Select Committee on Trade and Industry Written Evidence


APPENDIX 2

Memorandum by the Department of Trade and Industry

INTRODUCTION

  1.  The DTI welcomes the Trade and Industry Committee's decision to conduct an inquiry into the effectiveness of the electricity supply industry's contingency plans and their progress in dealing with the issues identified following the storms of 27 October 2002. This memorandum sets out the background and how the Department has been involved. A discussion on areas for further consideration is included.

  2.  The Committee is also reviewing arrangements for the payment of compensation to customers affected by power failures and the processing of claims arising from 27 October. These matters are covered by Ofgem in a separate memorandum.

BACKGROUND

  3.  On Sunday 27 October 2002, storms with winds gusting up to 100 mph hit much of England and Wales, causing widespread damage to electricity distribution networks. These storms were severe both in their intensity and their impact.

  4.  Major storms affecting the electricity infrastructure in the UK have been infrequent but they are not unusual. Other notable examples include the 1998 Boxing Day storm, the Burns Day Storm of 25 January 1990, the Great Hurricane of 16 October 1987 and two major blizzards in the winter of 1981-82. In more recent memory a severe storm swept across northern France in the winter of 1999-2000 causing widespread damage to power lines.

  5.  On 27 October 2002 up to two million customers in England and Wales were affected by loss of electricity supply due to storm damage; most customers were reconnected within 18 hours, but supplies were not fully restored until Tuesday 5 November, nine days later. There were significant differences between similarly affected regions in the speed with which the distribution companies were able to restore supplies and in the way in which companies communicated with their customers. Energy engineering consultants British Power International (BPI) were appointed by DTI to conduct an investigation which was published in December 2002[1].

GOVERNMENT RESPONSIBILITIES FOR ELECTRICITY SUPPLY

  6.  Legal responsibility for energy security is shared by the Secretary of State for Trade and Industry and Ofgem. The Secretary of State is responsible for setting the overall regulatory framework for the supply of electricity. A key part of that framework is set out in section 3A of the Electricity Act 1989 as amended by the Utilities Act 2000. Key objectives of the Secretary of State and Ofgem are:

    —  to protect the interests of consumers in relation to electricity conveyed by distribution systems, wherever appropriate by promoting effective competition;

    —  to have regard to the need to secure that all reasonable demands for electricity are met;

    —  to have regard for the need to secure that licence holders are able to finance their activities;

    —  to have regard to those who are disabled, of pensionable age, on low incomes and who live in rural areas;

    —  to promote efficiency and economy in relation to distribution and supply of electricity; and

    —  to protect the public from dangers arising from the generation, transmission, distribution or supply of electricity.

  7.  Electricity for domestic consumers is provided through their contracts with electricity supply companies, which are trading organisations, not responsible for the electricity infrastructure such as overhead lines. However in many cases an electricity supply company will have links with a distribution company (see paragraph 8) for historic reasons. This separation of roles, which was part of the introduction of competition into the electricity industry, was brought into effect with the introduction of the Utilities Act 2000.

  8.  In each electricity distribution region the physical supply of electricity to customers is the responsibility of a monopoly Distribution Network Operator (DNO), regulated through an Ofgem licensing system. In England and Wales DNOs draw power from National Grid Transco's (NGT) 400 kilovolt (kV) and 275kV network. In Scotland the 400kV, 275kV and 132kV lines are operated by the two companies that are also responsible for the Scottish DNOs (Scottish Power & Scottish and Southern Energy) in their respective licence areas. The Secretary of State lays down Standard Licence Conditions which include, for example, reference to the Distribution Code. Enforcement of the licence conditions is for Ofgem.

  9.  The electricity distribution companies are subject to Guaranteed Standards of Performance which provide for compensation to be paid at a rate of:

    —  £50 for domestic consumers without power for more than 18 hours; and

    —  an additional £25 for subsequent 12 hour periods without power.

  However companies can be exempted from paying this compensation if severe weather has prevented the company from restoring the supply. Initially it is the companies that decide whether to offer compensation or to claim the severe weather exemption. Consumers can challenge non-payment of compensation through the consumer organisation Energywatch and, in the final instance, Ofgem. Ofgem has statutory powers to determine disputes on matters relating to payment of compensation under the Standards. It is also open to the companies to make ex-gratia payments to affected customers.

  10.  The Government actively monitors general gas and electricity energy security over the medium term through the Joint Energy Security of Supply (JESS) working group, consisting of DTI, Ofgem, NGT and Foreign Office representatives. It makes the conclusions of that group publicly available through twice-yearly reports assessing supply and demand information and periodically reviewing the dependence of the networks on particular facilities. Information gathered by JESS is used as a guide to issues in the market or regulatory system or elsewhere (for example planning) that may be preventing an adequate market response.

  11.  Ofgem requires DNOs to submit detailed information on the performance of their networks on a regular basis. Ofgem uses this information to monitor DNOs' performance against target levels agreed at the commencement of the regulatory period. The companies also submit information on major power interruptions to the Secretary of State; the Engineering Inspectorate at DTI collates this information and uses it to investigate incidents or influence policy as appropriate to the circumstances.

  12.  Many of the distribution companies have made substantial improvements in quality of supply performance since the early 1990s. Analysis by Ofgem has shown that the average number of power cuts per customer has fallen by 11% and the average duration has fallen by at least 30%.

  13.  The Engineering Inspectorate comprises electrical engineers appointed under section 30 of the Electricity Act 1989 (as amended by the Utilities Act 2000) to examine the generation, transmission, distribution or supply of electricity and to inspect and test electrical plant. In practice Inspectors liaise closely with DNOs in the performance of their duties, which include investigating accidents involving the public and complaints about safety or supply interruptions.

  14.  The Minister for Energy has recently made a new statutory instrument—The Electricity Safety, Quality and Continuity Regulations 2002 (SI 2002 No 2665)—requiring electricity companies to protect the public from danger, to maintain standards in power quality (ie maintain voltage within statutory limits) and to ensure continuity of supply. Regulation 3(1)(b) requires DNOs to construct, install, protect, use and maintain their equipment to prevent interruption so far as is reasonably practicable. The qualifier so far as is reasonably practicable requires a balance to be struck between the risk of interruption and the costs of preventing the interruption.

  15.  In recognition of the importance of a secure electricity infrastructure for Great Britain, the DTI Business Plan 2003-06 includes an objective to ensure the continuity and security of energy supply at affordable prices through competitive markets, whilst minimising environmental impacts and delivering social objectives (pages 40 and 41). One of DTI's aims is to ensure that sound emergency plans and secure and reliable networks for electricity and gas are in place, and that any disruptions and emergencies are successfully dealt with.

DTI'S INVOLVEMENT BEFORE THE STORM OF OCTOBER 2002

  16.  In February 2002 DTI commissioned a study into the ability of the electricity transmission and distribution companies to recover from an emergency. The study was not triggered by an incident or crisis, but Ministers considered it timely to review good practice across the industry. There had been much commercial restructuring, it was more than two years since the last major exercise preparing for the year 2000, there was concern about more erratic weather patterns, and of course post 11 September heightened awareness of the possibility of terrorist attack. In addition there had long been reports, eg from the Trade Unions, of cost cutting and loss of skills in the sector since privatisation, although this did not seem to be supported by the companies' performance records.

  17.  After a competitive tender process BPI, power engineers with many years' experience in the sector, were appointed to carry out the study. They visited all the electricity transmission and distribution licence holders in mainland Britain to discuss how their plans had developed in response to changes such as reorganisations and mergers in the industry and recently observed erratic weather patterns. The study looked at the quality of the emergency planning and systems that were in place, but did not attempt to test them in practice.

  18.  BPI's report (the first BPI report) was published in June 2002[2]. It found that the industry was, in most critical areas, better prepared and equipped to handle emergencies than was the case a decade ago. This was because technical, managerial and structural improvements in the companies were likely to mitigate the effects of staff reductions. However, there was still scope for more sharing of best practice across the industry in terms of emergency management structures, processes and planning.

  19.  BPI presented the findings to the industry at the Electricity Association's Emergency Response Seminar in the West Midlands on 4 July 2002. The specific recommendations of the report included one that companies should clarify their arrangements for access to contracted-out resources, such as field staff, equipment and call centre services, in a widespread emergency where more than one company was affected. In a letter to company Chief Executives, former Energy Minister Brian Wilson asked the companies to look closely at the findings (see Annex 1).

DTI'S RESPONSE TO THE STORM OF OCTOBER 2002

  20.  Before 27 October 2002 DTI was already considering commissioning follow up work and had been discussing its scope with BPI. When, following the storm, it had become clear that the performance of some companies had fallen short of their contingency planning, this work was brought forward as a matter of urgency. Brian Wilson announced on 29 October that BPI would carry out a review of how companies had performed and would make recommendations. The lessons learned and recommendations would be reviewed by a team comprising DTI (including the Engineering Inspectorate) and Ofgem to help ensure that future supplies to consumers were not affected to the same extent.

  21.  The BPI Review was published on 19 December 2002. They found that all companies generally had good high level plans in place. The better performing companies were able to estimate accurately the amount of resources needed to restore supplies; they mobilised their resources early and were able to manage them effectively during the incident. The companies that performed less well suffered extensive damage to their infrastructure as a result of falling trees and branches, and their customer communications and troublecall systems did not meet expectations. BPI made a number of recommendations for the companies, DTI and Ofgem with a view to improving storm performance in the future. Importantly, BPI concluded that there appeared to be no fundamental reason why those companies that performed less well should not meet the standards set by the best in how the event was anticipated and managed.

  22.  Following the publication of the second BPI report in December 2002 the then Minister for Energy, Brian Wilson, wrote to each of the Chief Executives of the DNOs in January 2003 seeking confirmation of their specific plans to improve their performance in the event of a similar incident in the future (Annex 2). The companies responded offering their own interpretation of their performance and, in some cases, listing their intended actions to improve network resilience. These responses were subsequently published on the DTI's website[3].

  23.  In order to receive reassurance that the industry was responding positively to the BPI recommendations, DTI officials met with the Electricity Association in London on 15 January 2003. Further to this discussion DTI officials attended the meeting of the Electricity Association Networks Board on 27 February 2003 to encourage the companies towards best practice in storm performance. The meeting was attended by directors from the DNOs and a representative from Ofgem. At this meeting it was agreed that a working party involving DTI, Ofgem and the DNOs would be established (later to be called the Network Resilience Working Group—see paragraph 28).

  24.  DTI officials also met with a number of the companies to discuss issues around network resilience and storm performance. Some of these meetings were arranged at DTI's request, and others were in response to the invitations by the companies. The meetings were hosted by the companies at their offices. The dates of the meetings were as follows:

    —  Western Power Distribution at Bristol on 11 February 2003;

    —  Aquila at Worcester on 12 February 2003;

    —  LE Group in London on 22 May 2003 (DTI officials attended other meetings with LE Group on 8 May and 20 June 2003);

    —  NEDL/YEDL at Castleford on 19 June 2003; and

    —  SP Manweb at Prenton on 6 August 2003.

  25.  DTI officials have also met with representatives from the unions to obtain their perspective on the companies' performances following the storm. Officials attended one meeting with Prospect (3 February 2003) and two meetings with Amicus (28 January and 25 March 2003). Reports from trades unions members were mixed. Some felt that management and staff had worked well together during the incident; others felt that staff were disorganised due to lack of information, that there were insufficient authorised persons at hand to instruct staff and that imported staff were not used effectively. These comments have helped officials to take a practical and balanced view when dealing with the companies.

  26.  DTI officials attended and supported the Emergency Response Seminar on 10 April 2003, which was organised by the Electricity Association and held at the Institution of Electrical Engineers in London. This seminar was arranged to highlight problems associated with network resilience and to discuss ways forward for the industry.

  27.  In order to seek confirmation from the DNOs that their various improvement initiatives are completed or well advanced, the new Minister for Energy Stephen Timms wrote to chief executives of NGT and the DNOs on 22 August 2003 (see Annex 3). It had always been the intention of the Minister to write to the companies in the autumn, ie in advance of any winter storms, and this action was brought forward by several weeks to fit with the timing of the Committee's inquiry. Responses are sought by 8 September 2003 and these will be published on DTI's website.

  28.  Following the meeting with the Electricity Association Networks Board on 27 February 2003 (see paragraph 23), the first meeting of the Network Resilience Working Group was held on 15 April 2003. At this meeting the terms of reference were drafted (see Annex 4), and it was agreed that the Group would be chaired by a DTI official and DTI would also provide the secretariat. A key aim of the Group is to provide a joint platform to facilitate the development and delivery of solutions in line with the BPI generic recommendations included in their report of December 2002. The main areas the Group is exploring are: changing weather patterns, the national availability of engineers and craftsmen, incentives associated with the existing regulatory regime, vegetation management, techniques to improve network resilience, customer expectations and customer communications, and also emerging risks facing the electricity industry.

  29.  Representatives from all the DNOs have participated in the work of the Group as well as representatives from Ofgem and Energywatch. Since the first meeting the Group has met regularly at the DTI office, 1 Victoria Street, London. The Group intends to publish the full text of its report by the end of October 2003.

RECENT EVENTS AFFECTING POWER SUPPLIES IN NORTH AMERICA

  30.  The events in north east USA and eastern Canada on 14 August 2003 leading to collapse of transmission and distribution systems appear to be different to the areas addressed in the BPI report of December 2002 and the scope of the inquiry by the Committee. The incident in August was associated with the North American extra high voltage (transmission) system linking several states and straddling the USA/Canada border. It is not yet certain what triggered these events or why, once triggered, the problem spread so quickly. DTI eagerly awaits publication of the findings of the US/Canadian task force which is investigating this incident. The Department and Ofgem will look closely at the findings and recommendations and will give careful consideration to any implications for the UK. A joint DTI/Ofgem working group has already been established to monitor developments as news of the North American incident emerges.

  31.  The storm of 27 October 2002 affected high voltage and low voltage overhead lines operated by the DNOs. NGT's transmission lines were not affected by this storm and therefore NGT were not subject to the investigation by BPI. The scope of BPI's second investigation was strictly the networks operated by the DNOs, ie 132kV down to 230V.

  32.  The factors that may be attributed to these two incidents appear to be different. The British outages were caused by multiple incidents due to storm damage affecting a number of adjacent distribution networks (15,490 faults in total). It appears that the American experience was initiated by a single incident (or a few incidents) affecting transmission networks linking distribution networks in adjacent states. For these reasons the Department's view is that it is not appropriate to link the two events, at least until the conclusions of the US/Canadian task force are published. It could be, of course, that common factors may emerge from the North American investigation, for example vegetation management.

POWER FAILURE AFFECTING LONDON ON 28 AUGUST 2003

  33.  The Department is very concerned about the power failure affecting London and parts of the south east on the evening of 28 August 2003. At 18:20 supplies were lost to about 410,000 customers. All supplies were restored within 41 minutes, but problems continued with the transport system apparently due to an early decision to evacuate passengers from trains. Early reports point to coincident faults on NGT's 275kV network, one associated with a transformer and another with a circuit or switchgear for this circuit.

  34.  The Minister has written to NGT for their advice as to the circumstances of this incident and what measures may be taken to avoid a similar power failure in future (see Annex 5). NGT will report their findings to the Minister. DTI will work closely with Ofgem in reviewing the circumstances of this serious incident with a view to taking forward any necessary recommendations. At this moment in time it is too early to speculate on the outcome of NGT's investigation.

DISCUSSION

  35.  It is the DTI view that it is appropriate to be involved in these issues, alongside Ofgem as the industry regulator, both because of the Department's joint responsibility with Ofgem for security of energy supply, and because the industry is so crucially important to the economy and national life.

  36.  The Department continues to believe that electricity services are best delivered by private firms under a regulated system. It would be inappropriate for Government to specify exactly what measures companies should adopt to deal with emergencies. These judgements are best made by the companies who have detailed local expertise and knowledge and who are directly subject to the performance standards in the regulatory system.

  37.  However DTI believes that it is appropriate to monitor the workings of the system closely to see whether the regulatory system is delivering today's needs, for example modern expectations of customer information. It is also appropriate to gather information about good and less good practice from major incidents such as the October 2002 storms, and to make this available to companies and the public. In this way lessons can be learnt and the impact on consumers from similar incidents in the future can be minimised.

  38.  It is DTI's assessment that all the DNOs have responded positively to the BPI recommendations and to the Minister's enquiries, and that arrangements have been put in place by the DNOs to bring about an improved performance in restoration of supply following a storm. The better performing companies have been reassured that their facilities and arrangements are suitable to respond to major storms, and they have identified opportunities for improvement where processes could have worked better. The companies that performed less well have benefited from a wake up call; they have identified numerous initiatives to improve their performance including improvements to their customer communications and troublecall systems, reorganisation of emergency plans and resources, and review of vegetation management contracts.

  39.  DTI is confident that these practical initiatives would result in more rapid restoration of supply following another storm comparable to that of 27 October 2002. However, the extent of improvement in storm performance is to some extent limited by several factors, at least for the short term due to the volume of work, difficulty and costs associated with addressing outstanding issues. These factors include tree cutting near overhead lines, selective refurbishment of overhead lines and reorganisation of networks; such works may be necessary over large areas requiring some time (possibly years) to bring to fruition. In the meantime it is conceivable that prolonged interruptions may follow another major storm in some parts of the country.

  40.  DTI is also pleased to note the positive contribution made by each of the DNOs to the Network Resilience Working Group. This forum has proved to be a useful opportunity for representatives from DTI, Ofgem, Energywatch and the DNOs to air their respective concerns and to propose ways forward.

  41.  The BPI investigation and DTI's involvement in follow up actions point to important areas which Government may wish to consider further. The key issues which appear to be emerging from DTI's perspective are adequacy of tree cutting programmes and the existing regulatory framework.

  42.  The BPI investigation revealed that the majority of faults were caused by tree damage to overhead lines, and they recommended that Government and companies should ensure more focus on this important area. BPI identified two key aspects—housekeeping maintenance (ie trimming branches to keep them a safe distance from conductors, say two metres) and tree clearance (ie cutting all trees back to falling distance from lines, say 10 or 20 metres). It is DTI's view that the performance of the DNOs in housekeeping maintenance is variable; the better performers operate strict and regular tree trimming programmes, aware that this work is important for public safety as well as network performance. However not many DNO's operate tree clearance programmes, largely because of the difficulty of agreeing works with landowners and because of the cost effectiveness of the works. The companies have statutory powers to enable them to lop trees interfering with lines (Schedule 4 of the Electricity Act 1989 as amended), however they appear to be reluctant to use these powers in order to avoid confrontations with landowners over their equipment. DTI considers that the problem of trees interfering with, or potentially interfering with, overhead lines needs to be addressed by all companies in order to present a step forward in network resilience for the UK. The Department also recognises that extensive tree cutting is an emotive issue and therefore any change to Government policy would have to be carefully considered. It is recognised that solutions need not involve tree trimming or felling, for example diverting, insulating or undergrounding lines. However alternatives to tree cutting are invariably expensive and may be difficult to justify as measured by numbers of customers benefiting from the works.

  43.  The varying performances of the DNOs following the storm of 27 October 2002 raise questions about why the impacts and responses were very different for similar storm conditions. Naturally the DNOs may point to different specifications of overhead lines, different types of trees, the density of tree populations and reluctance on behalf of landowners to permit tree trimming particularly in the home counties; their bespoke systems (eg troublecall and customer communications systems) as well as management arrangements are other differentiating factors. Whatever the different reasons attributing to DNOs' performances, it is important to ensure that the regulatory regime, ie statutory instruments, published guidance, licence conditions and financial incentives/penalties, presents DNOs with the necessary motivation to work towards better network resilience. The Department and Ofgem will continue to liaise closely in this respect.

  44.  It is important to acknowledge that other storm conditions would impact differently on distribution networks, eg lightning or blizzards. DTI is aware that the impact of various severe weather events is currently being reviewed by Ofgem.

CONCLUSION

  45.  DTI intends to maintain network resilience as a high profile issue and will continue to work with Ofgem and the industry to improve network resilience and storm performance. The Department eagerly awaits the views of the Committee resulting from this inquiry; full consideration will be given to all comments and proposals.

Department of Trade and Industry

Amended 2 September 2003




Annex 1

Text of letters in June 2002 from Brian Wilson to NGT and DNOs concerning first BPI report

  I am writing to thank you for your cooperation with the recent study carried out for DTI by British Power International (BPI) into the resilience of the electricity transmission and distribution systems. I very much appreciate your willingness to share information and make people available for meetings, often at very short notice, during the course of the study.

  I understand that BPI is sending a copy of the main report and the findings specific to your own organisation to the people they dealt with directly during the study. I shall be announcing the findings of the study on Tuesday 18 June, and the main, non-confidential, part of the report will be available on the DTI website at www.dti.gov.uk/energy/bpifinalreportelec.pdf. I was very reassured that the study found that the electricity transmission and distribution companies are generally better prepared to handle emergencies than they were 10 years ago.

  There must nevertheless be scope for best practice to be shared more widely across the industry; although the companies studied are performing well in most respects, none was outstanding in all respects. I attach BPI's description of what a company that had adopted "best practice" in all areas might be like. I would be very interested to know your reaction to the report and any action you may be taking as a result; it would be most helpful to have this by the end of July.

  For my part, I will be considering what Government can do to help achieve the best possible systems to avoid or minimise the failure of power supplies, bearing in mind the report findings. As a first step in spreading best practice, BPI will be presenting their findings at the Electricity Association's Emergency Response Seminar in the West Midlands on 4 July.

Brian Wilson

STUDY OF THE RESILIENCE OF ELECTRICITY TRANSMISSION AND DISTRIBUTION SYSTEMS CHARACTERISTICS OF "GOOD PRACTICE" COMPANIES

  The report of the study includes a number of key recommendations but woven throughout are examples of systems and processes which can be identified as "good practice" in terms of planning, confidence in plan execution, risk mitigation and governance and management. Much good practice is common to all companies. However, summarised below is a simple list of areas where some demonstrate more sophistication than others—and it is therefore these areas that may offer the most scope for learning and sharing good practice.

    —  Existence of a fully documented, comprehensive and audited governance process which incorporates emergency planning, the management of risk and customer recovery plans.

    —  Evidence that planning and response arrangements are built on processes—rather than a reliance on a small number of key individuals. (The optimum is, of course, good processes and good people to implement them.)

    —  Presence of a "dedicated" emergency planner.

    —  Regular, well documented and audited simulated emergencies, covering a range of credible scenarios, with follow up action incorporated into the risk management process.

    —  Use of electronic document management system which facilitates the control, ease of access and regular updating of emergency plans (and related documents/process charts/resourcing schedules).

    —  Integrated network management centres incorporating customer reporting, resource dispatch and management and system control.

    —  Implementation of asset condition monitoring which is incorporated into investment strategy.

    —  Robust contracts for out-sourced services which may be critical during emergency conditions, with evidence of providers/suppliers having robust business continuity plans and a commitment to supply during times of stress.

    —  Environmentally sensitive tree cutting contracts where reward and penalty payments are related to network performance indicators.

    —  Innovative approaches to system management and supply restoration strategies during emergencies.

BPI

May 2002

Annex 2

Text of letters in January 2003 from Brian Wilson to DNOS concerning Second BPI Report

  I enclose a copy of the final main report from BPI on the performance of distribution network operators in the South, West and Midlands of England and in Wales during the storms of late October 2002 together with a copy on the performance of your particular company. I understand that my officials sent electronic copies of these, and of the report on other operators to you before publication. The reports demonstrate clearly that while a number of network operators performed well—indeed in the best traditions of the industry—others fell short of that standard. Equally BPI concludes that even the best performers still have room for improvement. I have no doubt that you and your managers will have studied all of the reports with interest.

  I am writing now to ask you to provide to me and to Callum McCarthy a note setting out the actions which you are now putting in place to address the issues raised in the annex relating to your company. In keeping with the openness of the whole process, I would wish the note to be in a form which can be put into the public domain. Consequently, any commercially confidential information should be clearly flagged as such. It would be very helpful to have such a note by the end of this month.

  A number of recommendations relate to the industry as a whole, and indeed some to government. My officials will therefore be in touch with the Distribution Board of the Electricity Association very shortly to discuss how these might be taken forward.

  Finally, I would like to take this opportunity to than you and your staff for the open and frank way in which you responded to the requests from BPI in what must have been very difficult circumstances. It is precisely that openness which has helped us—and I suspect you also—to focus quickly on the issues which need to be addressed, and that the exercise proves beneficial to the companies, those who work in it, and of course your customers.

  I am copying this letter to Callum McCarthy.

Brian Wilson

Annex 3

Text of letters in August 2003 from Stephen Timms to NGT and DNOS concerning follow up to second BPI report

LETTER TO DNOS

  I write to enquire about your company's state of readiness to respond to major storms that may affect electricity supplies this coming autumn and winter.

  I have noted the positive response from your company to the BPI recommendations following the storm of 27 October 2002 in your previous reply to Brian Wilson the then Minister for Energy. I am also aware of your company's contribution to the Network Resilience Working Group. DTI welcomes the forthcoming inquiry by the Trade and Industry Select Committee, which along with recent events in North America has helped to raise the profile of this important matter.

  In view of the possibility of further storms this winter, I would be grateful if you would advise me concerning the following:

    (a)  In their responses to Brian Wilson earlier this year the companies outlined a number of particular initiatives that they intended to implement in response to the BPI recommendations. I would be grateful if you would let me know how your initiatives are progressing for your company;

    (b)  In view of the high numbers of faults caused by trees on 27 October 2002, could you also let me know how far advanced are your tree cutting programmes across your network?

    (c)  Please confirm your company's state of readiness to respond to a severe weather event affecting your network; and

    (d)  Could you also confirm your level of confidence that your customer communications systems will continue to operate during a major incident?

  As touched upon earlier, I am mindful that, the events which have taken place in North America have raised the profile of electricity resilience and security even further. It would therefore be safe to assume that the Inquiry will wish to examine the US disruption from a UK perspective. Whilst I appreciate that at this early stage no firm conclusions can be drawn it would also be very helpful if you could comment on your network's resilience to other external shocks, and whether in your view there is more the industry needs to do—or industry and Government—to ensure that the UK does not experience a US style blackout.

  The information that you and your fellow network operators provide in response to this letter will be extremely important not just in providing evidence to the Inquiry, but also in providing assurances to customers that lessons have been learnt. For my part, I can assure you that DTI will continue to engage with the industry to encourage and facilitate best practice.

  In view of the timing of the inquiry I would therefore be grateful if you could reply by 8 September. It is also my intention to publish individual company responses on the DTI website.

  Finally, may I once again offer my gratitude to you and your company for your continued efforts in these matters.

Stephen Timms

LETTER TO NGT

  In view of the forthcoming inquiry by the Trade and Industry Committee into distribution network resilience following the storm of 27 October 2002, I write to enquire about NGT's level of confidence in the robustness of the 400kV and 275kV systems in the UK.

  For your information I have written to all the DNOs to seek assurances that they have implemented the recommendations identified in BPI's report and the various other improvement initiatives identified by the DNOs. I appreciate that NGT's network remained secure during the storm of last October and therefore NGT was not included in BPI's follow up investigation. However for completeness I would be grateful if you could advise me concerning any improvement initiatives you have undertaken arising from your experience of this incident.

  It is my expectation that the Committee may also enquire about any implications for the UK following the incident on 14 August 2003 in the USA and Canada. I am aware and am grateful that NGT has agreed to share its own findings with Government and to consider any implications for the UK and of course much will depend on the findings of the US/Canadian task force that has been established to review the causal factors attributing to the blackouts. Given that this information is likely to only become clear by mid to late September I would be grateful if you would share any early views on whether more needs to be done to avoid such a large scale blackout.

  In view of the timing of the inquiry, it would be helpful if you could reply by 8 September. It is my intention to publish the responses from the DNOs and NGT on the DTI website.

  I look forward to hearing from you.

Stephen Timms

Annex 4

Draft terms of reference for Network Resilience Working Group

1.  INTRODUCTION

  The main purpose of the Network Resilience Working Group is to consider the generic recommendations arising from the BPI report (dated 16 December 2002) into the performance of the electricity companies following the storm of 27 October 2002.[4]

  A specific objective is to provide a joint platform (ie the Industry, Government and Regulator) to facilitate the development and delivery of solutions in line with the BPI generic recommendations. The Working Group will also seek confirmation that the specific recommendations by all the named parties are implemented or are in hand.

  The Working Group will seek to promote strategic positioning for network performance standards into the future to match changing customers' expectations. The Working Group will propose best practice and innovative solutions, supported by appropriate funding regimes, to further improve network resilience.

2.  SCOPE

  The workplan for the Working Group will cover the following issues:

    (a)  Review of weather patterns—Have the weather patterns in the UK changed since the Baldock Report (September 1982)? What weather patterns can reasonably be expected in the future? What are the implications for overhead line design and construction standards?

    (b)  Resources—How to ensure that the national and local resources (numbers of staff and their skill range) in the future will meet customers' expectations under storm conditions.

    (c)  Operational communications—Review the arrangements distributors have in place to provide operational communications with field staff. How robust are these systems in storm conditions?

    (d)  Incentives for long term network investment—What is the effect of Ofgem's incentive schemes on distributors' long term network investment plans for fault prevention/mitigation? How might incentive schemes be adjusted in favour of long term investment? What is the impact of the current incentive schemes on sharing best practice between companies?

    (e)  Toolbox for network improvements—What particular strategies and actions may be utilised by distributors to improve network resilience? Ideas from network operators in other countries will be sought. The menu of suggested responses should take into account the environment and network constraints. Three particular scenarios should be considered:

      (i)  network performance under storm conditions;

      (ii)  network performance during normal weather patterns; and

      (iii)  strategies for improving networks supplying worst served customers in rural areas.

  The toolbox should also include best practice in tree cutting—strategies for vegetation management, management of contractors and management of dissatisfied landowners eg wayleave terminations, compensation claims, etc. What are the constraints on tree cutting (both real and perceived)? How might they be addressed?

    (f)  Customers' expectations for future storm performance—What maximum restoration times should distributors aim to achieve in future severe storm conditions? When and how will distributors be able to reach this level of performance and demonstrate this? What other types of severe weather events need to be addressed? What different actions, if any, are needed? How do customers' expectations in the UK compare with those abroad for similar networks/environments?

    (g)  The changing risks arising from external stakeholders—What up and coming risks may impact on a distributor's performance (eg legislation)? How can all parties influence these issues in order to manage risks/expectations?

    (h)  Particular BPI recommendations on each company—In addition, and further to the individual reports from the companies to the Minister, the Working Group will seek confirmation from each distributor that his particular actions arising from the BPI report have been completed.

    (i)  NEWSAC review—The group will enquire about progress with the NEWSAC review and seek verification that improvements / recommendations have been implemented.

    (j)  BT platform—Is the BT platform now sufficiently robust to handle customer calls in the event of a major storm?

3.  ASSESSMENT OF BENEFITS

  The Working Group will make an assessment (including related costs) of initiatives against the following performance criteria:

    —  network resilience and quality of supply;

    —  public and employee safety; and

    —  environmental impact.

4.  OUTCOME

  The Working Group expects to deliver a report covering each of the areas listed in the workplan, which will be presented to the Minister, the Regulator and directors of distribution companies.

  The Working Group will aim for completion of the report by 30 September 2003 in order to feed into the forthcoming distribution price review. At this time the Working Group will consider how any further work should be taken forward.

5.  MEMBERSHIP OF WORKING GROUP

  The Working Group will comprise representatives from:

    —  Ofgem;

    —  Energywatch;

    —  DTI (Engineering Inspectorate and Energy Markets Unit); and

    —  Distributors (including Electricity Association).

  Energywatch will be invited to provide a customer's view on these important issues.

  Giles Scott of the Engineering Inspectorate (DTI) will chair the group. Steve Jacobs (DTI) will act as secretary.

  Members agreed to consider sharing as much information as possible regarding how they manage their networks, on the basis that they (and the whole industry) may benefit from the outcome. However, it is understood that there may be a few issues that provide commercial competitive advantage, which should be respected.

  The HSE is welcome to all meetings in the capacity of observer and all correspondence will be copied to HSE for information.

Annex 5

Text of letter to NGT following incident on 28 August 2003

  Chief Executive,

  National Grid Transco

  29 August 2003

  As you will be aware, I wrote to you on 21 August seeking your assurances of the level of confidence you had in the robustness of the 400kV and 275kV system in the UK. This was as a consequence of the Trade and Industry Committee Inquiry into distribution network resilience.

  I am now writing to register my deep concern about the major power disruption, which affected London and the South East on the evening of 28 August, and its knock on effects for the transport system in London. With this in mind, I should be grateful if, as a matter of urgency you would supply me with:

    —  A full report explaining the reasons which led to the power failure;

    —  What actions were taken to get supply power on track;

    —  The risks of a similar incident occurring in the future;

    —  Given the risk of a potential repeat occurrence what measures you will be implementing to ensure that a similar problem does not arise in the future, including details of planned investment in London.

  It is essential that assurances can be made that the reasons for the disruption are clearly understood and that lessons will be learnt.

Stephen Timms






1   Department of Trade and Industry October 2002 power system emergency post event investigation-overview report and individual annexes on each company investigated are available at: http://www.dti.gov.uk/energy/domestic_markets/security_of_supply/bpireport/index.shtml Back

2   Department of Trade and Industry Resilience of the Electricity Transmission and Distribution Systems dated 10 May 2002-available at: http://www.dti.gov.uk/energy/domestic_markets/security_of_supply/bpifinalreportelec.pdf Back

3   Letters from CEOs may be viewed at: http://www.dti.gov.uk/energy/domestic_markets/security_of_supply/stormdresp.shtml Back

4   Recommendations directed at individual companies are being taken forward by these companies and have been the subject of reports to the Minister for Energy. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 13 December 2004