Select Committee on Trade and Industry Minutes of Evidence


Examination of Witnesses (Questions 1-19)

EDF ENERGY NETWORKS

16 SEPTEMBER 2003

  Q1  Chairman: Good morning, Mr Cuttill and Mr Carey. Thank you for coming in. It might seem in some ways that we are bringing back to you memories which you prefer to forget—although I would imagine that the lessons you have learned you would want to keep in mind; but, as we would have thought we were beginning to get near the time when people would be more dependent upon electricity for heating—although it might be the case that in an area like we are talking about, which is not predominantly but relatively prosperous, they might be concerned with air-conditioning as well—we thought it would be better to get a view of what has happened and how you see the forthcoming winter/autumn storms. There is always an element of luck in this. We understand that. It is certainly the situation that you were better able to handle the problems that you had in January than you were in October. Maybe you could explain to us how, in the period between October and January, you set about trying to get your house in order—if that is the right question: Why is it that it was not in order before? Certainly you had difficulties. Perhaps we could start there.

  Mr Cuttill: Thank you very much, indeed. It is a good opportunity for us to share with you our experiences of last October and, as you rightly say, the lessons we have learned. January this year, in terms of the weather at the end of the month, presented us with some further challenges in terms of electricity restoration, but we were able to use the lessons of October 2002 to perform better. I think I would like to say right up front that in terms of October, whilst huge efforts were made during the event, most notably by all of the staff working for us, it is clear that a sizeable number of our customers did not receive the service which they are reasonably entitled to expect from us. We have said consistently that that is a matter of considerable regret for us and we have apologised unreservedly for that. But the weather of the last week of January was, I would say, just as severe as the weather we saw at the end of October, and we did have to learn the lessons very quickly. The three main areas on which we concentrated were our ability to anticipate the resources required to cope with the large number of faults, particularly on the low voltage system; an understanding of the scale of interruptions from a perspective of communicating with our external stakeholders; and also the ability of our customers to contact us. The initial outcome from the October event was for a number of reports to be prepared. One was our own internal review in which we identified 57 points of action and by the turn of the year 2002, and into 2003 we had implemented a number of those and made significant progress on just about them all. That meant that when the January incident came along we did have a better contingency plan. There is no doubt about it. The important aspect also was that we had a greater focus of management attention on the issues. We were able to muster our resources quicker and earlier, we were better at anticipating what was going to be required—and those are resources both in terms of people, technical support and transportation support. We implemented aspects of our revised communication strategy, which was to use the large call centres that our supply business use on a normal basis, so we were able to move calls straight to them in accordance with the arrangements we had made. Crucially, we had been able, in the intervening months, to establish much better contacts with the emergency planning authorities of county councils. We had met most of them and therefore we were able to use those in a much better way to help us. We had used the principle of all our staff having what we call a "storm role", so they understand what it is that we would like them to do during this period. That was something we did not have in October. I think we made a better attempt at explaining early on in the incident what the likely restoration period would be,  such that on the morning of the Friday of the   particular incident we had a very clear understanding of the numbers of customers affected and an indication of duration. They were all the lessons that we had identified and we had put plans in place to perform better. Again, there are always lessons to learn from each incident that you experience, but I believe that as an organisation we did respond significantly better in January and that was as a result of the very severe lessons of October 2002.

  Q2  Chairman: The extremity of the weather, the change in the conditions, had this ever been encountered before either by the British part of EDF or the French part? If it happened in France, what would have been the response? Would it have been as muddled and confused as it was in England?

  Mr Cuttill: France had a very bad weather incident, as you may recall, 1999 into 2000. The response by EDF was obviously considerable. The UK did provide significant resource and logistical support in their restoration process. They saw outages, if I recall, of up to about three or four weeks in some areas because of the severity of the destruction to their overhead network. So I do not know whether in terms of restoration it was better than in the UK. In terms of early communication, certainly from the experience that we have had in our network I think the communication was potentially clearer and the scale of the event was clearly something that had visibility on a national scale.

  Q3  Chairman: Really what I was asking, and maybe I did not make it very clear, was that within EDF the lessons of France were not learned and applied in England.

  Mr Cuttill: I think that is right in terms of EDF France. In terms of our own activity in the UK, the network in the south-east of England that we acquired during the summer of 2002 had some very good lessons for us that we also put into place after the October event. So there has been some learning within our own organisation and we do have very good exchanges with our French colleagues, but I think it would be wrong to say that those exchanges had occurred before October 2002.

  Q4  Chairman: When EDF emerged in the UK, there was a bit of understandable chauvinistic resentment of a French company coming in here. The fact that Americans and others come in was of no consequence. It was the Francophobia of parts of the south-eastern press that perhaps led the charge. But the point I am really getting at is that one of the arguments in favour of a major European player coming in is that the best practice of Europe would be translated into the UK, and in fact, in this instance, the lessons which were learned in France in  2000 were not translated either literally or technically into the UK experience in a way that might have avoided some of the difficulties that you encountered.

  Mr Cuttill: It is certainly the case that we had not, as I have said, had the exchanges with them that we have now seen post event.

  Q5  Chairman: Or which you should have had really, because experiences of that character would have been useful to have had to hand and to have applied to your setup earlier rather than later.

  Mr Cuttill: I think that is right. But I would also say that clearly as a UK industry there is plenty of sharing of experiences going on at all times, so I think it would be incorrect to say that there was no attempt on the part of either us or the UK industry as a whole—

  Q6  Chairman: Yes, I am not talking about the UK industry, because bad weather occurs across the UK, but one of the advantages of getting foreign ownership of UK utilities is that of foreign experience, which by definition is probably likely to be different and in no area is more guaranteed to be different than in that of the weather and the impact of sudden changes in weather. It does seem a rather gaping hole in your experience and your communications within the organisation, with such a traumatic experience as that of the millennium winter in France, for that not to have been incorporated within your emergency planning schedules within the UK.

  Mr Cuttill: I would say that in terms of our planning and our contingency arrangements pre-October they were clearly under management attention and had been assessed earlier in the year and been found to be robust. The point where I would agree with you: the scale of the events of October 2002 clearly applied significant pressure on what was believed to be a robust plan and the plan did not stand up to that pressure.

  Q7  Mr Djanogly: Good morning. With thousands of my own constituents having lost their power, I am pleased to see the commitment you are making to putting things right. However, looking at the memorandum you sent to the Committee, you have suggested in various places that the DTI report underestimated some of the factors that were beyond your control. The things which come to mind are that the wind speeds were particularly high, particularly in certain towns in East Anglia; that power lines are more likely to be routed along hedgerows than across open fields there; and that, because the region had not suffered strong winds in the recent past, the trees were not up to the job, so to speak, and therefore had a higher felling rate than in other parts of the country. Whilst you obviously cannot control any of those aspects, should your contingency planning for high winds have taken account of the established practice of routing power lines beside hedges and the likely presence of more weak trees?

  Mr Cuttill: In terms of our planning, we clearly have to take in all the local environmental conditions. These are networks that are built up over many, many years. Assets are on the networks for 40, 50, 60 years. We had been the owner of this particular network for round about nine months by the time the storm of October 2002 came, therefore our ability to influence significantly the basic design of the network, taking into account the local environmental factors, was shaped by the fact that we had only owned it for those nine months. One thing that we did undertake within that nine-month period was to understand that there were significant increases in investment required, we felt in terms of capital expenditure on the network, and we increased the spend by around 20% in the year that we acquired the network. I think the factors that you are describing are factors that play into the long-term design, make-up and adjustment of the networks. Also, I think, in terms of the way that the vegetation is actually managed, the whole tree-cutting programme is obviously something that has to be kept under very close review. In the three years 2003 to 2005 there will be a very significant increase in the amount of money that we spend on controlling the vegetation; that is, through our tree-cutting programme. So I think we understand the environmental conditions to which you refer and the impact that they can have on our network and we are doing something about it.

  Q8  Mr Djanogly: East Anglia is flat and winds do sweep across it.

  Mr Cuttill: Yes.

  Q9  Mr Djanogly: And they always have done and they always will do! This problem is likely to happen again. In which case, are you not going to start looking at putting more cables underground?

  Mr Cuttill: We do make strategic decisions around undergrounding cables. We have, for instance, made some investment this year in some kilometres whereby we actually take the cables underground. However, clearly, undergrounding all of the network in this particular region would be not only a very costly process but obviously a very, very lengthy process as well and may not be the most sensible solution. One of the reasons for that is that, in an underground situation, in the event of a cable fault it is more time-consuming to excavate and then repair the fault and then reinstate. We obviously see that in our urban networks. So a careful balance does have to be struck between the weather-related incidents, which can affect overhead infrastructure, compared with the urban issue of undergrounding. But we certainly do underground where there is clear  vulnerability, particularly on escarpments and   things like that. We will always consider undergrounding as an alternative and, in some instances, where we wish to re-configure the network, quite often the planning permissions to do that from the local county councils require us to underground rather than string overhead. So it is a combination of both the environmental factors and changes in planning permissions.

  Q10  Mr Djanogly: You mentioned councils. One of the things that I have found, speaking to local councils, is that they did not really seem to have much of an ongoing relationship with you.

  Mr Cuttill: Yes.

  Q11  Mr Djanogly: And they did not really seem to know what was going on at all. I did note that in your opening remarks you said that had changed.

  Mr Cuttill: Yes.

  Q12  Mr Djanogly: I hope that is the case because I think that is going to be very important. Chairman, if I may just go back to the underground cabling. I would say that in East Anglia this is going to be one of the most significant things, particularly if we are not going to be chopping down trees wholesale. Have you produced a paper on this? You mentioned cost benefits. Is there some information you could provide to the Committee that would give us an idea of what the implications are for putting cables underground?

  Mr Cuttill: We can certainly provide a briefing note on that point. I am very happy to do so. Clearly, the whole discussion around how we design our networks, going forward, will have to feature as a very significant part of the forthcoming distribution price-control review. In our consultations with Ofgem, a discussion around network design, balancing the risks against those design practices is clearly a very key part of that discussion and we look forward to the conversations with Ofgem around that.

  Q13  Mr Hoyle: That is a very good point my colleague has made. I think the big talk is on the environmental impact of ugly pylons, electricity cables going across beautiful countryside, but, I think we have to be honest, it is so rare that you actually put cables underground. It is only when you are being forced by some lobby group or some planning condition. That is the only time. I would be interested to know what percentage of cables you have actually put underground voluntarily outside an urban area.

  Mr Cuttill: I do not have that right to hand.

  Q14  Mr Hoyle: No, I understand that, but if you could let this Committee have that. You dress up a very nice argument, but I think statistics will show that you go for the cheap option, the quick option, and then unfortunately it takes a disaster like this to happen before realities come into play. I would like to think that the electricity companies will reconsider the short-term gain for the long-term gain, that (1) the customers ought to be the priority but never seem to be, but (2) that the shareholders ought not to be put first in cases like this. Undergrounding is a major solution, not only environmentally but, obviously, as more storms may appear and we see climate change out there coming in the future. Therefore, companies ought to take the long-term gain rather than the short-term. If you could let us have those figures, that would be interesting.

  Mr Cuttill: Your analysis that the amount we have voluntarily put underground is small, I suspect that would be the outcome of the note that we give you. I think the debate about the holistic approach in terms of overhead, taking into account all the factors, as opposed to undergrounding, is a very real debate that must, as I have said, feature as part of the distribution price-control review, the very way these distribution monopolies are financed and their business economics. We are happy to do that.

  Mr Hoyle: Thank you.

  Q15  Chairman: Would it be the case, Mr Cuttill, before we leave this point, that you, of all the utilities, are best placed to conduct such a study as this because you have so much of London cabling underground in the first place, so you can compare and contrast?

  Mr Cuttill: Exactly, Chairman. Our London network, as you have rightly identified, the vast majority is underground. We have a few pylons to the east of London, but . . . So we know exactly the economics of undergrounding, including cost of repairs, as compared with overhead lines. We do have the two very contrasting networks under our control.

  Q16  Chairman: You said you had only been in ownership of the assets for some nine months.

  Mr Cuttill: Yes.

  Q17  Chairman: Had you in that period begun to realise that re-cabling may have to be done ? Had you made any decisions that certain areas of the cabling perhaps would be better underground than as they were presently constituted, in the light of your experience as a bigger operator than the previous one?

  Mr Cuttill: I think in that initial nine-month period we had concentrated on further, let me call it, due diligence in terms of the actual condition of the network, and, as I have said, we did increase the capital expenditure by some 20% in the year of acquisition to address issues. I would not wish, however, to overemphasise the point that the majority of that money would have been spent on straightforward asset replacement as opposed to the alternative of undergrounding. I know one case where we have done some undergrounding of a two kilometre line in the Aylesbury area, which is part of this particular network, and that is in response to local consultation with customers, where there have been significant repetitive faults on a line and we have undergrounded that one. That is the one that is immediately in my mind.

  Chairman: Thank you.

  Q18  Mr Berry: Good morning. You have described the changes you have made to your emergency planning system since October. Could you tell the Committee what your emergency planning system was in October?

  Mr Cuttill: As I have mentioned already, we had a plan. It had been assessed in April 2002, along with all contingency plans. It was found to be robust, but, as I have said, it did not perform under the pressure that October 2002 put upon it. There was a line of management control. There were elements in place by which we would commence communications with external stakeholders. It was clear, though, that the scale of the event was such that the elements of the plan, when put under the strain of October 2002, did not stand up to that extreme pressure. That is why we have done what we have done and why our performance subsequently has been better.

  Q19  Mr Berry: You say you have introduced the role of an emergency planning and business continuity manager. Presumably that person now has overall responsibility for emergency planning.

  Mr Cuttill: This is an individual who reports to Mr Carey, so we have taken it outside of the normal management lines.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 13 December 2004