Select Committee on Trade and Industry Written Evidence


APPENDIX 7

Memorandum by the Electricity Association

BACKGROUND

  1.  The Electricity Association (EA) is the national trade association for the UK's major electricity generation, transmission, distribution and supply companies. EA represents the UK industry at both a national and international level. EA will be restructuring on 30 September 2003 resulting in trade association activities for electricity networks being passed to the new Energy Networks Association (ENA). The UK's 14 distribution network operators (DNOs) are members of EA and the founding members of ENA.

SUMMARY

  2.  BPI's report confirmed that "the UK's electricity supply networks are being managed by operators who are deploying appropriate risk management processes and implementing adequate design standards and maintenance policies within the constraints of their regulatory price allowances." The varying performance of DNOs on this occasion was attributable to a combination of individual company specific issues and national industry wide issues. However, there was "no inherent or generic problem in the network."

  3.  Distribution Network Operators have made significant progress in addressing the specific and generic recommendations in the British Power International (BPI) report. All the companies are committed to working with the Government, the Regulator and their colleagues in the industry to minimise the impact of storm damage. Due to the diverse nature of severe weather events, however, it must be recognised that industry best practice will not in itself prevent or avoid significant and extended supply disruption in the future.

  4.  The BPI report raised generic network resilience issues which cannot be solved by the electricity industry alone. For this reason the industry has joined with the Department for Trade & Industry (DTI) and Ofgem to establish a joint Network Resilience Working Group. The group is currently developing actions that can be taken in the short, medium and long term to minimise the risks of supply interruptions arising from severe weather events. Energywatch has also been invited to participate. The group will report its initial findings in October 2003.

  5.  Key short term issues are vegetation management and customer expectations. Long term issues centre around the level of resilience required for networks in the future. Moving from baseline operations resilience to a storms resistance approach, or from fault mitigation to fault prevention, will require detailed work streams supported by substantial funding and investment within a framework of clearly identified efficient levels of expenditure. BPI recognises that "investment, possibly beyond that which can be reasonably economically justified under the current regime, will be required—with costs being passed on to customers. Significant environmental impact may be a consequence." Management of these issues necessitates wider involvement than just industry, government and the regulator.

  6.  DNOs accept the principle of compensation where justified. However, there is a need for a wider debate of the issue as the process and speed of dealing with payments to customers requires reform. This debate should take place in the wider context of price control arrangements, as any increase in compensation payments would reduce capital available for investment in networks. DNOs are keen to work with the regulator and others to develop a better framework.

PROGRESS MADE BY ELECTRICITY SUPPLY COMPANIES (DNOS) IN ADDRESSING THE ISSUES IDENTIFIED BY BPI

The recommendations

  7.  The key recommendations of the BPI report, based on national best practice, were:

    —  Ensure that emergency plans are adequately and routinely tested.

    —  Develop predictive tools which relate weather forecasted weather conditions to likely damage to the network and demand on resources.

    —  Ensure rigorous testing of telephone response and answering services with contingency plans in place in the event of system failure.

    —  Provide realistic estimates of length of repair and inform customers.

    —  Provide feedback to customers with regular updates.

    —  Ensure maintenance programmes are up-to-date with trees and vegetation kept under control.

  Primarily these recommendations address short term issues. However the investigation of the event also identified longer term matters which will need to be addressed if the short term recommendations are to have the anticipated effects.

Individual commitments

  8.  Individual companies responded to the company specific recommendations in the BPI report in January and February 2003 outlining the actions they would be taking to address the key areas of concern. The Minister published these responses on the DTI website in April 2003, see http://www.dti.gov.uk/energy/domestic_markets/security_of_supply/stormdresp.shtml

  These responses confirmed the good progress made in addressing the BPI recommendations and that there was, and remains, genuine commitment on the part of DNOs to improve performance. Examples of actions introduced or completed by companies include:

    —  The annual review of major incident management plans covering both its testing and implementation was revised to include both IT and telecommunications systems and consideration of lessons learned from recent exercises.

    —  Development of and implementation of a branch-wide emergency plan covering three licensed networks.

    —  Establishment of a 132kv live insulator washing group to help protect against flashovers caused by salt deposits and misty conditions.

    —  Doubling the number of call takers available during a system emergency through better utilisation and training of employees from elsewhere within the organisation.

Collective action

  9.  Through EA, the industry has collectively been considering the issues of NEWSAC development, customer communication and telephony issues.

NEWSAC

  10.  NEWSAC has proved extremely effective and an important means of providing mutual aid across the country when required. It enables the industry to provide mutual support to respond speedily and efficiently to major system emergencies by sharing resources. A review of the NEWSAC arrangements has identified a number of areas for amendment. For example,

    —  The productivity of staff imported from another company or area during an emergency it is recognised, will typically be lower than that of indigenous staff due to differences in network, local knowledge and safety. The development of generic staff authorisation safety codes, across agreed areas will significantly reduce the staff induction times required for transferred or on-loan staff.

  11.  The IIP Project penalises and rewards companies based on their Quality of Supply performance. It is important that Ofgem recognises that companies who donate staff under NEWSAC are not penalised by putting their IIP targets at risk whilst serving the common good.

Customer communication

  12.  EA held its annual emergency response seminar following the industry's own storm review. The seminar was open to a wider audience than previously, and agreed four priorities, three of which related to customer communication:

    Sharing of best practice and information exchange between companies under emergency and normal operating conditions. Following the separation of the electricity businesses, customers now have a much closer relationship with their supplier rather than their distribution company. Customers are often unclear about this delineation. This raises questions about the involvement of suppliers in managing such incidents, and how DNOs can best manage information sharing with customers. The volume of calls handled during the incident necessitated the use of traditionally non-call centre staff by vertically integrated companies. This was viewed by BPI as a positive and efficient use of resources.

    Keeping customers informed of DNO activity and their commitment to restoring supplies. During the incident in addition to the DNOs, a number of energy suppliers, energywatch and other stakeholders received calls from customers, reporting or requesting information regarding their quality of supply status. In such emergency situations everyone has a responsibility to ensure that the focus of attention is on the most urgent issue—that of getting people back on supply. Where these are not already in place, systems need to be established to enable parties to share information and ensure that all interested groups are up to date on the action being taken. EA members believe central data collation and dissemination is a useful activity in such incidents and can play a supportive role to individual company activities. EA has therefore formalised its emergency response system which will enable the collation and distribution of information regarding these incidents between members and interested parties such as DTI, Ofgem, energywatch, and the media. This has been welcomed by DTI.

    Awareness of MACC (Military Aid to the Civil Community) and the various triggers that would allow DNOs to receive assistance under MACC. EA is seeking to ensure that all DNOs have details of contacts within the MACC community. Particular issues will need to to be addressed, as electricity distribution work requires specific competences and authorisations that military engineers may not have.

Telephony services

  13.  All companies have systems in place for call handling, customer feedback, incident management and network management. BPI recognised that most components generally proved effective. In terms of internal communications BPI concurred with EA's view that consideration should be given to giving priority to such communications. This could be achieved through the inclusion of HV and LV sub-stations in the Government Telecommunications Preference Scheme, access to the Emergency Services Airwave platform and/or access to ACCOLC, a Government approved scheme that enables mobile call prioritisation when there is a system overload. EA is pursuing discussions with DTI on these matters.

  14.  In terms of customer communications, the incident highlighted inadequacies in the BT system which raises issues at an industry as well as an individual company level. Given the national importance of these systems, there is a need of greater cooperation between Ofgem, Oftel, and the DTI. Through EA, the industry has therefore been working with BT to identify what actions can be taken to prevent this from occurring in the future. A new system is currently being tested with one EA member. Results will be shared across the industry and implemented as required.

GENERIC NATIONAL NETWORK RESILIENCE ISSUES

  15.  The implementation of industry best practice will not in itself prevent similar disruption in the future. Due to the diverse nature of severe weather events eg wind, snow, rain, serious disruption is always a possibility during such incidents. This raises generic issues of both short term and long term significance. For this reason the industry has joined together with Ofgem and the Government in the Network Resilience Working Group (see appendix 1) to identify what actions can be taken to address the key issues of concern. Management of the short term and long term issues requires both industry and stakeholder commitment. The group will report its initial findings in October 2003.

Short term

  16.  For wind related events, a key issue is the proximity of trees to overhead lines, which can cause brushing contact, produce wind borne debris or actually fall onto lines. To resolve totally this problem will require cutting trees back to falling distance. This is one of the BPI recommendations; effectively the removal of trees or the removal of the network. All companies have tree trimming and cutting programmes, but all have problems in enforcing their statutory powers (relative to safety clearances, not falling distances) in the face of terminable wayleaves, and even these powers allow no margin for re-growth. In some isolated instances landowners are unwilling to allow access for tree trimming or removal. There are also obviously environmental issues to be taken into consideration regarding tree clearance. This issue would benefit from a wider national debate and may require legislation.

  17.  Equally, customer expectations have risen and supply interruptions have become less tolerable than in the past. Supply interruptions generally are viewed as unsatisfactory, and large numbers of interruptions extending beyond 24 hours are bound to produce significant public and media reaction. Even following extreme weather, any volume of interruptions beyond 48 hours appears unacceptable to the public. Whilst efforts can be made to mitigate the customer impact when incidents do occur, (eg tree operations), minimising the potential for incidents will require longer term action. In the short term, efforts need to be made to keep customers better informed.

Long term

  18.  Overhead networks may face increased vulnerability to severe weather events in future years. Experts suggest that the growing season is extending, the leaf cover duration is longer, and the window in which storms are most likely is extending. Such events are expected to become more extreme and occur more frequently over the next 30 years. During these events, overhead networks will continue to suffer significant disruption (often 60 times the normal levels of fault activity) and resources will be overstretched which will result in extended restoration times. In contrast, underground networks generally experience faults on a random basis, which enable resources to be matched to incidents. This raises questions of whether selective undergrounding, the acceleration of upgrading of overhead lines and the redesign of the network with interconnection and duplication would be to the long term benefit of the UK economy. All of these issues were identified in the BPI recommendations resolution will require detailed work streams supported by adequate funding and investment within a framework of clearly identified efficient levels of expenditure.

  19.  In essence the issue that needs to be tackled is what level of resilience is required for networks in the future. Should this be determined by baseline operation or storm resilience considerations? Taking into account weather patterns, customer expectations and the skills base available should a policy of fault mitigation, or fault prevention, or a mixture of both be followed? The Network Resilience Working Group is considering these issues.

GUARANTEED SERVICE STANDARDS

  20.  There is a need for a wider debate on the issue of compensation, and the processes and methodology used to determine fair outcomes for both customers and companies. This is particularly true in relation to events like the October 2002 storms, where the possibility of claiming financial compensation from DNOs under the provisions of the guaranteed service scheme has been well publicised and a large number of claims have resulted. Nevertheless, companies' obligations under this scheme do not apply in restoring supplies in exceptional circumstances in the aftermath of storms.

  21.  Around 3,500 claimants exercised their ultimate right to have their entitlement to compensation formally determined by the regulator. This was an unprecedented number, and the resource impact on Ofgem in terms of the need to process and determine these claims speedily and efficiently was therefore very substantial.

  22.  Ofgem's solution to this problem in the October 2002 storm was to group the claimants according to the engineering characteristics of the supply to their premises, and then to assess the performance of the DNOs in restoring supply to each such group by comparison with the performance of a benchmark comparator chosen by Ofgem. Ofgem took as the benchmark comparator the "best performing" of all the DNOs, and on this basis was able to "determine" the compensation liabilities of each DNO for each of the specified groups of customers. This methodology, which treats customer determinations rather like a series of small class actions, has the apparent merits of speed and simplicity, and the DNOs have accepted it in the interests of their customers.

  23.  However, DNOs are concerned that their acceptance of Ofgem's approach to the post-October determinations should not be taken as a precedent for the treatment of future determinations arising in relation to supply restoration performance. They are keen to work with the regulator to produce more robust arrangements for the next price control period and a better framework during the interim, so that customers and companies benefit from a fair, practical and equitable system for determining entitlement to compensation.

Electricity Association

29 August 2003





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2004
Prepared 13 December 2004