Select Committee on Defence Minutes of Evidence


Examination of Witnesses (Questions 180-188)

MR PETER WHITEHOUSE AND COMMODORE (RTD) TIM HARE

28 MARCH 2006

  Q180  Chairman: If that was what it wanted when would an initial gate investment decision be needed?

  Mr Whitehouse: Given the affordability, engineering obsolescence and related dimensions, I would not markedly change my view that work would need to start on that immediately once it had been selected as the option. One does not know when one can downselect and say that is what one will do, but it would probably be within 18 months to two years in order to be sure that one has the first submarine available when needed and, looking at it from the industrial dimension, to try to create continuity in the build programme at Barrow.

  Chairman: Let us now move on to the warheads.

  Q181  Mr Havard: From what you have just been saying, it seems to me that there are almost two timelines running side by side. One is to do with platforms and one is to do with the actual warhead. Can you say what decisions need to be made and when about the actual warheads?

  Commodore Hare: I have to say from the outset that I am not a warhead expert. Questions on warhead probably need to be addressed to AWE scientists. I will just give my view. A warhead is like any other piece of technology; it consists of a number of piece parts, some of which in time become obsolescent. Rather like one's car, one carries on replacing the piece parts until one day one either goes to a dealer or wakes up one morning and decides it is time for a new model. One moves from one's Ford Escort to a Ford Focus, to use that analogy. The UK warhead goes through a continuous process of safety and reliability assessment and pierce parts that become obsolescent are replaced, continuing the process in accordance with AWE Aldermaston's remit. I suspect that some time in the mid to late 2020s it will be time, if we still have a Trident system, for a replacement warhead to be procured.

  Q182  Mr Havard: In terms of decision-making you seem to be suggesting that if there is to be the replacement that you describe, as far as the platforms or boats are concerned the decisions at the conceptual stage need to be made next year?

  Commodore Hare: I think that some study work needs to be started about the nature of the platform.

  Q183  Mr Havard: When do decisions need to be made about the weaponry?

  Commodore Hare: The warhead is related more to the Trident system. If we assume that we will still have a submarine-based system the warhead decision can be taken independently of the submarine. The warhead relates just to the missile. My personal view—it is just that because I do not know the answer to the question—is that one would not need to have a replacement warhead until well into the mid to late 2020s. One has, therefore, a little time on one's side before one has to make any decisions or have a peak in expenditure at Aldermaston.

  Q184  Mr Havard: One set of decisions has already been made about Aldermaston. What do you see as the rationale for that?

  Commodore Hare: In my limited dealings with Aldermaston I have always been hugely impressed by its dedication, skills and experience. I have always been hugely confident that it is able to fulfil its dual remit which is to maintain the stewardship of the current stockpile for safety and reliability and to be in a position to design and procure a new warhead should the government of the day decide that it wants one. When I was in post with Aldermaston there were two problems. First, its infrastructure was becoming very dated, by which I mean that a lot of its buildings were crumbling. Secondly, the workforce was following my age line, if you like; it was getting to the end of its professional careers. One needed to inject some young blood into AWE to perpetuate the skills base. My understanding is that the recent expenditure by government is focused on those two areas to ensure that the infrastructure is able to support the twin remit of Aldermaston and that the demography of the workforce remains sensible and there is an injection of new blood to replace retiring people.

  Q185  Mr Havard: The Government says that the expenditure is to retain core skills, the safety of the current stockpile and its effectiveness and the replacement of facilities. As I understand it, the Trident missile system is a combination of things. The D5 is to be upgraded by the Americans to the D5(A), or whatever it is. It has on it a W76 warhead, or something similar. There is also work being carried out on the re-entry vehicle. We are putting £350 million a year into Aldermaston between now and 2008 and 1,000 scientists are to be recruited. There is the Orion project which is a new laser that can simulate nuclear explosions, because we cannot test in the way that we did in the past. That is one-third owned by Lockheed Martin which is the company which produces the missiles. Are we really retaining a capability to develop our own nuclear deterrent? Is that what it is really all about?

  Commodore Hare: I believe that we are. I can only speculate because it is a long time since I have been engaged with AWE. My information is the same as yours. I must correct one point. AWE Aldermaston is government-owned but contractor-operated. In the jargon it is called a GOCO (Government-owned contractor operated) facility. You said that it was owned by Lockheed Martin.

  Q186  Mr Havard: As I understand it, there is a contractual agreement and one-third of it is owned by Lockheed Martin.

  Commodore Hare: My understanding is that the operation of Aldermaston is through a consortium of Serco, British Nuclear Fuels and Lockheed Martin. You are quite right that Lockheed Martin is American-owned.

  Chairman: Let us move on to the defence industrial strategy.

  Q187  Linda Gilroy: Affordability is a key issue. Mr Whitehouse, can you tell us what are the prospects for the formation of Subco in addressing the issue of affordability and the extent to which it is likely to be able to do that if it comes about? What is your view on how we continue to obtain value for money beyond 2016 in relation to the shipbuilding and submarine requirements of the Government?

  Mr Whitehouse: I think that the cost issues associated with the submarine capability in the UK are quite fundamental at this point, with a planned force level moving down towards eight SSNs and four SSBNs and the requirement to consider the procurement of further attack submarines as well as the need to cope with the decision on the future SSBN. There is a clear and absolute need to achieve consolidation and rationalisation because the nuclear facilities bring with them a lot of skills and very specialised and expensive infrastructure. The majority of those costs are fixed. Therefore, to take the whole enterprise forward and to keep it affordable, it is of paramount importance to have cross-site consolidation and rationalisation. I focus on Faslane, Devonport and Barrow. As far back as 1994 when I was working on the initial tender document by Devonport to the Government after the decision to privatise we went a long way towards bringing the then VSEL, the owners and operators of Barrow, into the DML consortium to try to start that. That was 12 years ago. The need even then was quite obvious. Where we sit today it is very important. The prospects for it are under debate at the moment. They have been influenced by some of the press coverage of possible developments last week, which I do not want to go into, but one way or another cross-site consolidation is fundamental. It must happen in order to save significant costs if a future SSBN is required and it is to be affordable.

  Q188  Linda Gilroy: On the skills and knowledge base, if the decisions that we have talked about this morning were delayed what would be the implications? If there was a decision not to replace Trident and somebody wanted to take a future decision to do so what would happen to the skills base in the interim, and with what implications?

  Mr Whitehouse: That is a very interesting point. A decision not to do things within the required timescale implies an intent at some time in the future not to have a deterrent. That is a fundamental message to send 15 years away from not having a deterrent through inaction. That is a very important political and philosophical point. First, in terms of the practicalities, in the event that work does not start within the required timescale—there are slightly differing views on that—an obvious point is that to keep the current deterrent going as long as possible perhaps more rather than less work would have to be done in the second refits. Secondly, near certain workload gaps would appear in the design and build capability associated with Barrow, unless it was possible to slow up the build rate for the Astute-class submarines and produce them over a longer period of time. But then it would be quite likely that the SSN force level would begin to drop because one would not have submarines coming into service quickly enough to replace the Trafalgars as they go out of service. It is almost like a matrix of influences and results, but there is no doubt that the key result would be a major affordability issue within the industrial base. Capability would be retained but would have nothing to do or one would have to let that go. It is a bit like weapons capability; once it is allowed to go it would be very difficult if not impossible to recreate it.

  Chairman: We are going to finish the first part of the session here. On behalf of the Committee I would like to thank both of you for coming along and giving clear evidence and answering our questions so concisely.





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 30 June 2006