APPENDIX 4
Response from Derek Mortimore to ECGD
submission
BPBTC PIPELINE PROJECT
ECGD REPORT TO
TRADE & INDUSTRY
COMMITTEE RE
BTC
Response from Derek Mortimore
A copy of this report has been given to me by
the committee for my review. I do not propose to comment on the
financial aspects of the workings of ECGD but their document contains
a technical report on the field joint coating from Worley Parsons(WP),
carried out for ECGD, which contains many inaccuracies and in
which they make personal statements about me and try to refute
comments I had made when I reviewed the field joint coating specification
in November 2002 at the request of BP.
I find it extraordinary that the introductory
paragraphs of WP's report refer to my relationship with BP in
a derogatory manner and try to impung both my character and my
professionalism. Anyone reading this report would have to ask
the question:
"If Worley Parsons were working for ECGD
and no other party, how could they obtain erroneous information
regarding Mortimore's involvement with BP and why would they feel
it necessary to put such inaccurate comments into a technical
audit document?"
They state:
"After he issued his comments he asked to
be paid for his effort."
Totally untrue.
This refers to my review of the field joint
coating specification that was given to me in BP's offices in
Baku in October 2002. They make no reference to the documentary
reviews I had been carrying out from May 2002 thru October 2002
or the other instructions I had accepted from BP up to that point.
Why not? Obviously they were not aware of them neither could they
have had any details of any of the activities I had undertaken
in accordance with such instructions. In other words, their informant
in BP had only given them the information he wanted to in order
that they would gain a false impression of my involvement.
They further state:
"Since a BP employee had asked Mr Mortimore
to review the documents, BP issued Mr Mortimore a contract to
cover the work he did."
This is an appalling travesty of the truth.
In February 2002 1 was contacted by BP's ACG
(Offshore) group and asked to undertake a very urgent assignment
to secure the establishment of a new pipe coating facility in
Azerbaijan. I accepted instructions and was working in Baku 72
hours later. During this engagement and in a social environment,
an old friend in BP's BTC group asked for some advice which I
willingly gave.
Present at that meeting was my employer in the
ACG group and he suggested to Paul Stretchthe BP man from
the BTC group that he make use of me as I was the only BP pipe
coating expert in Azerbaijan. Subsequently, Stretch asked me to
review one short document and give him an opinion. This document
was in connection with the field joint coating. I was so concerned
by what I read that I informed Paul Stretch that the writer, Trevor
Osborne, was wrong and that BP needed to assess properly all available
technologies for the field joint coating because at that stage
this had clearly not been done and if they proceeded on the basis
of the very limited research outlined in the first document, then
they would come to the wrong conclusion and make a very serious
mistake.
You should note that even today, all the available
technologies have never been looked at by the project team and
their specification was written on the basis of a pre determined
conclusion.
My comments to BP led to me being asked to review
other documents and later to undertake various tasks all at the
same day rate that had been agreed with the offshore group.
For the record, I was previously involved in
the BTC project in 2001 at the pre-engineering stage at the direct
request of Bob Schofield, a long time friend, who was then the
project manager for BTC. At his suggestion, I attended his offices
and gave a film show and talk to his staff on the philosophy that
needed to be developed for the life time protection of the BTC
pipeline and the benefits of three layer HDPE for the primary
protection. I made a very strong recommendation for this system
and I answered many questions from his team regarding both factory
and field joint coating. You should note that at that time, the
consultants were recommending a different factory applied coating
but Bob Schofield agreed with me that three layer HDPE was their
best option.
I gave a full day of my time and no fee or even
travel expenses were sought.
WP have chosen to question the fact that I had
made comments on "non-technical issues, ie contractual, costs,
contractor capabilities, trade laws, insurance and contractor
claims"of course I did, that was my duty to my client.
All of these matters had been discussed in BP's Baku office and
I had been specifically asked to comment on them but clearly their
informant in BP was not aware of the instructions from BP Baku.
WP did not contact me at any time and clearly
did not verify facts.
The way WP worded their introduction is no more
than an attempt at a cheap smear, it is based on false information
provided by somebody within the project who clearly bore malice
towards me, I have no problem with personal malicious attacks
from people who know that they are in the wrong but I cannot understand
why a company of WP's standing allowed themselves to be used as
a conduit for this particularly pernicious attack. To have made
these comments in their report demonstrates a clear bias and in
my opinion compromises the document's worth to the point of invalidity.
It is noteworthy that they comment only on parts
of one document I had written (they must not have been given any
of the many others) and amazingly they print what purports to
be BP/BTC comments on my report. You should note that these "BP/BTC"
comments have never been made at any time previously!
If these are BP comments then this is the first
time that BP have responded in writing to any comments I have
made. It has only taken from 12 November 2002 until this report
dated 15 July 2004 for BP to respond to issues that required urgent
attention two years ago!
In order to assist the committee through this
"comment/counter comment" cycle I attach herewith following
documents to help you:
My response to Worley Parsons document.
Copy of my letter to CEOWorley
Parsons.
BP Field Joint Coating Specification
given to me in November 2002.
My original critique of this specification
made in November 2002.
An explanation of science involved,
prepared by Dr John Leeds, a leading authority in the field.
I hope this documentation will help and both
myself and Dr Leeds remain ready to appear in person if required.
BPBTC PIPELINE
DEREK MORTIMORE'S
RESPONSE TO
WORLEYPARSONS
DOCUMENT
WP's words are printed thus: This desktop
study . . .
My words are printed thus: This desktop
study . . .
PAGE 2, ITEM
1. INTRODUCTION
Para 4Also, the polyethylene and adhesive
layers are cut back an additional 50 mm leaving a fusion bonded
epoxy (FBE) toe on the steel.
Not so. This may have been the original intent
but was not achieved in practice. Many of the "toes"
were incomplete and many were contaminated with PE adhesive. To
explain this in simple language, the toes referred to are at the
end of the pipe coating which is "cut back" from the
end of each pipe as the welding process in the field would damage
the coating. BP specified to the factory pipe coater that they
must cut back the PE to expose a 50 mm toe of FBE, the primer
layer, sticking out around the full circumference of the pipe
end. The reason for this was that the specification writers knew
that the SPC material did not take up good adhesion to the PE
and therefore a seal would be effected between the liquid coating
and the FBE coating at either side of the joint. As this seal
is paramount to the performance of the joint coating it is fair
to say that the in-service performance of every joint was predicated
on this FBE toe being present in a full and secure condition.
Nowhere in the WP document is it stated that
any joint without this must fail. But that is the reality.
They do not mention the configuration of the
end cut to the PE. This was supposed to be feathered, that is
chamfered to a gentle slope to eliminate any sharp edges, but
in many cases was left square cut. This means that the square
cut ends of the PE coating acted as a "crack inducer"
to the joint coating material. These are failures in BP's quality
assurance programme which directly led to many of the early failures.
This gives the lie to the repeated assertions in the WP document
that all of the failures were the fault of the application sub-contractor,
the British company PIH Ltd, but of much more concern to me is
the absolute certainty of future failures in service.
Para 5"We have not independently verified
that this information is comprehensive, complete, accurate or
up to date".
I understood that WP acted for ECGD to audit
the technical specifications on which the pipeline was to be built.
This statement that they did not verify any documents, statements
from BP etc is absolutely astounding and clearly invalidates the
whole report.
PAGE 3, ITEM
2EXECUTIVE SUMMARY
"BP (AGT Pipelines Project) completed a detailed
large diameter pipeline field joint coating evaluation, testing
and selection process prior to selection of Speciality Polymer
Coatings (SPC) SP-2888 liquid field joint coating for the BTC
and SCP pipeline projects. The evaluation, testing and selection
process was very thorough . . ."
This is not true. The majority of available
systems were not considered.
I listed all the available systems to BP in
Baku in June 2002, these are:
Liquid systemsepoxies, urethanes
or hybrids such as phenolic epoxies, urethane ureas, epoxy urethanes
etc.
Footprint systemstape plus
ie well-known anti-corrosion tapes with the addition of overwraps,
rockshields etc or shrink sleeves, of which there are many different
types.
Mimic systemsFBE + PE adhesive
+ PE top coat with the top coat applied by one of the following
methods:
Such systems are well known, at least to those
of us active in all types of pipelines in all areas of the world,
but clearly not to the group of people who had resolved no matter
what, that one product only would be used.
In July 2002 I arranged a demonstration of all
of these technologies as clearly they had not been evaluated before.
I arranged PE coated pipe with prepared field joints, together
with laboratory and test facilities at the premises of a major
pipe coater. The system suppliers were to come to the site in
Northern France to carry out demonstrations at their own cost,
these suppliers were coming from UK, Italy, USA and Germany. The
idea was for BP to see all of the available technologies and then
draw up a short list of systems to be fully evaluated.
When I had completed these arrangements I informed
BP Baku of this and the following day was instructed by BP Baku
to cancel the whole thing as BP London's mind was already made
up.
This demonstrates very clearly a desire on the
part of some people within BP London that the best systems were
not even to be demonstrated as their superiority over the ludicrous
coat of paint already decided on, would be apparent to all.
You may wish to question the motivation of these
people.
The words used by WP "detailed evaluation
. . .very thorough . . . etc" are not valid, the "evaluation"
was only of a very limited selection of systems and they did not
even look at "21st century" options. Unbelievably they
then referred to the "step change" they were effecting
in the industry! As I wrote at the time, it was a step changea
backward step!
WP then list a number of documents they were
given by BP/SPC.
You will note that only the first document,
The Advantica Report, was issued prior to the issuing of
the specification.
This is crucial. Any investigation of this matter
requires the investigator to draw the time line through all actions
by all parties up to the preparation and issuing of the specification
as this document was included in the bid package and construction
started with this specification as a contractual obligation. From
the documents available, the investigator will easily identify
a clear "push" for one product only to be considered.
All of the documents issued since and all subsequent changes made
to this specification arise out of the fact that the specification
was and is, inappropriate. It was in my words "under developed
and should never had been issued".
They ignored the advice given in my November
2002 document but since then, and mainly because of serious failures,
we have seen a flurry of reports, the sum total of which is a
cobbling together of answers to questions which should not have
had to be asked and would not have been asked if the matter had
been engineered properly at the outset. You should also note that
BP have in their possession a number of reports which specifically
show that the SPC material could not meet relevant international
standards and therefore should not have been used. These reports
were not given to WP.
It is of particular interest to me that their
comments on pages 14 to 19 are all about the specification review
document I submitted to BP in November 2002, yet they do not declare
having received this document in their list on page 3. Why not?
PAGE 3LAST
PARAGRAPH
"At the request of Pipeline Induction Heat
etc . . . "
It was not at the request of the applicator.
I have checked with PIH. A pity that WP did not verify any facts
before submitting their document.
You will note that the SPC cold room report
is listed by WP dated September 2003. My document dated 12 November
2002 advised BP that they needed to know all about the curing
and performance behaviour of the epoxy and therefore needed to
carry out a significant cold weather evaluation in order that
they could instruct the contractorPRIOR TO THE COMMENCEMENT
OF THE WORKSThis did not happen.
Again, I have checked with PIH,
PAGE 4"IN
EARLY DECEMBER
2003, BP/BTC COMPLETED
A FIELD
TEST PROGRAM
VERIFYING THE
PRE-HEAT/POST-HEAT
TEMPERATURES AND
TIME REQUIRED
TO SUCCESSFULLY
CURE THE
SP-2888 FIELD JOINT
COATING MATERIAL"
Seventeen months after they had issued their
specification they finally found out how to cure the epoxy. This
finding did not prove the viability of the field joint, only how
to cure the paint. So if they previously did not know how to cure
the paint, how could they have proven the viability of the field
joint coating specification?
This simple question is key to the whole problemthey
did not prove the viability of the field joint coating before
issuing the specification. This is beyond question.
How could such a serious mistake be made, was
it a simple abrogation of responsibility, an error made in ignorance,
a stupid act by an incompetent person or was it something else,
something that should make you question the motivation of the
people concerned.
PAGE 5"IN
APRIL/MAY
2001, BP, AS PART
OF ITS
PIPELINE COST
REDUCTION INITIATIVE,
DECIDED TO
PERFORM A
MAIN LINE
FIELD JOINT
COATING PRODUCT
EVALUATION. AN
ADDITIONAL DRIVER
FOR PERFORMING
A PIPE
FIELD JOINT
COATING EVALUATION
WAS BP AND
ITS ENGINEERING
CONTRACTORS' LACK
OF CONFIDENCE
IN THE
FIELD JOINT
COATINGS USED
TO DATE
ON THREE
LAYER PE SYSTEM
COATED LINE
PIPE"
This statement about confidence would be very
funny if the situation was not so serious. The reality is that
the world has no confidence in using liquid epoxy paint on field
joints on polyethylene-coated pipe to the point that nobody in
the world uses it, yet BP are saying that they have no confidence
in what the whole of the rest of the world is doing!
Three layer PE had been in use for 30 years
at this time so they are saying that all owners of three layer
coated pipelines had been doing it wrong for all of this time!
Did they talk to these owners?
Tapes and shrink sleeves have served the industry
very well but more importantly, 21st century technology three
layer "mimic" field joint systems had been in use for
some years. Why did they ignore them in favour of technology that
had been rejected by the rest of the world?
There are many points I could address here but
for most of them I would be repeating myself. I will only comment
on one more before addressing all of the comments made against
me personally.
PAGE 10ITEM
3.7
"Limited adhesion of field joint coatings
to 3 layer HDPE equally applies to all other HDPE field joint
coating systems"
Absolute rubbish. The systems I refer to as
"mimic" systems employ HDPE in molten form as their
top coat. This melts into the HDPE at the sides of the joint and
forms a cohesive mass, there is no adhesion. Clearly the BP/BTC
team did not investigate this but it is appalling that the WP
team who carried out the technical audit did not even know of
such systems.
RESPONSE TO PERSONAL ATTACK
PAGE 14ITEM
4.1
1 have addressed all items in my introductory
remarks
You should note that all of the following
remarks by WP and BP/BTC refer to my original response when i
first read the Field Joint Coating Specification in November 2002.
The BP/BTC Comments are extraordinary as they have never been
made before, they did not respond to my critique at any time and
you must remember that when i made my remarks, i was acting for
BP, trying to help them.
PAGE 14ITEM
4.2
"BP/BTC ResponseThe BTC pipeline will
operate at 50 degrees C so this is not an issue . . . "
Operational temperatures of the pipeline had
been discussed in BP's Baku office on the day I was given the
specification in 2002. 1 was informed that the pipeline could
well run at over 70 degrees C. Now they are saying that it will
run at a maximum of 50 degrees. I do not know what temperature
the pipeline will run at, do they?
"If we adopted the same negative attitude
to the selection of line pipe coatings we would still be applying
coal tar and asphalt enamel to wire brushed steel surfaces rather
than benefiting from the superior performance we get from FBE
and three layer FBE-polyolefin coatings"
This incredibly crass statement is made in response
to my pointing out that this would be the first time that liquid
epoxy paint had been used for field joints on polyolefin coated
pipe. My statement to them was true and confirmed as such by BP
themselves in their published article entitled "CASPIAN CONNECTIONS"
(Frontiers Magazine, BP's in-house magazine, August 2003, available
from BP web site) in which they state in relation to the field
joint coating:
"As far as we know, this is the first time
that such a system has been employed", this statement confirms
the fact that BP knew they were using this pipeline for "guinea
pig" engineering and defeats totally the many comments in
the WP report regarding track record of the SPC material.
Their comment re coal tar and asphalt enamel
should be viewed in the light of the fact that the vast majority
of North Sea pipelines are coated with asphalt enamel, this is
still the current practice including by BP themselves and their
comment re FBE and 3-layer should be viewed in the light of the
fact that there have been many failures of all pipe coating systems,
including FBE and three layer polyethylenes. I do not say this
to denigrate them, I have worked with every type of pipe coating
for over forty years and I recognise reality. We develop our thinking
regarding their use through our experiences, both good and bad,
and our understanding evolves through this process. We do not
guesswe know. We do not hopewe prove.
They try to imply that I am some sort of backwoodsman
when in fact I have been at the forefront of coating technology
for years. Typically, with regard to field joint coating I have
developed with various people many innovations and the offshore
pipeline joint coating system we developed in 1972, for BP, is
used throughout the offshore pipeline construction industry to
the extent that it was applied to its 8th million joint last year.
Multi billion dollar pipelines can not be used
as guinea pigs for an individuals ideas, needs or wants, they
must be built to known standards with proven technology. This
project ignores this principle and therefor cannot be proved as
"fit for purpose" for its design life and the insurance
implications are obvious.
The WP comments are even worse. They try to
draw a distinction between adhesion and bond. Their statement
that SP2888 cures in place is true, just as it is when you buy
white emulsion paint from your local DIY store and apply it to
your lounge ceiling. All paints cure in place. What we are interested
in is the permanence of the adhesion (bond) to the substrate(the
surface to which it is applied)
Their attempt to say that the adhesion of the
specified material is superior to all others is pathetic as well
as being totally untrue. The adhesion of liquid epoxies to grit
blasted steel is generally good, the problem here is the adhesion
to polyethylene. In the specification, this failure is recognised
by BP as they state the adhesion test result is to be considered
a pass when "the coating peels in large pieces from the substrate".
This is of course a failure in every international standard and
every specification in the global pipeline industry. Only the
BTC specification allows what is a clear failure, to be considered
a pass and this is just another example of certain peoples determination
to use one product only to the exclusion of all others, even falsifying
a pass result with obvious consequences to the long term integrity
of the pipeline to achieve their objective.
We need to look at three aspects of the physics
of adhesion in this case where the paint is applied over the polyethylene
at either side of the joint:
POLAR ADHESIONas the polyethylene
is a non-polar material with very low surface energy, there is
no polar adhesion.
CHEMICAL ADHESIONnormally
defined as the process whereby the applied coating changes the
surface chemistry of the substrate, this does not happen when
liquid epoxy is applied to polyethylene.
MECHANICAL ADHESIONin simple
terms this means surface wetting translated into surface tension
thereby forming adhesion to the substrate. When the substrate
is grit blasted prior to application, this expands the available
surface to be wetted thereby increasing the adhesion, but with
polyethylene, it cannot be blasted aggressively for this purpose
but can only be lightly abraded. The expansion of available surface
for wetting is therefore only marginal. Additionally, the polyethylene
has very low surface energy and the problem of obtaining adhesion,
particularly by high energy paints, to polyethylene is well known
in the paint and plastics industries.
Compare the above with the use of hot melt polyethylene
joint material which melts into the overlap areas and forms a
cohesive mass, but then BP very pointedly would not even look
at such systems even when the demonstration programme had been
set up. WHY NOT?
Page 16. "There is a known way to remake
the cutback on 3 layer FBE-polypropylene in the field and this
was used successfully on the ADCO Thamama C and F project in Habshan,
UAE, in 1994 on every field joint. This procedure could be employed
on three layer FBE-polyethylene with minor changes to the procedure".
They are right, the "Hancox" rotating
knife system was used to re cut ends on the Thamama pipeline.
I should know, I was a consultant to one of the coating contractors!
The following factors should be taken into account:
The work was done in very hot desert
conditions
The pipe was a much smaller diameter
There was a substantial thickness
of FBE
But what is most important is that the design
and construction management contractor had looked at liquid paint
systems and rejected them. He could not identify a commercially
available system which would meet the service requirement of the
pipeline and was forced into developing his own field joint coating
system. This system, subsequently known as "DAWPA" was
based on a three layer mimic system using a pre-cut sheet of polypropylene
as the external layer. This was seam welded and fillet welded
at the sides of the joint using polypropylene wire welding.
This resulted in homogenous "End to End"
polyolefin protection, exactly as I recommended to BP and which
they very vigorously avoided looking at!
So here we have BP/BTC using this joint as a
reference and yet they avoided even looking at it for BTC. You
have to askWHY?
The pipeline operator's corrosion engineer in
Abu Dhabi has recently confirmed the good performance of this
system on a pipeline operating at higher temperature than BTC
and in very bad ground conditions.
You should also note that where joints have
failed on BTC and are being blasted off and the SPC material being
re-applied, no re-cutting of the ends of the PE is being done
so one would have to conclude that BP have accepted that these
repaired joints will fail.
PAGE 16"THE
CONTRACTOR WILL
BE PROVIDED
WITH COMPREHENSIVE
DATA IN
RESPECT OF
THE IMPACT
OF TEMPERATURE
ON CURING
RATES"
Nohe was not.
Otherwise there could not have been the cracking
problem.
PAGE 16"ROLLERS
WERE USED
. . . "
My comment was very clear, they did not do any
testing of roller applied material in the original Advantica test,
they then specified it in the formal specification.
PAGE 17"THE
COATING MAY
OR MAY
NOT BE
DAMAGED IN
COLD WEATHER,
BUT IT
WILL CERTAINLY
NOT SUFFER
THE SAME
DAMAGE FROM
SOIL STRESSING
AS THE
ALTERNATIVES AVAILABLE"
I cannot believe the crassness of these statements.
They are saying that they did not know if the joint coating would
be damaged, or not, during backfillingabsolutely astounding!
But then of course they could always find out "on the job",
another example of the "guinea pig" engineering culture.
Then they say definitively that it will not
suffer soil stressing as badly as alternativeswhen they
did not test any of these alternatives. This is the judgement
of the crystal ball! It is certainly not an engineering judgement.
The fact is that had the joint been coated with a mimic three
layer system employing injection moulded PE top coat, the field
joint would actually have had superior soil stressing resistance
to that of the factory applied coatinga dramatic advance
in field joint coating technology.
Little or no reference is made in the WP report
with regard to in-ground performance of the epoxy yet this is
fundamental to the coatings ability to protect the pipe in the
long term.
Oil and gas pipelines are not passive, inert
items, they are live, dynamic structures that move due to ground
movement and most importantly, pressure changes within the pipe.
Movement can be lateral, linear and concentric. The coating has
to accommodate such movement. The operating temperature will fluctuate
with pressure changes and should the pipeline be shut down for
any time, the pipe temperature will drop down to the in-ground
ambientestimated by BP to be å5º to +50º
C in the worst case (Caspian Connections article, BP's Frontier
Magazine, August 2003). This means a temperature range of
-5º to +50ºC. How will this affect the performance of
the coating particularly at the PE/epoxy interface with significant
differences in the expansion/contraction rates of the materials?
This question has been discussed throughout the whole pipeline
industry and I am yet to hear any individual say"it
will be OK, the system is fully proven"
PAGE 17"WE
DISAGREE WITH
THIS COMMENT.
SINCE FIELD
JOINT COATING
IS IMPORTANT,
ESPECIALLY IN
THE CASE
OF 3-LAYER
PE COATED PIPE,
WE DO
NOT BELIEVE
IT IS
ACCEPTABLE TO
LET THE
PIPELINE CONTRACTOR
SELECT THE
FIELD JOINT
COATING MATERIAL
TO BE
USED. THE
PIPELINE CONTRACTOR
WILL BE
INCLINED TO
SELECT A
COATING BASED
ON PRICE
AND EASE
OF APPLICATION,
WHICH IS
DIFFERENT THAN
THE PIPELINE
OPERATING COMPANY
GOAL TO
USE A
PIPELINE COATING
SYSTEM THAT
PROVIDES LONG
TERM CORROSION
PROTECTION FOR
THE PIPELINE".
The principle that the industry works to, is
to first establish the necessary performance criteria for the
field joint coating, this obviously may be limited to certain
generic systems. And then to allow the contractor to exercise
his commercial right to negotiate with potential suppliers and
then crucially, for the contractor to prove the viability of his
favoured system to the client, PRIOR to commencement of the works.
Because the contractor has to certify his work as being fit for
purpose, it is in his interest that the field joint material is
correct.
What we saw was the client instructing the contractor
to use a material which was not proven, was unsuitable and which
failed. In specification terms, they chose the material and then
set the performance criteria to suit the very limited capability
of the chosen producta complete reversal of best practice.
At this point you should be aware that the specification
issued for contract bid was a revised version, the original had
specified three named paints, the final document nominated only
the SPC material. The contractors bidding for the field joint
coating contract reported to me (remember I was working for BP)
that they were being offered the now disqualified paints for six
dollars per litre delivered and the SPC material at 18 dollars
per litre. This discrepancy is greater than any I have ever seen
in 43 years of dealing with pipeline coatings and cannot be explained
in normal commercial or technical terms.
Essentially, BP paid three times as much, for
a material that failed.
Apart from the unexplained cost, you should
be aware that the companies who bid to carry out subcontract field
joint coating as well as the main construction contract bidders
all queried the sole source specification and expressed their
disquiet when instructed by BP that the specification was written
in stone, ie, no alternatives would be considered.
PAGE 18"THERE
IS NO
BEST INDUSTRY
PRACTICE FOR
FIELD JOINT
COATING . . . "
This is the excuse for using a process that
is clearly wrong? Is not knowing best practice a reason to use
worst practice?
"Materials used on previous projects have
been shown to be inferior to the selected material"
Totally untrue. A statement made without a shred
of proof.
I refer you to both BP and my own comments on
Thamama C&F.
Did they talk to RuhrGas in Germany, they have
over 200,000 kilometers of PE coated pipe in the ground. Not one
single field joint of which is coated with a liquid epoxy paint
and they are totally satisfied with their field joint coating
system which was one I recommended to BP to look at but which
was rejected unseen.
PAGE 18"THE
SPECIFICATION IS
FAR MORE
DEVELOPED THAN
MANY PREPARED
FOR SIMILAR
PROJECTS AND
MOREOVER IS
SUPPORTED BY
THE RESULTS
FROM A
DETAILED TEST
PROGRAMME"
Totally untrue, in my critique of the specification
in November 2002 I concluded that it was under developed and should
not have been issued. I have discussed the matter with many in
our industry and can say that the general opinion is incredulity
that the specification was ever issued.
The test programme referred to was the original
Advantica testing where they tested the SPC material applied over
a primer, they then specified it without primer thereby nullifying
the findings of the Advantica report on which their whole support
for the specification rested.
You should note that the "best practice"
advocated by SPC, who after all, formulated and manufacture the
product, is as follows:
"THE CONCERN WITH THE EPOXY TO POLYETHYLENE
BOND HAS BEEN ADDRESSED BY FLAME TREATING THE POLYETHYLENE AND
APPLYING AN EPOXY PRIMER"
The above is an extract from a paper entitled
"Liquid epoxy coatings for today's pipeline coating challenges"
written and presented by Mr J BanachTechnical Director
of SPC, the paper was given at the British Hydraulic Research
Group's PIPELINE PROTECTION CONFERENCE at Aachen, Germany in October
2003. This conference is the leading forum in the pipeline protection
industry and the paper was given to 160 delegates from 21 different
countries.
This paper was not provided to WP by BP.
My written opinion in 2002 was that the original
test results bore as much relevance to the project as the results
of the then recent Eurovision Song Contest.
(I was reprimanded for this comment.)
PAGE 19"IT
IS HARD
TO BELIEVE
THAT IT
(THE SPC MATERIAL)
DID NOT
MEET BTC HSE REQUIREMENTS"
I had raised the fact in my November 2002 document
that the material contained high levels of Bisphenol A, a known
endochrine disruptor and I asked that we (BP) check that it was
allowable both under the company's HSE policy and the specific
project policy as we were crossing thousands of open waterways
and shallow aquafers. This was a perfectly proper comment for
me to make.
As the first priority on a project is health
and safety, I find the expression"hard to believe
it did not meet etc" to be a clear indication that WP had
not checked and did not know.
PAGE 19"IS
THE AUTHOR
REFERRING TO
HEAT SHRINK
SLEEVES IN
HIS USE
OF `END
TO END'
HOMOGENOUS PE PROTECTION.
IF SO
THESE DID
NOT MEET
THE REQUIREMENTS
OF THE
TESTING REGIME"
I have made clear the sort of homogenity that
I was looking for and which was readily available to them. Shrink
sleeves take up adhesion through a variety of different adhesives
but none of them could be considered to provide homogenous PE
protection. Shrink sleeves were one of the seven systems I asked
them to look at. They tested one out of a possible 30 different
sorts of shrink sleeves and condemned the technology outright
even though it is serving the industry very well.
Of particular interest is the Trans Canada Company's
specification for the use of liquid epoxy paints as a rehabilitation
coating for polyethylene coated pipe. This is where an operating
pipeline may be exposed and sections of the original coating removed
to facilitate some mechanical repairs. They specify that the liquid
coating (SP-2888 is approved and used) must only be applied to
steel surfaces, in transition areas ie, where the rehab coating
overlaps onto the PE, the liquid must stop short of the PE and
a shrink sleeve be used for the transition. This specification
was written after Trans Canada carried out a test programme with
liquid epoxies onto PE which failed them as a joint coating.
A copy of the Trans Canada report was given
to BP in August 2002, it is one of many documents which could
have been made available to WP but which was denied by BP.
Clearly WP did not know of the three layer systems
I referred to BP in 2002 but somehow knew of the three layer system
used in Abu Dhabi in 1994!
They were told that the coating at the pipe
ends was re-cut in Abu Dhabi but not told that this was not being
done to the cracked field joints on BTC.
PAGES 19 THRU
24
Much of this refers specifically to the cracking
problem. What has not been recognised is that this is not THE
PROBLEM. The cracking is no more than a physical manifestation
of the inappropriateness of the chemistry employed.
BP and WP refer to a number of reports that
support the use of a liquid epoxy paint for field joint protection
on a polyethylene coated pipe. BP do not refer to any of a number
of documents in their possession that clearly condemn this concept.
To disclose that 26% of the joints coated in
Georgia were cracked is both extraordinary and unforgiveable.
Then to try to ascribe the blame to the applicator as the sole
guilty party is an act of cowardice and frankly, stupidity, the
like of which I have never seen before.
The client, BP, is responsible for the construction
of the pipeline. All specifications and instructions in the implementation
of them are the responsibility of the client. The construction
proceeds only when the client has agreed all of the contractors
and their sub-contractors, quality plans which are then incorporated
into the project quality plan.
To have 26% of the coated joints cracked is
a terrible failure of quality assurance but it is no more than
a graphic illustration of the key failure which was to employ
an unproven and inadequately tested coating system in the first
place, that is the essential failure of quality assurance.
As you read the pages of the WP report you see
a clear picture emerging of inadequate attention to matters of
paramount importance. Almost all of the referenced documents were
only prepared after the problems came to light. They also reveal
that more and one assumes, proper inspection personnel were placed
on the project from JANUARY 2004, six months after construction
started. If these people were necessary in January 2004 then they
were necessary in July 2003. No wonder that BP's quality assurance
failed.
Reference is made to DCVG and temporary cathodic
protection. These passages of the report are risible. They demonstrate
a minimal understanding of the technology, I refer you to Dr Leeds'
explanation of the science.
The significance of the field joint coating
cracking problem has been under estimated by BP and their response
in physically dealing with it amounts to the worst gross negligence
I have ever seen in the pipeline industry.
These cracks take three basic forms:
Full or almost full, circumferencial
cracks at the edge of the factory coating or over the girth weld.
Shorter lengths at these locations.
Tensile cracks in crescent shapes
around the circumference.
BP and WP state clearly that the cause of the
cracking was:
"due to thermal cycling of the pipe while
the coating was not adequately cured (limited flexibility)"
This is the only explanation advanced and all
their comments are focused on the failings of the applicator but
then we read on page 22:
"They indicated that the small cracks that
were found were caused by other reasons"
What other reasons? Here we have a statement
with no explanation and we are left hanging in the wind.
Cracks of six inches or less are not being repaired,
Why? Are we to assume that because BP do not know what is causing
them, it is OK to leave them?
It is not OK.
Assumptions have been made that the area of
exposed steel at any crack will be protected by the cathodic protection
(CP) and that the crack itself and the steel it exposes, will
not change during the next 40 years. Both assumptions are totally
wrong.
Firstly the cathodic protection, for the above
to be true, BP have assumed that the CP system will give an even
spread of current to the whole pipe surface, thereby achieving
the necessary level of pipe to soil potential level that we know
provides protection. How that will be achieved using remote ground
beds in rock conditions (high resistance) or in wet salt-laden
soils (low resistance) is beyond me and all the CP experts who
have debated this. BP's assumption is unsupportable. In addition,
as the corrosion process develops at a crack, the surrounding
coating will lift and the most serious corrosion will occur under
the disbonded coating, where the CP is totally ineffective.
Secondly, the cracks themselves. These will
lengthen over time and in some cases, also widen due to the dynamics
of the hydraulic operation of the pipeline. As corrosion occurs,
the "lifting" process as described above will take place.
The corrosion engineer has two main weapons
in the fight against corrosion on cross-country pipelines. The
barrier coating is always considered the primary system with the
cathodic protection considered as a complementary system. Where
serious cracking of the coating has occurred on BTC and then been
ignored by the corrosion engineer, no power on earth can guarantee
the CP will protect at every location yet here we have BP making
the CP their only form of protection. I do not know of
a single professional corrosion engineer working in the pipeline
industry who would support that.
The most frightening thing of all is that short
cracks at the edge of the PE, through to the steel, will provide
the perfect initiation point for the formation of stress corrosion
cracking (SCC). This phenomena is considered the greatest scourge
of the modern high pressure pipeline industry. I am not aware
that BP conducted a specific programme at the design stage of
the project to ensure the conditions known to cause SCC were recognised
and eliminated but I will state categorically that to leave perfect
"nesting sites" in the coating is the height of folly
and frankly, is beyond belief.
CONCLUSION
I have been engaged in protecting pipelines
for over 40 years. I have worked on a number of BP projects and
served the company in a number of different capacities, directly
or indirectly, over that time. I am not anti-BP. Everything I
have done with regard to this project is out of my desire to help
them. That is still my position today.
What has gone on in the BTC project is appalling.
It is essential for the committee to consider the actions of the
individual consultant and the BP personnel in the period leading
to the writing and issuing of the field joint coating specification.
The lies, half-truths and deliberate misleading that went on led
the client to issue a specification that was inappropriate, underdeveloped
and clearly, when implemented could not prove the necessary "fitness
for purpose" to sustain beyond question, the structural integrity
of the pipeline for its design life.
As corrosion engineers, we know that we cannot
defeat the laws of nature, the best we can do is hold back nature
for a definable period of time.
BP have a number of reports which they purport,
validates their specification. They also have a number of reports
that does the exact opposite. The best you can say is that their
fundamental decision to use the unproven system was a guess.
The principle that we work on is the holistic
principle, ie:
WHOLE PIPEWHOLE LIFE
Essentially this means that we design the corrosion
protection system so that all elements are proven to provide the
protective service, in all ground conditions, for the design life
plus, of the pipeline.
This principle has been ignored in this case.
There is nothing in the WorleyParsons report
that proves their case; the fact is that the WP report, if anything,
proves the opposite. I refer you to my detailed comments and the
explanation of the science prepared by Dr John Leeds.
WorleyParsons says:
We have not independently verified
that this information is comprehensive, complete, accurate or
up to date.
So what was the objective of their report? It
does not provide any of the verification one would expect to see,
on which ECGD could base their financial decision.
The WorleyParsons report is one of the most
extraordinary I have ever read. It has been rewritten, dated only
four days before ECGD submitted it to the committee, and dedicates
25% of its content to attacking me. Can anyone believe that this
attack was in their original report; of course not, it has been
prepared together with an individual in BP, in an attempt to assassinate
both my character and my ability.
The report does not deal with the events leading
up to the issuing of the specification. This is the period that
is most critical in the whole sorry saga. Had the requirements
of the project been recognised and dealt with properly and professionally
at that time, then no failures would have occurred and the pipeline's
structural integrity would have been assured. As it is, the structural
integrity of this pipeline is not assured, joint coatings will
fail in service and the subsequent corrosion will be uncontrollable.
The truth appears sporadically from the miasma
of half-truth, untruth and obfuscation.
The reality is that there was a consistent and
shameless promotion for the use of one product and this clouded
the judgement of people who should have known better.
Others have made direct allegations regarding
the potential criminal conduct of some of the personnel involved
during that critical period, particularly with regard to the material
selection process, and clearly the only way to resolve the truth
of the situation is for a proper forensic investigation to be
conducted by the police into all the individuals' actions. I will
of course provide the investigating authority with all the relevant
documentation, including reports written by some of those involved,
to BP, containing half-truths and deliberately misleading statements.
Such investigations can reveal any connection
between those involved in writing the specifications and the company
whose product was nominated. (At three times the cost of its competitors)
Information regarding this was given to BP along
with many other documents in an evidence file in August 2002.
BP subsequently held an internal audit. The auditors contacted
me and I told them of the existence of this evidence file. They
seemed very excited and immediately asked me for it, I responded
that the file was in the hands of one of BP's managers in Baku
but that the file belonged to me. They told me that they had just
been in Baku and were not made aware of this file. They appeared
desperate to obtain it, so feeling that an audit would reveal
the truth I told them I would phone Baku and advise the manager
concerned that he could hand the file over to them. This I did
and they went to Baku within 48 hours to pick the file up. Of
course, copies of this file are in both Baku and UK although the
original one that they picked up seems to have disappeared.
FACTwhen they issued the specification
they had one report only, the seriously flawed Advantica report,
that supported the use of the SPC product. The evidence file contained
seven reports that condemned it, Three of these written by Advantica.
The circumstances in which I received documents
dealing with the relationship of the man who promoted the SPC
material and wrote the specification for BP, to the SPC company
were explained to the auditors and the name, telephone number
and location of the individual who gave me the documents and who
had asked me to confirm to the BP auditors that he would have
a statement notarised if necessary was also given to them. The
individual concerned is one of the most respected, leading professionals
in the industry, his character is unimpeachable and he had no
interest in the project at that time.
It did not surprise me that the auditors did
not contact him, not at that time or at any time since. This fact
may surprise you.
This is the audit that the Sunday Times
became aware of and asked for the report, which was of course
denied by BP.
In this critical period in 2002 there was a
concerted effort to avoid the truth, to avoid any and every doubt
expressed regarding their pre-determined decision to use an unsuitable
product. I was not the only person expressing doubts, remember,
I had been approached for help by senior BP managers.
I was warned before Christmas 2002 that I was
to be removed from the project and my involvement was terminated
at the end of January 2003 even though I was engaged in tasks
at that time instructed by BP Baku. During 2002 I had written
much on the field joint protection concept and specification.
Not one single point I had raised was ever responded to during
this period or later, up to the writing of the WP report where
a few comments from "BP/BTC" are quoted.
After my termination I contacted the project
compliance manager for BP Mr David Winter to express my deep concern
that the company was making a terrible mistake and asked for a
meeting. He eventually agreed and I met him at the end of March
2003. Present for part of that meeting was David Fairhurst, the
BP corrosion engineer.
Mr Winter greeted me with the words "thank
you for coming Mr Mortimore but I must tell you that nothing you
say will change our minds" at which point I realised that
I was wasting my time. However, I had prepared properly for this
meeting and decided that I would proceed with my plan which was
to give him the historical background of the use of PE and epoxies,
establish the fact that their testing had been utterly inadequate,
criticise the issued specification in an unanswerable way and
try to get them to realise that they must review the whole situation.
The meeting lasted over five hours but I failed to get any change
in their attitude, which remainedthis may not be right
but we are going to do it anyway.
One of the instructions I had had from the project
management in Baku was to procure some of the SPC product for
evaluation by them not by the London office of BP. I had obtained
the material from Canada and had made some free film samples at
my home. I showed these to Winter and bent them in front of him
to demonstrate the lack of flexibility, the samples shattered
when bent but he would still not accept that the material was
unsuitable due to its lack of flexibility. I reminded him of the
Advantica flexibility test report that I had included in the evidence
file, that showed the SPC material failing dismally when tested
to a recognised international standard (Transco CW6) and he would
not accept this evidence either.
Mr Winter informed me at the end that I would
not be re-hired on the project, I would never work for BP again
and that if I stood up and opposed BP, he would ensure that I
was made bankrupt. This pathetic threat was treated with the contempt
it deserved.
After the Sunday Times published their
devastating article in February, I wrote to Lord Browne, the CEO
of BP. I used the expression "last desperate plea" in
this letter. I was at my wits end in my worries over the project
and the company's future. Five weeks later I received a letter
from the MD of the BTC Pipeline Company in Baku, denying me a
meeting on the grounds that "nothing could be gained".
You can make up your own mind as to whether or not they could
have gained something useful from such meeting.
During the first two months of this year I was
placed under severe pressure over this matter, I had as many as
seven investigators trying to get me to whistle blow, this included
phone calls, knocks on the door even feet in the door. Having
been strong, fit and healthy for all of my sixty years I was shocked
to suffer a heart attack at this time. This has resulted in some
damage for which I am scheduled to have surgery later this year.
The cardiologist's opinion was as all tests to find a background
cause were negative, the attack was almost certainly caused through
stress. The only stress I was feeling at that time was my worry
over BP and my own deep sense of guilt that I had failed them.
I am now retired from the oil and gas business,
only partly through health, but primarily though the realisation
that my sort of corrosion engineering is not wanted anymore, by
a company like BP. Respect for the laws of nature, employment
of basic engineering principles, the establishment of performance
parameters before undertaking any form of engineering research
etc seem to have gone out of the window to be replaced by thethis
will do, lets make a few quid, we can make it up as we go alongculture,
which I consider to be totally unprofessional, completely unethical
and which will eventually result in the greatest disasters that
the oil and gas industries have ever seen.
I have spent a lot of time dealing with the
integrity problems of existing pipelines. I have probably looked
at as many as 400 pipelines spread over all six continents where
serious corrosion problems have occurred. The golden thread running
through all of these is that the coating has failed. The failure
mechanism is usually identifiable and we can conclude that a mistake
has been made and can define rehabilitation strategy. It is also
a fact that at least 90% of these pipelines were cathodically
protected.
The BTC pipeline is unique in my experience
in that the failure mechanism has been designed into the pipeline.
In my original submission I gave you some of
the historical background to the use of epoxy paints and polyethylene
coating in the oil and gas industries. You may be interested to
know that there maybe as many as 350 paint manufacturers in the
UK with many of them making epoxy paints.
Not one of these companies markets its epoxy
paint as a joint coating for polyethylene coated pipes. WHYbecause
they know it would not work.
As I intend that this shall be the last document
I ever write on the subject of BTC, I would like to finish with
these words from that most perspicacious of American writers,
Walt Whitman
The earth does not argue,
It is not pathetic, has no arrangements, does not
scream,
Haste, persuede, threaten, promise,
Makes no discriminations, has no conceivable failures,
Closes nothing, refuses nothing, shuts none out
Whitman was right, only man can conceive of
failure, our duty is to prevent it.
I will make myself available to the committee,
if required, anytime after 22 September.
26 August 2004
BPBTC Pipeline Project
1. BP FIELD JOINT
COATING SPECIFICATION
2. ORIGINAL REVIEW
DATED NOVEMBER
2002 WRITTEN BY
DEREK MORTIMORE
PROJECT NAME:
AGT PIPELINES PROJECT
DOCUMENT TITLE:
SPECIFICATION FOR
FIELD JOINT
COATING
DOCUMENT NO:
410088/00/L/MW/SP/015
CONTENTS
1. INTRODUCTION
1.1 GENERAL
1.2 SCOPE
1.3 DEFINITIONS
1.4 REFERENCE CODES AND STANDARDS
1.5 MATERIAL APPROVAL AND CONTROL
2. CONTRACTOR'S SCOPE OF WORK
2.1 GENERAL
2.2 HEALTH, SAFETY AND ENVIRONMENT (HSE)
2.3 QUALITY SYSTEMS
2.4 CERTIFICATION AND TEST REPORTS
2.5 FIELD JOINT IDENTIFICATION
2.6 PRE-QUALIFICATION ACCEPTANCE TESTS
3. SURFACE PREPARATION
3.1 PRELIMINARY CLEANING
3.2 BLAST CLEANING AND PREPARATION
3.3 POWER TOOL CLEANING
3.4 AIR QUALITY
3.5 AMBIENT CONDITIONS
4. APPLICATION AND REPAIR OF COATINGS
4.1 GENERAL
4.2 CONDITION OF COATING MATERIALS
4.3 PREPARATION OF COATING MATERIALS
4.4 COATING APPLICATION
4.5 THICKNESS TOLERANCE
4.6 REPAIR OF COATINGS
5. INSPECTION AND TESTING BY CONTRACTOR
5.1 ENVIRONMENTAL CONDITIONS
5.2 VISUAL INSPECTION
5.3 HOLIDAY TESTING
5.4 THICKNESS TESTING
5.5 IMPACT RESISTANCE
5.6 ADHESION STRENGTH
5.7 PENETRATION INDENTATION TEST
5.8 HARDNESS
5.9 CATHODIC DISBONDMENT TESTING
TABLE 1APPROXIMATE DESIGN ENVIRONMENTAL
DATA
ANNEX A INSPECTION/TESTING SUMMARY, PREQUALIFICATION
ANNEX B INSPECTION/TESTING SUMMARY, PRODUCTION
1. INTRODUCTION
1.1 General
1.1.2 The cross-country pipelines for the
AGT pipelines project will be buried and will be protected against
external corrosion by external coating and Cathodic Protection
systems. The external coatings shall be suitable for the operating
conditions to which they are subjected and shall have proven good
resistance to cathodic disbondment.
1.1.3 Approximate pipeline design and environmental
criteria are typically as given in Table 1.
1.2 Scope
1.2.1 This document and related specifications
cover the minimum requirements for the field joint coating of
linepipe coated with three Layer High Density Polyethylene (3LHDPE).
The 3LHDPE coating system will be supplied in accordance with
project specification 410088-00-L-MW-SP-006, Specification for
Three Layer Polyethylene Coating of Linepipe.
1.2.2 Field joints shall be coated using
a liquid applied system as described in Section 4.1 of this specification.
1.3 Definitions
For the terms "COMPANY"
and "CONTRACTOR" refer to General Conditions of Contract.
The term "MANUFACTURER"
shall mean the particular company responsible for manufacture
and supply of the coating materials.
1.4 Reference Codes and Standards
1.4.1 This Specification references the
following Codes and Standardssee Section 1.4.2 to 1.4.3
below. Where an edition date is not specified the latest edition
at the time of contract award shall be used unless otherwise agreed
with COMPANY.
1.4.2 ASTM Standards
ASTM D 2240-91
| Standard test method for rubber property (durometer hardness).
|
ASTM D 5402-93 (1999) | Standard practice for assessing the solvent resistance of organic coatings using solvent rubs.
|
ASTM G 8-96 | Standard test methods for cathodic disbonding of pipeline coatings.
|
ASTM G 14-96 | Standard test method for impact resistance of pipeline coating (falling weight test).
|
ASTM G 17-96 | Standard test method for penetration resistance of pipeline coatings (blunt rod).
|
ASTM G 42-96 | Standard test method for cathodic disbonding of pipeline coatings subjected to elevated temperatures.
|
| |
1.4.3 British Standards/International Standards Organisation
(ISO)
BS EN ISO 9001 | Quality SystemsModel For Quality Assurance In Design, Development, Production, Installation and Servicing (1994).
|
BS EN ISO 9002 | Quality SystemsModel For Quality Assurance In Production, Installation And Servicing (1994).
|
BS 7079 Part Al | Preparation of steel substrates before application of paints and related products. Visual assessment of surface cleanliness. Specification for rust grades and preparation grades of un-coated steel substrates and of steel substrates after overall removal of previous coatings. (1994). [Identical with ISO 8501-1].
|
BS EN ISO 8501-1 | Preparation of steel substrates before application of paints and related productsVisual assessment of surface cleanliness.
|
BS EN ISO 8503-2 | Preparation of steel surfaces before application of paints and related products. Method for the grading of surface profile of abrasively blast cleaned steel using a comparator (1995).
|
| |
1.4.4 Canadian Standards Association
CAN/CSA Z245.20-M92 | External fusion bond epoxy coating for steel pipe (1992).
|
| |
1.4.5 NACE Standards
RP 0274/93 | Standard recommended practice for high voltage electrical inspection of pipeline coatings prior to installation.
|
| |
1.4.6 The SUPPLIER shall make these standards available
to all personnel engaged on the work and shall ensure any sub-contractor
follows the same requirements.
1.5 Material Approval and Control
COMPANY shall approve MANUFACTURER(s) and coating materials
to be used. Coating work shall not commence until all relevant
documents, the Quality/Inspection plan and supporting procedures
have been approved by COMPANY.
CONTRACTOR shall submit to COMPANY certified copies of the
results of tests made by MANUFACTURER covering the physical, chemical
and performance characteristics of all materials to be used in
the work, plus detailed specifications and instructions for handling
and application.
Coating shall be applied, inspected, tested and repaired
in accordance with procedures as approved by COMPANY. The work
shall be under the supervision of CONTRACTOR'S specialist coating
personnel as approved by COMPANY. All coating inspectors shall
be suitably experienced and qualified, eg to NACE Coating Inspectors
Certificate, and career details shall be provided for COMPANY
approval.
During the work, the following actions shall also be subject
to approval by COMPANY:
Time lapse for application to prepared steel
surfaces.
Use of power tool cleaning.
Use of thinners for coating materials.
Treatment of defective and damaged coatings.
2. CONTRACTOR'S
SCOPE OF
WORK
2.1 General
CONTRACTOR shall provide testing and inspection equipment,
all properly calibrated, for use by COMPANY during testing and
inspection. CONTRACTOR shall be responsible for continuous supervision
and inspection of the work.
CONTRACTOR shall supply, and maintain in good working order,
all labour, transport, supervision, consumables, materials, plant,
tools, equipment, lighting, spare parts, inspection and holiday
detection apparatus, safety equipment, protective clothing, site
cabins, weatherproof enclosures with humidity control for blast
cleaning and coating, stores with temperature controls, transport,
well drained stockpile area, and all other items needed to perform
the work described and specified herein.
CONTRACTOR is responsible for ensuring that all work is performed
to the standard of quality required by the approved project Specification.
COMPANY may request the provision of coating material samples,
and prepared and coated test panels. CONTRACTOR shall demonstrate
production of the specified surface cleanliness and roughness
for site preparation.
Coating and abrasive materials shall be clearly identified
with type, manufacturer's name, batch number, expiry date, pot
life, etc details.
2.2 Health, Safety and Environment (HSE)
The CONTRACTOR shall fully comply with the HSE requirements
of the CONTRACT. CONTRACTOR shall ensure that all work and storage
is performed in accordance with all applicable laws affecting
health and safety at work and follow recommendations of MANUFACTURER.
2.3 Quality Systems
The CONTRACTOR shall operate a Quality Management System
in compliance with BS EN ISO 9001: 1994 or BS EN ISO 9002: 1994
as appropriate. A Quality Plan shall be submitted within 4-weeks
from contract award, for acceptance by the Company. This Plan
shall ensure compliance with the requirements of the contract
or purchase order and any statutory authority requirements that
may apply and include all activities to be undertaken by the CONTRACTOR
to meet the Scope of Work.
COMPANY shall be allowed access to inspect all items and
phases of the work. Where field joint coating procedure acceptance
tests have been agreed, COMPANY will witness these tests.
2.4 Certification and Test Reports
CONTRACTOR shall establish a full reporting and recording
system and shall produce daily reports, and submit a full documentation
package at the end of the work, including, where applicable:
Items prepared, method of preparation, abrasive
type and grade, standard of cleanliness and profile achieved
Coating material type, name, colours, application
method, thickness measured, etc
Application and inspection personnel
Ambient temperature and humidity conditions
Outstanding areas for coating/repair, repair results
Certificate of conformity
Certified copies of test results made by MANUFACTURER
covering the physical, chemical and performance characteristics
of his products, data sheets, including cathodic disbondment results.
CONTRACTOR shall provide the following procedures where applicable:
Field joint preparation and induction heating
Coating materials, storage, application and repair,
curing
Measures to be adopted during periods of adverse
weather
Inspection and testing, including acceptance criteria,
and frequencies, coating thickness
Preservation, packing, shipping and storage: to
include methods, materials and any requirement for periodic inspection
CONTRACTOR shall supply data sheets and details of coating
materials to establish the suitability of the proposed coating
for the given use of the coated item. All coating materials shall
conform to the specified composition. MANUFACTURER shall confirm
in writing that the coating systems meet the requirements of this
Specification and can be applied successfully to the relevant
substrate.
2.5 Field Joint Identification
Details of field joint number and coating type/date shall
be generated and recorded by CONTRACTOR's tracking system and
all data shall be provided to COMPANY in an agreed format.
2.6 Pre-Qualification Acceptance Tests
Pre-qualification tests for the field joint anti-corrosion
coating shall be carried out by CONTRACTOR. These tests shall
prove that CONTRACTOR can provide an applied coating which meets
all the specified properties.
Before field application of field joint coating materials
the CONTRACTOR shall pre-qualify his materials, process and application
procedure. Two full field joints shall be prepared and coated
under conditions that replicate those expected in the field; one
joint shall be coated by spray method and the other by hand using
a brush or roller. When the coating is fully cured the tests in
Appendix A shall be conducted.
3. SURFACE PREPARATION
3.1 Preliminary Cleaning
Weld splatter, sharp edges, etc shall be removed. The surface
shall be decontaminated of hydrocarbon deposits and moisture,
using a solvent wipe if necessary, in accordance with SSPC-SP1
(BS 5493, Clause 14.2). The surface shall be allowed to dry out
before proceeding to the next stage of the work. After cleaning,
unless otherwise approved, the field joint shall be uniformly
heated to 80ºC to remove all moisture and to preclude any
condensation of moisture on the surface after blast cleaning.
Also, if environmental conditions require it, the steel substrate
shall be preheated to a maximum of 80ºC by induction method
immediately before application.
The shop applied linepipe coating, adjacent to field joints
shall be decontaminated as above.
If salt contamination of the steel surface is suspected,
tests shall be made for the presence of corrosion promoting salts.
Testing shall be with potassium fern-cyanide test papers to BS
5493, Appendix G or approved alternative. Salts shall be removed
and surfaces re-tested until no corrosion promoting salts remain.
Salt contamination shall be removed with a solution of bio-degradable
detergent in water.
3.2 Blast Cleaning and Preparation
The blast cleaning standard shall be ISO 8501-1, Sa 2% unless
specified otherwise. The amplitude of the profile of the blast
cleaned surface shall be tested and shall be in the range 75 to
100m unless specified otherwise for a particular coating. All
rust, scale, dirt and other contaminants shall be removed.
Abrasive material shall be of the expendable type. Abrasive
shall be stored under shelter and in sealed packing before use.
Abrasive shall be of the correct particle size to achieve the
specified profile and shall not leave any residue embedded in
the profile of the blast cleaned surface. Sand shall not be used
for blast cleaning.
Expendable abrasives shall not be recycled and shall be free
of contaminants, such as chlorides and other soluble salts, metallic
copper and not more than 2% by weight of copper oxide.
All dust, abrasive, debris and accumulations shall be removed
from the blast cleaned surfaces before coating begins by vacuum
cleaning, blowing with clean and dry compressed air, or with clean
brushes.
Nozzles for blast cleaning shall be of Venturi design and
shall be discarded when wear reaches 30% of the original bore.
All nozzles for blast cleaning shall be provided with remote
control of the blast stream. The remote control mechanism shall
be kept in good working condition and shall only be kept in the
"on" position by the operator's hand during blast cleaning.
Blast cleaning and preparation of the shop applied linepipe
coating, adjacent to field joints shall be carried out in accordance
with the approved procedures for the selected field joint coating
material. The FBE landing and adjacent PE parent coating shall
be sweep blasted to provide a key for the liquid applied field
joint coating system. Hand abrading of the exposed FBE may be
used as an alternative to sweep blasting (under no circumstances
shall the FBE toe be completely removed during blast cleaning
the intention is that the surface shall be roughened by the bias,
process only). The PE coating shall be sweep blast cleaned for
a minimum distance of 75mm from the edge of the field joint area
to provide a key for the field joint coating.
Where specified flame treatment shall be applied as a preparation
treatment for the HDPE coating for a distance of 75mm from the
edge, in accordance with an approved procedure. Flame treatment
shall be applied on pipeline sections that are to be installed
using horizontal directional drilling or thrust bore and on pipeline
sections designated as having an operating temperature above 50ºC.
3.3 Power Tool Cleaning
Power tool cleaning shall not be permitted as a general alternative
to blast cleaning for field joint surface preparation. The use
of power tools for localised areas may be permitted subject to
approval by COMPANY of the relevant procedure.
3.4 Air Quality
Compressed air for surface preparation (or coating application)
shall be free of oil and condensed water. These shall be determined
daily with a blotter test. If necessary, after-coolers shall be
provided to reduce the water content to an acceptable level. Traps,
filters and separators shall be regularly emptied and cleaned.
3.5 Ambient Conditions
No final surface preparation shall be carried out when the
following conditions exist, or are likely to occur in the near
future:
temperature of the steel surface is less than
3ºC above the dew point of the surrounding air
temperature is outside the limits set by the manufacturer
air temperature is below 5ºC
wind is raising dust (unless work is being carried
out under cover)
during rain (unless work is being carried out
under cover).
MANUFACTURER's recommendations for maximum allowable relative
humidity shall be observed. In all cases, the required surface
cleanliness grade shall be evident on the surface of the steel
at time of coating application.
4. APPLICATION AND
REPAIR OF
COATINGS
4.1 General
A liquid applied field joint coating procedure shall be developed
by the CONTRACTOR to ensure consistent quality specifically with
regard to cure, film thickness, adhesion and low temperature flexibility
characteristics.
The coating system shall be urethane modified epoxy, SPC
2888 RG (manufactured by Speciality Polymer Coatings Inc.)
All coating materials shall be mixed, applied and cured in
accordance with this Specification and MANUFACTURER'S written
instructions and datasheets.
The coating shall not show a tendency to "curtain"
when applied to a vertical surface. It shall possess good flow
characteristics and give a smooth continuous film of uniform appearance.
The applied coating shall have adequate adhesion, to steel and
polyethylene, as proven by the adhesion test.
The coating application process and repair technique shall
comply with the established written procedure, which shall define
all relevant details including: coating name, data sheets, pipe
cleaning, blast cleaning medium and technique, surface quality,
dust removal, coating application, curing procedure and coat stripping
technique. The application procedure used during the pre-qualification
testing once qualified shall be strictly applied and monitored
to ensure consistent application quality.
The shop applied linepipe coating, adjacent to field joints
shall be decontaminated as described in 3.1 above. The surfaces
of the FBE landing and adjacent PE parent coating shall be prepared
strictly in accordance with the MANUFACTURER's instructions and
the approved coating procedure. The PE coating shall be cleaned
and prepared as stated in Section 3.2 of this specification. .
All post application testing shall extend over the whole field
joint area and the 75mm liquid coating overlap.
Inspection and testing during production shall be as detailed
in Appendix B of this Specification
The coating materials shall be stored and applied by CONTRACTOR
in accordance with MANUFACTURER's recommendations. An adequate
proportion of the field joint coating material shall be provided
in small packs. The coating system applied to a particular item
or group of surfaces shall be the product of one MANUFACTURER.
All coatings shall comply with proposed UK Department of
the Environment regulations for Volatile Organic Compounds (VOC)
content for year 2000.
4.2 Condition of Coating Materials
Coating materials shall be delivered in their original, sealed,
undamaged containers with name of MANUFACTURER, product reference,
batch numbers, shelf life and storage requirements clearly marked.
Containers shall remain unopened until required for use.
Coating materials shall be stored in a safe, dry enclosure
or building in accordance with local laws, MANUFACTURER's printed
recommendations and Contract safety regulations. The storage location
shall be adequately ventilated and containers shall not be exposed
to direct sunlight during storage. With local high ambient temperatures,
temperatures within enclosures/buildings shall be maintained in
the range as recommended by MANUFACTURER. Materials shall be handled
in such a manner to prevent damage or contamination that would
make them unsuitable for use. Any material, which exhibits evidence
of contamination or deterioration, shall be rejected.
Field joint material products shall be used in chronological
order of the date of manufacture. Coating materials whose shelf
life has expired shall not be used. Coating materials, which have
deteriorated during storage, shall not be used. In all cases where
deterioration is suspected, the MANUFACTURER's guidance shall
be obtained.
4.3 Preparation of Coating Materials
Individual components of two-part (or more) coating materials
shall be mixed strictly in accordance with MANUFACTURER'S requirements
and the approved procedure.
Particular attention shall be paid to adequate mixing to
ensure that all components are fully dispersed in the medium prior
to application. Materials shall not become fouled or contaminated,
or allowed to thicken unduly from evaporation.
The pot life of coating materials shall be noted and monitored.
Any mixed coating material, which has exceeded its pot life, shall
be discarded regardless of the apparent condition.
4.4 Coating Application
Field joints shall be prepared and coated only after the
joint has been radiographed, visually inspected and accepted by
COMPANY.
Coatings shall be applied to surfaces that are free of dust,
moisture, oil and grease, residues of welding, salt, mud, rust
staining and any other form of contamination.
Immediately after the surface preparation to the required
standard, the coating shall be applied in a single coat to a thickness
in accordance with section 4.5 of this document and the MANUFACTURER's
recommendations. The coating shall extend over the prepared "toe"
of FBE and the prepared 75mm of PE at each side of the joint.
A uniform coat shall be applied.
The coating system shall be hand applied using a roller,
although spray application may be used. Spray application, however,
shall not be used on pipeline sections designated as having an
operating temperature above 50ºC.
4.5 Thickness Tolerance
The dry film thickness of the coating shall be a minimum
of 750 microns and a maximum of 1,250 microns. While the thickness
of the coating in some areas may exceed the stated maximum limit,
any which exceeds the MANUFACTURER'S recommended maximum shall
be grounds for removal; and reinstatement of the coating. CONTRACTOR's
procedures for thickness measurement shall include proper calibration
of equipment and for the use of suitably qualified personnel.
4.6 Repair of Coatings
Repairs to coatings shall be carried out in accordance with
the approved procedure. Repaired areas shall match the properties
of the main coating. All repairs shall be holiday tested.
Defective and damaged coatings shall be removed by scraping,
abrasive disking or sweep blast cleaning until a surface suitable
for repair coating is obtained. Overall preparation shall be used
if it is not possible to identify local areas of damage.
Areas of damage exposing the substrate shall be prepared
by spot blast cleaning and then coated again fully. Areas of damage
not exposing the substrate shall be washed down, allowed to dry,
the edges chamfered (without damaging underlying coating layers)
and the coating repair system applied.
The first 25mm of intact coating surrounding the damage shall
be feathered to a fine edge by sanding or disking taking care
not to damage underlying coatings.
At cathodic protection cable connection points made at field
joints (minimum distance between circumferential weld and cable
connection point shall be 75mm), the damaged coating shall be
repaired with a liquid applied repair grade material in accordance
with an approved procedure and holiday tested. The coating shall
extend over the connection point and onto the cable insulation.
5. INSPECTION AND
TESTING BY
CONTRACTOR
The inspection and testing requirements are as described
below and as summarised in Annex A for prequalification testing
and Annex B for production field joints.
5.1 Environmental Conditions
The following shall be measured and recorded at least four
times a day, including once at the start of each shift, and shall
relate the values to the requirements of this Specification:
dry bulb temperature (hygrometer)
wet bulb temperature (hygrometer)
substrate surface temperature.
5.2 Visual Inspection
Each field joint shall be visually inspected after application
of the coating. The field joint coating shall consist of a uniform
film that is free of runs, sags, misses, dry spray, blisters,
pinholes, poor bonding, laminations, porosity, air entrapment
at welds and is uniform in colour and properties when cured. There
shall be no visible runs, sags or bubbles. The examination shall
include checks for soft spots.
5.3 Holiday Testing
After application of the coating, field joints shall be 100%
holiday tested generally in accordance with NACE RP0274. All post
application testing shall extend over the whole field joint area
and 200mm onto the parent coating. The holiday test shall be carried
out at 4 KV, using a portable instrument. A fine wire metallic
brush electrode shall be used with a travel rate of 300mm per
second. Equipment shall be earthed as recommended. CONTRACTOR's
procedures for holiday testing shall include details of calibration
techniques. The maximum number of acceptable holidays per field
joint or coated item is four. If two consecutive pipe joints show
more than two holidays, the cause shall be investigated immediately.
If four consecutive pipe joints fail, the coating process shall
be stopped until the cause is determined. Pipe joints with more
than four holidays shall be stripped and re-coated. All holidays
shall be repaired and re-tested.
5.4 Thickness Testing
The coating thickness over bare steel at every field joint
shall be measured at five equidistant locations and recorded.
Every reading shall be in accordance with Section 4.5. The coating
thickness instrument shall be calibrated hourly.
5.5 Impact Resistance
Once fully cured, the impact resistance of the coating applied
over bare steel shall be tested to ASTM G14 and shall withstand
an impact of at least 1.5J without a holiday being caused (J =
9.81 * impact height (m) * impact weight (kg). Frequency of testing
shall be four locations 50mm apart on the crown of the pipe every
100 joints. Test will fail if a holiday is found at any impact
test site. Holiday test to be carried out as defined in 5.3 above.
If impact resistance is found to be below the required value then
further tests shall be carried out to determine the reason for
failure and the coating process modified to conform to the requirements
of this document. All affected items or field joints between the
failed item or field joint and the last acceptable test location
shall be stripped and re-coated.
5.6 Adhesion Strength
The adhesion of the field joint coating shall be determined
at all three interfaces at ambient temperature at two locations
by the "St Andrews Cross" method. Using a sharp knife
two straight incisions shall be made in the coating through to
the steel, the FBE or the PE, as appropriate. The incisions shall
intersect at an angle of 30º/150º The coating shall
resist disbondment when attempts are made to lift it from the
30º angle with the point of a sharp knife. Tests shall be
carried out at the frequencies required in Annex A and B.
Adhesion of the field joint coating shall also be determined
after hot fresh water soak at 50ºC for 21-28 days.
Ranking | Result
|
Fails adhesively as a complete | 0
|
Pees in large pieces adhesively from substrate
| 1 |
peels in small pieces adhesively from substrate
| 2 |
Peel cohesively in large pieces | 3
|
Refuses to peel or peels cohesively in small pieces
| 4 |
| |
The coating shall be considered a pass if the adhesion strength
determined from the above table is met as follows.
Over PE- Minimum result: =/> 1
Over Steel and FBE, Minimum result: =/> 3
5.7 Penetration Indentation Test
Three samples shall be cut from three separate field joints,
and tested for resistance to indentations in accordance with ASTM
G 17. The test shall be performed at design temperature of 23ºC
and 74ºC. Maximum penetration depth exhibited after testing
shall not exceed 5% of the coating thickness. The test result
at 74ºC is for information only.
5.8 Hardness
The hardness of the coating layer shall be measured according
to ASTM D-2240-91. The minimum value shall be 80 Shore D. The
test shall be carried out on the fully cured coating.
5.9 Cathodic Disbondment Testing
Pre-qualification cathodic disbondment testing shall be performed
for 28 days at an electrolyte temperature of 23ºC and 74ºC
(~ 2ºC). Electrolyte shall be 3% NaCl in ionised water. The
Holiday size shall be 6 mm. The acceptance criteria shall be 6
and 8 mm respectively average radial disbondment from the edge
of the predrilled hole. The test shall be performed in accordance
with CSA-Z245.20-M92. The test result at 74ºC is for information
only.
The Contractor may propose alternative cathodic disbondment
test standards (eg ASTM G42) and methods, providing the essential
requirements of this Specification are retained. Any such alternatives
shall be submitted to COMPANY for review and approval.
Table 1 APPROXIMATE DESIGN ENVIRONMENTAL DATA
Design life | 40 years
|
Pipeline material | API 5L, longitudinal seam or spiral welded linepipe
|
Pipeline wall thickness | 12.7 to 23.8 mm approx
|
Pipeline design temperature | Maximum service temperature 74ºC
|
Pipeline construction method | Laying in open trench with subsequent backfilling (some HDD and thrust boring possible)
|
Concrete weight coating (special crossings)
| Applied by mould or compression coat process
|
Protection potential range of steel ("instant off" value), versus Cu/CuSO4
| more negative than minus 850mV to of the order minus 1,200mV
|
Coating defect surveys (full pipeline) |
holiday testing at mill and prior to laying. Direct current voltage gradient after laying. Coating defects to be repaired.
|
Soil temperature, 1m depth | 0ºC to +35ºC
|
Soil types | typically wet, with clay and gypsum possible (wet/dry cycles possible) some areas stony and rocky
|
Soil resistivity | Can be below 10ohm.m (severely corrosive)
|
Water table | 1m assumed |
Temperature in shade (air), in direct sunlight
| -26ºC to +43ºC, +78ºC max |
Elevation, m | up to 3,000 above MSL
|
Relative humidity | 100% max
|
Environment air quality | exposedcorrosive to non-pollutednon corrosive wind borne salt and sand very fine clay-like dust
|
| |
Annex A
INSPECTION/TESTING SUMMARY, PREQUALIFICATION
LIQUID FIELD JOINTING MATERIAL
Property | Relevant
Clause
|
Acceptable Values |
Number of Tests*
|
Before Cleaning | |
| |
Pipe condition | 3.1 | No weld spatter, sharp
edges, surface clean
| Full surface each joint |
Chlorides | 3.1 | No chlorides
| 2 locations each joint |
Oil contamination | 3.1 |
No indications of oil
contamination | Full surface
|
After Cleaning | |
| |
Cleanliness | 3.2 | Sa 2
| 2 locations each joint |
Profile | 3.2 | 75-100 m
| 4 locations each joint |
Chloride | 3.1 | No chlorides
| 2 locations each joint |
Dust, Oil & other
contamination |
3.2 | No indications of dust, oil or other contamination
| Full surface each joint |
AFTER COATING | |
| |
Visual Examination |
| | |
Field joint coating | 4.1 |
Test for cure ASTM
D5402. | Random each joint
|
Visual Examination |
| | |
Field joint coating | 5.2 |
Free of runs, sags, misses, dry spray blisters, pinholes, soft spots etc.
| Full surface each joint |
Coating Thickness |
| | |
Field joint coating | 4.5 |
750m-1,250m | 5 locations each joint
|
Holidays | |
| |
Field joint coating and over | 5.3
| No holidays (4 KV) | Full surface each joint PE
|
Adhesion Strength |
| | |
Over PE | 5.6 | Refusal to lift, no
separation of layers
| 2 locations each joint |
Over Steel | 5.6 | Cohesive, no lifting
| 1 location each joint |
Adhesion Strength/Hot Water Soak Test
| | | |
Over PE | 5.6 | Refer to section 5 . . .
| 1 location each joint |
Over . . . Steel | 5.6 |
| 1 location each joint |
Impact Resistance |
| | |
Over Steel | 5.5 | . . . (minimum) ASTM G14 and to failure, report impact values
| 4 locations each joint |
Penetration (indentation) |
| | |
Field joint coating | 5.7 |
5% of coating thickness maximum, at 23ºC and 74ºC
| 1 location each joint |
Hardness | |
| |
Field joint | 5.8 | Minimum value: 80 Shore D
| 1 location each joint |
Cathodic Disbondment |
| | |
Field joint coating | 5.9 |
28 day testAverage radius of disbondment <8 mm @ 74ºC and <6 mm at 23ºC
| 1 location each joint |
DESTRUCTIVE TESTS | |
| |
Flexibility Bend Test |
| | |
Field joint coating | 4.1 |
At ambient and at minus 30ºC. No cracking/disbondment or pinholes
| 1 location each joint |
| | |
|
* Number of Tests can be increased at the sole discretion of the
COMPANY. Surplus pipe shall be ordered to allow for losses due
to testing.
Annex B
INSPECTION/TESTING SUMMARY, PRODUCTION
LIQUID FIELD JOINTING MATERIAL
Property | Relevant
Clause
|
Acceptable Values |
Minimum Frequency*
|
Before Cleaning | |
| |
Pipe general condition | 3.1
| No dents, scabs, slivers, burrs, gouges etc
| Each field joint |
Chloride | 3.1 | None
| 1 per 10 pipes at 3 locations |
Oil | 3.1 | No indication of oil
contamination
| 1 per 10 pipes |
Blast Cleaning | |
| |
Grit type and size | 3.2 |
| Random |
Pipe condition | 3.2 | Conditions AandB of ISO 8501-I
| Each field joint |
Surface profile | 3.2 | SA2.5 with anchor pattern 75 to 100µm
| Each field joint |
Relative humidity | 3.5 |
<85% unless pipe is heated above DP | Each field joint
|
Elapsed time | 3.5 | Relative to Humidity
| Each field joint |
After Cleaning | |
| |
Cleanliness | 3.2 | Sa 2.5
| Each field joint |
Profile | 3.2 | 75-100 µm
| Each field joint |
Chloride | 3.1 | No chlorides
| 1 per 10 pipes |
Dust, Oil and other contamination | 3.2
| No indications of dust, oil or other contamination
| 1 per 10 pipes |
COATING PROCESS | |
| |
Pipe pre-heating | 4.1 |
Max pre-heat 80ºC (pre-heat dependent upon environmental conditions)
| As required to promote cure |
AFTER COATING | |
| |
Visual Examination |
| | |
Appearance of coating | 4.1
and 5.2
| No surface defects or soft spots | Each field joint
|
Longitudinal Welds | | No air entrapment
| Each field joint |
Coating Thickness |
| | |
Field joint coating | 4.5 |
750m -1,250m | Each field joint. 5 locations
|
Holidays | 5.3 | No holidays (4 KV)
| Full surface each field joint |
Adhesion | |
| |
Over PF
Over steel | 5.6
| | 1 per 100 joints, 3 locations, one over steel and 2 over PE, ie one each side of welded joint
|
Impact Resistance |
| | |
Over Steel | 5.5 | ...-J (minimum) ASTM G14
| 1 per 100 joints |
| | |
|
* COMPANY reserves the rights to increase inspection and testing
frequency if warranted by the circumstances.
BP CASPIAN DEVELOPMENTS
AGT PIPELINES PROJECT
REVIEW OF FIELD JOINT COATING SPECIFICATION No. 410088/00/L/MW/SP/015
(issue 02.10.02)
All comments made in this document reflect the fact that
BP have named the coating product to be used, with no alternatives
to the contractor.
1.1.2 "The external coatings shall be suitable for
the operating conditions to which they are subjected and shall
have proven good resistance to cathodic disbondment".
BP must therefore have clear, incontrovertible proof that
the named product will meet this clause. Probably the worst case
condition for an epoxy is immediately downstream of early main
pumping stations where the coating will be running hot, maybe
up to 70ºC in fully immersed state at different times of
the year, and of course its suitability must be validated for
the design life of the pipeline, namely 40 years PLUS.
2.2 "The contractor shall fully comply with the
HSE requirements of the contract. Contractor shall ensure that
all work and storage is performed in accordance with all applicable
laws affecting health and safety at work and follow recommendations
of manufacturer".
BP must have already subjected the named product to detailed
chemical analysis and COSHE risk assessment and be satisfied that
there are no health and safety risks to personnel in the use of
this material and no risk to environment particularly as the epoxy
will be mixed and applied on open site where the pipeline crosses
waterways and over shallow aquafers. More than 500,000 litres
of the liquid epoxy will be imported if all the joints are coated
this way. It will all be transported by truck to point of use.
Accidents will happen. Spillages will occur.
2.4 "Contractor shall provide the following procedure
where applicable: Coating materials, storage, application and
repair, . . . Measures to be adopted during periods of adverse
weather".
BP are specifying, by name with no alternative, the coating
material. The construction work will take place in ambient temperatures
from +40 to -20 degrees C. BP must know therefore how this material
behaves in this temperature range.
The contractor by definition is a pipeline builder not a
paint technologist. He must be instructed in the proper use of
the nominated product.
The reality is that epoxies do not normally cure at 5ºC
or below and amine materials crystallise at 0ºC and cannot
be reconstituted.
What is "adverse weather"rain, snow, high
wind, low temperatures, high temperatures?
Company is nominating the product to be used but not now
to use it, is this because the company does not know how to use
it in "adverse" conditions? The contractor who will
never even heard of this material before, certainly will not know
how to use it and will be within his rights to ask for instruction.
NOTEno pipeline owner has been identified who specifies
this product, for this exact purpose, anywhere in the world. It
has limited use as field joint coating on FBE coated pipe in Canada
but not on PE coated pipe.
It therefore cannot be considered as "best industry
practice" or even "normal industry practice" so
how can contractor be expected to produce definitive procedures
and how will company be able to agree validity of procedures if
it does not know how to use the material anyway?
2.6 "Two full field joints shall be prepared and
coated under conditions that replicate those expected in the field;
one joint shall be coated by spray method and the other by hand
using a brush or roller".
BP tested the product applied by spray and brush. No testing
was carried out at Advantica on roller applied material.
3.1 "After cleaning, unless otherwise approved,
the field joint shall be uniformly heated to 80ºC to remove
all moisture and to preclude any condensation of moisture on the
surface after blast cleaning. Also if environmental conditions
require it, the steel substrate shall be preheated to a maximum
of 80ºC by induction method immediately before application".
Will this heating procedure remove all moisture from undercut
areas? Has it been tested? How are we defining the requirements
of "environmental conditions"?
Heat, cold, wind, rain, snow? When is secondary preheat required?
The contractor cannot be expected to know, he must be instructed.
3.2 "The FBE landing shall be sweep blasted to provide
a key for the liquid applied field joint coating system. Hand
abrading of the exposed FEE may be used as an alternative to sweep
blasting (under no circumstances shall the FBE toe be completely
removed during blast cleaning the intention is that the surface
shall be roughened by the blast process only). The PE coating
shall be blast cleaned for a minimum distance of 75mm from the
edge of the field joint area to provide a key for the field joint
coating."
Leaving an exposed toe of FBE at the cut back on three layer
coated pipe has been a standard practice for some pipe coaters
for some time. Eupec have provided this on the BP ACG Group offshore
pipeline, of their own volition. They refer to it as the "WEATHERING
TOE", its use has arisen out of undercut problems being experienced
at the cut back areas on three layer coated pipe when stored for
some time before use. However, the toe that they offer is between
15-50mm long with no guarantee on thickness. Bredero and PPSC
are installing the same end cut equipment at the Kuantan plants.
The FBE toe provided to BP will vary in length and very significantly
in thickness. Some toes will only have a few microns of FBE over
the original blast profile and some will have significant traces
of PE copolymer left on. Clearly this specification does not recognise
this. An assumption has been made that the toe will be present
in a definably secure condition on every one of 500,000 pipe ends,
it will not. No provision has been made for anything else. What
action should be taken if the toe is not present? If new toe has
to be made by end cutting the PEhow is this to be done?
There is no known way to accurately recut the coating end by hand.
Who pays?
This last question is easy, BP pays. Why? Because experience
over many years has shown us what happens to FBE coating cut backs
and the contractor would be right in assuming that BP know how
the exposed FBE will behave when pipe is stored. The reality is
that BP do not know.
Where the FBE has been "skimmed" so that only 0-100
microns is left on the pipe, then there is too little FBE left
OVER the blast profile. This weak structure will take up moisture,
corrosion will be initiated UNDER the FBE. When the field joint
crew "dry out" the joint, as specified, this friable
material will "fly" when blasted or abraded. Where corrosion
deposits have formed beneath the FBE then it must be removed anyway!
What should the contractor do in this circumstance? Obvious, ask
for clients instructions, and any subsequent actions will be at
the clients cost.
Where the FBE is full thickness but with traces of copolymer
evident, what action should the contractor take? You cannot peel
the PE off, it is molecularly hooked to the FEE, to remove it
you have to remove part of the FEE. What happens if, when wire
brushing, all of the FBE is removed from part of the circumference?
Does contractor re-cut end? How? Who pays?
With regard to blasting the PE, this can only be done very
lightly as the PE will "fly" if blasted vigorously.
3.2 cont. "Where specified flame treatment shall
be applied as a preparation treatment for a distance of 75mm from
the edge. in accordance with an approved procedure."
What flame treatment and why?
No testing was carried out at Advantica on flame treated
ends.
Experimentation has been carried out on heat treatment of
PE by a number of authorities including this author who has tried
radiant heating, selected spectrum IR heating and propane torching.
Resultno discernable difference in adhesion of liquid urethanes
and epoxies to PE. Whybecause the root causes of the adhesion
problem are not addressed in any way by flaming the PE, rather,
the low energy aspect is made worse by flaming, not better!
No change can be made to the non-polar nature of the PE,
the epoxy exerts no chemical change at the interface so that only
leaves the possibility of mechanical treatment of the overlap
area as a means of improving adhesion. Why was this not tested/specified?
Experiments have been conducted on all types of scarification,
the information is availablebut was not sought.
"Flame treatment shall be applied on pipeline sections
that are to be installed using horizontal directional drilling
or thrust bore and on pipeline sections designated as having an
operating temperature above 50ºC"
Why? Adhesion, which is paramount for thrusts, is not changed
by flaming, Flaming cannot improve performance regarding in-service
temperature at all.
The reality is that the epoxy will have very poor adhesion
to PE at overlap areas and when pipe is thrust bored in cold weather
the epoxy will come off.
The "hot" areas will present a different but equally
damning problem, thermal cycling testing has shown that the epoxy
will crack circumfrencially at the transition area of original
coating/steel. The reasons for this are clearly apparent but appear
to have been disregarded.
3.5 "No final surface preparation shall be carried
out when the following conditions exist or are likely to occur
in the near future; temperature is outside the limits set by manufacturer.
Air temperature is below 5ºC".
<5ºC will be experienced throughout the winter period.
Should construction shut down for four months just because of
the paint?
Obviously the low temperature problem is a macro one. Can
the work proceed if a local micro condition can be established
at appropriate temperature? If so, why do we not say so?
4 . . . "The coating application process an repair technique
shall comply with the established written procedure, which shall
define all relevant details including . . . , curing procedure
and coating stripping technique . . . "
The contractor cannot know how to cure the applied epoxy
in all conditions and will ask for instruction from BP. Do we
know how to cure it? What work has been done to prove a stripping
technique?
4.4 "The coating system shall be hand applied using
a roller, although spray application may be used. Spray application,
however, shall not be used on pipeline sections designated as
having an operating temperature above 50ºC."
For the second time the spec calls for roller application
when this was never at any time tested prior to issue of spec.
When may spraying be done? Whose decision is it? What technique
will be allowed? Manual or auto?
Spraying will cause some atomised emissions, has BP had this
product and process subjected to COSHE risk assessment? If not,
then how could this spec have been issued to contractors, we are
in contravention of our own HSE rules.
Why can't spraying be done on the "hot" pipes?
It makes no sense.
Lastly the product comes in two totally different forms for
hand and spray application (see Advantica report) whichever the
contractor buys then he can only use one application process.
If he buys boththen mix up will occur.
4.5 "The dry film thickness of the coating shall be
a minimum of 750 microns and a maximum of 1250 microns"
Applying an amine cured epoxy in these thicknesses in one
pass is totally outwith normal paint industry practice. The material
is described as a "URETHANE MODIFIED EPOXY" but the
HSE data sheet issued by manufacturer shows no iso-cyanate or
other urethane components in the formulation. Applying epoxy to
this thickness will render the cured film brittle. Flexibility
is a primary requirement of all pipe coatings, lack of this quality
will reveal itself when "snaking" pipe into the ditch
in cold weather. Thermal cycling and strain polarisation tests
over the coating/steel transition area reveal this materials lack
of flexibility graphically. Test reports are in BP possession.
5.5 Impact Resistance
The spec calls for this test to be carried out on the coating
applied to the steel only. It is an absolute requirement that
the coating applied over the PE has sufficient impact resistance
to resist backfill impact as if it shatters the resulting cracks
will transmit into the coating on the steel.
Experience has shown this to be the case.
The reality is that the brittle epoxy over a flexible PE
will be cracked on impact In cold weather.
5.6 Adhesion Strength
"The adhesion of the field joint coating shall be determined
at all three Interfaces at ambient temperature at two locations
by the `St Andrews Cross' method.
Adhesion of the field joint coating shall also be determined after
hot water soak at 53 degrees C for 21-28 days".
The St Andrews Cross test is a simple "watershed"
test ie, pass or fail. The ranking system of result is on a scale
of 1-5 or in this spec, 0-4.
This spec states that a result of 1 on PE (Peels in large
pieces adhesively from substrate) is a pass. It is not, it is
a failure. It is clearly a failure in any other spec and to any
recognised standard. Most of all, it is a failure if common sense
is applied. No coating that peels off the substrate in large pieces
can possibly be acceptable. What this spec recognises is the inability
of the nominated material to adhere properly to PE. The acceptable
result on steel is stated as 3. This is the minimum acceptable
on PE.
The evidence of this clause is clear regarding item 5.5 above.
With regard to the hot water soak, do we test after 21 or
28 days or both?
5.7 Penetration Indentation Test
"Test shall be performed at design temperatures of 23
degrees C and 74 degrees C. Test result at 74 degrees C is for
information only".
Pipeline will run close to 70 degrees C in places and the
design life is 40 years PLUS.
If test fails at 74 degrees it is a FAIL result.
5.9 Cathodic Disbondment Testing
As above, spec says results at 74 degrees C are for information
only.
Pipeline is designed to run dose to this temperature for
over 15,000 days!
Failure to meet test criteria at operating temperature (or
very close to it) can only be considered as a FAILURE.
CONCLUSION
There are three elements to my conclusion:
1. Implications of the form of the specification
2. Potential contractual impact
1. It is clearly a serious mistake for BP to nominate
one material only.
We remove the contractors normal commercial negotiating ability
with his suppliers. We assume responsibility for performance of
the material. Comment is made above regarding the serious problems
of transportation, storage, mixing and cure.
In my opinion we are in contravention of European law with
regard to restraint of trade. We must hope that no supplier of
FJC materials takes this up.
It is not normal BP practice to specify in this way.
We are specifying material and application that is not "best
industry practice" or even "normal industry practice"
we are in fact completely out on a limb, we cannot identify any
pipeline owner who uses this epoxy by this application on PE field
joints anywhere in the world.
2. There are many openings for the contractor to justify
extraover costs. Clearly the use of the named material is going
to lead to a serious problem, particularly during the colder months,
with curing the applied paint. The joint areas are going to need
cover and heat during preparation, application and curing. Storage
at site will need to be in temperature controlled conditions.
Freezing will render the material unusable.
In use, the material is a known irritant and though the safety
data sheet states "Reproductive toxicityNone known",
it contains 5-15% Bisphenol A which is a known endochrine disruptor.
It is not possible for the company to issue this specification
to the contractors unless we have confirmed it fits with our HSE
policy totally, if it does not fit, spec should be withdrawn immediately.
The performance of the epoxy is contingent on the 2"
FBE toe being present. It wont be. Are we going to instruct contractor
that if he removes any of the toe during blasting that he will
have to re-cut the end of the coating? Because he will be removing
some or all of this toe on many of the joints and it will not
be his fault. He will be able to prove this very simply. Re-preparation
of ends will be at our cost and we will have to instruct re process.
Impact of backfill in cold weather will damage epoxy, particularly
on overlap areas. Post lay overline survey will reveal damages
through to steel. Who pays for repair? The contractor will be
able to prove the weakness of the system in cold conditions. Costs
for repairs could be astronomical.
3. FINAL COMMENT
I am at a loss to understand why this specification has been
issued.
Purely as a coating specification it is under developed and
incomplete. As a field joint coating specification on a major
pipeline it is utterly inappropriate as it does not confirm a
protective system that can be successfully applied in all the
conditions under which this pipeline will be constructed, nor
does it confirm the integrity of the protection for the design
life of the pipeline.
It is by no means the cheapest option.
The potential for claims against the company is open ended.
There are available industry-standard FJC systems that meet
all of the requirements of this pipeline, these systems provide
seamless, end-to-end homogenus PE protection which remove all
of the uncertaincies of this specification. They are even specified
by BP on three layer coated pipelines! Were they not considered
here? and if not, why not?
Company needs to initiate action immediately in order to
avoid a serious problem.
Lastly I draw your attention to my comments re clauses 5.5,
5.6, 5.7 and 5.9. The wording of the specification is a tacit
admission that the system cannot meet specific requirements of
the pipeline. Have you considered the insurance implications of
this?
Copy of letter from Derek Mortimore to the CEOWorleyParsons
I am in receipt of your company's report titled:
DESKTOP STUDY
FINAL REPORT
FIELD JOINT
COATING REVIEW
REDACTED VERSION
This report is embedded in an Export Credit Guarantee Department
(ECGD)a division of the Department of Trade & Industry,
UK Government, report on their lending to this project. Their
report has been submitted to the Parliamentary Select Committee
on Trade & Industry to the instruction of that committee who
are currently investigating various matters. The committee have
passed the documentation to me for comment.
I understand that ECGD commissioned your company to carry
out an audit of the engineering specifications on which the construction
is based. Your re-written report is 24 pages long with six of
those pages dedicated to attacking me. You have spent 25% of a
so-called technical audit document attacking a man on the basis
of inaccurate information from someone within BP and one document
out of many I prepared for BP when working to their instruction.
This is incredible. You did not contact me at any time, nor asked
for any clarifications from me.
Needless to say your uninformed comments are dealt with in
uncompromising terms in my response to the committee as are your
technical comments, both by me and also by a leading authority
in the field.
I enclose a copy of page 14 of your report and under item
4.1 you will see that you have made a number of comments about
me.
I highlight only two although I have dealt with them all
in my formal response:
You state "After he issued his comments he asked to
be paid for his effort"this is totally untrue.
You state "Mr Mortimore's comments were fairly general
with a lack of specific technical details or references"they
were not, they were very specific but as my document of November
2002 is now in the committee's hands, it is for them to decide
the validity.
You criticise me for making comments on non-technical issues.
That was my duty. Your informant neglected to tell you that all
of these issues had been discussed in BP's Baku office and I was
specifically asked by my client to cover them in my review.
Over the six pages of your report that you dedicate to me,
you set out BP comments which were never made before in response
to my original specification review. This is the first time that
any of us have seen these comments. Clearly your informant had
not bothered to tell you that but you then go on to make a number
of your own comments. I will not detail further here but inform
you that every single comment is responded to in my review document
to the parliamentary select committee.
I must state that I am appalled that a company of your standing
has allowed itself to be used as the conduit for somebody's malice
towards me.
Your report clearly states that you did not verify any of
the documents you were given neither did you verify the accuracy
of any of the statements made to you by BP personnel, in view
of this I would be pleased to receive an explanation of your actions.
I hope you are aware that the committee sits in September
and after they reach a conclusion in the first matter they are
investigating, they then publish all the submitted documents on
the UK Government website so our whole industry can read your
uncalled for comments about me and my very detailed response and
total rejection of your report.
A copy of this letter is included in my submission to the
select committee.
Derek N Mortimore
26 August 2004
|