Select Committee on Trade and Industry Third Special Report


Appendix 1: Response from the Department of Trade and Industry

Introduction

The Department welcomes the Select Committee's Report and its conclusions that the companies themselves and the public sector bodies responsible for the industry—DTI, Ofgem and energywatch—have worked hard to draw the correct lessons from the October 2002 storms and to implement appropriate changes to practice. The Department is pleased to note the Select Committee's commendation of the work of the Network Resilience Working Group (NRWG), and supports its conclusion that the distribution companies are now significantly better prepared to deal with the aftermath of severe weather than they were in October 2002. This is borne out by preliminary impressions of the performance of the distribution companies most affected in the restoration of supply in recent storms, although the Department has yet to complete a full assessment of that experience.

In considering the Committee's report, account needs to be taken of the respective roles and responsibilities of the Department and Ofgem the independent regulator. The Department's role is to set the regulatory framework within which Ofgem and the industry operates as well as determining the overall policy direction. This includes regulations dealing with the safety, quality and continuity of supplies. Ofgem's role is to protect the interests of current and future consumers, by promoting competition where appropriate and in regulating monopoly businesses where necessary. This will include provisions that gas and electricity markets work effectively and that Britain's gas and electricity supplies are secured.

Against this background, therefore, detailed responses to many of the points raised by the Committee in a number of its conclusions and recommendations are primarily matters for Ofgem rather than the Department. The Department therefore proposes not to respond to recommendations 4 and 8-26, which deal with such matters. However, the Department would make the following comments on the remaining recommendations

Conclusions and Recommendations

Lessons from the October 2002 storms

1. We commend the work of the Network Resilience Working Group, which produced a comprehensive assessment of best practice for companies to follow to reduce the impact of severe weather incidents and to improve procedures for recovery from such incidents. (Paragraph 35)

We are pleased to note the Select Committee's commendation for the work of the Network Resilience Working Group. The Group put forward a number of proposals aimed at improving resilience of the distribution networks to storms. These included: a review of weather patterns, resources (both numbers of staff and skills), operational communications, initiatives for long term network investment and a "toolbox" for network improvements. The Department is pleased that the Select Committee has based its conclusions around some of these issues. As joint signatories to the group recommendations, together with the industry, Ofgem and energywatch, we are currently taking forward those of its recommendations which were targeted at the Department.

On the issue of skills, for example, the Chairman of the Select Committee will be aware of the joint Industry-Government-Academia Skills and Recruitment seminar held at the Department's offices on 8 December 2004. Work is in hand within Government to take forward the issues discussed there with the industry.

2. It would seem that companies have worked to improve their performance during and after severe weather incidents both in the development of emergency plans and in their implementation. (Paragraph 42)

Distribution Network Operators regularly test their operational readiness and emergency planning policies. The Department is aware of the details from the tests carried out by some companies during the last quarter of 2004 and indeed was invited to participate in some of the scenarios. On this basis we have the same impression of general improvement as the Committee.

Weather forecasts

3. The relative infrequency of events such as that on 27 October 2002 should not preclude DNOs from being required to build into their emergency plans procedures to ensure proper consideration of severe weather warnings. We endorse BPI's recommendation that, if they have not already done so, DNOs should develop robust methods of predicting how forecast severe weather conditions are likely to damage networks and create a demand on resources and how to mobilise those resources accordingly. (Paragraph 14)

The Department notes the Committee's comments and also agrees with the BPI recommendations on consideration of severe weather warnings. We believe that, in general, all DNOs have become more "weather wise" and now have more resources ready to deal with adverse weather conditions. Emergency planning exercises also help test companies' readiness.

Communication with the public

4. Ofgem intends to develop an additional incentive for improving communications with the public during exceptional events. We welcome this development. (Paragraph 24)

This is a matter for Ofgem, the independent regulator.

Protection for vulnerable customers

5. Compilation and maintenance of the Priority Service Register should be a core task for all companies. Ofgem should undertake a review of the adequacy of the PSRs held by network operators and ensure that appropriate action is taken to rectify any deficiencies. (Paragraph 27)

This is a matter for Ofgem, the independent regulator.

Operational communications

6. The rapid restoration of an interrupted electricity supply is of primary importance to consumers, particularly if the interruption is on a large scale, as it is likely to be if the cause is severe weather. In such circumstances, the maintenance of reliable communications is so vital as to warrant the classification of electricity field teams as an 'essential service'. We support the industry's call for access to the Emergency Service Communications Network for those DNOs, which can demonstrate that such access is necessary to provide efficient and cost-effective repair and recovery. (Paragraph 30)

This is a matter for Ofcom together with the DNOs. We understand that negotiation on the industry's application to join the Airwave network is currently under way.

Control of Vegetation

7. We are pleased to note that Ofgem proposes to make a specific allowance of about £22.4 million a year for increased control of vegetation during the next price control period, 2005-10. No allowance has been made for any backlog as Ofgem considers that this expense should be borne by shareholders rather than customers. From absence of criticism, we deduce that the DNOs are satisfied with the size of the tree-cutting allowance. (Paragraph 34)

The price control is a matter for Ofgem, the independent regulator. However, by way of additional background the Department would note that the Electricity Safety, Quality and Continuity Regulations 2002 already require tree cutting for reasons of public safety (regulation 18(5)), and it is intended that these regulations will be amended to include a requirement to maintain tree clearances to avoid interruptions of electricity supply, so far as is reasonably practicable. Officials have developed a Regulatory Impact Assessment and Guidance to support this change and carry out a public consultation. The consultation is expected to commence in mid/end-February 2005, to be followed with the usual 12-week response period. The impact of such a change is likely to deliver an improvement in storm performance of distribution companies and would be intended to be phased in to allow for current tree cutting cycles.

As for the national transmission system, although historically there have been relatively few problems with trees coming into contact with National Grid's tower lines, it should be noted that contact with trees was a significant causal factor in the major power failures in North America on 14 August 2003 and in Italy on 28 September 2003. It is therefore proposed that transmission companies in Great Britain should also comply with the proposed requirement to cut trees for continuity of supply.

Officials have also explored with the Industry promoting usage of covered conductors as a measure that would improve storm performance as well as improving public safety. Those discussions concluded that widespread adoption of covered conductors in all circumstances for reliability purposes is not likely to be cost effective in addressing the combination of improvements such as increased circuit automation and better vegetation management. There appears to be no economic case for the widespread application of covered conductors on safety grounds. However, we understand that all companies are undertaking targeted installations of covered conductors of overhead lines where they believe this would have the maximum impact on overall circuit reliability.

Compensation to customers

8. The special storm payment offered by 24seven to those customers who suffered most from the disruption to their electricity supply was, no doubt, welcome to those eligible to receive it. It was, however, considerably less than the sum that would have been due to them had the company not chosen to claim exemption from the normal compensation mechanism. (Paragraph 49)

This and all subsequent recommendations deal with matters for Ofgem, the independent regulator on which the Department does not propose to comment.

9. It was regrettable that consumers had to wait so long for a decision from Ofgem on the validity of their compensation claims. However, this was perhaps inevitable given the scale of the problem and the large numbers of cases to be considered. We consider that the strategy developed by Ofgem to produce the determinations, although a significant departure from usual practice, was a pragmatic and effective solution to a difficult problem. (Paragraph 52)

10. We consider that, although the proposed new compensation mechanism is rather complex, it and the interim arrangements from which the new system has been developed represent a marked improvement on the previous compensation scheme. DNOs should be able to give clear, unambiguous advice to customers about their entitlement to compensation. In addition, greater precision in the definition of the circumstances under which compensation is payable should reduce the number of disputed cases to the regulator for determination, so settlement of compensation claims should be faster. (Paragraph 62)

Future investment in the networks: Consumer views

11. We understand that Ofgem did not want to base its whole approach to the 2005-10-price control review on the results of one survey. However, Ofgem seems unwilling to accept that British consumers may place a significantly higher premium on improved network resilience than other consumers do and than Ofgem appears to consider that they ought to. We would be unhappy if we thought that the regulator was insisting that it knew better than consumers what they wanted. (Paragraph 72)

12. We note, however, the regulator's assurance that the results of the survey have been taken into account in setting Quality of Service targets for the distribution companies. Our analysis of Ofgem's proposals confirms this in particular the emphasis on speeding up restoration of supplies after unplanned interruptions. This is enough at present. (Paragraph 73)

Investment for the future: Quality of service targets

13. On the basis of the ENA's and Ofgem's figures, an allowance of £2.30 per customer produced a 7 percent improvement in quality of service over 2000-05, while Ofgem's targets for 2005-10 are a 12 percent improvement on an allowance of less than £1 per customer. This comparison may be misleading, however, if Ofgem's proposals achieve less, but better targeted, expenditure. Ofgem has balanced requirements for improved standards with financial allowances for achieving these improvements. However, given the recent rate of improvement, Ofgem's targets appear ambitious. Without a very detailed analysis of the position of individual companies, which we are not in a position to do, we cannot say whether given that the targets are coupled with higher potential penalties for failing to meet them—they are nevertheless fair. (Paragraph 79)

Capital expenditure: Effect of Ofgem's proposals on individual DNOs

14. Although we agree with the principle that shareholders should not benefit from previous low levels of investment at the expense of customers, we would be very uneasy if applying this principle meant that the company would be hindered from making the capital investment necessary to provide its customers with as reliable an electricity supply as comparable customers elsewhere expect and receive. At the worst, there would be potential for a vicious circle of under-investment followed by penalties for failing Quality of Service targets, which would leave even less money for necessary capital investment. However, we have received no evidence that the customers of the companies concerned on this occasion would suffer as a result of Ofgem's proposals; and we note that the proposed allowances would enable these companies to invest more than they have done in the recent past. (Paragraph 86)

15. We take even more comfort from the inference that Ofgem intends in future to deter any similar under-investment by companies by means of the sliding scale mechanism. Both for the sake of the customers and for the promotion of efficiency of the electricity industry, we would much prefer that under-investment be prevented rather than punished. (Paragraph 86)

Special provision for putting power lines underground in National Parks

16. We are pleased to note that Ofgem has changed its views on whether it is appropriate for the regulator to make an allowance for investment to improve visual amenity. (Paragraph 94)

Capital investment to improve network performance

17. While we acknowledge that companies will be able to choose which particular projects will give the greatest benefits—and that it is always open to them to finance projects at the expense of the shareholders rather than the customers—the regulator does, and must, make a judgement on what companies need to do in order to decide how much money they need to do it. By refusing to make specific allowance for improvements to the network, Ofgem is, in effect, deciding that such improvements are not necessary from the customers' point of view: they are something which can be left to the discretion of individual DNOs. (Paragraph 90)

18. Ofgem argued that the companies' proposals for specific investment to improve network performance did not represent value for money given the few customers who would benefit. However, the charges that would be passed on to customers in their bills would amount to significantly less than several hundred pounds per year per affected customer. Moreover, as these costs would be spread over the whole customer base of the DNOs concerned, as such capital costs would be a relatively small proportion of DNO charges to customers as a whole, and as the cost of electricity distribution forms about 25 percent of domestic electricity bills, the actual increase in individual customers' bills would probably amount to at most a few pounds per year. (Paragraph 91)

19. In March we stated our belief that customers would be prepared to spend a modest amount extra to obtain a better network and more reliable electricity supplies, and we are confirmed in that view by the research subsequently undertaken into consumer preferences. However, while we are sympathetic to the companies' arguments for being allowed to undertake capital investment to increase the resilience of the network, we understand that—not least in view of previous under-investment by some companies—Ofgem is inclined to proceed cautiously and wishes to see a robust case for such extra investment. We cannot say that Ofgem is wrong in its approach, but we emphasise that Ofgem should keep an open mind about the need for further investment in the infrastructure if it wishes to increase Quality of Service standards. (Paragraph 95)

Overall conclusion on capital expenditure

20. Overall, we welcome the fact that, in its proposals for capital allowances, Ofgem has clearly acknowledged that extra investment to replace infrastructure is needed. The regulator may not have gone as far as we wished, but a gradual approach is justifiable. We simply reiterate our view that, just to enable ageing equipment to be replaced, investment in the electricity infrastructure will have to be significantly higher than in recent years and over an extended period, probably about 20 years. We urge Ofgem to view this five-year review as the opening of a long-term project to ensure the resilience of the UK electricity network. (Paragraph 96)

Operational expenditure

21. We do not propose to comment on the theoretical basis of Ofgem's approach, other than that setting price controls is arguably more of an art than a science. We note also that Ofgem itself has conceded that benchmarking has become increasingly difficult, as mergers within the industry have reduced the number of comparators. (Paragraph 103)

22. We appreciate that Ofgem's fine tuning of capital and operational expenditure allowances has produced the overall result that, with the exception of a small increase (1.3 percent on average) in the first year, the companies' revenue should rise only by the rate of inflation, as measured by the RPI, over the next four years. We also accept that there may still be efficiency savings that DNOs could make, and that Ofgem has made provision for costs over which companies have no control. However, this means that the areas in which Ofgem expects the cuts in operational expenditure to take place would be things such as staff costs and maintenance, which companies do control. We are still concerned that the age of the UK network and the rate of replacement of equipment means that, at least over the next few years, there may well be a need for more, and more expert (and therefore, in salary terms, dearer), maintenance. Unlike Ofgem, we therefore doubt whether current levels of performance can be maintained on smaller and smaller maintenance budgets. (Paragraph 104)

Accommodating renewable generation

23. The incentive scheme for distributed generation is complex, and its effects will vary from DNO to DNO depending on how much, when and where renewable generation capacity is built. However, we consider that Ofgem's incentive for such investment of an additional rate of return of one percent above the current allowed cost of capital of 6.9 percent represents a real 'bonus' to companies. Moreover, the regulator has moved to address one of the specific criticisms of the scheme made to us by the ENA, which was that DNOs would be penalised for any problems generators had with network access after they had been connected. (Paragraph 109)

24. Estimating demand from new renewable power generators is difficult. However, the DNOs are much better placed than Ofgem to make these judgements. Moreover, the construction programme to accommodate renewable generation will take many years, possibly a couple of decades. We are at the start of the process now, and, while we recognise that Ofgem is committed to the five-yearly review process and does not wish to operate continuous adjustments to price controls, we are confident that Ofgem would be willing to adjust its incentives/penalties schemes if there was real evidence of a need to make extra investment during the price control period. (Paragraph 110)

Funding of R&D

25. We are delighted to note Ofgem's proposal for an Innovation Funding Incentive to cover most of the cost of development projects that would provide real benefits to end consumers. (Paragraph 111)

Cost of capital

26. We understand that Ofgem had to wait until the proposals were in their final form to come to a definite decision on the cost of capital allowed for. We note the real danger, indicated even by Ofgem, that the 4.6 percent rate would seriously compromise at least some companies' ability to raise the capital they would require. We are therefore pleased to note that, in its final proposals, Ofgem has suggested a higher allowance for overall cost of capital of 4.8 percent post-tax, 6.9 percent pre-tax. This compares with the allowance under the existing price control of 6.5 percent before tax. Moreover, recognising that, under its modelling assumptions, EDF-SPN was likely to find it difficult to maintain a comfortable investment grade rating in the later years of the control period, Ofgem has proposed to adjust the price control proposals for this company to enable it to maintain its credit rating. (Paragraph 114)


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 15 March 2005