8 Capital expenditure
80. One of our main conclusions following our inquiry
into national network resilience was that "a faster rate
of replacement of capital assets is called for" and that
"there needs to be a significant rise in investment to achieve
this".[107] We
had been interested to explore how the regulator decided the rate
of capital investment necessary to maintain the performance of
the network. Ofgem explained to us that it was dependent on the
information supplied by the companies themselves to assess the
condition and investment needs of the electricity network, but,
because there were 14 distribution companies, Ofgem was able to
make comparisons between them and determine a benchmark for their
performance.[108] Ofgem
told us that it also employed external consultants to assess the
information supplied by companies and to advise on a range of
specialist issues.[109]
For this price control review, Ofgem has employed the consultants
PB Power to assess each company's capital expenditure needs, and
Ernst & Young to comment on aspects of the DNOs' operating
practices.[110] Both
the companies themselves and the consultants were asked to base
their calculations on the assumption that current network performance
was to be maintained.
81. The assumptions and models used by PB Power are
described in Ofgem's June proposals.[111]
For our purposes, it is enough to say that PB Power's initial
findings differed significantly from the companies' forecasts.[112]
PB Power subsequently held meetings with each company in August
2004 to discuss its findings, and made some changes to its conclusions
as a result. Ofgem also undertook some complex work on a more
flexible approach to capital expenditure that would not, however,
disadvantage companies that had provided "more reasonable
forecasts."[113]
Ofgem described this more flexible approach as "sliding scale
incentives on capex" to bridge the gap between PB Power's
and the companies' views of what was required. Ofgem told us that
the sliding scale mechanism was designed to allow companies some
scope for increasing capital expenditure while not providing incentives
to them to over-invest, and therefore increase the value of their
assets unnecessarily and at the expense of customers. Equally
importantly, from our point of view, Ofgem said that the mechanism
was also designed to discourage under-investment.[114]
In its September document, Ofgem reported: "Most companies
supported the sliding scale mechanism in concept but have continued
to argue for higher base capital expenditure allowances plus the
sliding scale capex allowance on top."[115]
82. The net result of these adjustments was that
Ofgem's September proposals for capital expenditure allowances
were higher than its initial ones, but it still proposed to allow
significantly less capital expenditure than the industry had forecasted
that it would need. Moreover, although some individual companies
would be allowed more than their forecast, others would be allowed
significantly less. The details are given in the table below.
TABLE
1: Ofgem's proposed capital expenditure allowances for each of
the DNOs[116]
DNO | Actual/ forecast capital expenditure for 2000-05
| Adjusted Company forecast expenditure for 2005-10
| Percentage increase/ (decrease) over 2000-05 expenditure
| Ofgem's proposed allowance for 2005-10 (excluding Quality of Service)
| Difference between company and Ofgem
| Ofgem's allowance as percent of company forecast
| Total allowance (including Quality of Service)
|
| £m
| £m |
| £m | £m
| | £m
|
CN-Midlands | 336
| 485 | 44%
| 477 | -8
| 98% | 501
|
CN-East Midlands | 301
| 480 | 60%
| 476 | -4
| 99% | 485
|
United Utilities | 347
| 457 | 32%
| 466 | 9
| 102% | 466
|
CE-NEDL | 228
| 268 | 18%
| 277 | 9
| 103% | 277
|
CE-YEDL | 242
| 358 | 48%
| 367 | 8
| 102% | 371
|
WPD South West | 221
| 269 | 22%
| 283 | 13
| 105% | 283
|
WPD South Wales | 191
| 171 | -11%
| 179 | 8
| 105% | 186
|
EDF-LPN | 260
| 536* | 106%
| 452* | -84
| 84% | 452
|
EDF-SPN | 283
| 479* | 69%
| 466* | -13
| 95% | 487
|
EDF-EPN | 438
| 745* | 70%
| 674* | -71
| 91% | 697
|
Scottish Power | 253
| 375* | 48%
| 361* | -14
| 96% | 361
|
SP Manweb | 240
| 455* | 90%
| 404* | -51
| 89% | 404
|
SSE-Hydro | 165
| 208 | 26%
| 204 | -5
| 98% | 204
|
SSE-Southern | 375
| 511 | 36%
| 536 | 25
| 105% | 561
|
| | |
| | | |
|
Total | 3,882
| 5,798 | 49%
| 5,623 | -175
| 97% | 5734
|
Increase on 2000-05 |
| 49% |
| 45% | |
| 48% |
* These figures have changed significantly from those
published in Ofgem's September proposals. As far as company forecasts
are concerned, in September EDF-LPN's figure was £543 million,
EDF-SPN's was £489 million, EDF-EPN's was £856 million,
Scottish Power's £395 million and SP Manweb's £465 million.
Ofgem's proposed allowance, excluding Quality of Service allowances,
was then: for EDF-LPN £454 million, for EDF-SPN £468
million, for EDF-EPN £701 million, for Scottish Power £367
million, and for SP Manweb £406 million. As a result, the
percentage figures and the calculation of the difference between
the company's and Ofgem's figures have also changed for these
companies, as have the overall totals. The most significant of
these alterations are discussed in paragraph 84 below.
83. Ofgem emphasised that, for many companies, capital
expenditure allowances were equal to or above what the companies
had sought. The exceptions were the three EDF companies and the
two Scottish Power companies.[117]
For the EDF companies, not only were the proposed capital
allowances overall much lower than they had requested, but also,
under the September calculations, they were the only companies
that would suffer a penalty for extra expenditure under Ofgem's
sliding scale mechanism.[118]
84. A comparison with Ofgem's September document
shows significant changes to company forecasts between September
and the final proposals in November, with smaller adjustments
to Ofgem's proposed capex allowance excluding Quality of Service.
The companies which have made adjustments are the three EDF companies
and the two Scottish Power companies. Ofgem noted that, following
discussions on the capital allowances and the operation of the
sliding scale mechanism, "some DNOs have suggested that the
inclusion of certain items of expenditure in their base case forecasts
was inappropriate and have requested that these items should be
removed from their forecasts."[119]
Ofgem agreed to these requests, which have had the overall effect
of decreasing the total allowance proposed by Ofgem from £5661
million (September proposals) to £5623 million (November
proposals), and the increase on 2000-05 actual/forecast out-turn
from 46 percent to 45 percent. They have also had the effect for
the EDF companies of eliminating the penalty for extra expenditure
under Ofgem's sliding scale mechanism. The November proposals
would give the EDF companies a very small incentive for such expenditure.[120]
85. Ofgem was understandably reluctant to comment
on the situation of individual companies before the publication
of its final determination on 29 November, but we felt that we
had to explore the reasons why the EDF companies appeared to be
so much out of line with the other DNOs. In oral evidence, Ofgem
said that it was quite difficult to pin down exactly why its and
the companies' estimates differed so widely; but in its September
proposals Ofgem commented: "In part, this may reflect the
timing of EDF's investmenthaving been relatively low in
the [2000-05 period] to date for EDF-LPN and EDF-EPN in particular".[121]
Ofgem believed that the company should not be rewarded for this
earlier low rate of investment and "consumers should not
pay twice for investment".[122]
Ofgem explained this statement as follows: EDF (and its predecessor
companies) had been allowed by the regulator a certain level of
revenue from consumers on the basis that, among other things,
they would incur a certain amount of capital expenditure. In practice,
however, these companies underspent their capital allowance between
2005-10, with shareholders benefiting accordingly. If Ofgem now
allowed the companies higher revenue to catch up with the investment
that ought to have been made in 2000-05 as well as dealing with
the investment for 2005-10, to some extent consumers would have
paid twice for the same pieces of equipmentonce before
2005, when it was not installed, and once after 2005, when presumably
it would be. Ofgem told us that it was for the shareholders, not
the customers, of EDF to pay for any extra investment needed to
make up for earlier under-investment.[123]
Furthermore, Ofgem argued, even these companies would be able
to incur significantly higher capital expenditure in the 2005-10
price control period than they had in practice made in the current
one: "For EDF, the proposed allowances are 67 percent higher
than they will have spent (on a comparable basis) in 2000-05.
For SP, the proposed allowances are 55 percent higher than they
will have spent in 2000-05."[124]
Ofgem commented: "These are very substantial increases."[125]
86. Although we
agree with the principle that shareholders should not benefit
from previous low levels of investment at the expense of customers,
we would be very uneasy if applying this principle meant that
the company would be hindered from making the capital investment
necessary to provide its customers with as reliable an electricity
supply as comparable customers elsewhere expect and receive. At
the worst, there would be potential for a vicious circle of under-investment
followed by penalties for failing Quality of Service targets,
which would leave even less money for necessary capital investment.
However, we have received no
evidence that the customers of the companies concerned on this
occasion would suffer as a result of Ofgem's proposals; and we
note that the proposed allowances would enable these companies
to invest more than they have done in the recent past. We take
even more comfort from the inference that Ofgem intends in future
to deter any similar under-investment by companies by means of
the sliding scale mechanism. Both for the sake of the customers
and for the promotion of efficiency of the electricity industry,
we would much prefer that under-investment be prevented rather
than punished.
87. The Energy Networks Association was not as sanguine
as Ofgem about future investment in the infrastructure by DNOs.
It agreed that Ofgem had largely accepted the companies' bids
for capital expenditure to maintain current network performance;
but said that Ofgem had rejected the companies' proposals for
investment to improve network performance whether to increase
resilience against severe weather conditions, or to improve quality
of service, or for improving the environment by, for example,
putting powerlines underground in National Parks and other sensitive
areas.[126] The ENA
also commented that companies had different approaches to the
task of maintaining the resilience of the network: some preferred
to increase maintenance levels for ageing equipment, while others
sought to replace it, and in the latter case they did not want
simply to replace like for like but preferred to install more
modern, efficient and, in many cases, reliable equipment. The
ENA argued that it was this sort of upgrading, which was particularly
designed to increase resilience against severe weather conditions,
that would be discouraged by the capital allowances proposed by
Ofgem in its September document.[127]
88. Ofgem dismissed the proposals for extra capital
expenditure to upgrade the network rather cursorily. A short section
of the September document dealt with suggestions by DNOs that
they should be allowed additional expenditure to improve network
resilience or performance for the worst-served customers. Ofgem
responded:
"For many of the projects or programmes
of work proposed [to this end], expenditures of over £1,000
per affected customer (incurring financing costs of hundreds of
pounds per year per affected customer) would be necessary to deliver
significant benefits. This would raise issues of the extent of
cross-subsidy. The schemes that are cheapest per customer tend
to deliver relatively little benefit or, in some cases, the benefits
have not been quantified by the companies concerned."[128]
Ofgem argued that the most important single action
to improve network resilience was vegetation management, and,
as we have noted above,[129]
that it had made additional allowances for this in the proposals
for 2005-10. The regulator concluded:
"In line with the approach taken throughout
the review (and at previous reviews), Ofgem does not propose to
endorse or reject specific projects. The allowances provided through
the sliding scale mechanism create some headroom for companies
to undertake expenditure in this area where they can justify it.
Ofgem is not persuaded that there is sufficient customer
benefit to justify additional targeted regulation in this area."[130]
89. We asked Ofgem, first, what assumption it was
making of the cost of capital that led it to the conclusion that
expenditure of over £1,000 per affected customer would incur
financing costs of several hundred pounds a year per customer;
and, secondly, whether the regulator had in mind any cut-off point
for cost per customer in assessing whether extra expenditure would
be cost-effective. Ofgem's response to the first question was
that its calculation of financing costs included not only interest
and other charges but also tax, and depreciation.[131]
In response to the second question, Mr Martin Crouch[132]
said that the determination of cost effectiveness was for the
DNOs themselves to make: Ofgem had no view on this.[133]
90. These responses
are a little disingenuous. While we acknowledge that companies
will be able to choose which particular projects will give the
greatest benefitsand that it is always open to them to
finance projects at the expense of the shareholders rather than
the customersthe regulator does, and must, make a judgement
on what companies need to do in order to decide how much money
they need to do it.[134]
By refusing to make specific allowance for improvements to the
network, Ofgem is, in effect, deciding that such improvements
are not necessary from the customers' point of view: they are
something which can be left to the discretion of individual DNOs.
91. Also, although
we recognise that the regulator has to take into account depreciation
when calculating capital costs, from the point of view of the
customer this is simply an accounting mechanism. The charges that
would be passed on to customers in their bills would amount to
significantly less than several hundred pounds per year per affected
customer. Moreover, as these costs would be spread over the whole
customer base of the DNOs concerned, as such capital costs would
be a relatively small proportion of DNO charges to customers as
a whole, and as the cost of electricity distribution forms about
25 percent of domestic electricity bills, the actual increase
in individual customers' bills would probably amount to at most
a few pounds per year.
92. One area where Ofgem has significantly shifted
its position is the question of investment in infrastructure for
environmental reasons. In March, Ofgem announced that it was reviewing
information provided by the DNOs on the cost of putting powerlines
underground in National Parks and Areas of Outstanding Natural
Beauty. It was also seeking consumer views via the survey described
above.
93. Although this issue was not considered to be
a very high priority, the respondents to both Ofgem's consultation
and the consumer survey were generally in favour of providing
companies with incentives to put cables underground for amenity
reasons, and the consumer survey indicated a willingness to pay
a little extra for this: for each percent of the network 'undergrounded'
per year, customers were willing to pay about £2.50 per year
or 0.7 percent of the total bill.[135]
Despite this, in its June proposals, Ofgem refused to make an
allowance for the cost of such undergrounding because: "Ofgem
does not consider that it is the appropriate body to make such
decisions". The reasons why Ofgem reached this rather startling
conclusion may be summarised as:
improving
visual amenity would benefit everyone who visited the area, so
the local DNO's customers would be paying for work that would
mainly benefit other people;
in practice, the amount of undergrounding
that Ofgem could allow for would be relatively small, given that
the total cost of undergrounding all lines in National Parks and
Areas of Outstanding Natural Beauty has been estimated as about
£6.9 billion; and
the Social and Environmental Guidance
issued to Ofgem by the Government explicitly stated that any environmental
measure which would have a significant financial implication would
be primarily implemented by Ministers rather than Ofgem.[136]
94. We
are pleased to note that Ofgem has changed its views on whether
it is appropriate for the regulator to make an allowance for investment
to improve visual amenity.[137]
It now proposes a modest, but reasonable, extra allowance with
expenditure capped at a level sufficient to allow undergrounding
of 1.5 percent of the network in National Parks and Areas of Outstanding
Natural Beauty at an average cost of £100,000 per km. The
allowance would be subject to DNOs' demonstrating that the expenditure
was made within these areas, was additional to normal expenditure
on infrastructure replacement, and that they had consulted local
environmental groups and/or planning authorities on how best to
prioritise this investment.[138]
95. In March we
stated our belief that customers would be prepared to spend a
modest amount extra to obtain a better network and more reliable
electricity supplies, and we are confirmed in that view by the
research subsequently undertaken into consumer preferences, which
we discussed earlier. However, while we are sympathetic to the
companies' arguments for being allowed to undertake capital investment
to increase the resilience of the network, we understand that
not least in view of previous under-investment by some
companies Ofgem is inclined to proceed cautiously and
wishes to see a robust case for such extra investment.[139]
We cannot say that Ofgem is wrong in its approach, but we emphasise
that Ofgem should keep an open mind about the need for further
investment in the infrastructure if it wishes to increase Quality
of Service standards.
96. Overall, we
welcome the fact that, in its proposals for capital allowances,
Ofgem has clearly acknowledged that extra investment to replace
infrastructure is needed. The regulator may not have gone as far
as we wished, but a gradual approach is justifiable. We simply
reiterate our view that, just to enable ageing equipment to be
replaced, investment in the electricity infrastructure will have
to be significantly higher than in recent years and over an extended
period, probably about 20 years. We urge Ofgem to view this five-year
review as the opening of a long-term project to ensure the resilience
of the UK electricity network.
107 Third Report, paragraph 80 Back
108 We
note that Ofgem itself recognises that benchmarking is becoming
increasingly difficult as mergers within the industry are reducing
the number of comparators: September proposals, para 4.48 Back
109
Third Report, Paragraph 36, Qq 2 and 9 (Part 2) Back
110
September proposals, para 1.2 Back
111
Paras 6.71-6.77 Back
112
June proposals, Table 6.7 Back
113
September proposals, para 4.63 Back
114
Q 7 (Part 2). The ENA admitted that there has been under-investment
in the past: Q 26 (Part 2) Back
115
September proposals, para 4.64; see also Q 25 (Part 2) (ENA) Back
116
This Table is based on 'Table 7.5: Comparison of capex allowance
to forecast total 2005-10 (£m, 2002/03 prices the percentage
increase)' in the November proposals, with the addition of our
calculation of the percentage increase over 2000-05 expenditure,
and the percentage increase over the revised company forecasts.
Back
117
September proposals, para 4.66 Back
118
Ibid., para 4.70 Back
119
November proposals, para 7.68 Back
120
Ibid., Table 7.7 Back
121
Q 9 (Part 2) and September proposals, para 4.56 Back
122
September proposals, para 4.56; see also November proposals, para
7.82 Back
123
Q 10 (Part 2) Back
124
November proposals, para 7.70 Back
125
September proposals, para 4.66 Back
126
Qq 25 and 40 (Part 2) Back
127
Qq 27-30 (Part 2) Back
128
September proposals, para 4.58 Back
129
Paragraph 34 Back
130
September proposals, para 4.59 Back
131
Q 11 (Part 2) Back
132
Ofgem's Director of Distribution Networks Back
133
Q 11 (Part 2) Back
134
This point was largely conceded by the witnesses from Ofgem: Q
12 (Part 2) Back
135
June proposals, paras 4.72-4.73 and Consumer Survey, para 4.6
Back
136
June proposals, paras 4.74-4.75 Back
137
November proposals, para 4.59 Back
138
Ibid, paras 4.60-4.62 and Table 4.12 Back
139
Q2 (Part 2) Back
|