Select Committee on Trade and Industry Written Evidence


APPENDIX 5

Memorandum by the co-ordinating groups of each of the Claimants' Solicitors' Groups

INTRODUCTORY REMARKS

  This document is provided by the Co-ordinating Groups of the two Solicitors' Groups representing men or the families of deceased men who claim compensation for:

    (a)  respiratory disease (RDL) caused by negligent exposure to excessive levels of mixed coal mine dust; and/or,

    (b)  vibration white finger (VWF) caused by negligent exposure to vibration from hand held tools;

when working in the coal mining industry.

  Litigation in respect of Vibration White Finger commenced in 1994 and in respect of Respiratory Disease in 1995. In preparing this document we have endeavoured to provide information pertinent to matters raised in the Committee's Notice in a succinct manner. We have not attempted to provide a report setting out the full history of each scheme nor of all of the problems identified including the many which have been overcome nor for that matter do we set out a full account of the successes.

  Unprecedented numbers of Claimants, former miners and their families, submitted claims under each scheme following successful litigation. This undoubtedly resulted in a substantial challenge for those faced with the tasks of devising and implementing processes to achieve fair compensation for those entitled to claim. Whilst there have been numerous issues that have had to be resolved some of which have taken some time, both schemes have delivered compensation to significant numbers of individual Claimants more efficiently than if assessment had been left for determination by individual claims brought before the Court. In the Vibration White Finger scheme 77,214 have now been settled with full and final payments and the figure for Respiratory Disease settlements is 152,500.

DEVELOPMENT OF THE SCHEMES

  There are two separate Solicitors' Groups. Membership of each group is open to any firm of solicitors that represents Claimants. Each group is represented by a Co-ordinating Group of member firms. Those Co-ordinating Groups have had responsibility for prosecuting the group litigation in each case, thereafter negotiating the terms of the respective Claims Handling Agreements with the Department of Trade and Industry (DTI) and negotiating the implementation of the provisions of those Claims Handling Agreements.

  The DTI personnel involved have with some exceptions, played their part for relatively short spells and have then moved on to other areas of work within the service. Their number has been supplemented by seconded staff from external sources, such as PricewaterhouseCooper. An external consultant (Mark Pyeman) provided project management advice to the DTI shortly after the RDL scheme was agreed. There have been six different Ministers with responsibility for coal health claims to date: John Battle, Helen Liddell, Peter Hain, Brian Wilson, Stephen Timms, Nigel Griffiths.

  The VWF Solicitors' Group existence is provided for by a Court Order made in July 1994. In RDL an Order providing for the Solicitors Group was made in January 1996.

  The active members of the VWF Co-ordinating Group are:

  Hugh James, Irwin Mitchell, Thompsons (Scotland), Thompson & Co, and Watson Burton.

  The active members of the RDL Co-ordinating Group are:

  Hugh James, Irwin Mitchell, and Thompsons (Scotland)

  In the VWF litigation there have been two High Court trials, one of preliminary issues and one of medical causation and quantum of damages. In both trials the Claimants prevailed and in each case the Defendant appealed to the Court of Appeal, unsuccessfully. The VWF Claims Handling Agreement came before the Court for approval in January 1999. It has thereafter been significantly amended and extended as issues have arisen in the assessment of claims.

  The Respiratory Disease litigation progressed to one High Court trial. There was no appeal. The Claims Handling Agreement was concluded in September 1999 and approved by the Court. This, too, has been significantly extended and amended for similar reasons.

  Copies of each of the Claims Handling Agreements will be made available to the Committee if required. Annex 1 provides an overview of each scheme.

  The litigation of both claims was pursued before the Courts in England and Wales. In relation to both, once legal liability was established the DTI accepted liability for Claimants who had worked in collieries in Scotland.

  Parallel Claims Handling Agreements were negotiated on behalf of all Scottish Claimants by solicitors instructed by the Scottish area of the National Union of Mineworkers. These Claims Handling Agreements are identical save where there are variations between the laws of Scotland and those of England and Wales (principally in relation to the assessment of posthumous claims).

  In addition, the Union of Democratic Mineworkers subsequently agreed a similar Agreement on its own behalf in respect of RDL. No other trades union has such an Agreement.

  That both the VWF and the RDL Agreements were negotiated after successful litigation establishing the Claimants legal right to compensation is significant. As a result both schemes are based upon what a miner or his family would recover if they brought a successful common law claim and consequently:

    1.  Damages are individually assessed based on evidence which means awards of damages vary significantly (in a significant number of cases life-changing sums of money have been received by miners and their families);

    2.  Legal advice has been, and remains, an integral part of the process of delivering full and proper compensation to miners and their families.

  In both cases the Claims Handling Agreements were achieved after extensive negotiation between the Co-ordinating Groups and the DTI. The amount of damages paid to any claimant under each scheme is determined by reference to tariffs of damages for various heads of claim which depend on the individual circumstances of the man and in particular his age and level of disability. The tariffs under both schemes are updated annually in line with the increase in Retail Prices Index. The tariffs are in line with that which would be paid at common law following the Courts' findings in the Judgments in the respective lead actions. The purpose of each Claims Handling Agreement is to provide for fair assessment of each claim, to pay appropriate compensation to those so entitled and to ensure consistency in assessment.

  Furthermore, in each case designated Judges of the High Court have continued to oversee the litigation receiving regular Reports to the Court through written documentation and oral submissions at hearings (see Annex 2).

  Scottish jurisdiction is of course separate from English and Welsh jurisdiction and there are certain substantive differences in the laws between the jurisdictions. The Agreements that govern the VWF and RDL compensation schemes have, so far as possible, operated on a national basis but there remain specifically Scottish issues outwith the scope of the supervisory oversight of the Court in England and Wales (see also Annex 3).

  The object of each of the Claimants' Solicitors' Group is to represent the best interests of the Claimants in claims for damages. Neither the Co-ordinating Groups nor the Solicitors' Groups have any disciplinary or regulatory powers. These are matters for the Law Society or other relevant regulatory bodies. It is for each firm to enter into appropriate arrangements with Claimants who instruct them and to ensure that proper advice is given, tailored to the circumstances of each individual Claimant, and to comply with professional standards, for example in relation to client care.

  In each case the Co-ordinating Group have issued regular Bulletins (112 in VWF and 96 in RDL) to member firms designed to assist those firms in properly advising their clients as to their claims. Training has also been provided.

  There has been some public controversy about solicitors charges. Both schemes provide that Claimants' legal fees will be paid by the DTI in successful claims but not in unsuccessful claims. In each scheme the legal fees are prescribed and for the most part agreed fixed sums are payable subject to individual circumstances. The Law Society of England and Wales issued guidance concerning solicitors charges in January 2004 and the Office for the Supervision of Solicitors has received a number of complaints. Where inappropriate charges outwith the Society's guidance have been queried we understand that repayments have been provided. Although this is a regulatory issue it seems to us appropriate that repayment is made in such circumstances.

EXTERNAL OVERSIGHT—MONITORING GROUPS

  The schemes have been, and remain, immensely important to individual Claimants and have a high profile in coalfield communities. No doubt, as a consequence, at an early stage the Minister established Monitoring Groups to review the schemes and report to the Minister. There are Monitoring Groups for each of England, Wales and Scotland and in England there are a number of Regional Groups. The Monitoring Groups assess the activities of the Claimants' solicitors, the DTI and the various contractors. We believe they have made a positive contribution.

IMPLEMENTATION OF THE SCHEMES

  In both schemes the claims assessment process has been streamlined when compared to the usual Court process. One medical expert is jointly instructed in each individual claim and the extent and nature of factual evidence and the method of presentation of that evidence has been standardised. As indicated above much work has been devoted to providing for the efficient assessment of the appropriate level of compensation dependent upon the evidence in each individual case. The process has been enhanced by the development of various computerised calculator models which include:

    1.  for VWF a programme that calculates services awards;

    2.  for RDL programmes that quantify:

    (a)  the extent of dust exposure over the working life of each Claimant dependent upon the colliery or collieries in which he worked and his job(s);

    (b)  the proportion of dust for which the DTI are liable;

    (c)  the extent of the contribution of smoking to causation of chest disease;

    (d)  the assessment of damages payable in each individual claim;

    (e)  the extent of any pension loss recoverable as part of the claim.

  There are differences as between the two schemes which flow from differences in the nature of the diseases in respect of which compensation is payable.

  Vibration White Finger is a condition which affects the hand or hands to varying degrees of severity with symptoms falling within two broad categories, vascular, induced by cold intolerance and sensorineural which include reduced dexterity, numbness and tingling. General damages are payable in respect of the condition varying according to the age of the Claimant and the severity of the disease. In addition, where proven damages may also be payable for handicap on the labour market, for the inability to undertake tasks (or services) for example, DIY, gardening, basic car maintenance and for wage loss.

  Respiratory Disease encompasses Chronic Bronchitis (a non-disabling functional disorder), Chronic Obstructive Pulmonary Disease (COPD) a disabling lung condition which can cause death, and temporary exacerbation of asthma. Both Chronic Bronchitis and COPD can be caused by smoking. As the extent of disability caused by COPD can be much more extensive than that caused by Vibration White Finger the range of or heads of damage are more extensive and arise more frequently in individual claims. They include general damages, loss of earnings, the cost of provision of care, loss of mobility, loss of pension and redundancy benefits and where death has been caused by COPD bereavement awards and loss of dependency.

  Both Claims Handling Schemes have closed to new Claimants. The number of VWF Claimants registered is 169,601[2]and the number of Respiratory Disease Claimants registered is 576,000[3]The numbers of Claimants for each scheme are unprecedented as is the amount of compensation paid to Claimants.

  Delays caused by difficulties with the handling of claims or certain categories of claims have been a continuing concern. In some instances the explanation may lie in the unprecedented volume of claims which for both schemes substantially exceeded most estimates. In both schemes the DTI's desire to close the scheme by imposition of a cut-off date for claims predictably served to produce a substantial influx of claims in the run up to each of the closure dates. In VWF there was a substantial influx of claims both before the end of the limitation amnesty on 30 September 2000 and a further influx before the cut-off dates of 31 October 2002 for live claims and 31 January 2003 for posthumous claims. In RDL, as of 31 August 2003 278,360[4]claims had been registered—over 300,000 additional cases were registered by the closure date of 31 March 2004.

  There have been recurring concerns about the planning for claims handling and the organisation and deployment of both IT and human resources and training of human resources by the DTI's contractors. We have also been concerned about the efficacy of arrangements between the DTI and its contractors and the extent to which the DTI has been able to manage its contractors and hold them to account. However, the contractual provisions and management control mechanisms have not been made known to us and therefore our concerns arise from close external observation rather than intimate knowledge.

  Numerous issues have arisen during the course of the implementation and operation of each of the Handling Agreements. Below, in separate sections for each scheme we set out what we believe to be the current principal points of concern.

  Historically, significant issues have included:

  RDL

  1.  Delivery by the first medical report provider, Healthcall both generally and in particular in relation to Respiratory Specialist recruitment and in responding to questions raised on behalf of Claimants in relation to medical reports.

  2.  The apparent inability of IRISC (now Capita) to respond to Claimants' Solicitors' correspondence and telephone enquiries generally and specifically in relation to the resolution of queries raised in relation to settlement offers.

  3.  The frequently experienced failure by IRISC to match incoming documentation from Claimant's Solicitors to files.

  4.  The lack of continuity of staff handling claims at IRISC and the absence of facilities to discuss claims.

  5.  Mineworkers who left the industry as a consequence of chest disease would, had they remained at work have paid additional contributions into their pension schemes as would their employer. As a consequence these mineworkers lost pension benefits as a result of their chest illness (the sums involved can be significant). The law provides that such losses are recoverable. The relevant Mineworkers' Pension Scheme and Staff Superannuation Scheme are complex and the benefits have changed over time. Recovery of pension loss was provided for in the Claims Handling Agreement and the parties began to work together with a jointly instructed actuary, expert in the relevant schemes, and a computer programmer to develop an agreed basis for calculating the losses. This proved to be a long arduous process. By January 2001 a calculator for the Mineworkers' Pension Scheme (MPS) Living Claimants had been prepared. In order to ensure that offers of settlement could be issued to at least some of the Claimants it was agreed that this rudimentary calculator should be operated on the basis that if a Claimant so elected he could, when the calculator was finalised, claim any additional amount of pension loss over and above the sum offered provided it exceeded £500.00. There are four components to the pension calculator: live and deceased MPS and live and deceased staff superannuation. The final component calculator was not distributed until October 2004. It should be noted that not all claims include pension losses but nevertheless many claims have been delayed from final settlement as a consequence of the development of the pension loss calculator. This is a clear example of an issue which has taken a long time to resolve. However, calculation of pension loss is complex and without the calculators the time taken to assess these losses would have been even longer.

  VWF

  1.  Timely provision of miners training records and earnings records in respect of which there was a long period of unsatisfactory delivery—the records are relevant to job or occupational group which is determinative of entry to the scheme.

  2.  The apparent inability of IRISC to respond to Claimant's Solicitors' correspondence and telephone enquiries generally and to progress claims. Items 3 and 4 above also arose in VWF.

  3.  The approach of IRISC to the investigation of Group 3 claims (see below)

  4.  The inability of IRISC to co-ordinate claims involving co-defendants (see below)

VIBRATION WHITE FINGER—CURRENT ISSUES

Group 3 Claims

  A summary of the approach adopted by the CHA to determining the issue of liability in individual cases principally by reference to the claimant's occupation is set out in Annexe 4.

  The original Claims Handling Agreement contemplated that claims would be brought by men in Group 3 occupations. They would be required to establish actual exposure to vibration. It provided brief guidance as to the information that such a Claimant would need to provide to enable the claim to be considered.

  However, it appeared that IRISC did not have in place arrangements for investigating and assessing Group 3 claims. In cases where claimants submitted evidence of exposure to vibration there was delay.

  Subsequently, in March 2001 after negotiations between the CG and the DTI, prompted by the delay in the assessment of Group 3 claims, the Occupational Group Procedure (OGP) was agreed. This was intended to provide an agreed procedure to facilitate the speedy assessment of Group 3 claims.

  It set out the evidence that was required to be submitted by the claimant and specific witnesses in a standardised questionnaire form. Provided such evidence submitted by the claimant confirming exposure to tortious vibration, was not deficient on its face or inconsistent with mining practice or other evidence then in the absence of evidence to the contrary the claim would be accepted.

  Although the OGP was intended to facilitate the handling of claims where evidence was submitted that met its requirements it was not intended to preclude consideration on its merits by IRISC of other evidence eg in other cases. However, the requirements of the OGP have been used by IRISC as a procedural bar. Where they are not met, in effect, the claim is passed back to the claimant's solicitor. There has been a refusal to consider cases in which the evidence submitted does not meet the OGP's requirements without detailed explanation as to why those requirements cannot be met and in some cases the approval of the DTI itself is required before IRISC may consider the merits of a case.

  IRISC employed a dedicated team, based in Sheffield, with mining experience to investigate Group 3 claims in general and in particular to consider whether the claim as put forward by the claimant "made mining sense". However, IRISC have found it difficult to recruit and retain sufficient staff for that team. There has been longstanding concern about the adequacy of IRISC resources to assess claims timeously.

  The rate of investigation has been slow and the approach of the investigators often controversial. Their approach particularly with regard to their application of "mining sense" has, caused disquiet among members of the National and Regional Ministerial Monitoring Groups who themselves have mining experience. So too has the relative (little) weight they have given to evidence from the claimant and his witnesses which will usually include mining officials.

  Following agreement of the OGP, evidence was submitted in many thousands of claims. The DTI imposed the cut off date of 31 October 2002 for submission of evidence in claims in which the denial was contested. This affected all but a small proportion of claims in which the denial was recent. The number of claims in which evidence contesting the denial has been submitted now exceeds 16,000.

  IRISC statistics reveal that prior to the cut off date of 31 October 2002 (approaching four years after the CHA was agreed) only 1,151 group 3 claims had been investigated.[5] In 2003 2,292 investigations were completed. That number rose to 4,055 in 2004. Over 5,000 are currently with IRISC for investigation and all told some six years after agreement of the CHA and over two years after the "cut off" date investigations have been completed in only about half of the claims in which evidence disputing the denial has been submitted. Investigations in potentially over 7,500 claims are outstanding.

  Of the claims investigated to date 1,923 (38%)[6]have been accepted as Group 1 or 2 suggesting that initially in many cases the claim was wrongly categorised by IRISC. 556 (10%) are accepted on the basis of exposure in a Group 3 occupation. 2,564 (51%) are denied.

  A significant proportion of the denials are disputed and of the 752 disputes resolved by 31 October 2004[7]in 105 (14%) had been accepted on the basis that the claimant was exposed to tortious vibration in a Group 3 occupation and in a further 132 (17.5%) it was accepted that the man had the necessary Group 1 or Group 2 employment making a total of 31.5% of disputes resolved in the claimant's favour[8]

Services Claims

  The major symptoms of VWF are numbness, loss of dexterity and cold intolerance. The latter is principally associated with the vascular component of the condition rather than the nerve damage (sensorineural) component. For claimants significantly affected there are implications for their ability to do everyday tasks such as gardening, decorating, DIY, car maintenance etc. ("services tasks"). At common law an injured claimant can recover the cost of assistance with everyday tasks such as these that he is no longer able to do, whether such assistance is provided gratuitously (usually by family and friends) or by professional assistance.

  In the lead actions a number of the significantly injured claimants recovered damages for this head of claim. Consequently, recovery for this head of damage was contemplated by the original CHA. However, initially no procedure for assessing such claims was agreed between the DTI and IRISC and IRISC did not make arrangements to assess these claims.

  Subsequently, following negotiations, in the latter half of 2000, a separate agreement was reached in early 2001 between the CG and the DTI, which provided in detail for the handling and assessment of services claims.

  The Services Agreement provided for submission of factual evidence in standardised (questionnaire) form from the claimant and those who currently provided assistance with various tasks. It was expressly intended to limit the factual evidence required to assess claims and provided for the assessment of claims by reference to agreed tariffs, depending upon the severity of the claimant's VWF, and after taking into account any co-morbid conditions that he suffered from which would have limited his ability to do the tasks in any event.

  The Services Agreement was then partially implemented as IRISC began investigation of the factual basis of claims. There were concerns from an early stage as to their approach, which in many cases involved detailed investigations of a nature not contemplated by the agreement and the relevance and focus of which was not apparent. There were also concerns about the adequacy and training of IRISC's adjusters. It is conceivable that the terms of the arrangement between the DTI and IRISC played a part in this regard but we have never been privy to these.

  There was also delay in full implementation of the Services Agreement because of the need to put the co-morbid medical assessment out to tender.

  Concerns about delivery of the Services Agreement remain. There are continuing concerns about the adequacy of the training of IRISC adjusters and the focus and relevance of their investigations in many cases. These matters may impact on the overall rate of investigations about which there are also concerns.

  Cut off dates by which claimants' must intimate claims and lodge evidence in support have been provided for, at the DTI's request, by Court Order. They will result in an increase in the rate of claims in the period preceding the cut off and may serve to adversely affect the claims handling process.

  However, although the cut off dates will cap the size of the pool of claims to be assessed, recent analysis of available statistics suggested that the DTI's aspirational end dates for settlement of all services claims are unlikely to be met by some margin.

  The extent to which IRISC and the DTI are able to monitor delays in the processing of claims at IRISC is not clear. It is understood that key stage analysis showing the length of time claims sit at any key stage in the process is not yet available for claims for Services (although it has been used for some time for early stages in the general VWF claims handling process). Following our suggestion this is now understood to be under discussion between the DTI and IRISC.

Co-defended Claims

  The approach of the VWF CHA and that of the RDL CHA differ in the manner in which co defendant claims are addressed. In the VWF scheme claims relating to exposure during periods of employment with mining contractors must be directed to the contractors (or their insurers) who deal with them in the first instance although the DTI contribute to meeting the contractors' liability.

  The VWF scheme was achieved in January 1999 and it was not until mid to early 2001 that the major contractors' insurers and the mining related defendants representing small mines and companies such as UK Coal (formerly RJB) joined the agreement after pressure had been exerted through a number of Court hearings. The number of claims in which there is involvement of mining co-defendants significantly exceeds 10,000.

  Under the CHA IRISC have the responsibility for co-ordinating claims involving co-defendants. The co defendant interests in the form of the various insurers and claims handlers have been disparate and uncoordinated themselves. It has appeared that initially IRISC focused on the bulk of claims in which there was no co-defendant interest and declined to focus adequate resources on the more arduous task of dealing with this category of claims. This has led to delays in dealing with claims with co defendant involvement which only comparatively recently have begun to settle in significant numbers.

Stalled Claims

  In early 2004 the DTI raised the prospect of introducing a procedure to address claims that had been stuck or "stalled" within the claims handling process and indicated that they wished to focus on such claims that had become stalled with solicitors. The CG indicated a willingness to discuss and develop such a proposal, providing that it was widened to also address claims that had become stalled with their contractors, principally IRISC.

  At the end of July 2004 the DTI tabled a detailed proposal addressing only the problem of claims stalled with claimants or their solicitors, which we were told they intended to proceed to implement despite the lack of agreement that they should do so and even though implementation represented a significant change to the claims handling process. A number of detailed objections were raised to the procedure which we considered was unfair and unworkable.

  As implemented, the procedure provided that following a request for information from a claimant (via his solicitor) if the information remained outstanding for more than three months then IRISC could write giving notice that the stalled claims procedure was to be invoked. If a substantive response was not received within a three month period, during which a further reminder would be sent, a claim could be closed. Once closed a claim could only be re-opened upon application to the Court.

  Between 1 October and 20 December 2004 IRISC wrote out on over 4,000 cases informing the claimant's solicitor that the case was subject to the stalled claims procedure and therefore, as noted above, the timetable towards closure of the claim within 3 months had begun to operate.

  In view of the draconian consequences for Claimants in receipt of such notification meant that Claimants' solicitors were obliged to divert resources from other claims handling activities to focus on claims that IRISC had identified as stalled. A high proportion of cases were put into the stalled procedure in error. The DTI have subsequently agreed to a number of amendments that the CG had suggested to the procedure intended to make it more practical. Had they been in place from the start many claims to which the procedure was applied would never have been subject to it.

  The exercise revealed concerns about IRISC's organisation and the training of their staff. It also raised concerns about their resources. They were unable to respond to replies from claimant's solicitors regarding claims to which the stalled claims procedure had been applied. Notwithstanding that the procedure required prompt response from the claimant's solicitor IRISC, with the DTI's agreement, did not plan to address such responses until the beginning of 2005. This approach, driven by limited resources at IRISC, created uncertainty as to the status of cases to which the procedure had been applied. During this period although the procedure had been implemented we sought to continue to negotiate with the DTI to improve its terms. Because of difficulties in its operation it was suspended between 20 December and beginning of February 2005.

  Its operation was the subject of detailed representations by the parties at a hearing on 21 January, by which time it had been substantially amended to make it workable. The major outstanding issues by then were as to when it should be introduced and whether it should be extended to apply to claims stalled with IRISC.

  On 21 January the Court directed that the procedure should be re-introduced from 1 February 2005. However, the Court indicated that in future IRISC needed to exercise greater care in the operation of the stalled procedure and in particular to ensure that it was only applied to appropriate claims.

  Introduction of the stalled claims procedure so far as claims "stalled" on the claimants side is concerned is largely a matter of recent history. However, it is significant because the episode illustrates the difficulties that arise when the DTI have sought to unilaterally impose changes without proper consultation or agreement. It is also significant because although when the proposal was first raised it was made clear that the CG considered that a similar initiative was required to address claims "stalled" with the DTI's contractors IRISC and notwithstanding that a detailed proposal was submitted months ago, that issue is one that the DTI and IRISC are clearly reluctant to contemplate and have, as yet, to give serious consideration.

RESPIRATORY DISEASE LITIGATION

Speeding Up The Scheme: Fast Track Offers

  From 1 March 2005, live claimants under the RDL scheme will be able to obtain fast track offers after a spirometry test in four distinct categories of case. This extends the opportunity for early settlement and conclusion of claims within the scheme that was previously possible only in a smaller number of cases under the expedited tariff. Damages are fixed by reference to the average payment made to date through the scheme, after a full MAP, to Claimants within each of the four spirometry categories.

  In addition to live fast track offers, the Court has ordered that in posthumous cases where there is no indication of COPD on a death certificate, called "category 3" cases, it will be possible for widows and families of deceased miners to obtain modest "fast track" payments if they wish to do so (cases with such an indication will proceed through the full MAP process without a fast track offer). It is not known yet when the posthumous "fast track" offers will be introduced but it looks as though this will not take place until the middle of the year.

  It is thought that 100,000 live "fast track" offers will be made within a year.

  As many as two-thirds of the remaining posthumous claims might be eligible for a "fast track" offer.

  The move towards introducing these "fast track" offers, which is supported by the Judge with supervisory jurisdiction over the RDL Claims' Handling Agreement, Sir Michael Turner, took place at first in a spirit of co-operation as all parties and the Court were agreed that it was wrong to take no action in the face of a projected end date for the scheme of December 2011. This distant end date arose as a consequence of the large number of claims registered by the closure date and the principal limiting factor upon "throughput" of Respiratory Specialists availability to carry out Claimants' medical assessments.

  By late September 2004, the DTI advocated—as it had done previously—a fast track option for miners to speed up their claims, or to allow them to proceed through the full MAP compensation process. Within a very short space of time however—a few weeks at most—the DTI's position changed for reasons unclear; instead, it argued for a compulsory "fast track" offer procedure that would have had the effect of leaving very few claims to proceed through the full process. It was only after a meeting at the House of Commons, in mid October, at which there was unanimous disapproval of the compulsory "fast track" scheme from coalfield representatives present, that the DTI altered its position and accepted that "fast track" offers should be optional.

  The DTI appears to have been content to let the Court rule upon the substance of the "fast track" offer and associated costs to be paid to claimants' representatives, rather than to engage in substantive negotiation, whether over the fast track tariff of payments or costs or over the important matters of detail that require to be ironed out so that the "fast track" procedures might be introduced speedily and effectively.

  As a consequence, there remains even now doubt as to the level of "fast track" payment to be paid to certain categories of live claimant and that only three weeks before the introduction of the tariff itself. Issues have arisen over the way in which the average payment has been calculated for the category of claimant with FEV 1 greater than 90%. There also remain issues over the inclusion of withdrawn cases in the cohort of claims used to work out the average payment. There is moreover, uncertainty over the identification of men who were medically unable to take the test as "avoidably unreliable" claimants or as men who were simply too ill to test properly.

  As regards posthumous cases, the payment scheme will not be introduced for several months yet, and important transitional arrangements have still to be agreed. The DTI proposed (and the Court has accepted) that the posthumous "fast track" offer will be an "opt in" scheme. As the cut-off point for eligibility to a "fast track" offer in category 3 cases will be the production of a MAP report from the medical service provider (ATOS), it is essential that claimants are able to postpone delivery of the MAP report to their representatives and to Capita until advice is given and instructions obtained in regard to the "fast track" offer entitlement that they may have. Representations to the DTI on this point have so far been rebuffed, save for an offer not to commission any further MAP reports (beyond those already in the system) as at 21 February 2005, until 21 August 2005. This leaves the problem group—category 3 cases currently in the MAP queue - unaddressed.

  These remaining issues will have to be resolved by the Court if not by agreement and it is to be hoped that a reduction in the overall life of the scheme is achieved.

Minimum Payment

  The protracted discussion over the possible introduction of a minimum payment for claimants under the RDL scheme has caused frustration to a large number of claimants. At one point during discussions last year, the DTI intimated that these might be of the order of 3,500 claimants or so, but it now appears that there may be as many as 7,500 claims blocked pending resolution of the minimum payment issue.

  The background is that in other compensation schemes such as that operated for industrial deafness claimants and pneumoconiosis claimants (and in other large settlement schemes overseas), a minimum level of payment was set. No doubt there were good reasons for this and one was that a claim meritorious to any extent should attract a value which should not be seen as an insult to the person to whom the payment was offered and so act as a disincentive to settlement.

  The DTI would not accede to the suggestion that there should be a minimum payment when the scheme was first set up in England and Wales in 1999. They also rejected a proposal from the Co-ordinating Group that in the event that a revised Chronic Bronchitis Only Tariff Scheme might be introduced, there would be transaction savings both in solicitors' costs and in costs incurred by the DTI's contractors and these might be used to create a fund for a minimum payment. These discussions broke down in 2002.

  In July 2003, claimants proposed a minimum payment scheme to be wholly funded by money released from adjustment of solicitors' costs. This required consultation and approval from the regulatory body in each jurisdiction. There was then consultation with the wider Solicitors' Group before a revised proposal was advanced to the DTI in March 2004 to top up offers falling below £500 by a reduction in the increase in solicitors costs that would normally have occurred through the Retain Price Index mechanism.

  The rate of progress made on this issue has been slow and we believe that the DTI has been reluctant to implement a minimum payment provision within the RDL scheme. Claimants frustrated at the delay experienced in resolving this issue over several years might by now have opted to accept very low payments. In any event, a very large number of settlements is likely to be obtained at a stroke when this scheme is introduced and it is to be hoped that it will not be delayed much longer.

  The DTI have said that the mechanism for the finding of minimum payments is now an issue and that a case by case approach is favoured rather than the RPI fund referred to above which takes the debate back to where it was some 18 months ago. The members of the Claimants' Solicitors Group are being consulted on this currently.

Surface Dust Exposure

  The RDL was pursued on behalf of lead claimants all of whom have worked wholly underground. Following the conclusion of the trial and during negotiation of the Claims Handling Agreement both the CG and the DTI were aware that there were certain jobs on the surface which led to exposure to coal mine dust. The CHA contained a Statement of Intent that the parties would seek to resolve liability for exposure to surface dust by agreement. Investigation of the likely extent of exposure to surface dust in certain occupations was initially undertaken jointly. In 2000 it was thought by the CG that agreement would be achieved and indeed the DTI submitted a Treasury Minute to Parliament (see Annex 5). Within a week or so of the publication of this Minute the DTI disclosed to the CG evidence as to levels of dust exposure that led to the conclusion by their appointed medical expert that no significant lung damage would result from surface dust exposure. This was not accepted by the Claimants and following further negotiation a mixed underground/surface worker agreement was achieved whereby men who worked in certain defined occupations on the surface and had also five or more years underground employment were compensated for that part of their respiratory disease caused not only by underground exposure but also by the surface exposure. The parties endeavoured to achieve agreement in relation to those exposed to dust in surface jobs only (or for less than five years underground). The DTI declined to accept liability in February 2003. The CG then investigated further the prospects of pursuing group litigation on behalf of the estimated 3,000 to 5,000 men who had registered claims. This involved extensive review of documents in the former British Coal Corporation archive and seeking medical and mining engineering evidence. The Court was advised, in December 2004, that group litigation would not be pursued. A significant factor was the risk of men having to pay the DTI's legal costs if the litigation was unsuccessful. The DTI were asked to waive this right but declined to do so. It is possible that claims may be pursued by some individual Claimants.

BOTH SCHEMES

Securities Investigation Department (SID)

  The DTI has appointed a specialist unit to investigate claims which may have been made fraudulently. From the outset, the CG accepted the DTI's right to do so, as it is plainly appropriate to seek to detect and deter potentially fraudulent claims. However, we have asked that the DTI should carry out their investigations into such claims within a reasonable framework, understood by Claimants and their Solicitors and that such investigations are completed within a reasonable timetable in the interests particularly of those claimants whose cases turn out after all to be genuine. In particular, we asked that Claimants should be advised of the basis of the DTI's concerns in any claim under investigation. We also sought clarification of the guidance or instructions given to investigative staff carrying out interviews of witnesses. Controversially, the DTI began to seek interview facilities in some cases with claimants themselves.

  As to the first of these requests, it has proved a difficult and slow exercise in cases under investigation to obtain from SID an account of their concerns. Initially, claimants' Solicitors complained that reference was made in correspondence from SID to "anomalies" in the presentation of evidence but little else was offered by way of explanation of them despite requests. There were also complaints in some instances, of heavy handed investigations of witnesses who were interviewed though unclear of the nature and purpose of the interview.

  The SID procedure appears beset by delay. Further, figures produced by the DTI suggest that only a very small number of cases under investigation do not return to the normal process eventually, to be assessed in the normal way.

    "Since May 2002, 1,470 potentially suspicious cases have been referred for additional investigation. These claims have a total potential claim value of "£21.3 million. Approximately 60 new cases are referred each month directly to the Security Investigation Department (SID). The majority of cases still relate to VWF Services, but since the COPD cut-off date the number of COPD claims being referred has increased dramatically. Currently 33% of all referrals relate to COPD claims.

    Of the 1,470 referrals, 737 are currently under investigation and 773 have had their investigations completed. Of those that have had investigations completed, 132 claims have been denied and 86 claims have been reduced, with a total value of £2.6 million.

    The remaining claims were returned for processing once it was confirmed that there was no fraudulent activity, a claim was valid within the remit of the schemes, or any anomalies were clarified. Process streamlining and improvements are continuing to be introduced to minimise any unnecessary delay to valid claims.

    Where the Department is unable to complete its investigations (for example, where a witness or a claimant declines to be interviewed), then such cases are held in abeyance until such time as the Department's concerns are either confirmed or allayed. Currently in excess of 34 claims are in abeyance."[9]

  In the meantime the Minister has recently indicated that he does not think it appropriate to disclose details of the procedure under which SID operate, since that may assist those intent upon falsifying claims. A recent request to the DTI for information as to the number of claims currently under investigation by SID has been declined and of that number how many have been under investigation for over three and over six months. The DTI insist upon their right to interview claimants where required in certain cases, although this would not be permitted in civil proceedings where a defendant would always have the right to cross-examine a claimant in evidence but not to interview him.

  Our continuing concern is that the public perception of the process will suffer if genuine claimants and their witnesses believe that procedures to investigate doubtful claims end up by stigmatising them and are characterised by secrecy and delay. In many of the cases under investigation, the CG believe that there are reasonable explanations that can be proffered for anomalies in evidence as regards dates of service provision and the like. Solicitors are willing to assist in the process in their client's interests and accept that if no reasonable explanation can be offered to SID then matters may proceed further. The balance to be struck as between the proper interest of the DTI in weeding out false claims and the interests of claimants who might be able to explain evidential discrepancies if given the chance to do so, is in our view in need of adjustment.

Openness

  We have been concerned, from time to time, as to whether or not the DTI has always been as open in sharing concerns about issues in relation particularly to the implementation of schemes as perhaps might have been hoped for in the interests of the prompt resolution of those concerns. This has been a more significant concern over the last year or so. By way of example, at Annex 6 we attach an article from "The Guardian".[10]We make the point that the words quoted from the internal DTI document indicate an unwillingness to share the idea of introducing of the proposed technology with the Co-ordinating Group: indeed, their intent was to conceal it.

CONCERNS FOR THE FUTURE

  Concerns for the future include:

  1.  The effectiveness of the implementation of Fast Track Offers process and whether or not in practice the introduction of such will reduce the time taken for the assessment of claims overall, and,

  2.  The management of the closure of each of the schemes. This is currently in progress in relation to VWF and will have to be addressed in RDL in the not too distant future.

  3.  The recent deterioration in constructive dialogue aimed at resolving issues by agreement. Much of what has been achieved has been as a consequence of, (often robust) discussion and agreement. It will hinder the operation of each of the schemes if this does not resume.

  4.  The length of time it is likely to take for IRISC to complete their investigation of VWF Group 3 claims and the factual basis of services claims; and with regard the latter the extent to which information submitted in support of the claim will become out of date and thus require to be supplemented with obvious inefficiencies in the claims handling process and frustrations for the claimants.

  5.  IRISC's capability to make available adequately trained staff at appropriate points in the claims handling procedure for both schemes so as to sufficiently reduce delays in the claims handling procedure that have been endemic to date.

  6.  The DTI's capability to monitor the performance of IRISC and keep it to account.

  7.  The DTI's willingness to always to share information required to monitor performance and to engage in constructive dialogue over proposed changes to the CHAs and claims handling process.

February 2005

FOOTNOTE

  As indicated above both schemes arise as a consequence of litigation which is an adversarial process and in respect of which both the Claimants and the DTI are entitled to legal advice which it would not wish to disclose to the other and, of course, are not obliged so to do as a matter of law. Please note that this has not impacted upon our ability to set out our views within this report.

Annex 1

OVERVIEW OF EACH SCHEME

VIBRATION WHITE FINGER

  1.  The Claimant submits questionnaires giving information about employment history in the industry.

  2.  If allocated to Group 1 or 2 proceeds to Medical Assessment Process (MAP);

  3.  If found to suffer from VWF/CTS is entitled to an offer of general damages;

  4.  In certain circumstances may be entitled to an additional award of damages for handicap on the labour market and/or for wage loss (in respect of wage loss there is a defined procedure).

  5.  Subject to extent of VWF disability may be entitled to claim for the value of lost services in respect of which a defined procedure exists.

  6.  If not found to suffer from VWF claim denied.

  7.  If not found to fall within a Group 1 or 2 occupation claim denied but Claimant has right to seek to establish either that he should be within a Group 1 or 2 occupation or that he was exposed to tortious vibration as a group 3 Claimant in respect of which a defined procedure exists.

  8.  Where employed by employers in the coal industry other than BCC the Claimant to pursue claims against those employers in accordance with CHA principles save to the extent that various employers do not accept some of the constituent parts of the agreement, notably services and wage loss.

  9.  There is a disputes procedure and the right to pursue a common law claim is retained.

  10.  There is a medical reference panel which provides oversight of the medical process.

RESPIRATORY DISEASE LITIGATION

  1.  The Claimant submits a claim indicating extent of ill health and work history and smoking habit;

  2.  Work history is relevant to calculating the extent and nature of the dust exposure;

  3.  A living miner attends for spirometry test and subject to the outcome may be entitled to an expedited offer of settlement;

  4.  If an expedited offer is made and refused or if the man is not entitled to an expedited offer he may proceed to a full Medical Assessment after medical record collection (MAP);

  5.  In posthumous cases following submission of Claims Questionnaires medical records are collected and the claim proceeds directly to medical assessment (MAP);

  6.  Following MAP if a relevant respiratory condition is diagnosed then subject to proof of employment an offer of damages will be advanced in accordance with the relevant provisions of the CHA.

  7.  Proof of employment requires establishing the Claimant worked underground in a British Coal Corporation colliery post 1954 and if he worked in a defined dusty job on the surface that he worked for more than 5 years underground.

  8.  There is no need to pursue a claim against a coal mine contractor who employed a miner to work in a BCC operated mine prior to privatisation. For men employed in the privatised industry post 1994 there is a need to bring a separate claim against that employer.

  9.  Small Mines employment (private licensed mines) is pursued separately and the block insurer, AGF for the period 1972 to 1992, has accepted that claims will be handled in accordance with the CHA.

  10.  There is a disputes procedure and the right to pursue a common law claim is retained.

  11.  There is a medical reference panel which provides oversight of the medical process.

  Both schemes contain procedural timetables for the advancement of individual claims. Unfortunately, these timetables were abandoned at an early stage in each scheme because the DTI's contractors were unable to meet them.

Annex 2

JUDICIAL OVERSIGHT OF EACH SCHEME

VIBRATION WHITE FINGER

  The nominated Judge is Lady Justice Smith. Lady Justice Smith was not the trial Judge.

  Last week Lady Justice Smith stood down and has been replaced by Mr Justice Mitting.

RESPIRATORY DISEASE LITIGATION

  The nominated Judge is Sir Michael Turner. Sir Michael Turner was the trial Judge.

  In both cases Review Hearings take place at a frequency of three or four per calendar year where formal Reports are delivered to the Court and where necessary indications are given by the Judge as to how issues may be resolved. In a number of specific instances there have been hearings to resolve disputes between the parties.

  The Court hearings take place in public and are regularly attended by members of the Claimants Solicitors Group, by members of the Monitoring Groups, by Union officials and, from time to time, members of the press.

Annex 3

SCOTLAND

  The Scottish version of the VWF Claims Handling Agreement was entered into after the English and Welsh Agreement in 1999. The RDL Claims Handling Agreement similarly, was negotiated after the English and Welsh Agreement, in 2000. Each Agreement was negotiated, with the NUM in Scotland taking the lead negotiating role for Scottish claimants there (the Agreements are open to all Scottish Claimants irrespective of Union membership); there is no formal Court Order or supervision of Scottish issues that arise from time to time and which are distinct from those dealt with by the Court south of the border. The role of the Ministerial Monitoring Committee (MMC) in Scotland in overseeing each Agreement assumes greater significance than that of MMCs elsewhere because of the lack of formal process.

  Like any Agreement, goodwill on both sides is needed to make it work. We believe that such goodwill did exist in the first two to three years of operation of the Scottish version of the Handling Agreement despite the enormous problems that were thrown up by the volume of claims, the complexities of the handling procedures and the initial lack of trained resource available to deal with cases in the numbers required. All parties worked together to ensure that Scottish claimants and Scottish issues where they arose, as they did from time to time, were handled in a constructive atmosphere and in a fair way, having regard to both the interests of claimants and of the public purse.

  Regrettably however, it has appeared in recent months that the DTI has been less constructive and less willing to heed the views of the Monitoring Committee in Scotland on issues of principle between the parties and on the best way of resolving them within a negotiated context.

  Recent examples of this approach are the protracted discussions over the Loss of Society tariff (bereavement award) in Scotland and the sensitive issue that arises when a widow entitled to a payment under the Agreement with the DTI for her husband's pain and suffering, whose husband died before 16 July 1992, herself dies in process and before the payment is made to her. The DTI have dragged their feet over agreeing a reasonable procedure to ensure a fair outcome in these cases consistent with its stated intention to see that no benefit should arise to the DTI from death in process. It continues to be difficult to get the DTI to honour that commitment for this group of claimants.

  The agreement with the DTI provides that the widow of a miner should receive his damages even though the law in Scotland (as it then was) made no provision for transmission of the deceased person's right to general damages (solatium) after his death. The lack of such provision in Scotland was clearly seen as indefensible, not least because of the approach of certain insurers in defending serious personal injury claims. Claimants who were dying from the effects of a disease for which they sought damages (such as mesothelioma) might receive no offer of compensation before their deaths and thus present the insurer concerned with a windfall gain in a claim destined to settle, equivalent to the injured person's damages for pain and suffering. The change made in the law has no retrospective effect on deaths before 16 July 1992, but the Scottish RDL agreement records that damages will pass to a miner's widow notwithstanding.

  The problem now is that widows are dying in process and the question arises as to whether damages that they ought to have received and to which they had a right under the agreement with the DTI, should in turn be allowed to pass to their estates in all cases. This is challenged by the department, which has dragged its feet over agreeing a reasonable procedure to ensure a fair outcome in these cases consistent with its stated intention—often repeated by the Ministers responsible—to see that no benefit should arise to the DTI from a death in process. It continues to be difficult to get the DTI to honour that commitment for this group of claimants.

  The position of co-defenders who have a joint liability with the DTI for coal health claims is one of the outstanding issues still to be fully addressed for Scottish claimants. Whereas contracting companies such as Thyssens (GB) Limited and AMCO have been largely willing to deal with VWF claims on the same terms in Scotland as apply south of the border, their position in regard to RDL claims is unclear. Purely Scottish companies such as Scottish Coal and Monktonhall Mineworkers Limited have still to confirm that they will accede to the RDL handling arrangement on the terms applied to AGF (for the small mine interest) or UK Coal claims.

  The DTI's claim handling office in Scotland is at Capita (formerly IRISC), 40 Torphichen Street, Edinburgh. The office was established to deal specifically with Scottish claims but does not deal with all aspects of the VWF and COPD Handling Agreement. Some matters such as Group 3 cases in the VWF Scheme and Fast Track Offers, are dealt with from Capita's Sheffield Office. There has from time to time been an unsure grasp of Scottish issues (such as the pre-16.07.92 issue referred to above) and there were for a time, resource issues as IRISC (as they then were) sought to recruit staff to deal with the large volumes of claims.

  It has appeared that Capita are very much a target driven organisation which may simply reflect the terms of their contract with the DTI (unknown and unseen on our side). In 2002-03, Ministerial targets for offers in the COPD Scheme were met but as there were no targets set for offers that required to be reviewed by Capita before a settlement could be obtained, considerable delays were experienced at that time before the necessary reviews were carried out.

  Capita in Edinburgh have been more responsive of late, particularly to the issue of old claims in the COPD Scheme that were not being addressed despite assurances from Capita in Sheffield that the "priority points" system would always work effectively to find such cases. This was not always our experience. To their credit, Capita in Edinburgh responded finally to our efforts to have them identify old claims "Stalled" at Capita and this has seen good progress made in recent months.

  In posthumous cases, title to a deceased person's estate needs to be formally completed before final settlement. In Scotland, the procedure required is to obtain a Confirmation from the sheriff court (a Probate in England and Wales). Whilst this in itself causes no undue delay, obtaining multiple Confirmations in cases where there is a "chain" of succession and deaths (from miner, to widow, to son/daughter, and on) is causing significant delay in a number of claims, especially those where the miner died a long time ago. Difficulties in tracking down relevant documents (old Wills and title deeds) and in tracing all relatives who may be entitled to succeed to compensation payable, are the cause of further delays. Insurance policies must be taken out in certain cases where no Will can be found. It would assist in speeding the process up—and be much less costly to the public purse - if the rules could be relaxed for the more modest settlement amounts due, say up to £1,000.

  There are continuing reservations over Capita's resourcing and application of such resource in VWF claims. The national picture on group 3 claims reflects the Scottish position as there is no separate service allocated to these cases in Capita Edinburgh's office. Services' claims have taken a very long time to begin to move through the procedure designed for them. Co-defended cases have simply not been handled as they ought to have been by Capita as the lead Insurer and continue to suffer from relative neglect at the handling stage, though allowance must be made for the difficulties in co-ordination of claims with reluctant co-Insurers. These have also attended upon the resolution of wage loss claims in the VWF Scheme. Looking to the short and medium term, concerns persist over the approach to the outstanding issues which may yet result in litigation in Scotland, affecting the management of the run down of each Scheme; these would benefit from a more constructive joint approach than has been evidence of late.

Annex 4

VWF GROUP 3 CLAIMS

  The original High Court ruling has established that British Coal should have known the risks of VWF by 1 January 1973 and within two years taken steps to warn the workforce, put in place a system of medical surveillance for employees who were exposed to vibration and take steps to reduce the vibration exposure of men exposed to vibration beyond a limited extent. In failing to take those steps British Coal were negligent and significant subsequent exposure was tortious.

  To avoid the need to investigate every claimants exposure to vibration (a lengthy and costly exercise) an approach was adopted whereby for certain occupations in which use of vibratory or percussive tools was either a substantial part of the job of use was likely to have been significant, time spent in that occupation would be taken as surrogate for establishing actual exposure to vibration. Jobs were categorised into occupational groups, "Group 1" being those in which use of tools was recognised as a substantial part of the occupation, eg face workers, development workers, blacksmiths and 12 months employment post 1 January 1975 in such an occupation was required to establish entitlement of compensation. "Group 2" comprised those jobs in which use of pneumatic or percussive tools may have been less than Group 1 occupations but nonetheless was likely to have been significant and 2 years in a Group 2 occupation post 1 January 1975 would establish entitlement of compensation . Examples of Group 2 occupations are face or development deputies, general underground labourers, salvage workers.

  This left a third group of occupations "Group 3" occupations for which there was no assumption as to use of vibratory or percussive tools and evidence of tortious exposure would be required to substantiate a claim. That group included transfer point attendants, deputies other than those on face or development work, loco drivers and men engaged on haulage supply work and many other occupations including all those not included in Group 1 or 2.

Annex 5

Letter from the Department of Trade and Industry to Irwin Mitchell

COAL HEALTH: SURFACE DUST

  I attach a copy of the Minute laid before Parliament yesterday advising the House that, subject to no objections being raised, the Department proposes to accept liability for disability caused by exposure to dust in surface jobs.

Ann Taylor

11 July 2000

NON-STATUTORY LIABILITY TO PAY COMPENSATION TO MINERS FOR EXPOSURE TO SURFACE DUST

  1.  It is normal practice when a Government Department proposes to take on a liability in excess of £100,000 for which there is no specific statutory authority, for the Department concerned to present to Parliament a Minute giving particulars of the liability created and explaining the circumstances.

  2.  This minute explains the liability the Department of Trade and Industry proposes to accept in respect of exposure to surface dust for employees in British Coal mines.

Background

  3.  In 1998 the Court found British Coal liable for exposure of mine workers to excessive dust which caused lung diseases. The DTI. Which had shortly before taken over the health liabilities of British Coal, was instructed by the judge to set up a Scheme to provide compensation for miners suffering lung diseases as a result of employment with British Coal. A Claims Handling Agreement to deal with compensation was negotiated with solicitors representing miners and signed in September 1999.

  4.  The Court case and the Handling Agreement dealt with dust exposure underground. There are currently nearly 110,000 claimants and compensation is expected to amount to approximately £1bn. It will take around three years to deal with these claims.

Surface Dust

  5.  Many of the existing claimants also have potential extended claims for exposure to dust in jobs on the surface at mines. In addition, some surface only workers have test claims pending. Exposure to dust on the surface leads to the same lung diseases as dust underground. The DTI has investigated the levels of dust prevailing in surface jobs in British Coal mines, measures which could have been taken to reduce dust and those which were taken. The DTI proposes to accept that British Coal did not fully meet its responsibilities towards certain categories of workers in dusty jobs on the surface. (If the liability is not accepted these issues will be put to the Court to decide.)

  6.  In accepting this liability, the DTI would propose to miners' solicitors that compensation for surface dust exposure be handled within the current Agreement for underground exposure. How this would work would need to be negotiated in detail. Agreement would be needed on what jobs would be covered and on what levels of dust could reasonably have been avoided.

  7.  Until these details have been agreed it is not possible to make any firm estimates of the likely costs of the new liabilities for surface dust. But it is likely to be substantial (perhaps upward of £100 million). provision for any payments to discharge these liabilities will be sought through the normal supply procedure.

  8.  Acceptance of this additional liability will mean that current claimants can extend their claim to cover time spent in dusty jobs on the surface and men who have only worked on the surface will be able to put in a claim.

  9.  The Department will keep the House informed of the extent of these new liabilities as they become clearer.

  10.  The Treasury have approved in principle the acceptance of this liability. If during the period of 14 days (exclusive of Saturdays and Sundays) beginning on the date on which this Minute was laid before Parliament, a Member signifies an objection by giving notice of a Parliamentary Question or by otherwise raising the matter in Parliament, final approval to proceed with accepting the liability will be upheld pending an examination of the objection.

Ann Taylor

Director of Coal Health Claims Unit, Department of Trade and Industry

10 July 2000





2   The DTI report to the Court for Hearing 20 December 2004. 13% of claims are made on behalf of deceased mine workers estates. The figure excludes the small number of claims against mining contractors for which the DTI also have some liability. Back

3   There are 248,000 claims brought by living miners and 327,000 posthumous claims brought by family members. Back

4   149,937 living miners, 128,423 posthumous. Back

5   In November and December 2002 a further 459 investigations were completed. Back

6   This percentage will decrease as a number of completed cases accepted as Group 1 or 2 were identified following special review exercises, now completed, and not part of the routine investigations. Back

7   More recent figures for the outcome of disputes are not available to us. Back

8   IRISC Group 3 figures. Back

9   DTI's Report to the Court January 2005. Back

10   Not printed. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 4 May 2005