14 Mar 2006 : Column 2164Wcontinued
Correspondence
Mr. Ruffley:
To ask the Secretary of State for Work and Pensions pursuant to his answer of 13 February 2006 to the hon. Member for Inverness, Nairn, Badenoch and Strathspey, Official Report, columns 169091W, on post office card accounts, when the three pilot schemes will be completed; and what plans he has to increase the number of people covered by these schemes. [56321]
Mr. Plaskitt:
The pilots began on 13 February 2006 and will be concluded by mid-March. When they are completed we will evaluate the results and discuss the findings with the Post Office and other key stakeholders. I have no plans to increase the number of customers covered.
Departmental Correspondence
Mr. Laws:
To ask the Secretary of State for Work and Pensions how many letters were received by (a) his Department and (b) each of its agencies in (a) 200304, (b) 200405 and (c) 200506 to date; and how many and what proportion of these letters were (i) answered within (A) 10, (B) 20, (C) 30 and (D) 40 working days, (ii) answered after 40 working days and (iii) not answered. [56456]
Mr. Plaskitt:
The Department's correspondence targets are:
To respond to letters from MPs/peers sent directly to agency chief executives on operational issues within 15 working days.
The information that is available on letters received and replied to is shown in the following tables.
Table 1: Receipt and response times of MPs letters to Ministers in calendar years
| | Number of letters replied to during the year
|
| Received during the
year | Replies | Within
20 days | Percentage within
20 days | 21 to 40 days | Percentage within 21 to
40 days | Over
40 days | Percentage over 40 days
|
2003 | | | | | | | |
|
DWP | 12,157 | 12,031 | 8,931 | 74 | 2,696 | 22 | 404 | 3
|
Child Support Agency | 240 | 227 | 199 | 88 | 27 | 12 | 1 | 0
|
Jobcentre Plus | 977 | 866 | 736 | 85 | 116 | 13 | 14 | 2
|
The Appeals Service | 13 | 13 | 13 | 100 | 0 | 0 | 0 | 0
|
The Pension Service | 777 | 754 | 400 | 53 | 305 | 40 | 49 | 6
|
| | | | | | | |
|
2004 | | | | | | | |
|
DWP | 13,320 | 13,463 | 11,536 | 86 | 1,497 | 11 | 430 | 3
|
Child Support Agency | 491 | 482 | 445 | 92 | 30 | 6 | 7 | 1
|
Jobcentre Plus | 879 | 943 | 880 | 93 | 58 | 6 | 5 | 1
|
The Appeals Service | 37 | 36 | 32 | 89 | 2 | 6 | 2 | 6
|
The Pension Service | 958 | 970 | 914 | 94 | 53 | 5 | 3 | 0
|
Disability and Carers Service | 78 | 60 | 60 | 100 | 0 | 0 | 0 | 0
|
The Rent Service | 6 | 6 | 2 | 33 | 4 | 67 | 0 | 0
|
2005 | | | | | | | |
|
DWP | 10,596 | 10,639 | 9,623 | 90 | 785 | 7 | 231 | 2
|
Child Support Agency | 572 | 560 | 556 | 99 | 4 | 1 | 0 | 0
|
Jobcentre Plus | 1,137 | 1,224 | 1,127 | 92 | 95 | 8 | 2 | 0
|
The Appeals Service | 32 | 30 | 30 | 100 | 0 | 0 | 0 | 0
|
The Pension Service | 701 | 683 | 669 | 98 | 13 | 2 | 1 | 0
|
Disability and Carers Service | 454 | 445 | 445 | 100 | 0 | 0 | 0 | 0
|
The Rent Service | 5 | 5 | 5 | 100 | 0 | 0 | 0 | 0
|
14 Mar 2006 : Column 2165W
Table 2: Receipt and response times of members of the public's letters to Ministers in calendar years
| | Number of letters replied to during the year
|
| Received during the year | Replies | Within 20 days | Percentage within 20 days | 21 to 40 days | Percentage within 21 to 40 days | Over
40 days | Percentage over 40 days
|
2003 | | | | | | | |
|
DWP | 17,289 | 16,479 | 13,583 | 82 | 1,487 | 9 | 1,409 | 9
|
Child Support Agency | 1,126 | 981 | 840 | 86 | 93 | 9 | 48 | 5
|
Jobcentre Plus | 3,447 | 2,413 | 395 | 16 | 475 | 20 | 1,543 | 64
|
The Appeals Service | 20 | 19 | 17 | 89 | 1 | 5 | 1 | 5
|
The Pension Service | 71 | 69 | 55 | 80 | 4 | 6 | 10 | 14
|
Disability and Carers Service | 671 | 682 | 634 | 93 | 33 | 5 | 15 | 2
|
| | | | | | | |
|
2004 | | | | | | | |
|
DWP | 19,371 | 18,671 | 16,904 | 90 | 233 | 1 | 1,534 | 8
|
Child Support Agency | 1,183 | 972 | 743 | 76 | 157 | 16 | 72 | 7
|
Jobcentre Plus | 5,176 | 4,873 | 4,830 | 99 | 43 | 1 | 0 | 0
|
The Appeals Service | 34 | 37 | 33 | 89 | 4 | 11 | 0 | 0
|
The Pension Service | 153 | 145 | 120 | 83 | 0 | 0 | 25 | 17
|
Disability and Carers Service | 688 | 669 | 647 | 97 | 15 | 2 | 7 | 1
|
The Rent Service | 4 | 4 | 4 | 100 | 0 | 0 | 0 | 0
|
| | | | | | | |
|
2005 | | | | | | | |
|
DWP | 19,724 | 19,530 | 19,027 | 97 | 410 | 2 | 94 | 0
|
Child Support Agency | 1,320 | 1,257 | 1,098 | 87 | 107 | 9 | 52 | 4
|
Jobcentre Plus | 2,319 | 1,793 | 1,688 | 94 | 93 | 5 | 12 | 1
|
The Appeals Service | 32 | 30 | 28 | 93 | 2 | 7 | 0 | 0
|
The Pension Service | 750 | 731 | 665 | 91 | 62 | 8 | 4 | 1
|
Disability and Carers Service | 684 | 707 | 703 | 99 | 3 | 0 | 1 | 0
|
The Rent Service | 4 | 4 | 4 | 100 | 0 | 0 | 0 | 0
|
Table 3: Receipt and response times of MPs letters to chief executives in calendar years
| Number of letters replied to during the year
|
| Received | Replies | Within 15 days | Percentage within 15 days
|
2003 | | | |
|
DWP | 6,324 | 6,357 | 5,044 | 79
|
Child Support Agency | 3,251 | 3,488 | 3,040 | 87
|
Jobcentre Plus | 1,052 | 891 | 614 | 69
|
The Appeals Service | 84 | 81 | 71 | 88
|
The Pension Service | 1,157 | 1,102 | 549 | 50
|
Disability and Carers Service | 554 | 567 | 564 | 99
|
| | | |
|
2004 | | | |
|
DWP | 8,519 | 8,556 | 7,618 | 89
|
Child Support Agency | 5,390 | 5,323 | 4,693 | 88
|
Jobcentre Plus | 1,136 | 1,216 | 1,097 | 90
|
The Appeals Service | 50 | 46 | 45 | 98
|
The Pension Service | 1,340 | 1,366 | 1,217 | 89
|
Disability and Carers Service | 451 | 454 | 453 | 100
|
The Rent Service | 0 | 0 | |
|
| | | |
|
2005 | | | |
|
DWP | 8,068 | 8,047 | 7,843 | 97
|
Child Support Agency | 5,367 | 5,332 | 5,275 | 99
|
Jobcentre Plus | 1,062 | 1,136 | 1,024 | 90
|
The Appeals Service | 60 | 64 | 61 | 95
|
The Pension Service | 1,042 | 976 | 961 | 98
|
Disability and Carers Service | 425 | 431 | 431 | 100
|
The Rent Service | 0 | 0 | |
|
Note:
Data for letters answered beyond the 15 the target are not available as most letters are answered within the target.
14 Mar 2006 : Column 2167W
Departmental IT Systems
Mrs. Villiers:
To ask the Secretary of State for Work and Pensions how much his Department has spent on IT systems in each year since 1997; what the purpose of each system is; what the outturn against planned expenditure of each system was; and what the (a) planned and (b) actual date of completion was of each system. [41315]
Mr. Timms:
The Department for Work and Pensions was created in June 2001. The Department and its businesses currently have in excess of 100 individual projects which encompass information technology (IT)
14 Mar 2006 : Column 2168W
changes to a greater or lesser extent. The Department's major projects are those contained in its modernisation programme. For the most part, these projects embrace both IT and business change.
The information in the table lists the Department's current major programmes and projects that include significant IT change, with information on their purpose, due end date, planned expenditure, outturn and actual end date.
It should be noted that project details may alter as they pass through the project lifecycle and as the Department considers its wider plans as part of the normal spending review process.
Project/purpose |
Due end date | Planned expenditure
(£ million) | Outturn
(£ million)(40) |
Actual end date
|
Customer Management System | | | |
|
This system is an information gathering business process for working age Income Support Jobseeker's Allowance and Incapacity Benefit claims and changes of circumstances. It will allow information supplied by the customer to be gathered electronically by staff, improving efficiency and customer service. Staff will be able to check information supplied against that already held. | November 2005 | 250 | 250 | Completed on time
|
| | | |
|
New Tax Credits | | | |
|
This project supports the implementation of new tax credits by the Inland Revenue by putting a tax credits service in place for DWP customers (principally through Jobcentre Plus) and ensuring that necessary amendments are made to DWP benefits. These systems will be used to complete IS/JSA(IB) Migration by April 2007 | April 2005 | 37 | 37 | Completed on time
|
| | | |
|
ISCS/JSA Modernisation project | | | |
|
Delivered initiatives that enhanced or augmented existing Working Age IT systems. These included the sharing of electronic data with Disability Living Allowance, Attendance Allowance and personal details computer systems. | August 2004 | 14 | 14 | Completed on time
|
| | | |
|
Digital Office Infrastructure | | | |
|
DOI provided a modern IT infrastructure platform across the Department providing access for all staff to the internet and intranet and modern business software. | June 2004 | 726 | 726 | Completed on time
|
| | | |
|
Managing Core Systems Estate | | | |
|
To improve the ways in which our core legacy systems are managed. | March 2006 | 5 | 5 | February 2005
|
| | | |
|
Pensions Forecasting Programme | | | |
|
To establish the new Combined Pension Forecasting Service and enhance and replace the existing individual Pension Forecasting IT system | April 2005 | 43 | 43 | Completed on time
|
| | | |
|
Pension Credit | | | |
|
This project successfully introduced Pension Credit in October 2003. It delivered new IT functionality to existing DWP systems, and associated business products (eg training, staff guidance, customer notifications). | October 2004 | 297 | 297 | Completed on time
|
| | | |
|
Pensions Transformation Project | | | |
|
The programme will transform the Pension Service, bringing together business and IT change in ways that improve customer service and deliver efficiencies. | Wave 1a November 2005, waves 1b, 2a and 2b by March 2008; waves 35 by 2010 | 668 | Project ongoing | Project ongoing
|
| | | |
|
Customer Information System | | | |
|
This project will deliver a database of key citizen information to be shared across DWP. The database will complement information currently available in the Department's key customer information systems, ie Personal Details Computer System and Departmental Central Index, and become their replacement. | July 2007 | 75 | Project ongoing | Project ongoing
|
| | | |
|
Payment Modernisation Programme | | | |
|
The Payment Modernisation Programme aims to establish direct payment into a bank or building society account as the normal, method of payment for all customers. This includes those who wish to collect their money from the Post Office. | December 2005 | 366 | 366 | June 2005
|
Resource Management | | | |
|
This programme will provide modernised HR, financial and procurement functions for DWP staff. It will introduce significant business process change, enabling departmental resources to be managed more effectively. | September 2006 | 176 | Project ongoing | Project ongoing
|
| | | |
|
Debt Management | | | |
|
The Debt Programme introduces a new organisational structure based on 10 Debt Centres and a Commercial off the Shelf (COTS) package to provide new Management Information Systems, combined with increased focus on the management and ultimately reduction of debt stock. | February 2006 | 105 | Project ongoing | Project ongoing
|
| | | |
|
Central Payments System (formerly part of Payment Modernisation) | | | |
|
New payment processing IT functionality is required to support the DWP to process payments for new entitlement management and financial scheduling systems. | September 2009 | 99 | Project ongoing | Project ongoing
|
| | | |
|
Benefits Process Replacement Programme (BPRP)2 | | | |
|
The programme enables modernised benefit processing, effective fraud management and improved service to employers. It provides the strategic IT platform for the Department providing the foundation for future policy initiatives. | TBA | TBA | Project ongoing | Project ongoing
|
(40) Outturn figures show the final investment cost for the completed projects.
(41) CSR: The Department had a Private Finance Initiative contract for the provision of IT services to the Child Support Agency worth approximately £456 million over 10 years. This contract commenced in August 2000 with a 10 year duration to August 2010. Under a general realignment of departmental contracts announced in August 2005, EDS will complete the system as currently specified, including correcting all agreed defects. The revised contract still has a completion date of August 2010 and the Department expects to save around £65 million (net present value basis) in Child Support information technology costs over the remaining period of the deal with EDS.
Notes:
1. The planned expenditure is;
for projects currently in progress, the latest forecast investment expenditure or
for completed projects the final approved investment expenditure.
2. BPRP: As part of the programme's governance it attended a gate on Monday 6 February 2006. At this gate a number of options for progressing the programme were presented. The gate reserved its decision and asked the programme to:
(i) Return to a gate in four months time having considered the impact of the Welfare Reform Green Paper; and
(ii) Continue its investment programme until the next gate by progressing work in areas common to all options presented.
Agreed forecast costs and completion date is dependant upon this decision.
14 Mar 2006 : Column 2169W