Select Committee on Trade and Industry First Report


Part 2: Future Investment in the Electricity Distribution Networks


5  Background

THE TRADE AND INDUSTRY COMMITTEE'S NETWORK RESILIENCE REPORT

64. In March 2004 we published a Report into the Resilience of the National Electricity Network.[68] Our reason for inquiring into the state of the electricity network was the series of power cuts, in the UK and abroad, that took place in the summer and early autumn of 2003. We noted that, although the electricity network in the UK performed well compared to those in other OECD countries, the majority of the network had been built in two main bursts of activity in the 1960s and mid 70s, and most of the equipment had a life expectancy of 40 years. Therefore, simply in order to maintain current performance, the network companies would have to replace much of the network over the next few years. We expressed concerns that "there is currently insufficient investment in the network to replace in a planned and orderly way equipment which is reaching the end of its life."[69] Moreover, we noted that the electricity and gas industry regulator, Ofgem, had consistently applied pressure on the network companies to minimise operational expenditure, which, we feared, might lead the companies to cut corners in the maintenance of equipment. We were particularly anxious over the state of the (regional) distribution networks, which were built to a lower operating standard and experienced a higher number of faults than the (national) transmission network. We concluded: "we believe that the age of sections of the infrastructure means that, without significantly faster replacement rates and more maintenance, power cuts are likely to increase in frequency."[70]

65. Because the network operators, both for the transmission and for the 14 distribution networks, form national/local monopolies, Ofgem has a role in regulating the charges that they can levy. Ofgem sets separate distribution and transmission network revenue controls for five year periods. These controls affect not only the companies' operational expenditure but also capital investment because they put a cap on the amount the companies can pay as interest and other charges when borrowing capital. We noted in our Report that the latest revenue control negotiations had just started, and said that we would keep a watching brief on these to ensure that Ofgem "set revenue controls in order to meet the reasonable longer-term programmes and forecasts of demand submitted by the network companies, rather than (as some have suggested that it does) focussing on what is needed for the next five year period."[71] We further suggested that "a rise of ten percent in distribution charges to support network security[72] would not be an unreasonable amount to pay, and that, in certain particularly vulnerable areas, the Regulator should be willing to consider more investment to enhance security."[73]

OFGEM'S PROPOSED REVENUE CONTROLS FOR THE DISTRIBUTION NETWORK OPERATORS

66. Ofgem's Initial Proposals for revenue controls for the DNOs were published in June,[74] following an already lengthy consultation process.[75] Press reports indicated that the DNOs found these proposals unacceptable, arguing that Ofgem was allowing them only a fraction of the capital expenditure that they needed to maintain the network, and was putting so much pressure on operational expenditure that efficiency savings alone would not suffice, with the result that there would have to be real cuts in service. Ofgem published revised proposals towards the end of September with a request for responses by 25 October.[76] Its final proposals were due to be published on 29 November. In the summary to its September proposals, Ofgem said: "In general, unless otherwise noted, the policy decisions set out in this paper are unlikely to change unless compelling new evidence or arguments are produced."

67. From initial reports, it appeared that the DNOs in general considered the September proposals an improvement on the June ones.[77] However, the September proposals still fell short of what the DNOs had told us would be necessary: for example, Ofgem proposed that the companies should be able to increase their capital expenditure by 46 percent over the next five years, whilst the DNOs' evidence to us on network resilience had been that investment would need to be at twice the current rate for the next 20 years just to maintain the existing network—in other words, not taking into account the cost of the renewable energy programme or network improvement.[78] Also, the September proposals continued to show wide variations between companies. Although Ofgem proposed to allow some companies virtually everything that they had indicated they needed, the allowances sought by other companies had been significantly reduced by the regulator.


68   Trade and Industry Committee, The resilience of the national electricity network, Third Report of Session 2003-04, HC 69-I (referred to subsequently as 'Third Report') Back

69   Third Report, Summary Back

70   Ibid., paragraph 88 Back

71   Ibid., paragraph 84 Back

72   Including to accommodate renewable generation Back

73   Third Report, paragraph 88 Back

74   Electricity Distribution Price Control Review: Initial proposals on www.ofgem.org.uk These are referred to from now on as "the June proposals". Back

75   The first consultation paper on the review was published in July 2003, with a further paper setting out key policy decisions being published in March 2004. The process also involved consultation on a number of specific issues, a workshop and a series of meetings with each of the companies, plus a consumer survey and two reports by consultants. Back

76   Electricity Distribution Price Control Review: Update paper on www.ofgem.org.uk These are referred to from now on as "the September proposals". Back

77   See, for example, 'Ofgem gives power firms a better deal', The Independent, 28 September 2004, p37, and 'Electricity companies can spend £5.7 bn' Daily Telegraph, 28 September 2004, p33 Back

78   September proposals, Table 4.6; Third Report, paragraph 72 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 13 December 2004