Select Committee on Environmental Audit Minutes of Evidence


Supplementary Memorandum from British Wind Energy Association

  Dear Mr Hennessy,

  Thank you for your letter of the 4th of July addressed to Michael Hay. He has asked me to answer the questions contained in that letter, which it is my pleasure to do. Before I address them directly, it is worth saying that we believe the consultation has generally addressed the right issues, leading us to be cautiously optimistic about the progress of the Bill. However, there are some key questions that are not addressed, some of which the Committee's follow-up questions have accurately identified.

  What developers want most of all is regulatory certainty. However, this Bill is unlikely to deliver certainty in the way that the authors might envisage. The prime problem is the possible wholesale shake up of the way renewable projects are consented. If this happens it will leave developers unsure as to how to proceed, and they will have to get to know the consenting system all over again, leading to delay and cost. This is not an issue that the emerging offshore wind and fledging wave and tidal industries should have to deal with it, especially when they are key in helping Government meet its renewable energy and carbon emission targets. If consenting power over them is given to an MMO this will lead to further delay whilst the organisation finds its feet.

  If this sounds cautious, it is because offshore renewables have a consenting system which, while not perfect, works and is understood by all parties. The issues we have with the process are due to the time taken for consulting stakeholders and slow progress in conflict resolution within Government departments, which do not stem from the basic legislation. On the principle of "if it ain't broke don't fix it", BWEA is reluctant to support a move away from the current system unless it is unambiguously clear that there will be benefits in doing so, and a radical overhaul could do more harm than good. For this reason it would be sensible to keep renewables out of an integrated consents system were one to be implemented, because it will allow development without delay.

  This argument also applies to Marine Spatial Planning. This has the potential to work well and create sensible approaches to development in the marine environment. However, were a binding system immediately imposed on all users of the sea, MSP could potentially be very damaging (including for the marine environment) if it is based on poor data and thus unworkable. At the least there needs to be a transition period to allow problems in the system to be ironed out and enough data to be collected, hence allowing the plans to be proved accurate. Once this is done, the plans can be come binding. This was the approach taken in land use planning where plans only became binding in 1990.

  Turning to the questions:

  1.  Having devolved MMOs does not necessarily result in paralysis of the system, but what it does ensure would be duplication of effort in different administrative centres, and possible inconsistency in application of the legislation. At the points where jurisdictions meet, there may be unnecessary disputes over which MMO has precedence over plans and projects. Also, developers of schemes such as the Robin Rigg offshore wind farm, which straddles the English/Scots border, would likely have to provide two sets of identical, or near-identical, data and paperwork, at considerable cost of effort and money. The sea knows no borders, and BWEA would much prefer if such confusion was eliminated through having a single MMO for the UK. This would be facilitated if consenting was devolved but the overall planning and data gathering was kept within a UK-wide MMO, as is BWEA's preference for the structure of the Marine Bill bodies.

  2.  BWEA's main concern around financing is that sufficient funds are devoted to the key issue of baseline data gathering. Any marine plan will only be as good as the data upon which it is based, and currently the knowledge base on the marine environment is sketchy at best. Binding plans can only be developed after considerable effort has been devoted to this data gathering effort. Offshore renewable developers expend considerable amounts on environmental surveys of their sites, but they cannot be expected to fund work over the wider areas within which they sit. BWEA is concerned that Treasury will not sanction the spending required for the comprehensive surveying that must be undertaken before meaningful plans are created. The consultation paper does not deal with such issues, which is of concern to BWEA.

  3.  BWEA has not made quantitative estimates of the possible costs and benefits of the Marine Bill proposals. Qualitatively, the are possible benefits in streamlining consents procedures, which would reduce development costs, and improved site screening through MSP could eliminate detailed (and expensive) examination of sites which ultimately prove to be unsuitable. Through reducing the regulatory risk at the site development stage, required returns could be lower, thus resulting in lower-cost power from these projects. On the downside, there is a risk of delay in implementing the Marine Bill provisions, resulting in a higher-risk regulatory environment and difficulty in securing development capital unless projects secure higher returns. If the Bill results in greater administrative burdens, then of course that would result in higher costs, though it is to be hoped that this can be avoided through careful design of the new law. BWEA is hopeful that on balance the Marine Bill will be beneficial, though it is difficult to be sure when so many details of the new legislation are yet to be settled.

  4.  BWEA's concern about further delay to the Marine Bill is that it will result in delays in development of the renewable energy potential of our seas, just when the urgency of exploiting all our indigenous, carbon-free power sources is rising. With a prospective Royal Assent in late 2008/early 2009, followed by a period while the new bodies set up and new processes are implemented, it is unlikely that MSP will be meaningfully in place before 2010. Given the long development cycle for offshore wind of five years or more, it will be necessary to allocate new sites well before 2010 if there is not to be a hiatus around 2015 as the Round Two sites complete construction; if the UK is to be seen as the prime country for offshore wind development, then it is vital that there is continuity in such work. Additionally, if the UK is to capitalise upon its current lead in the new technologies of wave and tidal stream power, it will need to be allocating significant sites well before 2010, which will require a Strategic Environmental Assessment and therefore a decision on where such generation projects should go. It is to BWEA's considerable concern, therefore, that recent statements by Energy Minister Malcolm Wicks indicate that he thinks that such processes can wait until after the Marine Bill has passed and MSP implemented. If the Bill is further delayed, and DTI continues to use the prospect of the Bill as a reason to delay SEA for wave and tidal, then this nascent industry may be stifled at birth for lack of sites.

  I hope these answers are helpful. Please don't hesitate to contact me or Michael should you need any further information in the course of the Committee's enquiry.

Yours sincerely,

Dr Gordon Edge

Head of Offshore

BWEA

July 2006





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 25 July 2006