Select Committee on Trade and Industry Written Evidence


APPENDIX 4

Memorandum by East Midlands Electricity

KEY POINTS

    —  East Midlands Electricity (EME) was identified in the BPI report following the October 2002 storms as a "good performer". EME has made further improvements since then, and continues to review its systems and processes to further improve the service it offers to customers.

    —  EME has made significant improvements in those areas identified by BPI as needing attention, including strengthening its contractual arrangements with key service providers and working to improve the information it provides to customers.

    —  Distribution businesses' high quality asset management processes have enabled them to extend asset lives well beyond those envisaged when the assets were constructed. However, under current levels of allowed investment, many parts of the electricity networks (such as poles, transformers and cables) will need to last for over 100 years before being replaced.

    —  Increased investment is now essential not only to maintain network performance and risk at current levels, but also to support distributed generation in line with the Government's Energy Policy. Ofgem must ensure that the next distribution price control review incentivises appropriate and efficient investment.

    —  The co-operative, inter-company NEWSAC arrangements that enable distribution businesses to request staff from other companies are an important aid during emergency situations. There is a danger that the increased use of comparative regulation could mean that companies will be reluctant to release resources to aid a competitor, which would be to the detriment of customers overall.

    —  It is essential that new and equitable arrangements for compensating customers are developed to ensure that a repeat of the lengthy determinations process following the October 2002 storms is avoided. EME is committed to working with Ofgem and the rest of the industry to develop robust arrangements for the future.

INTRODUCTION

  1.  East Midlands Electricity (EME) is a wholly owned subsidiary of Powergen UK plc, part of the international E.ON group of companies. EME distributes electricity to 2.4 million customers in an area covering 16,000 km2 in the East Midlands, using a network comprising 39,000 transformers, 44,000 km of underground cable and 24,000 km of overhead line.

  2.  This note sets out a summary of EME's performance during the October 2002 storm and the measures taken since then to improve future performance, and addresses a number of wider issues which have a major impact on the ability of network businesses to provide a high quality, sustainable service to their customers.

  3.  EME welcomes the opportunity to comment on the security and operation of networks under storm conditions. At the last price review and more recently, through the Energy Policy Review, we highlighted some of the key investment and security decisions facing the industry. The original BPI Asset Risk Management process and the October storm review once again highlighted some of those same issues, such as tree clearance, undergrounding of overhead lines and replacement of aged assets.

THE BPI REPORT

  4.  The October 2002 storm caused substantial damage to EME's overhead line network and caused loss of supply to around 191,000 customers. Of these, 175,000 customers were restored within 18 hours, and 188,000 within 42 hours. 99.98% of affected customers were back on supply within 90 hours.

  5.  EME co-operated fully with the review of storm performance carried out on behalf of the Department of Trade and Industry by British Power International (BPI).

  6.  The report identified EME as a good performer during the October 2002 storm and highlighted many areas of good performance, such as processing information, initial management of repairs, housekeeping maintenance, communications with stakeholders, deploying adequate designs and innovative network developments.

  7.  However, while the BPI report on EME was largely favourable, it did identify a number of areas for improvement. The company has worked hard since the BPI report was published, and has made significant progress in the areas identified, as described below.

    —  Prediction of storm impact and resource requirements:

    EME's use of predictive tools to forecast likely damage and resource requirements in emergency situations was identified as "good" by BPI, but the company has continued to review and further improve its systems and processes.

    The BPI report identified the need for the inclusion of predictive tools in EME's emergency plans, to relate forecast weather conditions to likely damage to the network and consequent demand on resources. EME has reviewed its comprehensive emergency plans, which now include a storm impact prediction tool and improved linkage to Met Office weather warnings through the Internet.

    —  Telephone response and answering service:

    There was a widespread problem with the British Telecom (BT) 0800 number platform during the October 2002 storms, which adversely impacted EME and a number of other distributors. Since then, EME has carried out a full internal investigation and has met with its service provider in order to secure improved BT performance. EME has now transferred to BT's more secure RIDE2 platform, and has also made adjustments to its systems as a result. EME believes these improvements will deliver a best practice telephone service to its customers.

    —  Management of repairs—beyond first day:

    The BPI report concluded that EME's management of repairs beyond the first day of the storm was moderate and could be improved. EME has changed its internal systems and processes in response to improve performance in future events. Levels of administrative support at regional operating centres have been reviewed and will now increase during storms in order to improve the information flows between field staff and central systems. This, together with the new technology that is now being used by EME's mobile workforce, will improve EME's ability to match and despatch resources to outstanding work more quickly and accurately.

    —  Management of repairs—NEWSAC (Northern, Eastern, Western and Southern Aid Consortium—inter company mutual assistance agreement) notification:

    The timing and co-ordination of requests for resources under the NEWSAC arrangements was raised as an area for improvement by BPI. EME has improved its processes and updated its emergency plans to reflect this. In addition, EME is now represented on the NEWSAC co-ordination meetings. However, EME believes that there are wider issues that could adversely impact on the availability of additional resources through NEWSAC arrangements, and these are discussed in more detail below.

    —  Provision of information to customers on restoration times:

    EME's ability to deal with customer enquiries during the storm was adversely impacted by the BT 0800 platform issues, as discussed above. However, BPI also found that the actual information available for customers was below the minimum level reasonably expected. In response to this, EME has made improvements to its processes, which have been thoroughly tested and found to work well, both in normal operations and during a recent emergency exercise. In addition, EME has expanded the type of information given to customers, for example, it now includes help and advice on practical issues such as protecting freezer contents.

  8.  EME believes that, as well as the issues identified by the BPI report following the exceptional weather last October, a number of other important issues have a major impact on the ability of networks businesses to provide a high quality, sustainable service to their customers.

TREE MANAGEMENT

  9.  The BPI report did not highlight tree trimming as a particular issue for EME, but EME's own investigation into the storm found that a high percentage of the incidents on the network were caused by trees. EME already had a substantial tree management programme in place, but has since expanded its scope. As well as an ongoing programme of tree trimming to maintain safe distances between trees and our equipment, we have negotiated permission from councils, local landowners and the Forestry Commission to carry out a tree felling programme to give much greater clearance for key elements of the network. We then offer to supply two new trees for each one that we fell, in line with our environmental objectives.

IMPACT OF CAPITAL INVESTMENT ON NETWORK PERFORMANCE

  10.  Electricity networks businesses have been the subject of RPI-X regulation since they were privatised 13 years ago. This approach has been very successful in driving costs out of the businesses, with the distribution portion of consumers' bills having halved in real terms over this period, to around £60 a year for a domestic customer. Companies are now leaner and smarter, with high quality systems and processes in place to manage the networks under their control. However, given the regulatory focus on cost reduction, there is no longer the level of in-house resource that could previously be deployed in exceptional emergencies. Rather, there is necessarily increased reliance on better focussed planning, resourcing, deployment and implementation.

  11.  Distribution businesses have developed high quality processes to manage the operation, maintenance, repair and replacement of the network assets in their control, based on risk assessment. This has enabled them to extend the lives of those assets, including transformers, overhead lines and underground cables, well beyond the lifetimes envisaged when the assets were constructed, but network risks have now begun to increase. The need for increased levels of investment in networks must now be recognised, not only to deliver the changes that are needed to support the Government's targets for increased renewable generation connected directly to distribution networks, but also to maintain current levels of performance and system risk.

  12.  EME is one of the largest electricity distribution businesses in terms of the number of customers it serves, but has had one of the lowest capital allowances under its regulatory settlement. Good asset management practices extend the life of assets, but refurbishment does not obviate the need for replacement in time and the "bow wave" in renewal investment (see graph) created by extensive electrification in the 1950s and 1960s is simply being deferred. Recent investment levels have replaced only a small fraction of the network infrastructure, and asset replacement timescales now stretch beyond a 100 years, which is clearly not sustainable.


  13.  The regulator needs to take account of these issues as part of the distribution price control process that will set the framework in which distribution businesses will operate for the five years from April 2005. The aim of the price control must be to incentivise efficient investment whilst ensuring that Government Energy Policy objectives are met, The networks are ageing, and replacement of these assets requires a long term, coordinated approach in order to minimise disturbance to customers, protect security of supply and ensure adequate skills, resources and funding are available.

NEWSAC RESOURCE SHARING ARRANGEMENTS

  14.  The BPI report looked at the NEWSAC arrangements under the terms of which distribution companies provide each other with resources in emergency situations. The ability of a donor company to provide staff to help a neighbour has always been dependent on the donor not being affected by a similar emergency situation, but in general terms, NEWSAC has contributed to reduced restoration times for customers.

  15.  Ofgem must take account of the possible adverse impact increasingly competitive regulation could have on the co-operative NEWSAC arrangements. There is a risk that, in a world of benchmarked restoration times, companies may be more reluctant to send their resources to assist a competitor. This would therefore extend overall UK restoration times rather than reduce them, and would only be to the detriment of the service that companies are able to give to UK customers.

COMPENSATION FOR CUSTOMERS

  16.  EME believes that the existing arrangements for compensating customers affected by power cuts as a result of severe weather do not work well, and this was illustrated very clearly by the recent determinations process following the October 2002 storms. An unprecedented number of customers (around 3,000) asked Ofgem to determine on their claims for compensation, which had a significant impact on Ofgem in terms of resources. Ofgem has recognised the welcome gestures of good faith made by companies in going beyond their legal obligations to resolve these claims expeditiously.

  17.  The existing arrangements form an integral part of the overall settlement made by companies with the regulator at the last price control, and would normally only be changed at the next review, for the period beginning April 2005. Any increase in the level of compensation paid to customers must therefore be considered in the wider context of the overall price control arrangements.

  18.  EME believes that it is essential to consider new and equitable arrangements to ensure that a repeat of the protracted determinations process following the October 2002 storms is avoided. We have asked Ofgem to work proactively with the industry to review the existing arrangements for customer compensation, and will participate fully in future discussion on the issue.

28 August 2003





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 13 December 2004