APPENDIX 6
Memorandum by Michael Gillard
I write this submission as a freelance journalist
with considerable experience investigating British Petroleum's
worldwide operations for national newspapers and television.
Working with others I have been responsible
for two World In Action documentaries exposing BP's human
rights and environmental record in Colombia. We have also written
investigative articles on BP in Alaska and Colombia for The
Guardian, when I was part of the investigation unit.
In Alaska, we exposed evidence from senior whistleblowers
that key safety equipment was malfunctioning and could cause a
major spill or explosion that escalated because of inadequate
emergency response plans. The main allegations of the whistleblowersBP
safety inspectorscentred on inadequate monitoring and preventive
maintenance of vital safety systems and equipment, and the falsification
of reports to show compliance with quality assurance programmes.
The articles helped US Congressmen and state
and federal regulators force BP to carry out a widespread audit
of its TAPS pipeline and oil terminals. It confirmed employee
concerns.
In the UK, the parliamentary International Development
Select Committee picked up on another front-page article that
had uncovered plans by BP's security department to supply arms
and training to the brutal Colombian armed forces protecting a
major new pipeline. We also exposed a spying operation against
the local communities living near the Ocensa pipeline, which BP
operates on behalf of an international consortium. MPs subsequently
grilled BP executives at a hearing in 1999. The oil company blamed
rogue elements in its security department.[79]
Most recently, on 15 February, 2004, I wrote
an article with The Sunday Times Insight team on BP's operations
in Azerbaijan and Georgia, where the oil company is operator for
an international consortium constructing an underground pipeline
from the Caspian Sea to the Mediterranean.[80]
The Baku-Tblisi-Ceyhan pipeline crosses archaeological
sites, nature reserves and 1,500 watercourses, from small streams
in the Caucasus Mountains to rivers and canals. Almost all the
route cuts through an active earthquake zone. Long-standing regional
conflicts with Armenian and Kurdish separatists add to the instability.
Unfortunately, again internal warnings were
ignored, this time claiming the BTC pipeline is being built with
a major design fault, which, if uncorrected, corrosion experts
warn will effectively see thousands of environmental "time
bombs" buried along the 1,000-mile route.
Ordinarily, this would not be a matter for this
committee but for the involvement of the ECGD and the comments
you have invited on its performance.
The committee may be aware that this year on
3 February the BP-led consortium secured a $2.6 billion loan agreement
with development banks, export credit agencies and commercial
banks for the construction of the BTC pipeline by the first quarter
of 2005.
It should be remembered that BP did not want
to build this pipeline. It was regarded internally as uneconomical
and wrought with reputation risk. The main impetus was the US
governments of Clinton and now President Bush, following BP's
merger with American oil giant, Amoco in 1998.
The BTC pipeline is the biggest and most challenging
BP has ever built. It is being constructed under the intense gaze
of international campaigners demanding the oil giant lives up
to its ethical commitments that followed the major environmental
and human rights scandals in Alaska and Colombia.
Neither of those pipelines have the geopolitical
significance of the BTC onethe first east-west energy corridor
that will reduce Anglo-American reliance on the Middle East and
OPEC.
In Whitehall, the pipeline is seen as vital
to Britain's energy policy as North Sea oil reserves dwindle.
It is also key to what analysts call the "New Great Game",
a geopolitical struggle between Presidents Bush and Putin for
control of the 15 new republics that emerged from the former Soviet
Union in 1991. Washington sees Azerbaijan and Georgia as bulwarks
against Russia and Iran. The Pentagon is training security forces
in both former Soviet republics to defend the offshore platforms,
oil installations and pipeline.
BP chief executive Lord Browne made it clear
to the Financial Times in November 1998 that there would
be no BTC pipeline without "free public money". BP,
who recently announced record profits of £15 billion, and
its BTC partners are putting in $1 billion of their own money.
This means 70% of construction costs will be met by loans from
the Lenders Group.
It is undisputed that without the support of
the World Bank, the European Bank of Reconstruction and Development,
political risk insurers and export credit agencies, among them
the US, French, Italian and Japanese governments, the commercial
banks, which includes the Royal Bank of Scotland, owners of NatWest,
would not have got involved in this mega-project.
In December 2002, Baroness Symons assured British
NGOs by letter that ECGD cover "would only be given if the
department was satisfied that the relevant environmental, social
and human rights impacts had been properly addressed and the financial
and project risks were acceptable."
A year later, the EBRD described the benefits
of the BTC project to Azerbaijan and Georgia in these terms: "The
application of the highest international environmental and technical
standards, highest health and safety standards."
On 17 December 2003 Mike O'Brien, the minister
responsible for the ECGD, informed parliament he was agreeing
with his department's recommendations to provide $150 million
cover. He said the decision was made after "a rigorous assessment
of the risks associated with the project and a thorough review
of the environmental, social and human rights impacts".
So it was that on 3 February, 2004 at the official
signing ceremony in Baku, the capital of Azerbaijan, the ECGD
agreed to provide cover of $106 million, approximately £58
million.
Before financial closure and up until the eve
of publication on 14 February, we were in discussion with the
ECGD. It, along with other members of the Lenders Group, assured
The Sunday Times that its cover came with unprecedented
levels of environmental and social monitoring during the construction
phase and afterwards.
In the ECGD decision document we noticed it
had referred to being in receipt of "allegations concerning
the quality control systems in use for construction of the pipeline."
We asked for further details and received this response:
"During the early construction phase of
the pipeline in June 2003, a contractor working for BTC experienced
some difficulties in producing welds of sufficient quality. The
company informed the lender groupthe banks, export credit
agencies, including ourselves and the IFC and EBRDof these
problems (which) aren't uncommon in pipeline construction.
"They confirmed all the faults would be
eliminated prior to the pipeline being laid underground. A few
months later we received allegations through an NGO (Corner House)
that the welding quality and the contractor's quality control
systems were not adequate. ECGD passed this information on to
the company, which indicated that it was in fact the same problem
they'd brought to our attention earlier.
"BTC reconfirmed that the Quality Control
systems for the construction of the pipeline were sufficiently
rigorous and all poor quality welds were being cut out and re-welded.
Something to bear in mind, the lenders group, which includes ECGD,
do have independent engineers and we are also checking on the
Quality Control systems as part of their regular monitoring visit
to the sites. Also, when the pipeline is actually physically completed
it will be tested both for the company itself but also for the
lender to check that it is fit for purpose.
"The documentation explicitly requires BTC
to inform us of incidents that are likely to have significant
environmental or social impacts. The fact that a number of welds
had failed their tests and were going to be cut out and re-welded
would not be classed as something significant, as this is part
of normal construction process of pipelines. Any leaks during
the operation would need to be reported to us however. But oil
isn't expected to be flowing through the pipeline until 2005,
so we are some time away."
The ECGD press office also told us it would
expect BP to make it aware of any issues that might affect the
integrity of the pipeline. And confirmed that the welding problems
in June 2003 were the only issues reported by BP before financial
closure on 3 February. The spokeswoman reassured The Sunday
Times it had been carrying out "extensive due diligence
for over two years before financial closure."
ECGD also told us that at financial closure
BP/BTC was "required to warrant that they have provided all
relevant information including that which relates to environmental
and social issues." Drawing down on the now agreed loan would
be prevented, ECGD said, if there was a default or "other
events occur that have a material adverse effect on the project."
All these unequivocal statements came after
the ECGD press officer had made over a week of extensive inquiries
of her colleagues at our insistence.
The Sunday Times investigation had by
this time already established the following facts, none of which
BP made known to ECGD nor were they picked up by its much-vaunted
independent monitoring systems:
In May 2002, two BP managers in BakuPaul
Stretch, Technical Manager, and Rod Hensman, Senior Project Engineerwere
concerned about proposals coming from London for coating the field
joints of the BTC pipeline. These are the welds on each 11.5 metre
section of the steel pipeline. There are approximately 150,000
field joints on the pipeline.
Stretch had been in the Caspian region for 10
years. He was responsible for ensuring all engineering aspects
were satisfactory to BP.
He and Hensman had received a report from a
Mr Trevor Osborne, BP's materials consultant for the BTC project.
BP had put together a Design Group based at the West London offices
of the US construction giant Bechtel. In June 2001, Bechtel had
won a US$150 million contract to provide procurement and detailed
engineering for the Azerbaijan and Georgia sections of the pipeline.
They contracted John Brown Engineering, who in turn contracted
Osborne.
Such was their concern about Osborne's report,
Stretch and Hensman commissioned a leading pipeline integrity
consultant called Derek Mortimore to review it. He was already
working for BP on its offshore operations in Baku.
The two BP managers were concerned Osborne's
report appeared to favour the use of a liquid epoxy paintmanufactured
by a Canadian company called Speciality Polymer Coatings (SPC)for
coating the field joint. Mortimore immediately felt this would
be a serious mistake.
Each section of steel pipe has a plastic "jacket"
to protect it from external corrosion. After the sections are
welded together on site, the field joint is coated with an anti-corrosion
paint. To be effective, the field joint coating must bond permanently
with the steel and the plastic. It must also be hardy but flexible
to earth movements when buried. Liquid epoxy paint was known to
have good adhesion to steel and poor adhesion to plastic.
Mortimore advised Hensman to find a proven alternative
as he predicted the Canadian coating, SPC 2888, wouldn't bond
to the plastic and could crack in the winter leaving the steel
pipe dangerously exposed to corrosion.
In effect, he argued that each field joint would
be a buried environmental time bomb waiting to explode as one
million barrels of hot, high-pressured oil coursed through the
pipeline daily.
On 27 July 2002, Hensman sent a list of questions
to Osborne about the use of SPC 2888. In one question Hensman
said: "Track record should be one of the key factors in selection
of any system. We should not be a testing ground for new materials,
especially when we are designing for a life of up to 40 years.
We need confidence in the long term integrity of the field joint
coating . . . the selection of the field joint coating is
one of the most important technical decisions on the project."
However, by this time Osborne was already organising
a performance test at the Advantica Laboratory in Loughborough.
SPC and two other products, one from the UK and the other from
Germany, were tested for a range of physical and environmental
factors like curing, adhesion, flexibility and impact.
A preliminary test had already raised a question
mark over SPC's adhesion to plastic. But the highly confidential
Advantica test report nevertheless gave SPC the edge over its
two competitors. Although significantly it remarked that, "no
single coating material consistently performed well in all tests".
In September 2002, at a crucial meeting in Bechtel's
offices, senior BP managers approved the use of SPC for the field
joints. However, the minutes described the decision as "a
step change in present industry practice, both technically and
commercially."
Clearly BP recognised the paint had no track
record on the type of pipeline it was using in Azerbaijan and
Georgia, but went ahead anyway.
Osborne then took the highly unusual step of
nominating SPC 2888 in the official BP specification as the only
paint to be applied when coating the field joints. In other words,
there would be no fall back position if it failed. Industry experts
consulted by The Sunday Times say single sourcing is so
rare because it removes any liability from the contractors.
A senior BP insider also questioned how Osborne
got away with this single sourcing when he said in normal circumstances
BP's procurement manager would have been all over him.
Stretch was now even more alarmed at Osborne's
specification and asked Mortimore to review all the paperwork.
He produced a seven-page report dated 11 November 2002. It was
passed to the BP Design Group in London, sparking an exchange
of emails with David Winter, BP's health, safety and technical
compliance manager, who worked closely with Osborne in the Design
Group and supported his approach.
Mortimore's conclusions were damning:
"It was clearly a serious mistake
for BP to nominate one material only" and "not normal
practice." He warned this could invite a legal challenge
for restriction of trade under European law.
"We (BP) are completely out
on a limb, we cannot identify any pipeline owner who uses (SPC
2888) on (plastic coated) field joints anywhere in the world."
"Clearly the use of (SPC 2888)
is going to lead to a serious problem, particularly during the
colder months, with curing the applied paint."
"Cost for repairs could be astronomical"
in the events of cracks in the coating, he warned.
Mortimore's report also said Osborne's
specification was "under-developed and incomplete" and
"utterly inappropriate to protect the pipeline for its estimated
design life."
"The potential for claims against
the company is open-ended." He recommended immediate action
and asked rhetorically whether BP had considered "the insurance
implications."
At the time BP received this report the oil
company was in an intense propaganda war with international NGOs
who were lobbying the Lenders Group to withdraw its financial
backing, especially development banks and export credit agencies
like the ECGD.
The Mortimore report also noticed the paint
had not been tested on a field joint in simulated weather conditions.
This is remarkable because arguably there was even more reason
than usual for BP to ensure a rigorous pre-qualification testing
regime as SPC 2888 was a single source product recognised in the
oil company's own internal memo as a "step change in industry
practise". In other words, it was experimental engineering.
The testing regime should have been exemplary
and above reproach. Unfortunately, our investigation suggests
this is not the case.
Firstly, two months before his November report,
Mortimore provided BP with a dossier in August 2002 containing
independent industry opinions supporting his conclusion that any
liquid epoxy, not just SPC 2888, would not adhere to a plastic
coated pipeline, especially in cold weather conditions and with
an expected guaranteed lifetime of 40 years.
The dossier was about one inch thick. It contained
a sworn declaration by Mortimore that he had no interests in any
products concerned. The dossier contained declarations from international
pipeline coating companies, corrosion consultants and scientists
saying the type of paint specified was not appropriate for the
BTC pipeline.
The field joint coating market is very small.
The Sunday Times spoke to a number of other specialists
in this field who manufacture liquid epoxy paint. One leading
manufacturer told me they didn't even tender for the estimated
£5 million BTC contract because they knew liquid epoxy didn't
bond to a plastic coated pipeline.
Secondly, the Mortimore dossier included the
results of a second test by Advantica on SPC 2888. Remarkably,
it contradicted the earlier one commissioned by Osborne and showed
that SPC 2888 exhibited poor performance. In other words, BP was
told well in advance that two tests by the same laboratory showed
different results for the performance of SPC 2888, yet still it
was the preferred option.
A suspicious competitor called ShawCor, also
from Canada, had commissioned this second test from the same lab
just weeks after the first test.
ShawCor makes liquid epoxy. They too didn't
believe it was appropriate for coating the field joints on the
BTC pipeline. Instead, they offered BP a conventional and proven
alternative called a Shrink Sleeve. This is wrapped around the
field joint. Heat is then applied so the shrink sleeve moulds
around the field joint. It has proven adhesion to plastic.
They felt BP, through Osborne, were not interested
in using a shrink sleeve at all. That is why they commissioned
the second test to see how their product compared with SPC 2888
and the two other paints.
Thirdly, we established that Osborne's specification
for the field joint coatingthe instructions to the contractor
on how to apply SPC 2888differed significantly from the
test regime carried out at Advantica.
Our investigation showed that in the first Advantica
test Osborne commissioned, the performance of SPC 2888 was aided
by the use of a wash primer. But no wash primer was included in
the specification he subsequently wrote.
The serious anomalies surrounding the testing
regime of SPC 2888 had also become a cause of major concern to
its British competitor E.Wood. They believed the selection process
had actually been "rigged" to favour SPC 2888.
Chris McDonnell, managing director of E.Wood
Ltd, told me: "Our view is that individuals within BP were
trying to cover up a decision which was clearly flawed and which
we believe was influenced by an individual who was closely associated
with our main competitor (SPC) . . . BP have never moved an inch."
McDonnell said such was his firm's sense of
"injustice" they were willing to risk their long relationship
with BP. At the time E.Wood had other contracts with BP. McDonnell
said he was used to winning and losing multi-million pound contracts
but always on a level playing field.
Consequently, in October 2002 he wrote to Jim
Mooney, the senior BP manager who had approved SPC's use in the
crucial meeting at Bechtel a month earlier. He also wrote to BP's
compliance manager David Winter.
McDonnell's letters suggested the first Advantica
test had been manipulated. He also alleged there was "a very
close association" between Osborne and SPC.[81]
In November 2002, Jim Mooney launched an internal
inquiry into E.Wood's allegations of procurement fraud and manipulation
of the selection process.
Two BP employees, Frank Ravenscroft and Tim
Charters carried out the so-called "independent audit".
They worked from the same building in Middlesex where the Pipeline
Transportation Team of BP's Upstream Technology Group was based.
This was the group that had signed off SPC 2888 as the right product
to use on the field joint.
Those who were aware of the "independent"
audit included Mooney and BP compliance manager, David Winter.
At this stage E.Wood didn't believe BP chief
executive John Browne and his board knew what was going on. So
McDonnell hired a lobbyist to alert more senior BP figures that
his firm was considering legal action for restriction of trade,
in which allegations of kickbacks would almost certainly surface.
The two BP auditors eventually contacted Derek
Mortimore on 21 November. He told them about the dossier of evidence
he had left with Stretch and advised them to collect it on their
trip to Baku. This they did.
Mortimore also informed the BP auditors of the
association between the SPC agent Mike Bird and Osborne. He also
suggested they contact an independent corrosion engineer called
David Norman, who could provide further information.
Norman is the former head of corrosion at British
Gas, where he worked for 25 years. Like Mortimore, he is now a
highly regarded independent corrosion consultant who works all
over the world for oil and gas companies with failing pipelines.
Norman confirms that Bird approached him as
SPC's agent in September 2001 to sell their products in India.
At the time he associated Bird with Osborne's group of companies.
Norman could also have provided BP auditors
with expert evidence that the selection process was seriously
flawed and that it was totally inappropriate to use any liquid
epoxy paint on plastic coated pipeline.
Norman is one of a handful of corrosion experts
who when he was at British Gas developed the industry standard
for testing pipeline products before they were used in the field.
This standard is known as CW6.
"I've never seen a single sourced large
diameter pipeline material anywhere in the world I've worked on
in 40 years," says Norman.
BP's auditors, he says, never contacted him
although they had his name. This year I contacted Ravenscroft
and Charters at BP, where they still work, and asked them to comment
on this. They declined.
Before working for SPC, Bird was a director
of the well-established British field joint coatings firm Winn
& Coles. However they confirm he was sacked in 1994, after
30 years, for highly unethical financial conductpassing
commercially sensitive information to one of Winn & Coles'
competitors in South Africa. Mr Bird did not contest the dismissal,
the company said and they do not accept the contention that Bird
resigned, which is how he has presented the matter to Companies
House.
Trevor Osborne was contracted to BP as its materials
consultant through his company Deepwater Corrosion Services (UK)
Ltd. Osborne marketed this and his other companies under the corporate
umbrella of the Deepwater Corrosion Services International Group
or DCSI Group.
Certainly by July 2001, while Bird was working
for SPC, he, Osborne and a Mr Eddie Field began a joint venture
to set up and market the DCSI Group. Field was a former director
of an Osborne company. The flyer for the DCSI Group says, "quality
guaranteed by director-owners". Bird is listed as the sales
director. Osborne is the managing director, his boss.
On 12 December 2002 the BP auditors produced
a report. Before publication, The Sunday Times formally
asked BP for a copy of the report and to discuss its conclusions.
They declined. Apparently the two auditors completely exonerated
Osborne and their employer.
We were able to establish however that Chris
McDonnell of E.Wood was not satisfied with BP's internal inquiry
and entered into further correspondence with David Winter in January
2003. Winter maintained E Wood had not been treated unfairly and
in a letter dismissed any suggestion of an undue influence by
Osborne in the selection process, saying it was a team decision
involving BP, Bechtel, John Brown Engineering and Advantica. He
also said SPC was chosen only after full internal discussions
within BP and that the oil company had made "the correct
product selection."
McDonnell had evidence that SPC was given a
copy of the full and confidential first Advantica test results
and was using it to drum up further business.
Winter responded claiming he had sought and
received a written assurance from SPC that they had not seen a
copy of the full Advantica report. He asked E Wood to provide
evidence of its allegations or the matter would be closed.
McDonnell responded on 28 February 2003. He
sent Winter a breakdown of Osborne's business interests and claimed
there was a "very close association" with SPC sales
agent Mike Bird. He also sent a letter from a Middle East company,
Anticorrosion Protective Systems, confirming that in October 2002
the managing director received a presentation from Bird in Abu
Dhabi during which he was shown the results from what was referred
to as the final Advantica report.
McDonnell was also intrigued at how SPC 2888
paint cost double its competitors per tin. He told Winter: "Your
letter merely raises more questions than its answers and leads
us to believe that the outcome of the whole evaluation programme
was already decided before the tests began . . . The good name
of BP is being dragged down by this selection process which has
been a poor reflection on the reputation and integrity of one
of the world's leading companies." Winter's boss, Richard
Halligey, BP's commercial compliance manager, had been copied
in on the correspondence.
McDonnell says Winter never replied to his letter.
He told me: "I still feel what happened (with the field joint
coating bid) was totally corrupt and totally wrong. One of the
weaknesses in BP is if there is a problem they close ranks."
He says he would like to see an independent investigation.
Meanwhile, Derek Mortimore's services were abruptly
dispensed with in January 2003. Two months later he sought a meeting
in London with Winter to press his case one final time. Instead
the compliance manager agreed to pay out his contract.
By July 2003, BP was ready to lay what it promised
the people of Azerbaijan and Georgia, their governments and the
Lenders Group was a state-of-the-art pipeline "built to the
highest international standards."
A wide strip of land 1,000 miles long was being
cleared and levelled across the Caucasus Mountains and three countries.
Sections of pipe were positioned end-to-end waiting to be welded,
coated and then lowered into a one-metre trench for burial.
Work progressed in Azerbaijan and Georgia at
a reasonable pace to take advantage of the summer sun. But by
September, BP was said by sources on the ground to be experiencing
problems applying SPC 2888 to the field joint.[82]
By mid-November, the greenish-grey SPC 2888
coating was cracking on the field joints, just as Mortimore and
BP managers had warned it would. Work stopped for the next six-eight
weeks on the Georgian and Azerbaijan sections of the pipeline
as BP, Osborne and SPC frantically worked out what they were going
to do.
Unaware, one month later trade minister Mike
O'Brien told the Commons the pipeline was safe, environmentally
sound and millions of pounds of taxpayers' money should be risked
underwriting it.
BP is trying to blame the contractors for having
applied the SPC 2888 wrongly, whilst maintaining that the paint
was correctly specified and is the right product for the job.
The contractors told me they didn't accept it was an application
problem.
The British firm that applied the paint in Azerbaijan
and Georgia is Pipeline Induction Heating. PIH hired David Norman
in December 2003 to examine the situation. He made a site visit
to the Tsvalka region in Georgia where the first cracked field
joints were found.
BP, he says, must recognise that Osborne's specification
was flawed because they have since modified it to try and find
the solution to the cracking paint.
This has now been temporarily achieved by adding
extra heat to the field joint on application of the paint to ensure
it dries in cold temperatures.
However, Norman and other corrosion experts
point out that cracking is an indication of a serious problem
with the paint's chemistry and a symptom of its inappropriateness
for a plastic coated pipeline that it can never protect.
BP convened several emergency and confidential
meetings in London, Tblisi and Baku between December 2003 and
January 2004. Again the Lenders Group was unaware of this.
BP compliance manager David Winter was at a
confidential meeting at the Hilton Hotel on 5 January where he
warned those present not to speak to the press, say sources. Winter
refused to comment when I contacted him.
We had also picked up claims from an insider
that BP personnel in Baku concerned about the issues raised by
Mortimore had their work phones and emails monitored as part of
a leak inquiry.[83]
By Christmas 2003 an estimated 15,000 field
joints had already been coated and buried in Azerbaijan and Georgia
and cannot now be regarded as safe. Exact figures are still hard
to come by because BP refuses to come clean about the scale of
the problem.
Part of the reason for this secrecy is the enormous
cost of putting it right and who is going to pay those costs that
could escalate to hundreds of millions of dollars.
Since the first cracks appeared BP has been
privately locked in a crucial contractual battle in Georgia and
Azerbaijan with its contractorsSpie/Capag/Petrofac/Amec
and CCIC respectivelyover the failure of the field joint
coating.
The contractors in both countries stopped work
from mid-November to early February safe in the knowledge that
the "standing time" following the failure of the SPC
2888 paint would have to be paid by BP. This cost alone is said
to be $40 million.
The contractors are normally to blame for a
failure of this sort. But Osborne's extraordinary specification,
nominating SPC 2888 as the single source product, has transferred
liability onto BP.
This is a critical battle between BP and SPC
on one side and its contractors on another. Whoever loses the
battle for responsibility for the cracking will ultimately be
liable for the standing costs, but more crucially, also liable
for the remedial repairs and any legal action the host governments
may take for loss of revenue because of these delays. That figure
is estimated to lie between $300 million and $1 billion.
David Woodward is president of BP Azerbaijan.
He has been in the region at the helm for five years. Before that
he was in charge of the Prudhoe Bay oilfield in Alaska.
On 15 January 2004 the BTC board met in London.
Press reports suggested the key issue was preparing for the fast
approaching signing ceremony of 27 credit and loan agreements
for the project on 3 February.
Since mid-January BP was briefing the media
that delays in construction were down to "bad weather"
and the Turkish section of the pipeline, where BP has no operational
role. In late January, Woodward accompanied the Azeri deputy prime
minister on a trip to Turkey to discuss the delays. The impression
given to reporters was that the Azerbaijan and Georgian sections
are on schedule. There was no public reference by Woodward to
the major row over the field joint coatings non-performance in
Azerbaijan and Georgia, and whether it should all be dug up and
recoated with another product.[84]
I visited Azerbaijan and Georgia in this period
shortly before the financial closure ceremony at the presidential
palace in Baku.
BP managers like Stretch appeared too frightened
to speak out. Another said the whole matter was "very sensitive."
Stretch reported my approach to BP. The oil company was aware
of my presence because I had also approached them. They declined
to facilitate a site visit to where the pipeline was being welded
and coated claiming bad weather conditions and denying there was
any work stoppage on the pipeline.
Back in the UK, just before publication, BP,
Trevor Osborne and Mike Bird of SPC declined to answer any detailed
questions. In fact, Osborne and Bird referred all questions to
BP.
The Sunday Times investigation had shown
that before financial closure of the $2.6 billion loan agreement
BP did not tell the ECGD about:
BP managers and Derek Mortimore's
concerns over the use of a liquid epoxy on a critical part of
the pipeline.
The Mortimore dossier and report
in August and November 2002.
The second Advantica test casting
doubt on the choice of SPC 2888.
The allegations by E. Wood of procurement
fraud and rigging of the selection process.
The internal audit and its report.
The cracking of the field joint coating.
The six-eight week stoppage in the
run up to the financial closure ceremony in Baku.
When I spoke again to the ECGD press office
just before publication at first a spokesman tried to claim they
were aware of the allegations. He withdrew this suggestion and
accepted they had not been told.
Consequently, it appeared that BP had misled
the ECGD and the ECGD's own monitoring systems had failed. ECGD
officials then misled their minister, Mike O'Brien, who in turn
unwittingly misled parliament.
We asked whether the ECGD would now investigate
its failure to discover the problems with the pipeline, which
on any reading had a "material adverse affect" on the
BTC project.
Remarkably, we received a statement from the
ECGD that attempted to minimise the field joint coating problem
and suggest the agency had "satisfied all its due diligence
procedures in coming to a decision to provide cover for the project."
The statement also stated the problem was being
dealt with by BP "as part of an ongoing testing regime which
is designed to ensure that the pipeline passes all required tests
before it is certified operationally fit."[85]
After the article was published, an additional
ECGD statement to the NGOs was sent to me. It said:
"We do not agree that The Sunday Times
article provides evidence of shortcomings in ECGD's diligence
with regard to the BTC pipeline."
"The article's central allegation is that
the BTC Pipeline Co failed to disclose an assessment that "discovered
`serious flaws' in the pipeline's design, which would make it
highly likely to leak."
"We do not dispute that BTC Co did not inform
ECGD of problems with the field joint coating material: this was
because its testing and use is regarded by both parties as a routine
part of the pipeline construction process. This was not a problem
that has had a materially adverse effect on the project, and as
such neither BTC Co nor BP was under any obligation to report
this to us. This was reflected in the brief duration of the halt
in work on the pipeline, which remains on target for completion
in 2005 and on budget.
"BTC Co and BP have now provided us with
more information about the coating. They have assured us that
any problems that have arisen with the field joint coating are
being dealt with routinely in the course of work. These problems
were detected by the ongoing inspection regime in place on the
pipelineevidence that the monitoring regime is doing its
job.
"The article also made allegations about
the procurement process that led to the selection of that coating.
BTC Co made their choice as a result of an extensive technical
exercise, which concluded that the SPC coating was the most suitable.
The choice of coating was scrutinised and approved by Parsons
Energy & Chemicals, the independent engineering company operating
on behalf of the project lenders. BP has also shared the outcome
of its internal investigation into the procurement of the field
joint coating material with ECGD, which concluded that any allegation
of impropriety was unfounded."
"We remain satisfied that all our due diligence
procedures were followed before coming to a decision to provide
cover for the BTC pipeline project. At present no monies have
been drawn down under the financing arrangements established for
the BTC pipeline. The drawing down of monies in respect of which
ECGD has agreed to provide cover prior to the pipeline's completion
is subject to ongoing scrutiny."
It strikes me that the ECGD's only defence to
its due diligence failings is to ally itself with BP and suggest
the problems with the BTC pipeline exposed by The Sunday Times
were "routine" and the oil company was therefore
under no obligation to report them before financial closure.
Such a stance does not bear scrutiny and begs
the question, why would BP voluntarily refer to the ECGD "routine"
problems concerning the welding in Turkey but not those that led
it to carry out an internal audit into procurement fraud and a
work stoppage in Azerbaijan and Georgia?
There is nothing routine about the problems
with the field joint coating. And if the ECGD monitoring system
was truly independent and functioning properly it would have known
that the selection of the coating is one of the most important
technical decisions on the project. Certainly BP managers thought
sothat is why they employed Derek Mortimore to review Osborne's
specification.
It is also very telling that the ECGD is quite
willing to accept BP's unsupported assurances, yet is unwilling
to attend a briefing by Mortimore and other corrosion experts
with a combined one hundred years of experience.
It also appears from its new statement that
the ECGD is relying on Parsons Energy & Chemicals' review
to explain why the field joint coating is safe. On 25 February
, I spoke to the manager of the Pipeline Group at Parsons responsible
for overseeing the monitoring work for the Lenders Group.
The ECGD said Parsons had "scrutinised"
the choice of the field joint coatings. This does not accord with
what Parsons told me:
The Parson contract was "to
review the design of the facilities, specifications, plans, execution
plans and preparatory work prior to starting construction."
The contract started in 2002 and finished in January 2004.
Parsons did no on site inspection
for the Lenders Group after The Sunday Times published
its story.
The reviewer was never permanently
based in Azerbaijan or Georgia. He was not a corrosion expert.
The review was a paper exercise.
It was not a quality assurance exercise.
The field joint coating specification
was one of over 100 other specifications that Parsons reviewed.
The review didn't guarantee the integrity
of the field joint specification for the pipeline's estimated
design life of 40 years.
Parsons carried out no independent
investigation into the coating or the selection process controlled
by Osborne.
Nor did Parsons look at how any specified
products were applied in the field.
Parsons determined SPC 2888 was an
industry standard coating, but couldn't name one major pipeline
where it had been used on plastic.
The Parsons reviewer was in Azerbaijan
between late 2002 and early 2003. But BP did not disclose to him
the Mortimore report nor did he see any background material behind
each specification or internal BP reports.
BP/BTC imposed on Parsons a confidentiality
agreement "not to divulge information" to third parties.
BTC paid Parsons for the work it did for the Lenders Group. BP
is also a client of Parsons.
It would be an abuse of the English language
to suggest this review was a thorough scrutiny of the field joint
coating selection process. This is no criticism of Parsons. They
say that was not what the Lenders Group commissioned them to do.
In effect it was a box ticking exercise, with BP picking up the
bill.
Given the major problems identified by The
Sunday Times investigation, it is my firm belief that before
£58 million pounds of taxpayers' money is risked any further
there should be several full and independent investigations.
One investigation should look at the science
underpinning the claims of BP and the ECGD. This is urgently required
because information I have very recently received suggests BP
is planning to continue using the problematic Canadian paint.
In fact I was told BP will shortly start digging up some of the
pipeline already buried in Georgia and recoat the field joints
with SPC 2888.
Corrosion experts I have consulted are appalled
at this strategy and say this is like worrying what colour the
Titanic is. The only way forward, they agree, is an independent
review of the entire field joint coating system for the pipeline.
This scientific review must be done by independent laboratories
in circumstances not controlled by BP or any of its agents.
A second parallel investigation should determine
how the ECGD got it so wrong and in what way BP misled the government
to secure the $2.6 billion loan and credit facility.
Before publication in the Sunday Times we spoke
with you, Mr O'Neill, as committee chairman. You agreed to raise
the matters with the ECGD and said the committee would examine
whether BP has fulfilled its obligations under the terms of the
loan and if they had done so with sufficient candour.
Derek Mortimore and David Norman have asked
me to inform you that they and others would be willing to appear
before your committee to provide evidence that the £58 million
of taxpayers' money is at great risk if the BTC project is allowed
to continue on its current path.
As a professional journalist for some time I
have been struck by the depth of concern felt by those industry
insiders who have spoken to me about the BTC project.
These are not people I have found to be ideologically
opposed to the extractive industries or who have allied themselves
with campaigners opposed to the BTC pipeline. On the contrary
they want to see the pipeline built, but properly.
A good pipeliner is a good environmentalist
because he understands that the field joint coating is the first
line of defence against corrosion and subsequent environmental
and human disaster. When they are not helping to build them, they
spend their lives putting right failed pipelines. I have learned
that the most frequent cause of ruptures is a failed coating.
Equally important issues surround the probity
of the selection process. These should not be allowed to rest
with the so-called "independent" audit BP refuses to
disclose.
The former chairman of Shell, Mark Moody-Stuart,
once said, "We are moving from a trust me world to a show
me world." The ECGD, however, is satisfied with BP's word
that the internal audit, which it wasn't aware of until the Sunday
Times mentioned it, exonerated the oil company. Mantra like and
without seeing it the ECGD now promulgates the view this was an
"independent" audit and therefore no further action
is required.
In June 2003, the Corner House criticised the
ECGD for "turning a blind eye" to corruption allegations
in those mega project it underwrote overseas. The ECGD responded
that it had just signed a memorandum of understanding with various
agencies about referring such allegations.
In the public interest, the selection of SPC
2888 as the single source product for the BTC field joint coating
should now be referred to the Serious Fraud Office or another
appropriate agency for a full investigation.
Michael Gillard
15 March 2004
Second memorandum by Michael Gillard
1. The WorleyParsons desktop study (WP report)
is the document that the Lenders Group of government export credit
agencies, development and commercial banks is already pointing
to as proof the BTC pipeline is safe and environmentally responsible.
The ECGD, World Bank and European Bank of Reconstruction and Development
also hope this document will re-establish their reputation as
a genuine and effective watchdog. For BP, as operator and main
shareholder in the BTC pipeline, the WP report is being used to
re-establish its credibility with host governments, especially
Georgia.[86]
2. In his covering letter to the Committee
dated 19 July 2004, John Weiss of the ECGD claims the WP report
"deals effectively" with the field joint coating issues
raised by veteran pipeline integrity consultant Derek Mortimore,
the BP Baku managers he worked for, and The Sunday Times investigation.
3. Mr Weiss goes on to say the WP report
"indicates the choice of coating was carried out after extensive
consideration of its suitability, and by appropriate experts.
It shows that the coating was subjected to rigorous testing, and
has a track record in similar conditions in a significant number
of other pipelines."
4. This submission will seek to persuade
the Committee that the WP report does nothing of the sort. In
fact, it makes the case for an immediate and independent audit
of the BTC pipeline before it is completely buried with a major
design flaw.
5. Mr Weiss also concludes "on the
basis of independent expert advice received, ECGD does not consider
the field joint coatings to be a serious ongoing environmental
issue."
6. This submission will explain why there
is no cause for reassurance. The £60 million of taxpayers'
money pledged by the ECGD is still at serious risk and BP's attempts
at self-regulation, to which the government gave free reign, have
failed and are hopelessly marred by conflicts of interest, corruption
allegations and evidence of a cover-up.
THE TIMING
7. The Committee chairman called for a report
on 11 May 2004. By this time the Lenders Group had already commissioned
WorleyParsons on 17 March as a result of The Sunday Times'
Insight team expose of the field joint scandal on 15 February.
8. WP sent its un-redacted report to the
Lenders Group before May. Nevertheless, it wasn't passed to the
Select Committee until late July. By then, Parliament had risen
for the summer recess and the opportunity to consider the report's
contents in oral committee hearings was lost until after the autumn.
Meanwhile, BP has been forging ahead with improper haste in Georgia
and Azerbaijan to complete a pipeline that has a major design
fault. BP managers and contractors receive bonuses for finishing
on schedule.
9. I understand from the Committee there
was some "haggling" between it and the ECGD, with the
export credit agency claiming that "commercial confidentiality"
prevented it from disclosing certain information. In fact, WorleyParsons
confirms that during this time they were also having "discussions"
with the Lenders Group and BP over who not to "embarrass".
THE REDACTION
10. ECGD has confirmed to me that the redaction
process was done with BP, although the government department says
it has no details of how it was carried out.
11. Jim Powers, the head of WorleyParsons
pipelines division, oversaw the desktop study as part of the "construction
monitoring" for the Lenders Group. In an interview on 7 September
2004 he told me WorleyParsons was asked to do "modifications"
and that the report went back and forth between his team, BP and
the Lenders Group.
12. He said: "I'm sure that there were
some things that were taken out. Probably names that might have
been embarrassing to people or any confidential information...(The
Lenders Group) asked for input on what might be embarrassing to
individuals." He didn't name them.
13. ECGD tell me they have no plans to make
the un-redacted version available to Parliament. I asked BP what
role any of the following employees had in drafting or redacting
the WP report:
Trevor Osborne (BP materials consultant)
David Winter (BP Compliance manager)
Richard Halligey (BP's head of compliance)
David Fairhurst (BP Corrosion chief)
Jim Mooney (BP Upstream Technology
Group)
Kevin Muller (BP Global SCM Integrity
Assurance Manager)
Jaime Potes (BP London Project Manager)
All these men figure in the events leading up
to the selection of SPC 2888 as the field joint coating in October
2002 and/or the remedial strategy after cracked field joints were
discovered in November 2003. BP refused to answer this or other
simple informational questions.[87]
THE INDEPENDENCE
14. Last March, Foreign minister Mike O'Brien
claimed in a letter to Corner House that Parsons (as they were
known before the merger with Worley) had "scrutinised and
approved" the selection of SPC 2888 before the financial
closure ceremony in February 2004, when the BP-led consortium
received US $2.6 billion in multilateral loans.
15. I refer the Committee to my earlier
submission where, in summary, Mr Powers confirmed that the Parsons
review supported Mr Osborne's field joint coating specification
but involved no independent assessment of the coating he selected
for BP or the quality of that selection process.[88]
16. More recently, Mr Powers confirmed to
me that the same project manager involved in the first Parsons
review was also involved in the second one. He refused to name
him for fear that any subsequent interview would seek to elicit
"discrepancies".
17. It is clear that before writing this
latest report WP had a position to protect on the field joint
coating issue. That position was identical to their client'sthe
Lenders Groupand to BP/BTC Co, who has paid for both WP
reports.
18. The latest report by WP cannot therefore
be considered in any way "independent", as Mr Weiss
repeatedly claims in his covering letter to the Committee.
THE DISCLAIMER
19. The illusion of independence becomes
even more apparent when one considers the extraordinary disclaimer
WorleyParsons has inserted on page 2 of its report.
20. Mr Weiss claims in his covering letter
that although his department is reliant on BP for information,
ECGD also relies on their "independent consultants"
WorleyParsons, to "verify" that information. Yet here
we have WP making it clear they have "not independently verified
that (the information from BP) is comprehensive, complete, accurate
or up to date."
21. Four of the most alarming failures in
the WP report are:
Not interviewing those people they
nevertheless choose to rubbish solely on the word of BP and SPC.
Not interviewing those who could
challenge the technical arguments from BP and SPC.
Not obtaining all documents in the
possession of BP and SPC that would cast doubt on their assertions.
Not doing a site visit before publishing
the report.
22. I return to my recent interview with
Jim Powers of WorleyParsons. He said the "instructions"
from his client, the Lenders Group, was to only carry out a desktop
study. This only involved, he said, asking BP and SPC for all
"pertinent" documents concerning the field joint coating
issue raised by The Sunday Times. He was thus reliant on
the integrity of BP and SPC to disclose all the relevant documents.
"You can't ask for things you don't know exists," he
maintained.
23. Mr Powers went on to say: "We did
what we were instructed to do. And you can call (the Lenders Group)
to find out why they didn't go into it further or want it gone
into further."
24. This statement provides an extraordinary
insight into the approach taken by the Lenders Group after its
much vaunted due diligence procedures were exposed by The Sunday
Times. They went on to limit the investigation of the field
joint coating issue to a simple desktop study wholly reliant on
one partial source of information, which the Lenders Group deliberately
chose not to independently verify.
25. Why would ECGD and its partners in the
Lenders Group impose such a limited remit on this vital investigation,
notwithstanding that WorleyParsons was the wrong company to do
it? What did the Lenders Group have to lose from a full and truly
independent investigation? Did the ECGD not want to hear evidence
from independent sources that would expose the inadequacy of their
due diligence when gambling with taxpayers' money?
THE EXECUTIVE
SUMMARY
26. WorleyParsons' key finding is that the
evaluation, testing and selection of SPC 2888 was "very thorough".
With these two words, BP, SPC, Mr Osborne and the ECGD are let
off the hook.
27. Of course the PR value of such a finding
for BP and the government is plain to see. But in reality it is
worthless. WorleyParsons is making a finding of fact, when in
the same breath it tells us nothing this finding is based on has
been independently verified as true.
28. The finding relies on eight tests provided
by BP and SPC. On the face of it this looks convincing. But on
closer examination of when these tests were carried out, it emerges
that the selection process controlled by Mr Osborne and overseen
by senior BP managers was not just seriously flawed but arguably
reckless.
29. In the course of my investigation I
have consulted widely with paint coating companies in the UK and
the US who supply the oil industry; corrosion and coatings consultants;
pipeline integrity specialists, field joint coaters and major
oil companies.
30. The consensus concerning best practice
for the evaluation, testing and selection of field joint coatings
is unanimous, logical and very simple. The client (in this case
BP) has the responsibility to specify material(s) that have been
fully tested to ensure full anti-corrosion protection in the conditions
the pipeline will operate in for its entire design life (40 years).
Once these tests have been carried out and the client is satisfied,
only then is the specification or instructions to the applicator,
issued.
31. It has already been established from
BP's own reports that the use of a liquid epoxy field joint coating
like SPC 2888 on a polyethylene (plastic) coated large diameter
pipeline like BTC is "a step change" in industry practice.
In other words, experimental engineering.
32. Extra care in the selection process
was therefore required. Some industry sources have suggested that
full lab tests followed by full field trials on a pipeline in
simulated weather conditions and then a further lab test on a
cut-out section of the coated pipeline would constitute best practice
before specification. This is even more necessary when the committee
considers that Mr Osborne and BP nominated SPC 2888 in their October
2002 specification to the exclusion of all alternatives. In other
words, the specialist contractor applying the coating to the field
joint was forced to use SPC 2888 and had no opportunity to rely
on a fully-tested fallback material if the chosen coating failed,
which of course it did.
33. The key point is this: All but one of
the eight tests were carried out long after Mr Osborne
had specified SPC 2888 as the single source field joint coating
(October 2002).
34. Three of the eight tests were carried
out by SPC on its own product. These looked at its appropriateness
when applied to plastic coated pipeline. Significantly, the Canadian
paint company only did these test after Mr Osborne had awarded
it the contract (October 2002); after the field joint coating
application had already begun (August 2003); and just a few weeks
before their coating cracked (November 2003).
35. A number of issues arise:
Why didn't Mr Osborne ensure these
tests were done before he selected SPC 2888 as the single source
field joint coating?
Why did BP compliance manager David
Winter and Corrosion chief David Fairhurst allow Mr Osborne to
warrant a product as fit for purpose and therefore environmentally
responsible before all these crucial tests had been completed
and proved it so?
How was this massive failure of BP's
quality control and assurance programmes possible, especially
after Derek Mortimore had warned the oil company between July
2002 and March 2003?
THE MISSING
REPORTS
36. Besides WP's failure to verify information
given to it by BP and SPC, there has been a repeat failure by
BP to disclose key reports that would have forced WP at the very
least to investigate the selection process more effectively.
37. In my earlier submission I explained
how Jim Powers confirmed that for the original pre-loan closing
Parsons review in March 2003, BP had failed to disclose any of
Derek Mortimore's reports on the field joint coating; the correspondence
between BP Baku (who had contracted Mr Mortimore) and the BP Design
Group in London (who were pushing SPC 2888); and the internal
audit report into procurement fraud allegations.
38. When I spoke recently with Mr Powers
he said: "It's likely that all the reports Mr Mortimore produced
were not seen by us. I don't know how many reports he submitted."
The Lenders Group only asked WP to review the one report quoted
in the Sunday Times article, Mr Powers revealed.
39. One of the eight studies relied on by
WP is a lab test carried out by Advantica in July 2002. It is
on this test that BP and Mr Osborne have based their entire selection
of SPC.
40. In my earlier submission I explained
that it was this test that led one of the unsuccessful competitors,
the British coatings firm E Wood, to allege Mr Osborne had "rigged"
it.
41. You will be aware that Mr Chris McDonnell
of E. Wood Ltd is making a direct allegation that Mr Osborne "slanted"
the ranking and weighting system in favour of SPC 2888. BP was
forced to conduct a secret internal audit following Mr McDonnell's
procurement fraud allegations. The oil company refuses to release
the report to The Sunday Times, but claims it fully exonerates
Mr Osborne and others. However in my earlier submission I also
explained how key witnesses were not interviewed and evidence
was not collected or acted on by the internal BP auditors.
42. I also revealed there is a clear conflict
of interest between Mr Osborne and the Canadian firm Speciality
Polymer Coatings, makers of SPC 2888, through their British agent
Mike Bird, who at the relevant times was setting up a materials
supply and corrosion consulting company with Mr Osborne. He doesn't
dispute this. In his defence Mr Osborne says the joint venture
never got off the ground. But it did get to the point of preparing
and distributing promotion literature. The fact still remains
that he and Mr Bird, who had been sacked from his previous company
for disreputable conduct involving a competitor, were planning
a business partnership in the run up to the selection of SPC 2888.
43. In my earlier submission I also explained
that ShawCor, another unsuccessful participant in the Advantica
test, was so concerned about the selection process that just a
few weeks later it commissioned the same lab to retest the materials.
On this occasion SPC 2888 failed.
44. Once again, BP has not disclosed to
WorleyParsons these Advantica test results, notwithstanding that
Mr Mortimore ensured a full copy was available to the internal
auditors. Mr Powers of WorleyParsons told me: "If we didn't
mention them in the report we weren't aware of them."
THE ADVANTICA
TESTS
45. The "confidential" Advantica
test (5426) in July 2002 is the only one BP can point to as evidence
that it carried out any evaluation before selecting SPC 2888 as
the field joint coating. The WP report says this Advantica test
was "rigorous".
46. Advantica is the former British Gas
laboratory. It is agreed that Trevor Osborne was responsible for
choosing the products that would be tested and also setting the
parameters of those tests and then weighting and ranking the test
results.
47. Mr Osborne selected three liquid coatings.
They were SPC 2888 (a urethane modified liquid epoxy made by SPC
from Canada); Copon 165 (a urethane made by E. Wood Ltd from the
UK) and Protegal 3210 (a tar modified urethane made by Goldschmidt
from Germany).
48. Mr Osborne also included another type
of field joint coating called a shrink sleeve. Unlike the liquid
coatings, which are sprayed or hand applied with roller to the
field joint, the shrink sleeve is wrapped around it and then moulded
on by heat. There are many shrink sleeve types. Mr Osborne however
chose Canusa, manufactured by ShawCor, also from Canada.
49. BP approved Mr Osborne's test programme,
which was carried out by Ian Thompson and Colin Murdoch from Advantica.
Ten performance tests were conducted on samples of each of the
four materials pre-applied to a plastic coated pipeline exactly
like the one intended to be used for the BTC project.
50. The tests included cure, adhesion, hardness,
impact, flexibility, abrasion and water absorption. The lab made
an alarming finding strangely missing from the WP report. The
Advantica scientists wrote that, "No single coating material
consistently performed well in all tests."
51. In the ranking and weighting table devised
by the projects team certain key test results were omitted. For
equally unclear reasons the ShawCor shrink sleeve was also excluded
from the ranking table.
52. SPC 2888 subsequently came first over
Copon and then Protegal. The Advantica test results said spray-applied
SPC 2888 outperformed the others on penetration/indentation, gouging
and abrasion, but says it performed "poorly" on impact
and water absorption. The hand applied SPC 2888 also tested poorly
on flexibility.[89]
53. Although the Canusa shrink sleeve was
tested with the liquid coatings, Mr Osborne excluded it from the
ranking table. ShawCor suspected this was because it would have
been shown to outperform SPC 2888. Consequently, that same month,
July 2002, ShawCor commissioned the same Advantica scientists
to test and rank SPC 2888, Protegal and the Canusa shrink sleeve
for adhesion and flexibility to plastic coated pipeline. The results
were remarkable and worryingly at variance with the first Advantica
test.
54. During the Advantica test (5405) for
ShawCor, SPC 2888 was shown to exhibit the worst adhesion of the
liquid coatings after it had been dried (cured) and when it had
been soaked in hot water for 28 days. Advantica failed SPC 2888
under the UK industry CW6 standard. Under the Canadian CSA standard,
Advantica ranked SPC 2888 with a 5, a "FAIL" defined
as "the coating can be removed as a single piece."
55. During the Advantica test (5435) for
ShawCor, SPC 2888 was also shown to exhibit very poor flexibility
on plastic coated pipeline. It cracked at just 1.0% strain, when
the minimum pass under the CW6 standard is 3.0%. It also delaminated
from the plastic coating.
56. What conclusions are we to draw from
this information? At the very least it puts a significant question
mark over the Advantica test which BP, Mr Osborne, SPC and WorleyParsons
are now relying on as proof that the chosen coating was properly
selected and is the best one for the BTC pipeline. At its highest,
this information proves that SPC 2888 was scientifically shown
to be an inappropriate coating for the BTC field joints as early
as July 2002. BP's internal auditors were made aware of the alternative
Advantica tests in November 2002. But by then SPC 2888 had been
selected by Mr Osborne.
57. BP ignored these results and continues
to do so after the coating cracked in Georgia and Azerbaijan a
year later.[90]
THE PEER
ASSIST
58. Weeks after the Advantica tests, on
5 September 2002 a Peer Assist Review by BP in London signed off
SPC 2888 during a meeting in the BTC Project Office at Bechtel.
Those in the Peer Assist team were Jim Mooney (BP Upstream Technology
Group construction consultant) and Kevin Muller (BP Global SCM
Integrity Assurance Manager) with attendance from the BP projects
team consisting of Ian Parker, BP's design manager, Jaime Potes,
Carl Slater, Steve Evans, David Willis and Trevor Osborne.
59. The minutes of the Peer Assist meeting
totally undermine repeated claims by minister Mike O'Brien and
the ECGD made after the field joint scandal was exposed that SPC
2888 has a proven track record on plastic coated (PE) pipelines,
especially those operating in cold climates.
60. Mr Weiss said in his covering letter
that SPC "has a track record in similar conditions in a significant
number of other pipelines." Yet the BP Peer Assist report
on several occasions made the point that SPC as a field joint
coating system with plastic coated pipeline was accepted to be
"a step change in present industry practice, both technically
and commercially". It also says "the selected field
joint system has previously only been proven on FBE (Fusion Bonded
Epoxy) systems." Later on in the same minutes it said: "Whilst
this clearly looks like an attractive field joint coating option,
it is relatively unproven on three-layer PE systems."
61. Furthermore, Ian Parker, who was part
of the Peer Assist meeting one year later was quoted in the BP
Frontiers magazine saying: "As far as we know the first time
such a system has been employed." Even the WP report concedes,
"SPC coating material may not have been used on projects
with three-later PE coated line pipe".
62. For these very reasons the Peer Assist
team made two sensible and precautionary recommendations:
"(a) full size field trial of
SPC 2888 to ensure repeatable performance under field condition",
and
further field-testing on alternatives
to SPC 2888 as a "fall back if problems are experienced."
63. One month later in October 2002 Mr Osborne/BP
issued the controversial specification nominating SPC 2888 as
the only field joint coating. Neither of the two tests required
by the Peer Assist team had been carried out.
64. The WP report refers to a "field
demonstration of the application of SPC field joint coating material."
British company Pipeline Induction Heating carried this out in
January 2003 in Algeria. The WP report suggests, presumably on
BP's word, that this test was in conformance with the Peer Assist
requirements. This is not the case.
65. If WorleyParsons had spoken to PIH it
would have been told the Algeria test was not a full size field
trial but a demonstration of how PIH's specialised equipment would
apply SPC 2888 in the field. They had been awarded the contract
to coat the field joints in all three countries.
66. The reality is that no proper field
test was carried out until December 2003, after SPC 2888 had failed
as a field joint coating and cracked in Georgia and Azerbaijan.
Only then did Mr Osborne oversee a field test by PIH on selected
field joints.
67. As to the second precautionary test
the Peer Assist team required, I have spoken with various sources
on the BTC project and can find no evidence that BP or Mr Osborne
ever conducted field-testing on alternatives to SPC 2888.
68. The only alternatives to SPC 2888 which
Advantica tested were in July 2002. But the Peer Assist team was
already aware of that when they asked for further tests as a "contingency
plan if the performance (of SPC 2888) is not achieved." This
never happened so when the field joints cracked in November 2003
there were no "fall back" coatings materials. This is
precisely because Mr Osborne had nominated SPC 2888 as the single
source coating.
69. Furthermore, I am informed that Raychem,
a major field joint coating manufacturer, was asked in 2002 to
make a presentation to BP Baku on the viability of shrink sleeves
over liquid epoxies on plastic coated pipeline. Raychem presented
to Technical Manager Paul Stretch and senior project engineer
Rod Hensman, both from BP Baku, who had already employed Derek
Mortimore to look at Mr Osborne's specification because of their
concerns about SPC 2888.
70. Additionally, Mr Mortimore had organised
a testing regime in Dunkirk, France where four companies would
demonstrate alternative field joint coatings for plastic coated
pipe. One of the four firms was Eupec, who were responsible for
the "Blue Stream joint" for a gas pipeline from the
Black Sea. But when the BP Design Group in London (composed of
Mr Osborne, Mr Winter and others) found out about this trial they
ordered BP Baku to cancel it, says Mortimore.
71. A senior source in Raychem told me the
main BTC contractors had complained to them they were being forced
to use SPC 2888 and felt it wouldn't work. Raychem then spoke
to BP corrosion chief, David Fairhurst, who informed them shrink
sleeves were not being considered as an alternative to liquid
coatings.
72. The WP report makes no mention of any
tests by BP on alternatives to SPC 2888. And BP has not provided
any evidence it complied with this second safety requirement of
its own Peer Assist team.
THE SELECTION
PROCESS (ADHESION)
73. The committee will have heard a lot
of technical terms in this inquiry. So for clarity I have included
a picture (Appendix 1) of the BTC pipeline that I took earlier
this year in Azerbaijan.
74. The photo shows the field joint after
welding but before the coating has been applied. It shows the
three different surfaces SPC 2888 must stick to in order to provide
full anti-corrosion protection over forty years.
75. The black material on either side is
the plastic coating (or polyethylene jacket) of the main pipeline.
The plastic is made up of three layers, which is why it is sometimes
referred to as "three layer, high density polyethylene".
These three layers are (from the outside in) plastic, adhesive
and fusion-bonded epoxy (FBE), the green material in the photo,
which lies on top of the bare steel. The brown material is the
bare steel.
76. When each 11.5 metre section of the
pipe comes from the factory the plastic jacket should be cut back
a little at each end to reveal some bare steel for welding and
a 50 mm wide ring of FBE (called a FBE toe).
77. The SPC 2888 field joint coating is
being applied by spray using special equipment that rotates around
the pipe. It is unanimously accepted in the pipeline world that
liquid epoxies like SPC 2888 have good adhesion to steel and FBE.
Equally, it is widely accepted that liquid epoxies have very poor
adhesion to plastic and therefore carry risks that can be removed
by using another proven type of field joint coating system.
78. The most critical point is the overlap
area where the SPC 2888 must bond to the black plastic on either
side of the weld. If it doesn't, and the SPC 2888 disbonds, then
you get water ingress between the two that will eventually travel
towards the bare steel and start the corrosion process.
79. The ability of the SPC 2888 coating
to stick to plastic is therefore the most crucial test that any
proper evaluation process should prove before selection, let alone
before making it a single source nomination. It is truly alarming
that the WP report confirms Advantica only carried out this test
in January 2003 after Mr Osborne and BP had awarded SPC the contract.
80. The committee might ask whether the
earlier Advantica test in July 2002 (referred to in Points 45-57)
looked at adhesion when it compared SPC 2888 to the two other
liquid coatings before selection? The answer is yes but BP is
not readily revealing the conclusions. Why not? Because they showed
there was a big "question" over SPC 2888's long-term
adhesion to plastic.
81. I have seen a BP document prepared soon
after this Advantica test in July 2002. I believe it supports
Mr Mortimore's contention that there was a "push" to
choose SPC 2888, despite recognised doubts about its ability to
do the job. The document also appears to show that the ranking
and weighting system adopted by Mr Osborne was wholly unscientific,
and again demonstrated a bias for SPC 2888.
82. The document states:
The results for adhesion to plastic,
curing and water absorption were "omitted" from the
Advantica ranking and weighting table that gave SPC 2888 the edge.
The adhesion of SPC 2888 to plastic
"diminishes rapidly"/"dramatically reduced"
during temperature changes. This was confirmed by SPC's own follow-up
tests.
83. The document ends by saying: "There
is a question regarding the SPC product and its adhesion to (plastic),
which needs to be resolved." However, the WP report confirms
that this question was not revisited until a further Advantica
test in January 2003, six months later. By which time SPC had
been awarded the contract and had been written in to the specification
of October 2002.
84. The Osborne specification, authorised
by BP, is a remarkable document. On the issue of adhesion it allows
the contractor and on-site inspectors of the field joint to pass
what in normal circumstances would be considered a massive failure
in performance. On page 13 of the specification it says, where
the SPC 2888 is found to "peel in large pieces adhesively"
from the plastic this should be considered "a pass".
Corrosion consultants I have spoken to, other than Mr Mortimore,
are aghast at this and say if the coating peels so easily then
it is failing to adhere and cannot therefore be considered fit
for purpose for one minute let alone 40 years.
85. The adhesion test Advantica did for
ShawCor in July 2003 "failed" SPC 2888 on this very
point and after a 28-day hot soak. (See Point 54) All of which
might explain why the adhesion test Advantica carried out for
BP in January 2003 contains no glowing endorsement of SPC 2888.
The WP report chose merely to extract one sentence from it, which
states a known proposition: that SPC 2888 will adhere better if
the plastic surface is slightly roughened. This is by no means
a scientific endorsement that it will stick permanently for the
estimated design life of 40 years. Subsequent events have shown
it hasn't. I have photographs of the SPC 2888 coating coming off
in chunks leaving the bare steel exposed.
86. The WP report refers to a Technical
and Risk Assurance Process (TRAP) carried out in January and May
2003 on the field joint coating. It makes the very interesting
concession that the SPC 2888 coating has "limited adhesion"
and "slow curing" when applied to plastic coated pipeline.
What is extraordinary about this statement is that it was also
being made seven months after the SPC coating had been selected.
THE SELECTION
PROCESS (CURE)
87. The committee will by now be aware that
SPC 2888 coating was discovered to have cracked on the field joint
in November 2003. BP claims this was a cure problem, which has
now been solved. Cure here means how to dry the coating on the
field joint in changing ambient temperatures, which go from warm
(when the coating is applied during the day) to cold (as it tries
to dry overnight). This fluctuation in temperatures is known as
thermal cycling.
88. The curing of the SPC 2888 is aided
by heating the field joint immediately before and after the coating
has been applied. It is universally recognised by the industry
that it is the responsibility of the client (BP) to ensure it
has developed the appropriate curing regime for the selected material.
This is especially the case when nominating a liquid epoxy like
SPC 2888, which had well known problems of curing in cold temperatures.
BP would also have known that Georgia in particular gets very
cold in winter both above and below ground, especially in the
Caucasus Mountains.
89. Yet BP admits in the WP report that
it did not know how to cure (dry) the SPC coating when it issued
a specification for a field joint that was supposed to last 40
years. Furthermore, BP, Mr Osborne and SPC only developed a curing
regime for SPC in December 2003, some 17 months after the spec
was issued and one month after the cracking had been discovered.
90. The WP report confirms that BP started
coating the field joints with SPC 2888 in August 2003 without
having any idea how to cure the paint in cold weather. The on-set
of winter was just weeks away. Industry experts I have consulted
say this is plain reckless. And finding out how to eventually
make the paint dry has nothing to do with making the field joint
work for forty years. BP projects were aware of a lab report by
TransCanada, an energy company responsible for 38,000 kms of pipeline
in bitterly cold areas of North America. In the late nineties
they had tested the viability of using liquid epoxies on plastic
coated pipe. It failed EVERY test. The TransCanada report concluded
that the two materials were "not compatible". Furthermore,
it disputed the canard BP and the ECGD have now come up with:
that having sorted out how to dry the paint ipso facto there is
no problem and the field joint is safe and fit for purpose. Far
from it. TransCanda's leading scientist wrote: "The coating
may be applied and (dry) to look acceptable, but once (buried)
and operation of the pipeline is started, the coating will fail
(on the overlap area onto the plastic coating)."
91. SPC only did a cold weather test on
26 August 2003 and a cure test in September 2003. These tests
are designed respectively to see how the field joint coating behaves
in cold weather conditions, and to see what sort of heating regime
is required when applying the coating to the field joint to ensure
it dries correctly and is therefore not liable to crack and expose
the steel to corrosion when buried in moist soil for 40 years.
92. These SPC tests were done without BP
present. Similarly, PIH were not invited to witness this test,
despite the fact it was already applying SPC 2888 to the field
joints in Azerbaijan and Georgia. The results of these SPC tests
have not been made public. And the WP report gives no indication
of how SPC performed. What we do know is that the coating cracked
on site weeks later in November 2003.
93. Derek Mortimore had pointed out back
in November 2002 the dangerous lack of cure information in the
BP specification. Exactly one year later the coating cracked.
94. If, as it appears, BP was determined
to use SPC 2888 come what may then it was incumbent on them to
ensure that Mr Osborne and his team selected it based on the highest
standard of pre-qualification testing. The WP report, when stripped
way, proves Derek Mortimore's warning that the selection process
was at the very least "seriously flawed, underdeveloped and
incomplete".
THE CRACKING
95. The WP report says BP became aware of
the cracking problems sometime in November 2003. BP declined to
tell me exactly when. The date is important because between 4
and 11 November the International Finance Corporation and the
European Bank for Reconstruction and Development approved US $250
million loan each to the BTC project. The cracking had occurred
approximately three months before the crucial formal financial
closure ceremony for the full US $2.6 billion multilateral loan,
marking the end of the BTC consortium's spending. From that point
on the Lender Group would finance construction with loans underwritten
by the taxpayer.
96. On discovery of the "many"
cracks BP did some preliminary checks and determined it was down
to "improper application at low ambient temperatures".
In other words, BP put all the blame on PIH.
97. BP then "suspended" the field
joint coating process and formed an "investigation team"
made up of SPC, the BTC Projects Team and UTG in London. In other
words, the very people whose failures of quality assurance and
control had led to the cracking. Unsurprisingly, this investigation
team reaffirmed the early decision that the cracking was an application
problem. BP will not say when this decision was made.
98. Over the following eight weeks, when
all field joint coating stopped, BP, Mr Osborne and SPC determined
yet another new heating regime to cure the failed coating in cold
weather. New corrective instructions were issued to PIH on 9 February
2004, one week after BP had received the multilateral US $2.6
billion loan.
99. On the basis of 87 field joints per
kilometre of pipeline there are 150,000 field joints on the project
in Azerbaijan, Georgia and Turkey. There are 38,450 field joints
in Azerbaijan and 21,500 in Georgia.
100. By the time BP issued new instructions
to the field joint coating applicators in these two countries,
we are led to believe, there were 16,276 field joints coated with
SPC 2888. The overwhelming majority (11,386) were said to be in
Azerbaijan. Of those BP estimate 300 were problematic. Of the
4,890 joints in Georgia, BP estimate 1,260 were faulty, a staggering
26%. The reliability of these figures as a true assessment of
the scale of the problem is dealt with in the next section. But
taken at face value it is still a compelling indictment of the
selection process.
101. BP failed to report any of this to
the Lenders Group before the financial closure ceremony in front
of the world's press on 3 February 2004. Incredibly, ECGD has
supported BP's position and still maintains that none of the above
represented a material adverse threat to the integrity of the
BTC project.
THE REMEDIAL
PLAN (HOW
BIG A
PROBLEM?)
102. The Lenders Group has allowed BP to
assess the scale of a major engineering problems caused by its
own lack of quality control and inspection. It has also allowed
BP to oversee its own remedial work. Mr Weiss says in his covering
letter that ECGD is currently "reassured" BP has identified
the problems and has put in place "rigorous monitoring and
corrective action systems." The WP report endorses this view,
without having done a site visit.
103. I have evidence, contained in BP documents,
suggesting there is a cover-up to downplay the scale and importance
of the problems with the BTC pipeline, especially in Georgia.
It appears vital checks on the pipeline are not being done for
fear they will increase the repair programme and delay the project.
Consequently, field joints that cannot be regarded as safe are
being buried like environmental time bombs. The internal BP documents
show the men who devised this secret plan are those who also approved
the selection of the failed SPC 2888 coating.
104. Other internal documents also reveal
a major split within BP. Senior Operations managers, who will
shortly inherit the BTC pipeline from the BP Projects team, are
questioning the integrity of the declared repair programme and
have been slapped down.
105. According to the WP report, BP planned
to "remove and recoat" all cracked field joints in Georgia,
weather permitting, from July 2004 onwards. The WP report does
not say this followed a limited number of inspections from late
March to early June to establish the scope of the remedial work.
Mr Osborne and his team say they inspected 1,000 field joints
(between kilometres 147-175) in the Tabatskuri region of Georgia.
Only coated field joints were inspected. Coated and buried field
joints were not inspected. Nor were those sections of pipeline
where the field joint had been coated but was lying in the trench
waiting to be buried (backfilled[91]).
BP will not say how many field joints are buried.
106. Based on this, Mr Osborne, the BTC
pipeline corrosion control consultant, and Mr Fairhurst, BP's
own senior materials and corrosion engineer, issued a report on
18 June 2004 outlining the entire repair strategy for all of Georgia.
It is from this report that WorleyParsons and Foreign minister
Mike O'Brien have based the figures given in point 100.
107. The committee should remember that
the cracked and otherwise failing field joints are to be repaired
and recoated using the same material, SPC 2888. BP refuses to
accept there is a problem with the SPC coating, because to do
so would leave the oil company, as BTC operator, open to major
financial liability. Instead, the remedial strategy is designed
to validate the unsustainable proposition that this is entirely
an application problem.
108. Determining a remedial strategy does
involve extrapolating from a sample inspection how many can be
considered "fit for purpose" (safe) and how many should
be repaired. Such a calculation depends on the inspectors not
being influenced by any other factors except the long-term integrity
of the pipeline.
109. However, in their 18 June report, Messrs
Osborne and Fairhurst wrote the following alarming paragraph:
"Cross cut adhesion testing was limited,
the decision to limit (it) was based on the acceptable outcome
of previous testing and the desire to reduce repair frequency."
110. The St Andrews cross cut adhesion test
is industry standard for determining whether the field joint coating
is bonding to the plastic coated steel pipeline. It would strongly
appear BP is trying to justify not carrying out full tests on
the basis that previous adhesion testing was acceptable. This
is unsupported by the evidence outlined above in this submission.
Put simply, if the previous testing was professional why has the
coating failed?
111. The more disturbing point though is
the second reason BP gives for not doing full testing: "to
reduce repair frequency." The irresistible conclusion one
draws is this: BP is not testing unburied field joints because
it doesn't want to identify more problems with the coating it
selected and therefore delay the construction schedule with additional
repairs. Also, as more data on the failed coating emerges, BP's
liability increases. And the greater the evidence of why SPC 2888
failed, the less arguable it becomes to continue using it on BTC
and on the parallel SCP gas pipeline, currently in the early stages
of construction.[92]
112. It remains to be seen whether ECGD
and the Lenders Group would endorse this secret remedial strategy,
which is totally at odds with BP's own "Corrosion Control
and Monitoring Philosophy"a document also written
by Mr Osborne. It states that to ensure the "high integrity"
of the pipeline and field joint coating they must be "proven"
and "compatible" with each other. Otherwise, the risk
of "general and accelerated corrosion" occurs. A poor
coating, the philosophy goes on, renders ineffective any cathodic
protection, the second line of defence, which suppresses corrosion
reaction on buried pipelines.
113. BP's secret corrosion control strategy
helps explain why it told WP that cracks of less than 6 inches
need not be repaired and can be buried.
114. The BP statement that "it is not
necessary to repair all coating flaws, especially minor ones"
has been roundly condemned by experts I've consulted, who feel
it is part of the same attempt to "reduce repair frequency."
Or put another way by Dr John Leeds, "out of sight, out of
mind."
115. One of the main concerns of not treating
every cracked joint is that it makes the pipeline more susceptible
to the life-threatening process of stress corrosion cracking.
For it to occur, a coating failure where the bare steel is exposed
must have happened. Stress corrosion cracking will split open
a buried pipeline like a tin can. The escaping high pressured,
hot oil and gas can easily explode into a fireball.
116. When I visited various villages in
Georgia and Azerbaijan there was concern about the pipeline being
built too close to settlements. In Akhali Samgori, for example,
village leaders told me their pleas to move the pipeline more
than 500 metres from their homes was rejected. They worry about
the gas and oil pipelines exploding either through technical failure
or rebel attack.
117. I interviewed David Norman, a leading
pipeline integrity consultant referred to in my earlier submission.
He was contracted by PIH, the application firm, to assess the
BP remedial strategy soon after the stoppage in November 2003.
Mr Norman attended two private meetings in Tblisi, Georgia and
later at Heathrow Airport between December 2003 and January 2004.
In attendance were Mr Osborne, Mr Fairhurst, Mr Winter, SPC, the
contractors and PIH. Mr Norman says he raised the issue of stress
corrosion cracking and asked what mitigation measures were in
place. He says BP told him it was not an issue. Mr Norman says
the exchange was documented in PIH's minutes, which BP refused
to agree.
118. BP has told WP that there has been
no cracking since 9 February 2004, when they issued the corrective
application specification to PIH. This does not accord with what
my sources on the ground say. They tell me there was cracking
in April, despite the new heating regime.
119. Returning to Mr Osborne's 18 June report.
It reveals there are other serious problems with the pipeline's
main plastic coating. The report says: "Many of the joints
inspected were contaminated or showed signs of damage other than
the cracking phenomenon." It then lists the following:
"A large proportion" of
the pipes have the plastic jacket disbonding from the steel at
the field joint interface.
Damage to the plastic coating on
the overlap area where it is covered with SPC 2888.
Damage caused by the welding and
field joint coating processes.
Damage caused where the plastic coating
is resting on large rocks prior to burial.
"Moderate to severe rain damage"
of the pipeline
120. According to David Norman, who has
conducted site inspections for PIH, there are other problems that
BP is not addressing. He says that a worrying number of 11.5 metre
pipe coming from the factory does not have the 50 mm FBE toe.
This is significant because BP claims the "toe" significantly
aids the adhesion of SPC 2888 to the plastic coating.
121. Mr Norman also informs me that hundreds
of field joints are being recoated without the FBE "toe".
This, he says, is being blasted off when the faulty SPC 2888 coating
is stripped from the faulty field joint.
122. A third problem which has apparently
emerged is the quality of the chamferthe point where the
plastic coating is cut back on the pipeline to reveal the FBE
toe and the bare steel. This is not smooth enough and has therefore
created hundreds of stress points that will cause the SPC 2888
coating to crack in the ground when the pipeline is operational
and therefore moving. This interface is the weakest spot in the
field joint coating system and if it cracks will allow water to
get underneath the SPC 2888 coating and between the plastic and
the steel pipeline.
123. A number of issues emerge: Did WorleyParsons
know about these additional problems with the BTC pipeline? And
if so, why wasn't it in their report? Or did BP fail to mention
this as well?
124. So far I've concentrated on the remedial
strategy for the coated but unburied pipeline. Mr Weiss and the
WP report say BP have engaged "an independent company"
to do a technical survey (or DCVG test) to indicate flaws in the
plastic and field joint coating of the buried sections of the
pipeline. BP, writes Mr Weiss, has told ECGD that "any sections
where material flaws are identified will be excavated and the
problems corrected."
125. Ionic Consulting, part of JP Kenny,
is the company carrying out the DCVG survey. Both companies already
have a major contract with BP on the Shetland Islands. Ionic confirmed
to me that Mr Osborne contracted them to do the DCVG survey. The
Institute of Materials directory entry for Ionic lists Mr Osborne
as one of their "key personnel". Ionic also confirmed
that Mr Osborne is a consultant of theirs and is in pole position
when they land a new contract.
126. Furthermore, Ionic confirms that the
man who carried out the DCVG survey for Mr Osborne has recently
left to join WorleyParsons. The DCVG survey is therefore incomplete
and about 25% of the work, mainly in Azerbaijan, remains to be
done, Ionic say.
127. The preliminary Ionic report dated
7 May 2004 suggests there are 23 "anomalies" that "could
be classified as small where repair is not recommended as they
are of low importance." Dr John Leeds, a world expert on
DCVG surveys, will I understand be critiquing the Ionic preliminary
survey. He is not alone in raising serious concerns about its
adequacy. This after all is the mechanism through which BP will
determine what field joints have to be dug up, stripped and recoated.
128. Documents I've seen show the BP Commissioning
and Operations team in Baku have already expressed reservations
to BP Projects about the attempt to play down these anomalies
(holes/cracks in the coating). The documents also show BP Operations
are worried about the continued use of SPC 2888 on the oil and
gas pipelines.
129. BP Operations feel BP Projects did
the DCVG survey to prove everything is fine, and not to appraise
the true scale of the coating failing. They point out that the
survey doesn't deal with the integrity of the buried field jointsthe
very point it was commissioned to address.
130. BP Operations believe all small defects
in the coating are potentially significant. They therefore want
to independently review the field joint coating issue but were
over-ruled by BP Projects and its sponsors in London. BP compliance
manager David Winter is one of the leading supporters of the view
the DCVG survey by Ionic shows there is no cause for concern.
131. BP Operations are still unconvinced.
On routine pipeline patrols they discovered cracked field joints
with "rust seeping through the coating indicating disbanding."
They are not convinced that all joints coated before the stoppage
have been properly surveyed and a proper remedial strategy is
in place. They are also concerned about welding, and the effectiveness
of cathodic protection on pipeline that has been in the ground
for over one year. They are also very concerned for the corrosion
damage caused where unburied pipe had been allowed to gather water.
132. The documents reveal a major schism
within BP, which the WP report has done nothing to reflect. It
seems the field joint coating issue has come a full circle since
mid-2002. Then, BP Baku commissioned Derek Mortimore to review
the field joint specification coming from the BP design/projects
team in London. BP managers like Paul Stretch were over-ruled
and Mr Mortimore marginalized. Now a new group of concerned BP
managers are also trying to review the work of the same group
and have also been over-ruled.
THE FAILURE
OF QUALITY
CONTROL AND
ASSURANCE
133. The WP report tells us BP put "full
time coating inspectors" in Azerbaijan and Georgia from January
2004. Previously they were part time and had other responsibilities.
BP also plans to put "senior pipeline inspectors and BP/BTC
corrosion specialists" in the field. This is an implicit
admission that BP's Quality Assurance Programme failed during
the construction phase. The WP report goes on to say this QAP
failure made the cracking problem worse, in that the coating process
should have been halted earlier.
134. ECGD also shares in this failure. In
its 17 December 2003 letter of decision to underwrite the BTC
project, ECGD stated that its "independent engineers"
(WorleyParsons) had scrutinised BP's "quality control system."
Clearly this is not true, because if they had then they would
have noticed it wasn't functioning.
135. BP already has a very bad QAP record
in Alaska, where it operates the TAPS pipeline. Currently it is
under investigation by the federal investigator, the Environmental
Protection Agency. The EPA is investigating claims from over 12
whistleblowers who had worked as inspectors in BP's corrosion
division in Alaska. They have variously alleged the QAP system
is undermined by "falsification of inspection data and improper
procedures" and cost saving initiatives.
136. There is also a well-documented history
of harassment and intimidation of BP workers who raise concerns
internally.[93]
It is within this "shoot the messenger" culture that
I would suggest the unseemly attack on Mr Mortimore by BP and
WorleyParsons should be seen. It is equally disturbing that WorleyParsons
didn't seek to speak to Mr Mortimore or interview the concerned
BP Baku senior managers who contracted him. This left the wholly
misleading impression that he is a bitter, Jurassic consultant
detached from innovative thinking and unsupported by anyone inside
or outside the oil company.
137. There is no effective, independent,
well-funded regulator in Azerbaijan or Georgia. Consequently,
BP is doing an investigation into itself, with no effective oversight.
138. In the UK, if the field joint coating
issue and associated problems had been discovered on a pipeline
under construction that intended to run near highly populated
areas and major mineral water sources like the Malvern Hills would
BP be able to get away with this? The HSE would in all probability
have stopped the job, issued a 28-day notice and overseen the
remedial work it had a hand in drafting.
139. The thrust of the WP report is to attribute
blame on Mr Mortimore, the befuddled whistleblower, and on Pipeline
Induction Heating, the British company BP now publicly blames
for misapplying SPC 2888 coating to the field joints.
140. WorleyParsons never interviewed PIH.
Had it done so, PIH would have told them Mr Osborne's specification
was "incomplete" and SPC 2888 was "the wrong product".
Furthermore, sources close to the company have told me that PIH
has not incurred any financial penalty for its alleged misapplication
of SPC 2888. Indeed, if PIH had cocked up as badly as BP and the
ECGD have publicly suggested, one would not expect it to be paid
to carry out the remedial work. It is understood PIH are also
in line for the contract to coat the Southern Caucasus (gas) Pipeline.
141. There are complex negotiations going
on at the moment over how to quietly sort this problem out without
ending in the civil courts, where a lot of dirty washing would
be aired. The negotiations are between Mr Osborne and BP's compliance
department on one side and the contractors (Spie Capag and CCC)
and PIH on the other.
142. Who had primary and secondary responsibility
to ensure the field joint coating was fit for purpose, is a key
questions. The issue of criminal negligencewhether warnings
were ignoredis another and also whether procurement fraud
played a part in the choice of the failed coating.
143. Experts consulted say primary responsibility
lies with the client, BP, as it had overall responsibility through
its compliance department to ensure and enforce the Quality Assurance
Programme. The QAP is a document developed in agreement with BP's
contractors. The single sourcing of SPC 2888, also puts BP in
a very difficult situation.
144. Things get trickier because BP's compliance
manager David Winter and in house corrosion engineer, David Fairhurst
sided with Mr Osborne and SPC over Mr Mortimore, and others in
BP.
145. PIH does have a responsibility to point
out failings or problems in its instructions from the client before
or during the work, in this respect they may have failed.
146. Another bizarre anomaly is the situation
in Turkey. This is the longest section of the BTC pipeline with
90,000 field joints. Botas, the Turkish state oil and gas company,
is to carry out the construction but Bechtel/BTC has an overall
design assurance role. You could be forgiven for thinking that
SPC 2888 is also being used on the Turkish section. It isn't.
They are using Protegal 3210. If the name sounds familiar it's
because Protegal was one of the three liquid coatings Advantica
tested for BP in July 2002. In that test Protegal came last and
SPC 2888 came first. At the time of writing I am still waiting
for answers from Botas about whether they were made aware of the
Advantica test. And from BP/Bechtel about why they allowed Turkey
to use a field joint coating it disqualified for poor performance
in Azerbaijan and Georgia. If Botas weren't told this raises major
questions about BP's quality assurance. If they were told and
dismissed the Advantica test, it raises questions about the reliability
of the test that put SPC 2888 first.
147. At the very least, the BP Projects
team is hopelessly conflicted as the appropriate body to design
and oversee the remedial strategy. The BP board in London has
allowed this situation to develop and endorsed the aggressive
PR strategy of toughing it out in front of the select committee.
The government, through its ECGD department, has adopted this
line as evidenced by ministerial statements, responses to parliamentary
questions, Mr Weiss' appearance in front of the committee on 11
May and more recently the preposterous WP report. Like BP, the
ECGD refuses to accept its own mistakes and instead commissions
study after study to try and make the original selection of SPC
2888 look responsible. As the field joint scandal has escalated
with the announcement of the select committee inquiry BP has indulged
in a further cover up. The evidence lies in the extraordinary
BP document dated 18 June 2004.
148. An independent investigation into the
commercial and scientific aspects of the selection of SPC 2888
is, I submit, the only safe way forward for the people and environment
of Georgia, Azerbaijan and Turkey, and the British taxpayer.
1 October 2004
79 I enclose copies of two of these front-page articles.
Should the committee want to copy tapes of the documentaries please
contact me. Back
80
Not printed. Back
81
The SPC UK sales agent at all material times is a man called Mike
Bird. He has been employed by SPC since at least March 2001, although
E.Wood recall Bird and SPC's Canadian chairman, Bob Alliston,
coming to their offices in Yorkshire in 1999. Back
82
We had also heard claims that a batch of SPC 2888 paint had to
be placed in quarantine because it was in effect watered down
or had separated. So far these allegations remain unconfirmed
but the committee could ask BP to provide details of this. The
ECGD, we understand, was not informed. Back
83
At first blush this may seem far-fetched. But anyone familiar
with BP's activities in Alaska will know how its hand in a spying
operation on employees, external critics and a US congressman
was exposed in the eighties and nineties. Back
84
The Turkish section of the pipeline is not using SPC 2888 and
is being constructed to a different spec by another contractor. Back
85
ECGD statement to The Sunday Times dated 14 February 2004. Back
86
In August 2004 the Georgian government suspended work in the Borjomi
region, where the national mineral water company is based, following
reports from independent consultants that the BTC pipeline needed
more environmental and security measures. BP had not told the
Georgian government about the earlier field joint coating stoppage
in November 2003. Back
87
BP also refused to explain why the report was redacted, what role
SPC played, the names of its investigation team dealing with the
failed field joints and the number of field joints that were buried
in Azerbaijan and Georgia by February 2004. Back
88
Mr Powers now claims I misquoted him in my earlier submission.
I re-checked those bullet points against the tape-recording of
our conversation on 25 February. They are accurate, as are these.
I shall release the tapes should the Committee require it. Back
89
In my earlier submission I pointed out the Advantica test on SPC
2888 was carried out using a wash primer. But in the specification
Mr Osborne wrote soon after this test, nominating SPC 2888 as
the sole source field joint coating material, he excluded a wash
primer. This leaves a number of unresolved questions: Was the
wash primer one of the reasons why in certain tests SPC 2888 appeared
to outperform its two other liquid coating competitors? And does
its absence from the field joint coating specification in part
explain why SPC failed when applied to the BTC pipeline? The WP
report does not address this properly. And neither BP nor Mr Osborne
has provided an explanation. They simply ignored the question
when the Sunday Times put it to them. Mr Mortimore had drawn the
wash primer question to BP's attention in November 2002. In January
2003 BP commissioned Advantica to do a test, which is referred
to in the latest WP report. Advantica determined the use of a
wash primer was "detrimental" unless used with flame
treatment. Mr Osborne is now using this to explain why the wash
primer was not included in his field joint coating specification
dated October 2002 and therefore not used on the BTC pipeline.
But even this has been contradicted by SPC during an industry
conference in Germany. Jim Banach, a leading SPC representative,
gave a paper in October 2003 that confirmed a wash primer and
flame treatment were best practice. What are we to believe? This
is further evidence the selection process was at best incompetent. Back
90
Ian Thompson of Advantica refused to return repeated calls to
his office. Back
91
After the welded field joint has been coated it's lowered into
a ditch and backfilled with small, sharp rocks dropped at a height
in bulk on the pipeline. Naturally the plastic and field joint
coating must therefore be resistant to penetration, abrasion and
impact. The WP report shows BP only did a backfill test on how
the SPC coating behaved when rocks were dropped on it after SPC
had been selected. Furthermore, BP has taken what experts consider
to be an extraordinary decision not to bed and pad the pipeline
with a fine material like sand. Is this a cost cutting measure,
perhaps in line with its Pipeline Cost Reduction Initiative? Dr
John Leeds wonders what prior testing of SPC 2888 was done to
see how it behaves on a full and operational buried pipeline that
is repeatedly rubbing against large diameter rocks instead of
sand. Back
92
BP is the operator and joint main shareholder of the SCP gas pipeline.
The WP report confirms SPC 2888 will be used to coat its field
joints. Back
93
See Financial Times `Probe into BP Alaska Widens' by Sheila McNulty,
8 August 2004 and The Guardian, 12 July 1999 and New Solutions
magazine 2000 by M Gillard, M Jones and A Rowell. Back
|