly investigated; as such reports can constitute
an important quality control mechanism to check on the efficacy
of the internal processes. However, the WorleyParsons report makes
clear that when problems were raised (presumably by Mr Mortimore),
the response was "the least significant testing effort"
of the programme.[58]
Despite the experimental nature of the coating system, and
its lack of rigorous and relevant testing, BTC did not employ
full-time coating inspectors, to check the application process,
quality and performance of the coatings when applied in the field
to the pipeline, until after the cracking problems were reported.[59]
Inspectors are a key part of a quality control process even for
a tested technology; it is deeply disturbing that they were not
used in this case.
B. Is the ECGD justified in claiming that the failures
of the field joint coating system have been remedied?
31. To clarify once again, there are two main problems
with the SPC 2888 coating:
It does not stick to the polyethylene coating
on the pipe sections; and
It cracks in cold weather.
Both problems can lead to the ingress of water, and consequent
corrosion of the pipeline, thus undermining its safety and leading
to a risk of leaks or ruptures.
32. The WorleyParsons report makes no mention of any
field testing of the coatings' adhesion performanceeven
though concerns about adhesion with polyethylene were raised both
by Mr Mortimore and by BP's own tests[60]
(see paragraph 30 [ii], above). Prior to January 2004, there were
no full-time coating inspectors on site in Azerbaijan and Georgia.[61]
33. We are gravely concerned that by focussing solely
on the cracking problem, the non-adhesion has been ignoredcreating
an environmental timebomb. We believe that ECGD must urgently
review the adhesion performance,[62]
and make the results available to Parliament and to the public.
34. ECGD claims that the problems that led to the cracking
of the field joint coating have been adequately corrected.[63]
However, the information presented in the WorleyParsons report
does not reassure us that this is the case.
35. According to the WorleyParsons report, the only weld
coatings tested[64] for
cracking were those that had been applied after early November,
when the problem was first observed.[65]
The full extent of the problem is therefore not yet known:
(i) Although there is evidence that cracking can occur
in the cold regardless of the temperature at which the coating
was applied, there appears to have been no evaluation of how joints
coated before the onset of winter performed once the winter arrived.[66]
On the basis of BP's published figures for pipe-laying progress,
we estimate the number of such joints to be in the region of 12,200,
of which only a fraction were tested by BP.[67]
(ii) The WorleyParsons report does not indicate how the
acknowledged 1,560 faulty joints were recoated. We understand
that it is technically difficult to remove the field joint coating
without damaging the polyethylene coating on the pipe sections.
We are surprised that no comment is made in the report on the
methodology.
(iii) In Azerbaijan, a joint coating fail rate of 2.6%[68]
is reportedbut this does not appear to include pipes where
small cracks (less than 6" long) have been found since BP
maintains that "such cracks were caused for other reasons".[69]
BP does not clarify what these "other reasons" might
be. BP's claim was apparently not investigated by WorleyParsons.
(iv) Although the WorleyParsons report maintains that
the testing procedures were rigorous and that the need for pre-
and post-application heating was known prior to commencement of
construction,[70] it
is clear that new procedures were implemented on the hoof,[71]
largely, it would seem by trial and error. The changing of specifications
during construction, and development of procedures on the pipeline
itself, rather than by earlier trial, is hardly reassuring, and
does not strike us as diligent project management.
C. BP's and WorleyParsons' rebuttal of Derek Mortimore's
report
36. As noted above, we are gravely disappointed at ECGD's
dismissal of Derek Mortimore's efforts in bringing serious safety
concerns to light, and at its acceptance of the unfounded personal
attack on him in the WorleyParsons report.[72]
We believe the inclusion of the personal comments on Mr Mortimore
in the WorleyParsons report can have had only one purpose: to
blacken Mr Mortimore, and thereby his report. We believe that,
in doing so, WorleyParsons and ECGD have rendered a grave injustice
to a brave and honourable professional whose views deserve respect,
not baseless denigration.
37. We also consider that many of the responses to Mr
Mortimore's criticisms of the selection process for SPC 2888 provided
in the WorleyParsons report by both BP/BTC Co. and WorleyParsons
themselves are inadequate and do not serve as credible rebuttals
to serious concerns. Thus:
(i) BP's response to Mr. Mortimore's point that "no
pipeline owner has been identified who specifies this product
for this exact purpose, anywhere in the world," is:
"If we adopted the same negative attitude to
the selection of line pipe coatings, we would still be applying
coal tar and asphalt enamel to wire brushed steel surfaces, rather
than benefiting from the superior performance we get from FBE
and three layer FBE-polyolefin coatings."[73]
This wholly fails to even address the question;
instead of a reasoned explanation for choosing SPC 2888 on its
merits, it provides only a hortatory suggestion that it is worth
taking a risk on an unproven material for the sake of "progress".
Likewise, the WorleyParsons answer focuses on an almost ideological
belief that this coating is "very important" and "a
positive step change"; no proof is offered that it is, however,
safe.
(ii) This pattern of failing to answer the question is
repeated throughout Section 4 of the WorleyParsons report, which
deals with Mr. Mortimore's criticisms. Perhaps the most important
of these charges is his point that, "It is clearly a serious
mistake for BP to nominate one material only,"[74]
for reasons of leverage and efficacy as well as to pre-empt any
allegations of corruption.
BP/BTC does not make any response to this point
at all; WorleyParsons "disagree", but only on the grounds
that "we do not believe it is acceptable to let the pipeline
contractor select the field joint coating to be used." Again,
this is simply irrelevant; the suggestion is not that the contractor
be allowed to select the coating personally, but that BP ought
to have nominated several materials to ensure a more robust and
controversy-free selection process, something that plainly did
not occur.
(iii) Mr Mortimore points out that the coating material
contains "a known irritant", which the safety data sheet
misses out, and thus is unlikely to "totally" meet BP's
HSE policy. BP again makes no answer; WorleyParsons simply repeats
HSE policy on paper, and says that because the material has allegedly
been used in North America, "it is hard to believe it did
not meet BTC HSE requirements."[75]
WorleyParsons may find many things hard to believe, but Mr Mortimore's
evidence suggests that SPC 2888 failed BP's HSE policy; nowhere
in the response is that dealt with.
3. BROADER ISSUES
AND LESSONS
A. Are there other areas where ECGD's due diligence was
inadequate?
38. ECGD's Failure to Respond to EIA Comments and Concerns
As the Committee will know from its previous inquiries into
the ECGD's handling of the Ilisu Dam, the ECGD set a precedent
by releasing its own consultants' assessments of both the Resettlement
Action Plan for Ilisu and the project's environmental impact assessment
(EIA). Both can be found on the Department's website.
In the case of BTC, concerned NGOs submitted extensive and
detailed comments on the project's EIA, identifying over 170 violations
of World Bank and other international standards.[76]
Despite being presented with this analysis, the Department
has failed to offer a detailed response to the concerns raised,
merely issuing a statement that they had been taken into account.
Moreover, unlike with Ilisu, the Department's assessment of the
EIA for BTC has not been released.
This stepping back from the Ilisu precedent can only be regarded
as an unfortunate regression from the increasing standards of
openness promised by the Government. We understand it was motivated
by concern that the NGOs might initiate a judicial review of the
project. If so, this might reasonably be held to imply that the
Department was less than confident of its grounds for rejecting
NGO criticisms of the project and that publication of a detailed
response would indeed contain grounds for a judicial review. It
might therefore be argued that the ECGD acted in a way that was
detrimental to the government's stated policy of improving the
accountability of public institutions.
We believe that this concern can only be laid to rest by
the ECGD releasing the report prepared on the project by the Business
Principles Unit for the Underwriting Committee. We would urge
the Committee to request this report and to validate both that
it addressed the concerns raised by NGOs and that its recommendations
were adopted in full by the Underwriting Committee.
39. Environmental and Technical Risks in Turkey
ECGD's failure of due diligence on the SPC 2888 field joint
coating in Azerbaijan and Georgia is matched by equally disturbing
failures on reports of systemic technical mismanagement in the
Turkey section. In this respect, we would refer the committee
to our submissions of 14 July 2004.
The concerns regarding the technical failures in Turkey were
first reported in the Independent of 26 June. They were based
on the statements of four senior pipeline professionals who had
worked on the pipeline, and who reported that the project is:
not hiring proper specialists to advise on engineering,
including on crossing seismic faults in the earthquake-prone region;
using inappropriate materials and construction
methods, which will not perform the function they are needed for;
not following construction design specifications
and procedures;
failing to carry out checks or keep records on
construction quality;
using staff without proper training or qualifications;
ignoring environmental or health and safety requirements.
These failures undermine the safety and technical integrity
of the pipeline, and risk causing a major spill. The problems
are of a systemic nature, going to the heart of the project's
management systems, and indicate that BP has completely lost control
of the Turkish section of the project.
The Baku Ceyhan Campaign wrote to ECGD, and to the Minister
for Trade and other ministers, on 15 July. It enclosed the statements
of the four professionals, and called on ECGD to carry out an
independent audit of the problems. Now, more than six weeks after
the letter was sent, neither ECGD nor the minister have even replied
to the letter.
There are disturbing parallels with the field joint coatings
case discussed in this submission, both in the nature of the issue,
and in ECGD's handling of it. As with the field joint coatings,
the problems were not picked up by ECGD's own monitoring. But
whereas in this submission we have criticised ECGD's investigation
for its inadequacy, in the Turkey case, ECGD has shown no sign
whatsoever of investigating the reports, let alone taking action.
Again, we offered to facilitate meetings with the professionals
concerned (including one of them before ECGD had made its decision
to approve support for the project)[77],
offers which again were not taken up.
We submit that the evidence provided by the four professionals
raises serious questions over the ECGD's due diligence both prior
to approving support for the BTC pipeline and subsequentlythe
more so since ECGD was warned of the problems, not least by BP's
own advisory panel,[78]
well in advance of its final decision to support the project in
February 2004. There is reasonable suspicion that ECGD has again
relied on the promises and reassurances of BP rather than investigating
thoroughly and independently the concerns raised by experts who
have worked on the pipeline. We believe this approach to be unacceptable.
40. Human Rights Due Diligence
The Kurdish Human Rights Project (KHRP) and The Corner House
have submitted evidence to the Committee separately on concerns
over the due diligence undertaken by the ECGD on the human rights
impacts of the project. We would refer the committee to this evidence,
noting in particular:
(i) The concern that ECGD failed to take account of the
wider human rights context in which the project was taking place,
notably the implications of the lack of freedom of expression
in both Turkey and Azerbaijan.
(ii) The concern that the Foreign Office (FCO) may have
misled the ECGD over advice it received from Amnesty International
over the case of Ferhat Kaya, the Turkish human rights defender
who was arrested and allegedly tortured as a result of his work
on the BTC project.
(iii) Although Amnesty told the FCO that KHRP was the
organisation most closely following the case, the FCO did not
contact KHRP for further information. This parallels the due diligence
failures we have outlined in relation to technical concerns.
(iv) The concern that ECGD failed to seek any documentation
relating to the 38 cases relating to the project that have now
been taken to the European Court of Human Rights by affected villagers
in Turkey.
(iv) The concern that the Foreign Office has failed to
investigate the bugging of emails from campaigners working on
BTC by the Azeri government.
B. What policy lessons can be learned from such inadequacies?
41. Notwithstanding our wider concerns that the BTC project
fails to fit with the ECGD's stated commitment to sustainable
development, we believe that the project holds important lessons
for the ECGD.
42. On the evidence available to us, we would conclude
that:
The ECGD's due diligence of BTC was insufficiently
rigorous and that it relied to a compromising extent on the project
sponsor for information and reassurances over the many detailed
concerns that have been raised by independent parties;
The ECGD's monitoring procedures failed to alert
ECGD to a range of problems that should have been picked up, notably
the problems that have arisen with the field joint coating system;
The human rights due diligence took insufficient
account of the context in which the project was being implemented
and the abuses that were likely to result;
The coating problem constitutedand still
constitutesa clear material threat to the project's timing,
safety and viability. The Minister's judgment that the field coating
problem was limited does not stand up to scrutiny. In our view,
BP was therefore in breach of its obligations by not reporting
the coatings failures.
43. We would recommend that immediate steps be taken
to address these institutional failures and that the project loans
be suspended until a full independent assessment of the project's
safety has been completed.
Baku Ceyhan Campaign
Corner House
Friends of the Earth (England, Wales and Northern Ireland)
Kurdish Human Rights Project
PLATFORM
6 September 2004
For summary, see Appendix B of Baku Ceyhan Campaign's first submission
to Committee, March 2004.
Letter from the Kurdish Human Rights Project and The
Corner House to the Trade and Industry Committee
Further to the Memorandum submitted by Corner House and the
Kurdish Human Rights Project on 6 July 2004 regarding the quality
of the human rights advice supplied by the Foreign Office to the
ECGD on the BTC pipeline project, we are attaching an exchange
of letters with the Foreign Office on this issue. We would like
to submit the correspondence as additional evidence to the Committee's
inquiry into the BTC pipeline project.
As you will note from the exchange of letters, the Foreign
Office has as yet made no response to the concerns we raised over
the misrepresentation of the advice received from Amnesty by Mr
MacShane with regard to Ferhat Kaya, the human rights defender
arrested and allegedly tortured as a result of his work on the
BTC project.
We have also challenged the FCO's position with regard to
the bugging of emails from NGOs by the Azeri government and believe
that the Foreign Office has been evasive in its replies to other
questions on which we sought assurance, notably with regard to
consideration of the wider human rights context in which the BTC
project is taking place
We hope that the additional evidence will be of assistance
to the Committee in its inquiry.
Kerim Yildiz
Kurdish Human Rights Project
Nicholas Hildyard
The Corner House
7 September 2004
Letter from The Minister of State, Foreign & Commonwealth
Office to The Corner House
Thank you for your letter of 6 July to the Foreign Secretary
and Mike O'Brien MP. Dr MacShane is Minister responsible for Turkey
and I am replying as Duty Minister in his absence.
I am surprised that your letter refers back to the letter
from the Kurdish Human Rights Project (KHRP) dated 8 January 2004
when the KHRP wrote to Mike O'Brien MP on the same subject on
7 May 2004. This latest letter repeats many of the issues raised
in the letter of 7 May to which I responded on 24 June 2004. I
enclose copies of both these letters for your information.
As I stated in my June letter, our Embassy in Ankara has
investigated the case of Mr Kaya. Mr Kaya's lawyer did indeed
tell our Embassy in May that Mr Kaya believed that the police
wanted to arrest him for his involvement in human rights campaigning
over the BTC pipeline and this is reflected in the statement from
Mr Kaya attached to your letter. A senior DEHAP official has recently
told us that he believes Mr Kaya's claims. Other sources we consulted
took a different view. We have still not seen clear evidence to
suggest that Erzurum Court's request for information on Mr Kaya
and his subsequent detention were linked to the BTC pipeline.
The indictments against Mr Kaya make no reference to his activities
in connection with the BTC pipeline. We will continue to monitor
Mr Kaya's situation closely, particularly in relation to the allegations
of torture. Senior officials have raised the case of Mr Kaya with
the Turkish authorities, most recently at the last round of our
Human Rights Dialogue with Turkey on 15 July in London. You will
be aware that the trial of 11 police accused of beating and torturing
Ferhat Kaya on 5 May began on 20 June.
I note that you state there are a number of applications
pending at the European Court of Human Rights that relate to the
BTC project. To date ECGD has received no substantiated evidence
that the project implementers are not meeting their commitments
regarding compensation and protection of human rights. Indeed
the second review of the independent Social and Resettlement Action
Plan Expert Panel dated February 2004 (www.caspiandevelopmentandexport.comiASP/PD_BTC.asp)
assessed that the BTC project implementers were meeting their
commitments as defined in the Resettlement Action Plan and the
Contractor Control Plans, although it recommended the strengthening
of project performance in a number of specific areas.
Your letter alleges that the Azerbaijan authorities are monitoring
the email correspondence of Mr Gulaliyev (employed as a monitor
of the implementation of the BTC pipeline): This is a matter that
you may wish to take up with the Azeri Government. Under Article
I of the ECHR the UK is obliged to secure to everyone within its
jurisdiction the rights and freedoms set out in the Convention.
But this does not extend to a general obligation to ensure that
other States are complying with their ECHR obligations. Whether
they are doing so can of course be tested in the European Court
of Human Rights, as is now occurring.
I understand from the ECGD that they did take account of
the requirements of the ECHR in their decision to provide support
for the BTC project in December 2003. For the purpose of reaching
a decision, advice had previously been sought from and provided
by, amongst others, the FCO. This advice covered a wide range
of issues including those mentioned in your letter. In all cases
the advice was that, if the project was implemented in accordance
with the commitments made by the project sponsor, there was no
reason for the ECGD to withhold support on human rights grounds.
A note of the ECGD's decision can be accessed on its website (www.ecgd.gov.uk).
I do not intend to provide you with copies of the documents and
other exchanges requested in your letter, as the ECGD and the
FCO consider that the information contained in these falls within
exemption no.2 (Internal discussion and. advice) of the Code of
Practice on Access to Government Information and it would not
be in the public interest to disclose it.
The Government welcomes. NGO and other public contributions
to its assessments of projects. It is also welcome that this scrutiny
extends to the construction phase. However the Government is not
responsible for ongoing project issues that are properly the responsibility
of the project managers. Once cover has been issued the ECGD's
role is to monitor a project's implementation to ensure that the
agreed project standards are being met. I am confident that, in
conjunction with the wider BTC lender group and with the assistance
of its independent consultants, it is rigorously carrying out
this role with respect to the BTC pipeline project.
Baroness Symons
2 August 2004
Letter from the Minister for Europe, Foreign &
Commonwealth Office to Kurdish Human Rights Project
Thank you for your letter of 7 May to Mike O'Brien, copied
to other Whitehall Departments, as well as officials from the
EBRD, the ECGD and the World Bank. I am replying as the Minister
for Europe.
I welcome the adoption by Turkey over the last two years
of a series of constitutional and legislative reforms that have
resulted in substantial improvement in the human rights situation
in Turkey. I am encouraged by recent changes including the release
of Leyla Zana, the commencement of broadcasting in minority languages,
and the passing of a new press law which contains further measures
to increase the freedom of the press. I believe that the pre-accession
process continues to underpin substantial reform in the country.
However, I would agree that yet more needs to be done to translate
the reforms passed into change on the ground. We take every opportunity
to urge the Turkish government to make rapid and demonstrable
progress in the practical implementation of the reforms they have
passed to safeguard human rights. The Prime Minister stressed
the importance of effective implementation of reforms at the first
UK/Turkey Summit on 17 May in Ankara, and Lord Falconer raised
concerns about human rights with Prime Minister Erdogan during
his visit to the UK at the end of May.
As part of the UK's support for Turkey's EU accession bid,
we hold a bilateral Human Rights dialogue to encourage further
progress in particular areas and to raise individual cases. The
next round of the dialogue will be held in July this year. In
addition, the British Embassy in Ankara monitors human rights
closely, attends key trials and raises individual cases with the
Turkish authorities.
Our Embassy in Ankara has investigated the case of Mr Kaya.
We have not yet seen clear evidence to suggest that Erzurum Court's
request for information on Mr Kaya and his subsequent detention
are connected to the BTC pipeline. Furthermore, BOTAS/DSA have
advised our contacts in Turkey that they had arranged no meeting
with Mr Kaya for May 2004. BTC representatives have also advised
that no meeting had been arranged with them in May 2004. We will,
however, continue to monitor Mr Kaya's situation closely, particularly
in relation to the allegations of torture.
The BTC pipeline is subject to a strict monitoring regime
by external organisations to ensure that it is constructed to
the highest standards. Land expropriation and compensation is
being monitored by the Social and Resettlement Action Plan (SRAP)
Expert Panel, whose recent report on its review conducted in February
2004 is available on the project website (www.caspiandevelopmentandexport.com).
The review included visiting the pipeline route in the Ardahan
province in Turkey and the report states that: "Land acquisition
activities in Turkey were observed by the SRAP Monitoring Panel
to be carried out in compliance with the Resettlement Action Plan,
applicable Turkish laws and World Bank Group policies".
Denis MacShane
Minister for Europe
24 June 2004
Letter from Kurdish Human Rights Project and The Corner
House to Mike O'Brien MP, Minister of State for Trade, Investment
and Foreign Affairs, Foreign and Commonwealth Office
BTC CAMPAIGNERALLEGED
TORTURE OR
ILL-TREATMENT
IN TURKEY
We are writing to express our gravest concern over the detention
and alleged torture or ill-treatment of a prominent human rights
defender following his work to protect the rights of Turkish citizens
affected by BP's UK-funded Baku-Tbilisi-Ceyhan oil pipeline. There
is strong and direct evidence of a link between his intimidation
and detention and his work in connection with the pipeline.
It is our understanding that Mr Ferhat Kaya, a former deputy
chair of DEHAP in the central district of Ardahan, had been working
to document the case of an individual whose land was being used
for the pipeline without having been legally expropriated or compensation
having been paid on 5 May 2004 he informed BOTAS, the company
building the pipeline under contract to BP, of his concerns and
he had been promised a meeting on Monday 10 May 2004. However,
he was then arrested and now remains in detention in Ardahan.
Witnesses and relatives yesterday observed blood on his clothes
and deep cuts on his arms and elsewhere following one day in detention.
According to information obtained by KHRP, a medical report is
consistent with allegations of torture. He was also derided as
a "terrorist" by the court prosecutor.
As you will know, witnesses, human rights and environmental
groups believe this is Mr Kaya's second detention in connection
with his work to highlight concerns over the pipeline. Last year,
he received death threats prior to meeting with the Italian Export
Credit Agency to inform them about social and environmental concerns
associated with the pipeline. He was later detained. Assurances
from Mr MacShane, the Foreign Office minister, that Amnesty International
had found no evidence of a connection between this detention and
his work in relation to the BTC pipeline have since been found
to be unwarranted: Amnesty International has not even investigated
the case.
Mr Kaya has been involved for some time in mitigating the
impacts of the BTC project by ensuring that local people obtain
the compensation to which they are entitled and that their rights
under the European Convention on Human Rights are respected. He
has assisted 38 villagers in bringing cases to the European Court
of Human Rights complaining of multiple violations of the ECHR.
This also reflects the ongoing failure of BP to fulfil its legal
responsibilities to people affected by the pipeline and to make
good on its pledges that nobody would be disadvantaged as a result
of the project.
We believe that it is incumbent on the British government,
as a sponsor of the BTC pipeline, to ensure that those like Mr
Kaya who seek to improve the project are not victimised for speaking
out. BP has specifically requested that local people help in identifying
problems with the project's implementation. For this to result
in detention and allegations of torture, as in this case, is not
only unacceptable but a savage indictment of the project and of
Turkey's commitment to human rights. Turkey is required to achieve
the "stability of institutions guaranteeing democracy, human
rights and respect for a protection of minorities" in order
to meet EU accession requirements; its accession bid is due to
be reconsidered in December 2004. Incidents such as the arrest
and alleged torture of Mr Kaya strongly indicate that legislative
reforms aimed at securing human rights in Turkey have failed to
be implemented on the ground.
We urge you to use your best offices to investigate the circumstances
of his detention and alleged torture or ill-treatment; to obtain
a guarantee that his human rights are respected; and to press
for his immediate release.
Kerim Yildiz
Executive Director, Kurdish Human Rights Projects
Nicholas Hildyard
Corner House
7 May 2004
cc. Secretary of State for Foreign and Commonwealth Affairs
Secretary of State for the Environment, Food and Rural Affairs
Secretary of State for International Development
Chief Secretary to the Treasury
Trade and Industry Committee
Environmental Audit Committee
Secretary General, EBRD
Chief Executive, ECGD
Tom Scholar, Executive Director, World Bank
Simon Ray, Executive Director, EBRD
1
Mr Weiss, ECGD, Oral Evidence to Trade and Industry Committee,
11 May 2004. See, for example, Mr Weiss' reply to Q496: ".
. . the quality of the coating of the pipeline in the BTC case
was fully assessed by Parsons, the engineers, to meet the highest
standards . . ." Back
2
Confirmed to Nicholas Hildyard by Matthew Trainer, ECGD, telephone
conversation, August 2004. Back
3
WorleyParsons report 2004, p 2. Back
4
See for example, responses by Mr Mike O'Brien MP to questions
tabled by Mr Simon Thomas MP, Hansard, 28 June 2004: Column
50W. Back
5
ECGD, Note on BTC Decision, 17 December 2004. Back
6
John Weiss, Letter to Trade and Industry Committee, 19 July 2004. Back
7
BP, "Caspian Connection", Frontiers, August 2003,
pp 18-25: "However, once the sections of pipe are welded
together in the field, each of the welded field joints must also
be protected. `Traditionally, heat shrink sleeves have been used",
explains Parker (Ian Parker, BP's engineering manager during the
design stage and now responsible for BTC's technical development
programme) "but these are not as resistant to damage as the
polyethylene pipeline coating. So we conducted a test programme
to find a better alternative that can be applied to the field
joints. The end results is that the pipe sections are supplied
from the coating plants with the polyethylene coating cut back
a short distance to expose the underlying FBE layer. Once the
weld is safe in the field, a liquid urethane modified epoxy can
be sprayed or hand-applied across the weld which adheres to the
exposed FBE layer as the primary barrier to moisture, but which
also sticks to the polyethylene as a secondary barrier. As
far as we know, this is the first time that such a system has
been employed. " (Italics added). Back
8
Mr Weiss's letter emphasises that, "ECGD's main concern is
that a project is built to cost, on time and to agreed standards."
There is no acknowledgement of the conflicting imperatives here:
that the pressures to finish a project on time and to agreed costs
inevitably leads contractors to cut corners and to subvert rather
than adhere to standards. That being the case, it is incumbent
on ECGD to carry out extensive due diligence procedures not merely
"well before the construction process" but both before
and during it to ensure that project quality does not succumb
to fiscal pressures. Back
9
Minister for Trade, Reply to Corner House, 17 March 2004. "BTC
Co did not inform the ECGD about the problems with the field joint
coating material." Back
10
Melissa Jones and Michael Gillard, "The Devil's tears",
Red Pepper, 1 May 2004. Back
11
WorleyParsons 2004, p 8. Back
12
BP, "Caspian Connection", Frontiers, August 2003,
p 22. Back
13
Letter from Mathew Trainer to Corner House, March 2004, p 2. Back
14
Letter from Mathew Trainer to Corner House, March 2004, p 2: ".
. . ECGD does not have this specific information". Back
15
On this point, the report is at times somewhat misleading, emphasising
the history of use of the product, without referring to the uncoated
nature of the pipes in its previous applications. For example,
the executive summary of the report states that "These liquid
epoxy coatings are becoming an industry standard for . . . field
joint coating" (page 3). Only on a detailed reading of the
full report does it become clear that previous use of the coating
has all been on uncoated pipes. Back
16
WorleyParsons 2004, p 15. Back
17
WorleyParsons 2004, p 18. Back
18
John Weiss, Letter to Trade and Industry Committee, 19 July 2004,
p 3: "the coating . . . has a track record in similar conditions
in a significant number of other pipelines." Back
19
For example, it may have been used elsewhere on uncoated pipes
(applied directly onto the steel), or on pipes coated with epoxy
(a material with totally different chemistry from polyethylene). Back
20
Mike O'Brien Minister of State for Trade, Investment and Foreign
Affairs, response to Simon Thomas MP written question "what
assessment has been made into the use of SPC 2888 by major pipelines
other than the Baku-Tbilisi-Ceyhan pipeline where the pipeline
is coated with a three layer, high density, polyethylene coating",
Mr O'Brien replied (without qualification) that "The WorleyParsons
report on the field joint coating issue (SPC 2888), included a
case history of use of SPC 2888 on other pipelines. It showed
that SPC 2888 had been used extensively in North America."
Hansard 28 June 2004: Column 50W, `SPC 2888.' Back
21
Minister for Trade, Reply to Corner House, 17 March 2004. "BTC
Co did not inform the ECGD about the problems with the field joint
coating material." Back
22
Melissa Jones and Michael Gillard, "The Devil's tears",
Red Pepper, 1 May 2004. Back
23
ECGD Minister, Letter to Corner House, 19th March 2004. Back
24
ECGD Minister, Letter to Corner House, 19th March 2004: "There
has been no problem that has had a materially adverse effect on
the project and this was reflected in the brief duration of the
halt in work on the pipeline, which remains on time and on budget
for completion in 2005. As a result of the limited nature of the
problem, BTC Co was under no obligation to report the findings
of the report to ECGD. Back
25
ECGD Minister, Letter to Corner House, 19 March 2004: "BTC
Co and BP have provided ECGD with more information about the coating,
in response to allegations about its suitability." Back
26
"BP accused of cover-up in pipeline deal", The Sunday
Times, 15 February 2004. Back
27
WorleyParsons 2004, p 20. Back
28
We understand from Mr Mortimore that the SPC coating tends to
crack in cold weather even if it has been applied at warmer temperatures,
or with proper curing. The BP testing in winter 2003-04 apparently
only looked at joints coated after the beginning of November 2003.
Nor does it consider the separate problem on non-adhesion of the
SPC coating to polyethylene. Back
29
WorleyParsons 2004, p 2. Back
30
WorleyParsons 2004, p 2, "We have not independently verified
that this information is comprehensive, complete, accurate or
up-to-date." Back
31
WorleyParsons, p 22. Back
32
It seems implausible, given the furore over coatings that had
been created by the Sunday Times allegations the month
before D'Appolonia's visit, that the company could not have been
aware of the problem. Indeed, D'Appolonia's major criticism of
BTC Co.'s work is that almost 300km of the Azeri section of the
pipeline had been strung together without being buried, due to
inadequate reinstatement work (D'Appolonia, Report of the Post-Financial
Close Independent Environmental Consultant, pp 8-24). In other
words, ample opportunity was available to the consultants to observe
how effectively the new coating processes were working; the complete
omission of the coatings issue from D'Appolonia's report shows
that such opportunities were unfortunately passed up. Back
33
WorleyParsons, 2004, p 14. "It is our understanding that
Mr Mortimore, a friend of a BP employee, reviewed the project's
Field Joint Coating Specification . . . as a favour. After he
issued his comments he asked to be paid for his effort . . . Mr
Mortimore's comments were fairly general with a lack of specific
technical details or references." Back
34
A parallel would appear to be that in a court case a judge decided
not to hear the defence case at all, on grounds that the prosecution
had asserted that the defence case was unreliable. Back
35
Hansard 28 Jun 2004 : Column 50W. Reply by Mr. Mike O'Brien
to Mr Simon Thomas: "In February 2004 ECGD were informed
by BP that an independent BP audit had been carried out into the
procurement process of the SPC 2888 field joint coating for the
Baku-Tbilisi-Ceyhan pipeline. The results of this investigation
(that the allegations were "unfounded") were conveyed
to ECGD at the same time." Back
36
"BP accused of cover-up in pipeline deal", The Sunday
Times, 15 February 2004. Back
37
We do not claim the competence to speak on the technical aspects
of the coating system's effectiveness. Indeed, we understand that
qualified experts are making their own submissions and responses
to the Committee. Rather, we wish here to highlight those aspects
of the WorleyParsons' report that relate to concerns over ECGD's
due diligence. Back
38
WorleyParsons 2004, p 15. Back
39
WorleyParsons 2004, p 9. Back
40
WorleyParsons 2004, p 10. Back
41
Advantica Intercoat Adhesion Investigation, January 2003. Back
42
WorleyParsons 2004, p 9. It is not clear whether grit blasting
of the polyethylene was actually applied in the final specification;
even if it was, there is no comment here as to the adequacy of
its adhesion. Back
43
In fact, compounding potential confusion, there are several instances
in the WorleyParsons report in which the capacity of SPC 2888
to adhere to polyethylene (PE), which again it does not do, are
confused or elided with its capacity to adhere to fusion-based
epoxy (FBE), the first layer of the coating. SPC 2888 does indeed
stick well to FBE, and as the "toe" of the joint is
comprised of FBE, that adhesion will indeed be called into action.
However, that does not override SPC 2888's inability to stick
to polyethylene, which will inevitably result in widespread leaks
and water ingress. The elision of the two may lead concerned parties
to mistakenly assume that because the coating sticks to FBE, it
will also stick to PE. Back
44
WorleyParsons 2004, p 5. Back
45
WorleyParsons 2004, p 8 (emphasis added). Back
46
The Field Joint Coating Selection Testing Program, carried out
by Advantica in March-July 2002. Back
47
WorleyParsons 2004, p 6. Back
48
WorleyParsons 2004, p 5. Back
49
Two reasons are given for this-(i) that heat shrink sleeves could
not be used for certain fittings, only for girth welds; and (ii)
that they showed poor performance. However, both reasons are irregular.
First, while a commercial decision might later be made to use
only liquid coatings, rather than heat shrink sleeves or a combination
of both, based on cost or performance, it does not make sense
to exclude evaluation of their relative performance. Second, if
the performance was poor, it is not clear why the heat shrink
sleeves could not be included in the ranking and ranked bottom.
The decision to exclude sleeves in the comparison does not help
reassure us that the selection was not pre-judged. Back
50
The Pipeline Coatings/Trench Backfill System Optimisation Study,
carried out by Advantica in January 2003. Back
51
WorleyParsons 2004, p 7. Back
52
WorleyParsons 2004, p 3. NB The size of backfill material used
(as stated in the final specification) has not been disclosed. Back
53
WorleyParsons 2004, p 9. Back
54
WorleyParsons 2004, p 12. Back
55
WorleyParsons 2004, pp 3, 12. Back
56
John Weiss, letter to David Lees, 19 July 2004: "the coating
was subjected to rigorous testing." Back
57
Minister for Trade, Reply to Corner House, 17 March 2004. "I
understand that BTC Co made their choice of coating as a result
of an extensive technical exercise, which concluded that the SPC
coating was the most suitable." Back
58
WorleyParsons 2004, p 11. Back
59
WorleyParsons 2004, p 22. Back
60
The WorleyParsons report states that "At low ambient temperatures
cure [of SPC 2888] over the PE overlap may be slower than over
steel and some post application cure may be required", and
that SPC 2888 has "limited adhesion" to plastic (HDPE),
but claims that the same problem exists for other field joint
coating systems (pp 9-10). Back
61
WorleyParsons 2004, p 22. Back
62
Or instruct its consultants to do so. Back
63
Letter from ECGD Minister to Corner House and others, 17 March
2004: "Work was halted on the application of coating for
a brief time only (other work continued), and pipe joints with
hairline cracks were identified in the process of transferring
the coated sections into the ground and were repaired prior to
burial." Back
64
By this we mean tested physically directly (eg visually, or by
the cross-cut and peel technique) as opposed to remotely after
burial (eg by hydrostatic testing or DCVG tests), as the latter
are clearly more limited in detecting coating problems. Back
65
WorleyParsons 2004, pp 19-22. In Azerbaijan, 261 joints were inspected,
all applied between 7 November 2003 and 11 January 2004. It is
not reported how many joints were inspected in Georgia. Back
66
This appears to be because joints were only observed during the
construction process itself-so performance in the cold was only
seen for joints that were actually coated in the cold. Back
67
By the time the cracking problem was discovered in early November,
at least 90km of pipeline had been welded in Azerbaijan, and 40km
had been laid in the trench. In Georgia, over 45km had been welded,
and about 20km had been laid. Much of this will also have been
backfilled (buried). This 60km that had been laid in Georgia and
Azerbaijan, containing over 5,000 joints coated with the SPC coating,
(and much of the further 75km, or 6,200 joints, that had been
welded) did not use the modified curing process, nor have full-time
coating inspectors present, nor was it tested for cracking. See:
David Woodward, President of BP Azerbaijan, at press conference,
reported in Interfax Central Asia & Caucasus Business Report,
10/11/03, "Baku-Ceyhan project costs reach $1.5 bln";
45km welded my mid-October. Georgian International Oil Corporation,
reported in Interfax Petroleum Report, 22/10/03, "Georgian
part of BTC pipeline 20% completed"; 16km laid by early October
(Mott MacDonald, Pre-Financial Close Environmental & Social
Construction Monitoring, Sept-Oct 2003, report published 17/12/03,
pp 4, 20-21, 34-35). 24km laid by mid-November (Georgian International
Oil Corporation, reported in Interfax News Bulletin Report, 24/11/03,
"Main trunk pipeline building on track in Georgia"). Back
68
WorleyParsons 2004, p 20. Back
69
WorleyParsons 2004, p 22. Back
70
WorleyParsons 2004, p 4: "The subject of pre-heat and post-heating
during winter work had been openly discussed and all parties were
aware of the requirements." Back
71
WorleyParsons 2004, p 24: "The field joint coating effort
was shutdown only for the short period during which pre-heat and
post heat parameters were developed and tested in the field." Back
72
WorleyParsons, 2004, p 14. "It is our understanding that
Mr Mortimore, a friend of a BP employee, reviewed the project's
Field Joint Coating Specification . . . as a favour. After he
issued his comments he asked to be paid for his effort . . . Mr
Mortimore's comments were fairly general with a lack of specific
technical details or references." Back
73
WorleyParsons 2004, p 15. Back
74
WorleyParsons 2004, p 17. Back
75
WorleyParsons 2004, pp 18-19. Back
76
Corner House, Baku Ceyhan Campaign, Kurdish Human Rights Project,
Platform and others, "Review of the Environmental Impact
Assessment for the Turkish section of the Baku-Tbilisi-Ceyhan
oil pipeline", 8 October 2003. Back
77
Corner House, Friends of the Earth (England, Wales and Northern
Ireland), Baku Ceyhan Campaign and Platform, Letter to Jeanette
Swindon, 10 November 2003. Back
78
Caspian Advisory Development Panel, Turkey Report, December 2003,
available from www.caspiandevelopmentandexport.com. Back
|