Memorandum submitted by British Nuclear
Fuels plc (BNFL)
INTRODUCTION
BNFL welcomes the opportunity to respond to
a number of increasingly important issues concerning security
of supply. The Energy White Paper of 2003 represented the first
comprehensive policy review of UK energy matters for many years,
and was a valuable revision of policy in several key areas. The
emphasis given to renewable energy and energy efficiency placed
the environment firmly centre-stage in policy thinking on energy,
and set a pathway for the UK to play a leading role in cutting
carbon emissions.
However, much has changed since 2003 (indeed
since 2002, when the bulk of the White Paper analysis was carried
out), with consequent impact on all the policy objectives of the
White Paper. The importance of climate change in policy thinking
has increased. This has been heightened both by rising carbon
dioxide emissions and by a further increase in the frequency of
unusual and sometimes devastating climatic events, most recently
the tragic impact of Hurricane Katrina in the Southern USA. Security
of supply concerns have grown, as the UK became a net importer
of gas earlier than expected. The widespread development of renewable
energy is lagging behind the pace needed to hit targets, and progress
on energy efficiency is also slow. Finally, energy prices across
the board have risen sharply, pushed up by the global oil price,
which has broken through a number of symbolic barriers, including
the $70 per barrel mark. In the UK alone gas prices have more
than doubled since April 2004[14].
We therefore believe that the time is right
for a re-examination of UK energy policy, and that such a review
should look at the useful role nuclear energy can play as part
of a future balanced energy mix for the UK.
Our responses to specific questions raised in
this consultation are provided in the remainder of this submission.
A. THE EXTENT
OF THE
"GENERATION GAP"
1. What are the latest estimates of the likely
shortfall in electricity generating capacity caused by the phase-out
of existing nuclear power stations and some older coal plant?
How do these relate to electricity demand forecasts and to the
effectiveness of energy efficiency policies?
The latest projections of UK electricity demand,
and the rate at which new capacity will be required as existing
stations close, are contained in the Government's Second Progress
Report on the White Paper. The following chart[15]
illustrates the projected mix, and the proportion of the mix in
2020 that will need to come from new plants:
This chart shows the closure of coal and nuclear
plants from the current operating fleetsbased on current
best projections of when such closures might take place. However,
it should be borne in mind that, in each case, these are decisions
which utilities will make based on the commercial, technical and
regulatory positions at the time, and so could varyto be
either earlier or later.
In terms of the impact of energy efficiency
measures, it can be seen that even though government projections
indicate a slight fall in overall demand by 2010, this increases
again so that by 2020 demand is higher than today. It should be
noted that UK electricity consumption has risen steadily over
the past several years, at an average of over 1% per year[16].
BNFL feels that fulfilling even these Government
projections for energy efficiency will be very challenging, and
there is a very real likelihood that electricity demand will continue
to grow year on year, as has consistently been the case in the
past. We believe that current energy efficiency policies will
at best slow the rate of growth, but will not themselves be sufficient
to achieve a real drop in demand. This is particularly true if
energy prices remain "affordable" which is one of the
Government's overriding priorities.
These concerns are shared by other knowledgeable
commentators and analysts. For instance the Environmental Audit
Committee report "Budget 2004 and Energy"[17]
concluded that:
"A more imaginative and radical strategyin
particular for transport and domestic energy efficiencyis
needed"
with the Chairman of the Committee commenting
at the time:
"It is also disappointing that the Treasury
has done so little to promote domestic energy efficiencydespite
two consultations on this topic in the last two years. There is
an urgent need to look afresh at the scale of the challenges we
face and develop an adequate response."
More recently, in July 2005, the House of Lords
Science and Technology Select Committee on "Energy Efficiency"
noted:
"We have been dismayed in the course of
our inquiry by the inconsistency and muddle of much current thinking
about energy efficiency."
The Committee concluded:
"No country in the world has succeeded in
combining a sustained reduction in energy use with economic growth,
and UK energy demand is still rising. Achieving the Government's
targets is a huge task, and needs clearer thinking and stronger
leadership."
It is very difficult to measure the true effectiveness
of energy efficiency measuressince so much depends on a
judgement of what the "baseline" demand would otherwise
have been. Equally, there is little reliable data on exactly how
energy efficiency initiatives have performed over recent years.
However, it is abundantly clear that there have been no "step
change" improvements.
It is worth noting that planned Government measures
to introduce tighter regulations on energy efficiency of buildings
were dropped in July, making the task of achieving substantial
reductions in demand that much harder.
Looking to the longer term, if we move to a
hydrogen economy (using hydrogen fuel cells to replace oil in
the transport sector) then the need to produce sufficiently large
amounts of hydrogen will inevitably push demand for power up much
more strongly. This will have to be factored in to any longer-term
projections on meeting that demand.
B. FINANCIAL
COSTS AND
INVESTMENT CONSIDERATIONS
2. What are the main investment options for
electricity generating capacity? What would be the likely costs
and timescales of different generating technologies?
At present the leading options for new power
generation capacity in the UK are:
Coal (with or without carbon capture technology)
Gas
Nuclear
Renewables (of which the variant most likely
to be built in the near future is wind)
Costs of different options are discussed in
more detail below.
The lead times for commissioning new generating
capacity are long as highlighted by the Public Accounts Committee
in their recent report on renewable energy[18].
Both pre-construction activities, as well as the actual construction
period, need to be considered when coming to a view on overall
likely timescales from inception to commercial operation.
For all options, pre-construction activities
will form a significant component of overall timescales. For some
technologies these pre-construction activities will be of longer
duration than the actual construction period. Examples taking
over five years or more are not uncommon, both for fossil plants
such as CCGT, where a number of projects (including Partington,
Fleetwood, Raventhorpe and Langage) have taken this long[19],
and in the renewables sector, where nearly 20% of UK wind farm
projects have been more than five years in the planning process[20].
Pre-construction activities include matters
such as site selection, environmental impact assessment, design
selection, securing development consent, obtaining a connection
agreement with National Grid Transco, and even securing investment
funds. The overall duration of any of these activities is highly
variable, although many of them can and do run concurrently. Nuclear
has an additional hurdle associated with securing nuclear specific
regulatory consents such as a site licence from the Nuclear Installations
Inspectorate, giving an overall pre-construction timescale of
around five years.
Other preconstruction activities can be lengthy:
for example the Electricity Act 1989 requires developers to seek
development consent from the Secretary of State (in England and
Wales) or Scottish Ministers (in Scotland) for the construction
of electricity generating stations over 50MW. Recent UK experience
suggests this process typically takes two to three years (which
may include a public inquiry).
Construction periods are much more technology
dependent. Typical durations are[21]:
4 years
Gas
2-3 years
Nuclear
5 years
Wind
1-2 years
What are the likely construction and on-going
operating costs of different large-scale technologies (eg nuclear
new build, CCGT, clean coal, on-shore wind, off-shore wind, wave
and tidal) in terms of the total investment required and in terms
of the likely costs of generation (p/kWh)? Over what timescale
could they become operational?
There are a large number of comparative studies
on the economics of nuclear and other generation sources. These
often come to different conclusions, due to nation-specific considerations
(such as costs of fossil fuels in different regions, or availability
of high quality renewable resources) or due to different financial
assumptions (for instance the rate of return required on an investment).
One recent wide-ranging study was carried out
by OECD[22]
taking data from a large number of different countries around
the world. The results of this are summarised in the following
chart, and showed that even without any allowance for the future
costs associated with carbon emissions, nuclear is extremely competitive
with fossil fuels and is much cheaper than the leading renewables:
The OECD study was an international one. The
most recent authoritative investigation into UK prices for different
forms of power was carried out by the Royal Academy of Engineering
(RAE), and published in March 2004[23].
The results of this study are summarised in the following chart:
In this figure, the dark magenta additions to
the wind power costs represent an allowance for the backup power
generation required due to the variability of wind output. It
can be seen that nuclear energy emerged from this assessment as
being closely competitive with CCGT gas plants, with these two
being the cheapest options. However, it should be recognised that
the long-term gas price forecast used in the study was 23 pence
per therm, compared to current forward prices for 2006 and 2007,
which are in excess of 55 pence per therm[24].
In terms of the breakdown of costs for the various
technology options, a good assessment of these can be found in
the RAE report, and we do not propose to go into detail here in
respect of technologies other than nuclear.
There are again many studies into the costs
of nuclear energy, with some of the most recent ones24, [25],
[26],
[27],
[28],
[29],
[30],
[31]
summarised in the following table.
| MT
(2003)
| PIU
(2002) | Chicago
(2004)
| RAE
(2004) | DGEMP
(2005)
| Finland
(2003) | OECD (2005)
|
Generating cost (p/ kWh) | 3.9-4.0
| 3.0-4.0 | 3.1-3.6 | 2.26-2.44
| 2.0 | 1.7 | 1.3-1.9
| 1.8-3.0 |
Rates of return | 11.5% | 8% & 15%
| 12.5% | 7.5% | 8%
| 5% | 5% | 10%
|
Capital cost | $2000/ kW |
$2000/ kW | $1500/ kW | $2000/ kW
| $1413/ kW | $1900/ kW | $1000-$200/ kW
|
| (£1150/ kW) | (£1150/ kW)
| (£865/ kW) | (£1150/ kW)
| (£990/ kW) | (£1330/ kW)
| (£610-1210/ kW) |
Load factor | 85% | 75-80%
| 85% | >90% | >90%
| >90% | 85%
|
Economic life | 15 years |
20 years | 15 years | 25 & 40
years
| 35-50 years | 40 years | 40 years
|
Construction period | 5 years
| Not
identified | 5-7 years
| 5 years | 5 | 5 years
| 4-6 years |
| |
| | | |
| | |
Capital investment in a new nuclear power station would be
likely to be in the range £1-2 billion, depending on the
exact design selected and its generation capacity. Whilst this
is a substantial sum, it is by no means unusual for a major energy
infrastructure project. Liquefied Natural Gas (LNG) terminals
and oil platforms routinely cost more than this, as can major
pipelines. Many studies show "overnight" capital cost
per unit output of around $2,000 per kW of installed capacity
for a standard international reactor design, which would equate
to around £1.2 billion for a 1GW single unit power station
(using an exchange rate of £1 = $1.65).
Timeframes for delivery of different forms of generation
capacity were addressed earlier in this submission.
With regard to nuclear new build, how realistic and robust
are cost estimates in the light of past experience? What are the
hidden costs (eg waste, insurance, security) associated with nuclear?
Although the nuclear cost studies outlined above produced
a range of different projections for the generation cost of energy
from future nuclear stations, there is a consistent picture across
the assessments. The main parameters determining generation cost
are the "overnight" capital cost andin particularthe
rate of return assumed in the study. The majority of capital cost
projections fall in a relatively narrow range ($1,500 to $2,000
per kW), as noted above, and so it is the variations in rate of
return assumed in the different studies which accounts for the
majority of the difference in generating cost projections. This
is illustrated in the following figure, which summarises the cost
and rate of return data for the studies noted above:
When considering the overall cost-effectiveness of a future
nuclear plant project in the UK, past experience is not a good
guide to future performance. Previous nuclear industry projects
(like many other similar projects of their era) were characterised
by many of the following features:
They were run by Government in one form or another.
Virtually every design was markedly different
from its predecessors.
There were delays in the licensing and approvals
processes.
Construction contracts were often of the "cost
plus" type, offering no incentive (indeed a counter-incentive)
to delivery within time and budget.
Plants were often re-designed throughout construction,
leading to extra costs and delays.
There was no strong driver to improve operational
performance in regulated markets.
Only the UK chose to build gas cooled reactors,
technology that was less cost effective than the light water reactor
types chosen by the rest of the world. This decision also meant
that most of the world's accumulated nuclear industry experience
was not directly relevant for the UK.
Today's deregulated market would bring a very different framework
for building new power plants. In addition, the regulatory and
approvals processes in place in the past, which allowed delays
and re-design to become the norm, would act as a major deterrent
to private sector investors. An improved delivery process would
be required in future for a nuclear project to become a reality.
This is achievable without legislative change but Government leadership
is required to provide the necessary resolve. Such a process would
retain the rigorous scrutiny and opportunity for democratic participation
and challenge, but would have scope and timeframe clearly defined
to bring predictability to the overall process. This means that
key approvals need to be granted before construction with a well-defined
scope and timetable for further approvals during construction
and commissioning.
It is likely that any future UK plant would be an internationally
recognised standard design, and the approvals process would need
to be geared towards implementation of such a design with only
those UK-specific modifications which were absolutely essential.
International experience shows that nuclear plant projects
can be delivered on time and to budget, and can be the most cost
effective means of power generation. There is a strong and impressive
track record of series build of modern reactors in South Korea
and elsewhere in East Asia. Closer to home, Finland elected to
construct a new nuclear plant largely on the basis of the attractive
economics and the benefits in terms of reducing CO2 emissions.
To summarise the features of a future nuclear plant project,
which give confidence that its construction and operational costs
would be predictable:
Consolidation of nuclear reactor vendors through
the 1990s has led to the development of "standardised"
internationally recognised advanced designs. As these designs
incorporate many years construction and operating experience,
utilise proven technology, and robustly address the regulatory
issues that were previously of concern, there is much more confidence
in construction times and operational performance than hitherto.
Modern designs incorporate fewer components than
older reactor concepts which, together with modern construction
techniques such as modular construction, makes today's plants
more straightforward to build, as well as being significantly
smaller, both of which help to keep down capital costs.
In the Far East (China, Japan and South Korea),
the nuclear industry has demonstrated a good track record of delivering
these designs on time and within budget.
Development of improved materials for construction
allow more reliable operation at high levels of output.
Recent life extensions of operating plant in the
US demonstrate that the typical design lifetime for advanced light
water reactors of 60 years is realistic.
Reactors are now designed for improved maintainability
which reduces operating costs and increases overall output.
Nuclear plants around the world show very good
operational performance, with load factors of 85% and above[32].
Modern reactors make much more efficient use of
the fuel, and so produce much less waste than earlier designs.
In terms of robustness of generation costs over time, nuclear
offers a major benefit compared with fossil fuel alternatives.
The cost of uranium accounts for only around 5-10% of the overall
generating cost of electricity from nuclear, compared with electricity
from gas, where the raw gas cost accounts for over 60% of the
overall generation costs. Total nuclear fuel costs (including
enrichment and fuel fabrication, as well as the uranium costs)
are only around 20% of total generating costs. In the current
era of rising fossil fuel prices, with strong links between the
price of gas and that of oil, with global increases in demand
and with the UK becoming increasingly dependent on imported gas,
the independence of nuclear energy from fossil fuel prices is
a notable benefit.
The implications of the high dependence of power from gas-fired
stations on the costs of gas itself can be seen from a look at
the recent trends in UK power prices. The following chart summarises
baseload power prices for the last few years[33]:
Uranium itself is a plentiful fuel around the world, and
over recent months there have been a series of new developments
in the field of uranium mining, indicating that reserves are likely
to rise from current levels. The issue of uranium availability
is discussed in more detail later, in the context of security
of supply.
With regard to the "hidden costs" mentioned in
the question, the position is as follows:
WasteThere are no hidden costs associated with
nuclear waste. Calculations of generating costs for replacement
reactor deployment in the UK include allowance for all waste handling,
treatment, packaging and disposal activities. The treatment of
nuclear waste, and the funding of waste management activities,
are discussed in more detail in the next section.
InsuranceUK nuclear power stations carry both
material damage and liability insurance. This insurance cover
is in place for every civil nuclear site in the UK. There is an
upper limit on the amount of insurance that operators are required
to have; currently this limit is £140 million as set in the
Nuclear Installations Act. This Act is, in turn, based on the
Paris Convention to which most European countries, including the
UK, are signatories.
Recent updates to the Paris convention increase the liability
limit to
700 million and it is expected that this will be enshrined in
UK legislation around the end of 2006 or early 2007. The UK insurance
industry is confident that they can provide this cover on a commercial
basis.
SecurityThe UK is already operating a fleet
of nuclear power stations which require robust and extensive security
measures to be applied. Security arrangements for the protection
and security of nuclear stations are independently regulated by
the Office for Civil Nuclear Security under the Nuclear Industries
Security Regulations (2003) that are based on international guidance
from the IAEA. The Government has established the Civil Nuclear
Constabulary, a statutory police force that provides armed protection
and response for the civil nuclear stations in the UK.
Importantly, the security measures that would be required
for any new build programme raise no new issues of principle or
policy. Any new stations would, just like the existing reactor
fleet, have extremely robust and resistant structures. Security
costs for new stations would therefore be at a similar level as
for existing stations.
Security costs are paid by the nuclear operators. They are
a minor part of overall operational and maintenance costs, typically
the operational costs for security measures are about 1.5% of
the total operating budget.
How do the waste and decommissioning costs of nuclear new build
relate to the costs of dealing with the current nuclear waste
legacy, and how confident can we be that the nuclear industry
would invest adequately in funds ring-fenced for future waste
disposal?
There is significant national and international experience
that provides assurance that waste from new reactors can be managed
safely and successfully. A distinction needs to be drawn between
wastes from new reactors and legacy wastes. New waste arisings,
as well as being small in volume, would be well characterised
and comparatively simple to manage. In contrast, some of the legacy
wastes, in some cases dating back to the 1950's, are chemically
and physically more complex and as a result are more difficult
to deal with.
These legacy wastes are being retrieved and packaged in a
way that makes them suitable for long-term storage or potential
disposal and the Government owners of the bulk of these wastes
(the Nuclear Decommissioning Authority (NDA)) have clear plans
and strategies in place for their management.
When looking at the potential waste arisings from new build,
it is important to see these in the context of the existing inventory[34]:
With or without any further reactors, the UK will need a
long term management route to be identified for the baseline high
and intermediate level waste inventory of 478,000 m3. The Committee
on Radioactive Waste Management (CoRWM) will recommend the long
term management route(s) for UK waste and spent fuel to Government
next July. The work they have published to date suggests that
deep disposal or interim surface storage will be the preferred
route.
The latest cost estimate from the NDA for management of the
legacy is around £56 billion (undiscounted total costs)[35].
It must be recognised that much of this cost relates to the safe
and effective retrieval of wastes from their current storage,
rather than directly to the treatment and management of the wastes.
International experience has demonstrated that waste management
costs from current power generation are a relatively small part
of total nuclear fuel cycle costs.[36]
There are well-established approaches to funding it in most countries.
Funds set aside now, and in the near future, would be expected
to earn reasonable rates of interest for many years before significant
draw-downs are required (eg for a geological repository, which
may not need to be in operation for decades). As a result, the
contributions required today can be modest. As examples, the USA
levies $0.001/kWh (
0.0008) on nuclear electricity production, whilst Sweden, Japan
and the Czech Republic are all similar in the range
0.001 to
0.002 per kWh. The size of the payments are generally kept under
review and increased (or decreased) if necessary, based on best
estimates of future costs. The money that accumulates is available
to pay for the packaging, transport and disposal of spent fuel
and Intermediate Level Waste.
Some countries without such levies require the waste producers
to set funding aside. For example, Switzerland has a government
controlled trust fund. Germany, where the funds already total
25-30 billion Euros, leaves the fund with the power utilities.
As in many other areas of waste management, Sweden offers
a useful model for consideration. The Swedish fund (established
in 1982) covers spent fuel encapsulation and disposal, nuclear
power station decommissioning and waste disposal, along with the
R&D necessary to implement all these activities.[37]
The fund is invested in the National Debt Office and overseen
by a board appointed by the government. The amount of money that
each contributor pays from year to year varies, depending on the
most recent estimates of future costs and how well the investments
made by the fund have performed. Cost estimates are produced by
the implementer, SKB, and submitted to the regulatory authority,
SKI, for review. Utilities must provide guarantees to compensate
for any fees which might not be paid into the fund if reactors
are shut down early (as is present Swedish government policy)
and if the costs of waste management prove higher, or are needed
earlier, than currently expected.
A similar model in the UK might be to require the operators
of new nuclear power stations to pay into a central fund, administered
(directly or indirectly) by the government. For a single reactor
of 1,000 MW output and a life of 60 years, the total fee paid,
if the levy was set at 0.1p/kWh, would amount to about £500
million, before accumulation of interest over the life of the
fund. With a return on investments of just 2%, this sum would
double over the 60 year lifetime of the reactor. It should also
be recognised that in specific circumstances it is possible to
take out insurance against any shortfall in funds.
For comparison, the estimated cost of the Finnish spent fuel
storage and disposal programme, to accommodate the fuel and waste
from four nuclear power stations is about £850 million. Sweden
estimates[38] that its
spent fuel encapsulation plant will cost about £600 million
and the spent fuel repository about £1,100 million. This
assumes that the 11 operational reactors operate for 40 years.
Together with the two reactors that have already closed, Sweden's
total nuclear installed capacity amounts to about 10 GWe, a very
similar value to that of the UK which totals almost 14 GWe for
historic stations and those that continue to operate.
Is there the technical and physical capacity for renewables
to deliver the scale of generation required? If there is the capacity,
are any policy changes required to enable it to do so?
We support the contribution renewable energy can make, but
we share the doubts of other observers over whether enough can
be donein a short enough timeto deliver the benefits
hoped for. The House of Lords Science and Technology Select Committee
studied this issue in detail recently[39]
and reported that they:
"found almost no one outside government who believed
that the White Paper targets [on renewables uptake by 2010] were
likely to be achieved"
Indeed, Government projections now appear to acknowledge
that the 2010 target to have 10% of electricity from renewables
is likely to be missed[40].
Confidence in longer-term targets being reached is therefore diminished.
If renewables generation were to deliver 10% of UK electricity
needs by 2010, this would equate to around 35 TWh. For comparison,
the power generated by renewables in 2004 was 14.2 TWh[41].
Of this, just 1.9 TWh came from wind (both onshore and offshore),
which is expected to be the dominant renewable technology over
the coming decade or so. Whilst there undoubtedly is enough wind
resource around the UK to underpin the 10% target, it is doubtful
that this will be achieved by 2010, given the difficulties being
experienced in respect of issues such as planning and securing
connection to the grid.
To meet this need for additional generation with wind turbines
(of a large 2MW design), would require close to 4,000 such turbines
to be built between now and 2010[42],
corresponding to a rate of over two turbines every day. If the
bulk are to be built offshore, that poses a further difficulty,
since offshore construction in areas such as the North Sea is
not possible year-round. Britain's two largest wind farms (North
Hoyle, off the North Wales coast and Scroby Sands, off the Norfolk
coast) each have 30 2MW turbines, so the progress needed is equivalent
to construction of a wind farm of this size every two weeks. Current
rates of construction are far below this figure (around 25MW per
month during the first eight months of 2005[43],
compared to the 120MW per month needed).
It is clear thatalthough the penetration of renewables
is increasing, a development which is to be warmly welcomedcurrent
policy is not delivering these technologies as quickly as was
hoped for. Given this, it seems that any policy changes ought
to be addressing to underlying objective of reducing carbon emissions,
rather than focusing on one specific means of contributing towards
this aim. We would urge the Government to provide encouragement
to all low-carbon technologies (renewables, nuclear, carbon capture
and storage, and energy efficiency).
What are the relative efficiencies of different generating
technologies? In particular, what contribution can micro-generation
(micro-CHP, micro-wind, PV) make, and how would it affect investment
in large-scale generating capacity?
In terms of efficiency, (net energy output expressed as a
percentage of the energy input) figures for a traditional coal-fired
power station are typically around 35-38%; a modern gas-fired
CCGT around 45-55%; a wind turbine between 20 and 40% (depending
on wind speed); a modern Pressurised Water Reactor (PWR) around
35% (taking as "input" the energy given out during fission);
a solar panel around 10%; and for a hydro station the mechanical
efficiency perhaps 80%. However, simply comparing efficiencies
is not really the best way of comparing different generation technologies
that use different energy sources (although it can be an appropriate
way of comparing different techniques that use the same energy
source, such as burning gas). For instance, wind is plentiful
and free, whereas conventional fuels have finite reserves and
are often in demand for many applications, so optimising their
usage may be seen as more important.
An additional way of looking at different technologies is
to examine their availability factors (the amount of power they
are able to deliver in a year as a proportion of what they would
provide if they operated continuously at full rated output). Baseload
power generation technologies (fossil fuels and nuclear) typically
have availability factors in the 80% to 90% range or even higher.
The figures fall short of 100% primarily due to the downtime associated
with scheduled maintenance shutdowns. In addition, for some fossil
stations (particularly gas) the actual load factor achieved may
be much less than the availability factor, due to load-following
operation, when the station is available to operate but demand
is not high enough to warrant it.
For nuclear power stations around the world, average load
factors have risen steadily over the past 15 years from around
80% to well over 85%. In many cases these improvements result
from sensible modern approaches to operating and maintenance and
to standardisation of fleets. In the US, progress has been much
more marked, due to the commercial pressures of operation in increasingly
competitive markets. Average levels there have risen over the
same timeframe from around 70% to over 90%. Nowadays, the best
reactors around the world routinely achieve load factors of well
over 90%.
Renewable energy has a vital role to play in helping to reduce
emission by producing carbon-free electricity, and by providing
sources of power which do not rely on imported fuel. However,
in one respect the picture for renewables is somewhat different
from other technologies, as the majority of renewable technologies
are inherently variable. Although they produce power for most
of the time, the amount of power produced varies according to
weather conditions. The bulk of future UK renewable generation
(at least in the medium term) is forecast to be wind energy, and
for wind (both on and offshore) typical load factors achieved
are 25% to 30%. These figures are higher than corresponding load
factors achieved in other countries, reflecting the fact that
the UK has some of the best wind resources anywhere in Europe.
For instancedata from Germany[44]which
has more wind capacity than any other country in the world, and
a more mature wind fleet than the UKindicates that the
average load factor achieved there by the 6000MW of capacity operated
by E.ON during 2003 was just 16%. In 2004 figures were slightly
higher[45]with
an average load factor of around 20%, but the figure was still
only 14% for half of the year.)
We have responded separately (and in rather more detail)
on the issues around micro-generation to the parallel DTI Consultation
on "Strategy for the Promotion of Microgeneration and the
Low Carbon Buildings Programme".
In summary, we support the concept of micro-generation and
the aims behind it, but we have doubts both over its likely rate
of uptake and over the effect it will have on the rest of the
electricity supply side if it does become a significant component
of the mix.
We believe that there needs to be a major cultural change
amongst householders and small businesses to underpin a substantial
move towards microgeneration in the UK, and that this is only
likely to take place slowly. There are currently concerns over
the scale of (and payback time for) the investment needed, the
responsibilities for care and maintenance of the equipment, andparticularly
for householders -the visual impact of the equipment along with
the impact on re-sale value of a property. The fact that the outlay
is a significant up-front payment, which does not lead to any
immediate functional benefit (in contrast withfor instancea
satellite TV dish, which carries similar cost and visual impact
issues), yet the benefits are only accrued over a long period
is likely to be a particular obstacle for householders.
Before microgeneration can realise its full potential, the
technology to allow export of power back to the grid (during times
of high output from the microgeneration equipment) needs to be
developed and deployed in parallel with the equipment itself.
New metering equipment and pricing policies will also need to
be developed, to allow for the fact homes and businesses with
such equipment will be both customers and suppliers. In addition,
when considering micro-CHP, it should be remembered that this
technology does still burn gas, and so still leads to the emission
of carbon dioxide, albeit in a way which makes more efficient
use of the fuel.
In terms of the impact of microgeneration on investment in
larger scale capacity, the widespread adoption of microgeneration
would tend to reduce the load factors of large generators, which
in turn would tend to encourage marginal plant to close and would
discourage investment in new capacity. If the microgeneration
capacity were well correlated with demand, this would not be a
major concern. However some microgeneration is poorly or inversely
correlated (for instance PV produces most power in summer, but
much less in winter, when demand is highest). This will tend to
result in reduced plant margins at peak periods, and so may reduce
overall security of supply. In addition, having a greater surplus
of power capacity at times of low demand means that the system
may not represent the most cost-effective overall scenario.
3. What is the attitude of financial institutions to investment
in different forms of generation?
What is the attitude of financial institutions to the risks
involved in nuclear new build and the scale of the investment
required? How does this compare with attitudes towards investment
in CCGT and renewables?
The scale of capital outlay for a nuclear plant is not a
major problem in itself for potential investors. As noted earlier,
the cost of a new nuclear power plant would typically be in the
range £1-2 billion, and such projectswhilst not commonplaceare
by no means unique in the energy infrastructure sector. Oil platforms,
pipelines and LNG facilities could all cost substantially more.
Investors however recognise two major areas of risk in a
potential nuclear plant project, which present real obstacles
to prospects for making a suitable return on the investment, and
therefore to prospects for such investment being deemed feasible.
The first is in respect of planning and regulatory approvals,
where the current framework provides little confidence on the
predictability of decision-making timescales.
However other power plant projects face many of the same
hurdles. Major fossil fuel generating plants often face long delays
at the planning stage, and planning difficulties represent one
of the major reasons why renewable energy progress has been less
dramatic than anticipated. For these reasons, the electricity
market has seen little investment in anything other than renewables
over the past few years, and the attractiveness of renewables
has been largely due to the revenue certainty that the Renewables
Obligation provides.
The second area of perceived risk for investors is unique
to the nuclear industry. It is in respect of waste policy, where
the lack of a clear policy is essentially an uncapped liability
for potential investors. This represents a significant deterrent,
and will prevent investment coming forward, in spite of the confidence
potential investors have in the conservative provisions they would
expect to make in respect of long term waste management costs.
It should also be noted that there has been very little investment
in any form of baseload generation capacity over the past few
years. This is due to a combination of over-capacity in the market
(following on from policies in the 1990s to encourage independent
power producers), and the relatively low (perhaps unrealistically
low) power prices which have prevailed as a result. Under these
circumstances, it is primarily renewable projects which have received
support and investment, due to the opportunity offered by the
Renewables Obligation. Utilities with conventional fossil plant
have preferred to "sweat" these assets (and in some
cases bring "mothballed" plant back into use) rather
than invest in new capacity. We are now approaching the point
where capacity is once again needed in order to maintain sufficient
margin, and (as noted earlier) market prices have risen sharply.
As a result, there are some early signs that investment is once
again starting to come forward in baseload plant projects.
How much Government financial support would be required to
facilitate private sector investment in nuclear new build? How
would such support be provided? How compatible is such support
with liberalised energy markets?
Any firm decision to invest in a new nuclear plant will clearly
be made under the prevailing market conditions (and projected
future conditions) at some time several years into the future.
Such a decision would depend on the detailed analysis undertaken
by private sector investor(s) of the economics of the project,
and on the way in which risk were to be shared between the various
participants in such a project.
However, two areas where Government support is essential
are already apparentalthough the support needed is not
financial. Government input is needed to bring confidence to the
decision making timescales for the regulatory and planning approvals
processes and to set a clear policy framework and implementation
strategy for the management of nuclear waste.
A clear indication from Government that it welcomes a new
generation of nuclear stations to replace the nuclear contribution
to the UK energy mix would provide valuable confidence to investors
that these issues would be effectively addressed.
With those two major barriers removed, and with some clearer
indication of what the longer term market for carbon dioxide allowances
(beyond 2012) might look like, it would be credible for nuclear
to be delivered within the UK climate.
In terms of compatibility with competitive markets, it is
right and appropriate that liberalised market frameworks are sufficiently
inclusive to allow all candidate technologies to compete. Provided
that the market framework also encourages delivery of the overall
policy objectives, such markets can then be relied upon to deliver
lowest cost solutions to achievement of these policy goals.
What impact would a major programme of investment in nuclear
have on investment in renewables and energy efficiency?
Provided that nuclear is not "picked" as a winner
in itself, but instead is delivered by the market as the lowest
cost option to balance CO2 targets and security of supply issues,
there should be no conflict with incentives to support other emission
reduction approaches such as renewables and energy efficiency.
As noted elsewhere, we believe that nuclear is needed alongside
renewables and energy efficiency in order to make the necessary
savings in carbon emissions in the medium to long term. These
options should not be seen simply as alternatives to one another.
However, if nuclear turns out to represent better value to
the UK taxpayer in terms of how to assure delivery of policy targets
than other options, then inevitably it will tend, to some extent,
to displace these options in the generation mix. In that context,
it is worth noting that a recent study by Oxera calculated that
nuclear represented a much less costly option than renewables
for the UK taxpayer in terms of delivering reductions in carbon
dioxide[46]. More recently
still, the Public Accounts Committee concluded[47]
that:
"The Renewables Obligation is currently at least four
times more expensive that the other means of reducing carbon dioxide
emissions currently used in the United Kingdom"
In any event, any energy saving measures that might still
be introduced by businesses and householders will be based on
cost-effectiveness, not on consideration of the generation mix
that delivers their supplies.
C. STRATEGIC BENEFITS
4. If nuclear new build requires Government financial
support, on what basis would such support be justified? What public
good(s) would it deliver?
Investment in nuclear, renewables and energy efficiency reduces
our reliance on fossil fuels. A recent study[48]
has suggested that this gives rise to a substantial hidden economic
benefit, in addition to the supply security and environmental
benefits discussed in more detail below. This arises because fossil-free
investments reduce the demand for, and hence the market prices
of, fossil fuels (relative to what they would be without the investment).
Fossil fuel price increases have a well-documented tendency to
suppress GDPso investments in non-fossil technologies help
to avoid these GDP losses, by putting downward pressure on fossil
fuel prices. The study concludes that this effect creates a substantial
macroeconomic benefit that is captured neither by the market nor
by private investors, and that ought to be taken into account
in societal valuation of non-fossil technologies. It estimates
in particular that the offset for nuclear is worth almost $800
per kilowatt of installed capacity. This would equate to a benefit
of close to £500 million for a single modern nuclear power
station, which would typically have a capacity of 1GW or above.
To what extent and over what timeframe would nuclear new build
reduce carbon emissions?
The contribution made by nuclear new build would depend on
the scale and timeframe of any new build programme. The contribution
would also depend on what assumptions are made regarding what
type of generation is being displaced by the nuclear generation.
An illustration of what could be achieved is shown in the
graph below. This assumes 10 new 1 GWe nuclear power stations
are built on a timetable of one new power station per year, with
each station operating for 60 years. It has been assumed that
the nuclear power stations will displace gas-fired generation,
with emissions of 0.4 MtCO2/TWh.
At their peak, for 50 years, these plant would generate 79
TWh annually, avoiding the emission of over 31 MtCO2 each year.
Over the entire 70 years period shown in the chart, these nuclear
stations would avoid the emission of nearly 1.9 billion tonnes
of carbon dioxide.
In comparison total UK carbon dioxide emissions for 2004
(including those from industry, transport and domestic use of
gas, etc) were around 580 million tonnes.
Yet, as noted earlier, today we see emission levels rising,
when we need to be making cuts. To put the scale of the challenge
into context in percentage termsthe UK has a target of
cutting carbon dioxide levels to 20% below 1990 levels by 2010.
Yetwith just six years to go, in 2004 the reduction in
emissions had only reached 4.2%, so more than three quarters of
the savings still need to be made. Indeed emission have risen
in each of the last two years, and are now higher than at any
time since 1996, as illustrated in the following chart[49].
It is clear that additional low carbon generation sources are
needed.
To what extent would nuclear new build contribute to security
of supply (ie keeping the lights on)?
Firstly, faced with a future electricity mix dominated by
gas and renewables, anything elseincluding nuclearcontributes
to increased diversity, which must of itself be helpful in reducing
risk. Without new stations, nuclear will be providing just 3%
of UK electricity in under 20 years time, compared with around
20% today.
Diversity is also important when considering the potential
for simultaneous closure of a whole fleet of generating capacity
for some "common mode" reason, for instance a technical
or political issue. Having a balanced mix means that the overall
system is much more resilient to such an event than if generation
were to be dominated by a single fuel type. Although such a move
cannot be explicitly ruled out for nuclear generation, it is worth
remembering that use of a standardised international design, with
a recognised pedigree built on many years of operational experience
of the key components ands systems, makes such an event much less
likely.
Reliable baseload generation is a key feature of nuclear
energynuclear stations operate round the clock, day in
and day out, irrespective of weather conditions. Apart from a
periodic and predictable maintenance shutdown, the stations operate
continuously at full power, providing the kind of baseload power
a leading 21 century economy demands.
Modern nuclear power stations need to be re-fuelled only
at infrequent intervals, typically every 12 to 18 months. Even
if a refuelling could not take place as scheduled, the reactor
could continue to operate for several months, albeit that the
maximum power output would slowly decline. Considerations of fuel
availability are therefore very different for a nuclear station
than for a coal or gas-fired station, where a continuous supply
of new fuel is required in order to generate electricity.
Furthermore, it is highly credible to retain strategic long-term
stocks of nuclear fuel, just in case there ever were to be any
sustained disruption to supply. The fabricated fuel to supply
a fleet of 10 new reactors (enough to supply 20% of UK electricity
needs) for a year would occupy only around 100 cubic metres. This
fuel could therefore be stored in a building no larger than a
very modestly-sized house.
Nevertheless it is still sensible to consider the availability
of uranium supplies and to ask whether this represents a realistic
risk of interruption that might lead to loss of power production.
The UK government has categorised nuclear energy as effectively
an indigenous source of electricity for the UK[50].
Some of the reasons for this are as follows.
Uranium is ubiquitous on the Earth, indeed it is approximately
as common as tin or zinc[51].
Uranium ores are found in plentiful quantities in many countries.
In particular, Australia and Canada are both major exporters,
as well as both having long histories of political stability.
Additional reserves are known to exist in Kazakhstan, South Africa,
Namibia and Russia. Independent assessment[52]
puts the scale of conventional uranium resources which are recoverable
for less than $130 per kg (a level which would have little impact
on overall nuclear generation costs) at around 11 million tonnes.
This is enough to last for around 170 years at current consumption
rates (much longer than the corresponding figures for oil and
gas). Looking at it another way, this would be enough to provide
a lifetime's fuel for all of today's nuclear reactors worldwide,
plus all those which might be built as far ahead as 2050, even
in a scenario where world nuclear capacity were to triple to 1200
GW by that date.
Uranium ore is imported to the UK and other countries, where
it is refined, enriched and converted into finished fuel. The
transport of uranium ore does not require specialised ships or
import facilities.
The diversity of source countries, the fact that several
of these nations have long and stable political histories, the
excellent track record of supply reliability, and the fact that
there are few infrastructure considerations means that sufficient
supplies of uranium to the UK can be considered to be assured.
The quantities of fuel involved for a nuclear plant are much
lower than for fossil-fuelled stations. Whilst a coal-fired power
station might consume several million tonnes of coal in a year,
a modern 1 GW nuclear station will typically require a few tens
of tonnes of fabricated fuel for each re-fuelling operation. As
noted earlier, this might only take place every 12 or 18 months.
Finally, again as noted earlier, nuclear energy also provides
valuable cost stability, as well as supply reliability. This is
because the cost of raw uranium ore accounts for only 5-10% of
the overall generating cost of electricity from nuclear stations,
whereas the cost of gas-fired generation is dominated by the cost
of the gas (which accounts for 60% or more of the full generating
cost). Increases in global market prices for fuel therefore have
a much greater impact on the costs of gas-fired generation than
they do on the costs of power from nuclear.
Is nuclear new build compatible with the Government's aims
on security and terrorism both within the UK and worldwide?
In today's society there is a wide range of potential terrorist
targets and it is important that the Government and organisations
alike consider the possible threats, consequences and contingency
plans that may prove necessary. The potential targets include
many aspects of the nation's activities on which we depend for
everyday life to proceed as normal. These therefore includeamongst
otherspublic transport systems, iconic and political targets,
and components of the infrastructure that provide important services
to the public and industry. This includes the energy and utility
industries, in the form of fuel import facilities, pipelines,
storage facilities, power stations and transmission systems and
in this context, it is appropriate to consider the physical security
of nuclear power stations, as one component of the national security
assessment.
Government aims to ensure the security of nuclear material,
nuclear licensed sites, sensitive nuclear information and those
working in the industry. These objectives are overseen by the
government's security regulator Office for Civil Nuclear Security.
The Director makes an annual report to the Minister on these matters.
In his 2005 report[53],
the Director continues to affirm confidence in the security provisions
of the nuclear industry and that the security measures applied
are proportionate to the threats faced.
Nuclear power stations are designed to be amongst the most
robust civil structures in the worldprimarily in order
to assure resilience against earthquakes, and to ensure that the
materials contained within are unable to escape in the event of
abnormal operation. This robustness also serves as strong protection
against external impact (malicious or otherwise), and in addition
stations have a multi-layered defence against possible terrorist
attacks. They are also subject to rigorous security arrangements
that include security vetting of all staff and contractors, identity
management and access control. As a result, their potential vulnerability
to terrorist or other malicious threats is minimised.
Modern reactors are built with massive reinforced concrete
shields and are designed to safely withstand extreme events, both
natural and manmade. Their structural resilience to earthquakes
and the thickness of the shielding make them extremely robust
against possible attack, for instance by hijacked passenger aircraft.
Detailed analysis has shown that penetration of the radioactive
core by an aircraft under such circumstances would not take place.
In addition to their physical robustness, modern nuclear
reactors are protected by extensive safety systems. The extent
and number of these systems is such that several systems would
need to be damaged, and no action taken by operators or emergency
responders, before a significant release of radioactivity to the
environment might occur. The design is such that it would be difficult
to defeat or damage enough of the systems to bring about a major
release of radioactivity. Emergency arrangements are in place
to immediately shutdown reactors in the event of a heightened
terrorist threat against them. These arrangements are regularly
tested.
5. In respect of these issues [Q 4], how does the nuclear
option compare with a major programme of investment in renewables,
microgeneration, and energy efficiency? How compatible are the
various options with each other and with the strategy set out
in the Energy White Paper?
There is no more obvious win/win/win generation option than
nuclear when looking at reducing carbon dioxide emissions, and
improving reliability of supply and electricity affordability,
when the scale of the benefits in each area is also considered.
Cost effective energy efficiency measures represent the only other
approach which can make simultaneous advances in the achievement
of all three of these objectives. Yet, as discussed earlier, energy
efficiency is unlikely to eliminate the need for new capacity
on the GW scale, whereas this is the scale of clean, reliable
and affordable supply which nuclear energy can offer.
Likewise there is no conflict with the 2003 Energy White
Paper strategy in having a substantial nuclear programme within
the future generation mix. Indeed we currently have around 20%
nuclear, and many of the other options are being promoted to sit
alongside this capacity. A balanced mix of technologies represents
a perfectly self-compatible approach and is also compatible with
the White Paper strategy. The White Paper was clear that the nuclear
option remained open, and recognised the low-carbon benefits of
nuclear, therefore nuclear is able to play a role in such a balanced
mix, alongside other technologies.
D. OTHER ISSUES
6. How carbon-free is nuclear energy? What level of carbon
emissions would be associated with (a) construction and (b) operation
of a new nuclear power station? How carbon-intensive is the mining
and processing of uranium ore?
Nuclear energy is a very low carbon form of generation. Its
lifecycle emissions per kilowatt-hour are similar to those from
renewable generation. This is the case even when emissions across
the full lifecycle of the nuclear industry are considered.
A comprehensive IAEA study[54]
shows both direct and indirect emissions for different generation
sources. This concluded that even the "high" end of
the range of emissions for nuclear energy is still almost a factor
of 20 lower than the best fossil fuelled plant (latest gas-fired
technology) and a factor of over 60 lower than older, coal-fired
technology. The "low" end of the nuclear range (representative
of more modern technology) shows a further improvement by more
than a factor of two on even this performance. This assessment
takes account of the emissions associated with all aspects of
the nuclear cycle globallyincluding the construction, operation
and decommissioning of nuclear power stations, as well as the
uranium mining and enrichment, and the manufacture and spent fuel
treatment of nuclear fuel.
A significant contribution to the emissions from nuclear
power generation is in the carbon content of the energy used in
the different processes of the fuel cycle. This is one reason
why emissions vary from site to site. For example, the enrichment
process is energy intensive (particularly if diffusion technology
is used as opposed to centrifuge enrichment). In the US electricity
from coal-fired stations is used to power the enrichment plant,
whereas in France the electricity used comes from nuclear power
plants. Consequently, the lifecycle emissions of nuclear power
plants using uranium enriched in France are lower than those from
plants using fuel enriched in the US.
The results of this study and two others into the lifecycle
emissions of different forms of generation are summarised below.
These results show that emissions for nuclear, wind and hydropower
are much lower than those of fossil fuels.
| Lifecycle Emissions gCO2/kWh
| | | |
|
| Nuclear | Wind
| Hydro | Gas |
Coal |
IAEA[55]
| 9-21 | 10-48 | 4-236
| 439-688 | 866-1306 |
International Journal of Risk Assessment & Management[56]
| 8.9 | 15 | 16
| Fossil fuels: 500-1200 |
Vattenfall[57]
| 3 | 10 | 5 |
409 | 696 |
| |
| | | |
The Vattenfall study includes a typical breakdown of emissions
for the different stages of the nuclear fuel cycle, shown below.
Stage of Nuclear Fuel Cycle
| Emissions
gCO2/kWh |
Extraction/leaching (mining) | 1.1
|
Conversion | 0.2 |
Enrichment | 0.1 |
Fuel Fabrication | 0.2 |
Operation of Nuclear Power Plant (NPP) |
0.2 |
Building & Decommissioning of NPP | 0.6
|
Waste Facility Operation | 0.4
|
Build/Decommissioning of Waste Plant | 0.1
|
| |
7. Should nuclear new build be conditional on the development
of scientifically and publicly acceptable solutions to the problems
of managing nuclear waste, as recommended in 2000 by the RCEP?
The importance of nuclear waste management, and the need
for scientific, political and public acceptance in respect of
this issue, should not be underestimated. A key factor in securing
such acceptance for any future nuclear build programme in the
UK must be confidence in the arrangements for the management of
spend fuel and wastes, and for reactor decommissioning. The absence
of disposal routes for higher activity radioactive wastes in the
UK is often cited as a barrier to such a programme. However, within
the nuclear industry waste management and decommissioning have
been carried out for over half a century in a safe and effective
manner.
Renewed confidence in this respect comes from Sir Anthony
Cleaver, Chairman of the Nuclear Decommissioning Authority, who
said in a recent radio interview:
"I think one of the first things anybody says when people
talk about a new generation is "do we know how to deal with
the legacy, do we understand what we're doing with waste?"
I think anybody who looks at this [NDA] strategy will see that
we really do have a coherent approach to it; we know how to handle
it and we have sensible plans that we can execute"
The argument that there should be no new nuclear build in
the UK until the waste disposal issue had been "solved"
originates from the RCEP report of 1976, under the Chairmanship
of Lord Flowers. That report58 concluded:
"There should be no commitment to a large programme of
nuclear fission power until it has been demonstrated beyond reasonable
doubt that a method exists to ensure the safe containment of long-lived
highly radioactive waste for the indefinite future".
Recently however59 Lord Flowers himself has concluded that
such a requirement has been achieved, and therefore is no longer
an obstacle to new nuclear build:
". . . a method to ensure safe disposal for the indefinite
futurenamely, underground storagehas been demonstrated
beyond reasonable doubt in other countries, especially Finland."
It is also important to recognise the scale of the waste
issue as it relates to potential new nuclear capacity. If, for
instance, the UK were to build a fleet of 10 modern reactors of
around 1GW each (such as the AP1000) and operate these for their
full design lifetime of 60 years, the additional waste produced
would occupy less than 10% of the volume occupied by wastes already
in existence, and being safely managed. A new fleet of power stations
on this scale would be sufficient to maintain the UK's share of
nuclear generation at 20 to 25% over this period.
In terms of identification of a final route for waste disposal,
there is an ongoing process within the UK to recommend and adopt
the most appropriate solution to the long-term management of such
wastes. This Committee on Radioactive Waste Management (CoRWM)
is scheduled to make recommendations to Government in 2006, from
a short-list of identified options. Given the depth and quality
of the work done to date by CoRWM, and the resulting confidence
that it will report as scheduled, it would be appropriate to take
steps now on the basis that a solution will have been identified
and adopted by the time a final decision comes to be made regarding
investment in any future nuclear power plant. If for any reason,
this turns out not to be the case, then no firm commitment to
build a new plant will be in place, and so the situation can be
reassessed at that point.
In summary, taking early steps to encourage new nuclear capacity
in the UK should not be contingent on further progress being made
on the waste issue.
23 September 2005
58 "Nuclear Power and the Environment"; Royal
Commission on Environmental PollutionSixth Report (Chairman
Sir Brian Flowersas he then was); 1976.
59 Hansard; 12 January 2005; Column 331.
14
"The Heren Report"; Data: 1 April 2004-24.4
p/therm, 14 September 2005-54.4 p/therm. Back
15
Adapted from "Second Annual Report on the Implementation
of the Energy White Paper"; DTI/DEFRA; July 2005. Back
16
Digest of UK Energy Statistics (DUKES)-Table 5.5; DTI;
2005. Back
17
"Budget 2004 and Energy"; Environmental Audit
Committee, HC 490; August 2004. Back
18
"The long lead times for commissioning new generating
capacity mean that the Department [DTI] now needs to decide urgently
which forms of generation to support and in what ways."
from "Department of Trade and Industry: Renewable Energy";
House of Commons Committee of Public Accounts HC 413; September
2005. Back
19
"Secretary Of State's First Report To Parliament On Security
Of Gas And Electricity Supply In Great Britain"; DTI;
July 2005. Back
20
British Wind Energy Association website; http://www.britishwindenergy.co.uk/ukwed/planning.asp Back
21
"Projected costs of generating electricity, 2005 update";
International Energy Agency; 2005. Back
22
"Projected Costs of Generating Electricity";
OECD/NEA/IEA; 2005 [Data converted to sterling based on £1
= $1.65, the rate used in the OECD study. Data also excludes Japan
and the Netherlands, for which estimated costs differed significantly
from the average.] Back
23
"The Cost of Generating Electricity"; Royal
Academy of Engineering; 2004. Back
24
"The Heren Report"; values from 8 September
2005. Back
25
"The Future of Nuclear Power"; MIT; 2003. Back
26
"The Economics of Nuclear Power"; Performance
and Innovation Unit Energy Review Working Paper; 2002. Back
27
"The Economic Future of Nuclear Power"; University
of Chicago; 2004 [Data converted to sterling based on £1
= $1.734 (exchange rate used in RAE study)]. Back
28
"The Cost of Generating Electricity"; Royal
Academy of Engineering; 2004. Back
29
"Reference Costs for Power Generation"; French
Ministry of Economy, Finance & Industry; 2003 [Data converted
to sterling based on 1EUR = £0.70 (Bloomberg, 10 March 2005)]. Back
30
"Competitiveness Comparison of the Electricity Production
Alternatives"; Lappeenranta University of Technology,
Finland; 2003. Back
31
"Projected Costs of Generating Electricity";
OECD/NEA/IEA; 2005 [Data converted to sterling based on £1
= $1.65. Data also excludes Japan and the Netherlands for which
estimated costs differed significantly from the average]. Back
32
"2004 Performance Indicators"; World Association
of Nuclear Operators; 2005 http://www.wano.org.uk/Performance
Indicators/PI_Trifold/PI_2004_TriFold.pdf Back
33
Data from "The Heren Report". Back
34
"CoRWM's Radioactive Waste and Materials Inventory-July
2005"; CoRWM Document No 1279; July 2005. Back
35
"NDA Draft Strategy-Appendix 4"; Nuclear Decommissioning
Authority; 11 August 2005. Back
36
Typically, the back-end costs of nuclear electricity generation
are only about 5 to 10% of the total costs-about half the fuel
costs, for example "Nuclear Electricity Generation: What
Are the External Costs?", NEA, 2003 ISBN 92-64-02153-1,
OECD/NEA, Paris http://www.nea.fr/html/ndd/reports/2003/nea4372-generation.pdf Back
37
"Plan 2003. Costs for management of the radioactive waste
products from nuclear power production". Svensk Karnbranslehantering
AB, July 2003. SKB Report TR-03-11. http://www/skb.se Back
38
http://www/skb.se Back
39
"Renewable Energy: Practicalities"; Fourth Report
by the House of Lords Science and Technology Select Committee;
July 2004. Back
40
". . . well over 5% . . ." of UK power to come
from renewables by 2009; Parliamentary Answer from Mike O'Brien;
Hansard-Column 650W; 19 October 2004. Back
41
Digest of UK Energy Statistics-Table 7.4; DTI. Back
42
An additional 20TWh of annual output is equivalent to a continuous
supply of 2.28GW. At a load factor of 30%, this requires 7.6GW
of capacity, equivalent to 3800 2MW turbines. Back
43
British Wind Energy Association website; http://www.bwea.com/ukwed/operational.asp;
Data from 12 September 2005. Back
44
"Wind Report 2004"; E.ON Netz; 2004. Back
45
"Wind Report 2005"; E.ON Netz; 2005. Back
46
"Plugging the Carbon Productivity Gap"; Oxera;
July 2005. Back
47
"Department of Trade and Industry: Renewable Energy";
House of Commons Committee of Public Accounts HC 413; September
2005. Back
48
"Exploiting the Oil-GDP Effect to Support Renewables
Deployment; SPRU Electronic Working Paper Series, Paper No 129,
Awerbuch, S & Sauter, R; January 2005. Awerbuch, S and R Sauter
(2005), "Exploiting the Oil-GDP Effect to Support Renewables
Deployment", SPRU Electronic Working Paper Series, Paper
No 129, January 2005. Back
49
"Second Annual Report on the Implementation of the Energy
White Paper"; DTI/DEFRA; July 2005. Back
50
For example-"The Energy Review"; Performance
and Innovation Unit; February 2002. Back
51
"Supply of Uranium"; World Nuclear Association
Information and Issue Brief; August 2004 (http://world-nuclear.org/info/inf75.htm) Back
52
"Uranium 2003-Resources, Production and Demand"
(The "Red Book"); OECD. Back
53
"The State of Security in the Civil Nuclear Industry
and the Effectiveness of Security Regulation: April 2004 to March
2005"; OCNS; July 2005. Back
54
IAEA Bulletin 42 (2) 2000. Back
55
IAEA Bulletin 42 (2) 2000. Back
56
Joop F van de Vate, International Journal of Risk Assessment
and Management 2002-Vol 3, No 1 pp 59-74. Back
57
57 Life-Cycle Assessment Vattenfall's Electricity In Sweden, Eng
30966_Lca_Divk, 2005. Back
|