Select Committee on Environmental Audit Minutes of Evidence


Supplementary memorandum submitted by EDF Energy

THE GENERATION GAP

—  The term "generation gap" is used to describe a shortfall in electricity generating capacity as compared to electricity demand assuming circa 20% plant margin needs to be maintained.

—  We estimate that 25-35 GW of new electricity generation will be needed by 2018 to fill the emerging "gap"

—  The gap will occur because of:

—  the closure of coal and oil plants through the impact of the LCPD;

—  the nuclear decommissioning programme; and

—  demand growth.

How we calculated this generation gap for 2018

—  We assumed peak demand increases from 62 to 68 GW:

—  This is based on National Grid's 2005 GB seven year statement that assumes average peak demand will grow by 0.79% per annum. This is the growth rate seen at the grid level, so it takes into account growth in distributed generation and improvements in energy efficiency, which has a negative effect on growth at the grid level. NG says that if distributed generation and energy efficiency were excluded the growth rate would be 1.4% per annum. They do not specify how much of this difference is due solely to energy efficiency.

  The gap figure takes into account the contribution of new renewables delivered through the Renewables Obligation.

—  This is estimated to be around 10 GW of transmission-connected renewables build. However even on a very optimistic assumption only 50% of this capacity would be considered "firm" ie not intermittent such as wind. Embedded (distributed generation) renewables build that also contributes to the Renewables Obligation target is implicit in the estimate of demand.

—  We have also assumed a system margin of around 20% needs to be maintained as is the situation at present.

—  All Magnox (BNFL) stations shutting by 2010 equals a loss of 2.5 GW.

—  The closure of a number of Advanced Gas-cooled Reactors (AGRs) owned by British Energy. Estimated loss of approximately 5 GW as early as 2014 if life extensions not given.

—  The limiting of output from "opted-out" coal as a result of the Large Combustion Plant Directive (LCPD). Could be as much as 19 GW of coal capacity by 2016.

—  Peak demand increases from 62 to 68 GW.

—  Eight GW nuclear closure.

—  Nineteen GW LCPD opt-out closure.

—  Demand increase -6 GW

—  Nuclear -8 GW

—  Opt out coal -19 GW

—  Renewables +5 GW (10 GW 50% capacity)

  Total generation gap = approx 28 GW (based on maintaining same system margin close to 20%.

February 2006





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 16 April 2006