Memorandum submitted by nef (the new economics
foundation)
CONTENTS
1. | Outline
|
2. | nef (the new economics foundation)
|
3. | Summary and proposed comprehensive energy path assessment grid
|
4. | The prospects for nuclear power
|
5. | The real costs of nuclear power and comparisons with renewable options
|
1. OUTLINE
1.1 This evidence particularly addresses aspects of inquiry
issues: B: Financial Costs and Investment Considerations.
1.2 The evidence is organised into three sections:
3.Summary and proposed comprehensive energy path assessment grid
4.The prospects for nuclear power
4.2 Current development plans
4.4 Cost reduction through "learning and
scale"
4.6 Timescale and nuclear's ability to tackle
climate change
4.7 Costs and hidden emissions
4.8 The problems of insurance
4.9 Questions of supply and cutting greenhouse
gases
4.12 Clarity, information and public message
management
5. The real costs of nuclear power and comparisons with renewable
options
5.3 Energy costs and learning curves
In addition,this evidence includes the following tables and figures:
4.The prospects for nuclear power
Table 1: Power stations in the UK
5.The real costs of nuclear power and comparisons with renewable
options
Figure 1: Preferences between nuclear and
renewable energy at equal prices (2002)
Figure 2: Learning curve and cost reductions
for nuclear and renewable energy
Figure 3: Projected electricity generation
cost, 2020
Figure 4: Cost of carbon saving, 2020
Figure 5: The escalating cost of nuclear
power (excluding insurance, pollution and terrorist risk)
Table 2: Job creation in the energy production
industries
2. NEF (THE
NEW ECONOMICS
FOUNDATION)
2.1 nef (the new economics foundation) independent
"think and do" tank that believes in economics as if
people and the planet mattered. nef's work focuses on key
policy areas including energy, climate change and international
financial and trade issues.
2.2 Andrew Simms is Policy Director and head of the Climate
Change programme at nef. Andrew is a board member of The
Energy and Resources Institute (TERI) Europe. His publications
include several reports on climate change, globalisation and localisation,
and development issues. He has been a regular contributor to the
International Red Cross's annual World Disasters Report, and his
book Ecological debt: the health of the planet and the wealth
of nations was published in Spring 2005.
2.3 David Woodward is Director of Global and National
Economies at nef. David has worked for the Foreign and
Commonwealth Office as an economic advisor, as technical assistant
to the UK Executive Director to the IMF and World Bank; research
coordinator on debt for Save the Children (UK); and development
economist in the Strategy Unit of the World Health Organisation.
3. SUMMARY
Nuclear power has been promoted as a solution to climate
change and an answer to energy security. On the basis of nef's
analysis it is neither. On the one hand, as a response to global
warming it is too slow, too expensive and too limited. On the
other hand, it is more of a security risk in an age of terror-related
threats, than a security solution.
In spite of newspaper headlines suggesting a come-back for
nuclear power, this evidence finds no substance to claims that
it has an increased role to play in a flexible, safe, secure,
and climate friendly energy supply system. These, in fact, are
the characteristics of renewable energy, which is abundant and
cheap to harvest both in the UK and globally. Successive investigations
by government and parliament have come to similar conclusions.
The opposite conclusion is only possible if renewable energy technologies
are negatively misrepresented, and if the numerous weaknesses,
high costs and unsolved problems of nuclear power are glossed
over.
The Government is committed to "evidence-based policy".
This alone should rule out a nuclear comeback. The limited criteria
of cost and security are enough to direct the UK down the path
of renewable energy. By adding further, meaningful criteria to
an assessment of energy choices, such a decision is merely confirmed.
It is beyond the scope of this evidence to present a fully comprehensive
energy path analysis, but not beyond its scope to recommend that
such an analysis be carried out. The energy assessment grid below
illustrates what such an analysis should include (see Table below).
Cost and the economic return on investment are issues at
the top of many people's lists. Using unadjusted figures most
renewables can outperform nuclear power. Using more realistic
figures for the cost of nuclear power leaves renewables easily
the better choice.
Renewables are quicker to build and need less energy pumped
in for every unit of power subsequently generated. Because renewables,
pound for pound, also generate far more jobs than nuclear power,
they contribute much more to broad based economic development
both at home in the UK and abroad. Importantly, renewables leave
no legacy of radioactive waste that endures in the environment
for tens of thousands of years.
It is clear that a new wave of nuclear power stations could
only be built with some form of large public subsidy. But given
that the public purse has limited resources, the Government must
make the best investment on the taxpayers' behalf. In this case,
the danger is that the huge and unpredictable costs of nuclear
power will crowd out vital investment into renewable energy, as
it has done for decades already.
In order to re-level the economic playing field for renewables
two things are needed. First the Government should remove the
existing direct and indirect subsidies to nuclear power that "feather
bed" its prospects. Secondly, in order that they achieve
their full potential, public support to renewables should rise
to match the levels historically enjoyed by nuclear power.
In a recently issued manifesto the Renewable Power Association
(RPA) called for particular fiscal measures that would, it said,
deliver the best value for money. [230]These
include:
Extending Enhanced Capital Allowances to all renewables.
Reducing VAT on wood-fuel boilers and other domestic-scale
renewables.
Introducing Stamp Duty concessions for buildings
with renewables.
Enhancing tax allowances for all renewable investments.
A Cabinet-level Energy Minister.
A private members' bill on renewable energy, introduced earlier
this year by Lord Redesdale, called for all electricity suppliers
to be obliged to purchase electricity from microgenerators. It
went further to require local authorities to set targets for their
take up and categorise certain types of microgenerator as "permitted
developments", to ease their planning path at the local level.
[231]
On the international stage, there is the need for an International
Agency for Renewable Energy to represent the sector at the global
level and to balance the already-existing equivalent nuclear institutions.
An unacknowledged benefit of microgeneration is that it puts
people back in touch with where energy comes from. We have taken
fossil fuels for granted for too long, and ignored the importance
of living in balance with the ecosystems upon which we depend.
Renewable energy is a great reminder that also offers us the chance
for greater independence. It is possible that nuclear power has
only survived for as long as it has because its true costs have
been hidden from us, and because its waste and pollution are invisible.
The potential for a climate friendly, non-nuclear energy
supply system has been acknowledged by extensive research carried
out from across government, parliament, the Royal Commission on
Environmental Pollution, to the wider research community and civil
society. There is now an opportunity and a need to make it happen.
4. THE
PROSPECTS FOR
NUCLEAR POWER
A generation has grown up in Britain having
forgotten how and why the future of a once optimistic nuclear
energy sector became so tarnished. For that reason it is necessary
to revisit the industry's journey from post war promise, to become
a sector in decline, and why it is that nuclear power is now back
on the political agenda. If recent events are indicative, any
renewed official enthusiasm for nuclear power will face significant
obstacles.
Earlier this year days after Labour Government
officials seemed to be positively entertaining the prospect of
new nuclear generating capacity, news emerged of a leak of 20
tonnes of plutonium and uranium dissolved in nitric acid at the
Thorp reprocessing plant in Sellafield. Classified on the International
Nuclear Event Scale as a "serious incident", it was
a poignant reminder of the Windscale reactor firewhose
scale and impact were kept secret from the British public for
25 yearsan event that led to the plant being renamed Sellafield.
The contemporary leak resulted in calls from the EU Commission
for tougher safety standards. Soon after, it was reported that
the Nuclear Decommissioning Authority wanted Thorp to shut for
good. This was due partly to the fact that it was a loss-making
operation, and partly because the controversial nature of reprocessing
is seen within the industry as a potential barrier to winning
the argument for a new generation of reactors. [232]
4.1 Historical context
Discovered in the 1930s, nuclear fission was
later pioneered in the 1950s by the United States, the UK, France,
Canada and the former Soviet Union as a way of supplying electricity.
[233]
The UK's first nuclear power station was Calder
Hall in Cumbria, a Magnox gas-cooled reactor, which came on stream
in 1956. Several of these aging Magnox reactors are still in operation.
The design was also exported. DTI proudly cites the stations built
in Italy and the one in Japan, which is still operating. They
omit to mention that North Korea's current controversial nuclear
programme is based on these same early generation British-designed
Magnox plants. [234]France
used similar technology early on then later followed the US focus
on water-cooled reactors. In the 1960s Britain went on to develop
advanced gas-cooled reactors before opting for pressurised water
reactors (PWRs) in the 1970s.
Their development is instructive for the current
debate about the potential of nuclear power to ward off climate
change. A public inquiry into the UK's first PWR, Sizewell B in
Suffolk, ran from January 1983 to March 1985 and it wasn't until
14 February 1995 that it began operations. Prime Minister, Margaret
Thatcher, planned to build a whole series of new nuclear power
plants, but as the DTI observes, "Since Sizewell B, no further
nuclear reactors have been built or ordered in the UK."
When plans to privatise the electricity supply
sector were announced in 1988, nuclear power was left out of the
proposals. High capital costs of construction, decommissioning
and waste disposal were the main reasons. But the other problem
that beset the nuclear sector then and still does today was, according
to the DTI, the serious "uncertainties over the costs"
of financing new stations.
In 1994 the Government undertook a Review
of the Future Prospects for Nuclear Power in the UK. After
analysing the "economic and commercial viability of new nuclear
power stations", it concluded that public support, or "subsidy",
for building new stations would constitute a significant and unwarranted
intervention in the market.
In 2000, the final explicit subsidy to nuclear
power was removed and replaced with an obligation on UK energy
utilities to buy 3% of power from renewable sources. [235]There
are 31 operating reactors at 14 powers stations currently in the
UK. See Table 1.
Table 1
POWER STATIONS IN THE UK
BNFL Magnox |
Capacity MW | Published Lifetime
|
Calder Hall | 194 |
2003 |
Chapelcross | 196 | 2005
|
Sizewell A | 420 | 2006
|
Dungeness A | 450 | 2006
|
Oldbury | 434 | 2008
|
Wylfa | 980 | 2010
|
British Energy | Capacity MW
| Published lifetime |
Dungeness B | 1110 |
2008 |
Hartlepool | 1210 | 2014
|
Heysham 1 | 1150 | 2014
|
Heysham 2 | 1250 | 2023
|
Hinkley Point B | 1220 |
2011 |
Hunterston B | 1190 | 2011
|
Sizewell B | 1188 | 2035
|
Torness | 1250 | 2023
|
(source DTI)
The Government's Performance and Innovation Unit (PIU) published
a review of UK energy policy in February 2002. It concluded that
new sources of low cost, low carbon energy should be developed.
It called for renewables to play a central role, and left the
nuclear option open. [236]
In February 2003, the Government published its Energy White
Paper Our energy futurecreating a low carbon economy.
[237]It sets energy
efficiency and renewable energy as Government's priorities. The
White Paper says that, "while nuclear is currently an important
source of carbon free electricity [note: this is not factually
correct], the current economics of nuclear power make it an unattractive
option for new generating capacity and there are also important
issues for nuclear waste to be resolved." Consequently and
clearly ruling out the prospect of any future public subsidy,
the DTI notes that, "In common with all generation options,
the initiative for bringing forward proposals to construct new
nuclear plant lies with the market and the generating companies".
So it was with an apparently strong contradiction that the
Government came to the aid of the financially crippled nuclear
sector in 2002, supporting British Energy with a £650 million
credit facility. The European Commission challenged the UK Government
under its rules prohibiting state aid to industry. [238]
The timescale for nuclear phase-out suggests all Magnox reactors
will close by 2010 and, with some exceptions, Advanced Gas-Cooled
Reactors (AGRs) by 2020. This implies nuclear power's share of
generating capacity falling from its current level of 23% to 7%.[239]
In April 2005, the Government launched the Nuclear Decommissioning
Authority (NDA), to manage the task of cleaning up the contamination
left on the sites of the 40 nuclear reactors that have operated
in the UK. Very conservatively the costs are estimated at tens
of billions of pounds over the coming decades. [240]The
transfer of assets and liabilities from British Nuclear Fuels
(BNFL) to the NDA is considered to remove "polluter pays"-type
obligations from BNFL. As the State is providing an advantage
to a company, the EC considers that it falls into the category
of potentially prohibited "state aid". An in-depth inquiry
has been instigated. [241]
4.2 Current development plans
Currently there is no active programme of new nuclear build
anywhere that electricity-generating markets have been liberalised.
[242]In the US no new
nuclear power stations have been ordered for over 25 years. In
Europe, Germany, Belgium, the Netherlands and Sweden are committed
to closing existing plants. Only one is being built in Western
Europe in Finland. If new build were to happen, the Westinghouse
Advanced Passive 1000 (AP1000) reactor is reportedly the most
likely candidate. [243]A
Government review of 2002 says that 20 years would be the minimum
timeframe to develop a programme using this technology, ruling
out any role for nuclear in cutting carbon emissions to control
global warming in the period in which the growing scientific consensus
dictates that action is essential.
In an attempt to escape the private sector's deep antipathy
toward the economic uncertainties of nuclear power, British Energy
is reported to be talking to city institutions about the possibility
of private funding for a nuclear-power building programme. Contrary
to past official assurances that there would be no new subsidy
to nuclear, the Treasury is also reportedly considering tax breaks
for private companies willing to support a new-build programme.
Such an approach would partly circumvent the twin barriers of
the Government's reluctance to use public cash directly, and British
Energy's lack of resources. [244]
British Energy is currently banned from operating any newly
built stations until 2010, because of the settlement terms resulting
from its brush with the European Commission after the Government's
credit bail-out. According to news reports, bankers have told
British Energy at London meetings that the "huge initial
costs of building nuclear stations, coupled with volatility in
the power market makes funding impossible" without a change
of government policy. [245]
4.3 The 2002 review
One of the problems of dealing with the strictly economic
aspects of choosing an energy path is the opaqueness of figures
offered by the nuclear industry. The 2002 report by the PIU lists
these reasons why the industry's figures about the costs at which
it could deliver new generation should be questioned: [246]
4.4 Cost reduction through "learning and scale"
The nuclear industry is over-optimistic about reducing costs
through "learning and scale effects":
The former because necessarily strict regulation
to do with the inherent dangers of nuclear materials, means that
it is unrealistic for the industry to "learn" substantially
from its mistakes, because a mistake in nuclear power terms might
be disastrous.
Even where possible "learning effects"
will be less for nuclear than renewable because, "Long lead
times for nuclear power mean that feedback from operating experience
is slower."
The latter "scale effects" would also
be constrained because, compared to the scale benefits for renewable
technologies, "The scope for economies of large-scale manufacturing
of components is less."
4.5 Construction costs
The nuclear industry is over-optimistic about construction
costs:
It claims that it can achieve costs below the
bottom of the range given in an assessment of nuclear's potential
by the International Energy Agency. But such an outcome would
depend on:
Achieving very high operating availability.
A series build of 10 identical reactors.
Short construction times; and regulatory stability.
The technology proposed for a new series of stations
is the AP 1000 which:
Is yet to be built anywhere in the world.
Carries "first-of-a-kind risks".
Comes at a time when no new stations have been
ordered in OECD Europe since 1993.
Performance will be difficult to guarantee at
proposed levels.
4.6 Timescale and nuclear's ability to tackle climate change
The earliest that new nuclear capacity could be introduced
means it can't tackle climate change:
Twenty years was considered to be the earliest
that a new generation of nuclear reactors of this type could be
introduced, whereas the scientific community say that action to
reduce greenhouse gas emissions is urgent with the next decade.
Given the sceptical tone of the PIU review and
the clear recommendations of the recent Energy White Paper in
2003, the question the industry has to answer is, what if anything
has changed in the intervening period to justify re-opening the
nuclear box?
4.6 Costs and hidden emissions
One of nuclear power's main problems is that it has proved
incompatible with any kind of market system for energy. Its high,
unpredictable costs and unknowable and potentially uncontainable
liabilities deter investors. Its inflexible method of power generation
renders the industry largely incapable of responding to changing
market conditions by varying output. The bailout of British Energy
in 2001 was attributed to a fluctuating market price that went
below nuclear power's operating cost, and to which the sector
could not respond by simply switching off reactors. [247]
Even the World Nuclear Organisation happily concedes that
when the external costs of various fuel cycles are studied, the
cost of wind power is up to four times cheaper than nuclear power.
[248]With reference
to the same methodology, however, they say that the external costs
of nuclearthose not to do with immediate generating costsare
much lower than most fossil fuels. However, specialists in the
measurement of ecological footprints say that the footprint of
nuclear power is at least equal to many fossil fuels. Footprint
analysts Best Foot Forward comment, "The losses through Chernobyl
alone suggest a footprint per nuclear energy unit larger than
that of fossil fuel. Life cycle studies of nuclear energy also
reveal the fact that a substantial amount of pollution is produced
in the production and processing of nuclear materials and the
construction of power stations." [249]
According to the US-based Nuclear Information and Resource
Service, the fossil fuel intensive processes involved in uranium
mining, conversion, enrichment, transport and construction of
power stations, mean that, "Nuclear power produces direct
and indirect emissions of 73 to 230 grams of CO2 per
kWh electricity." [250]
4.7 The problem of insurance
The nuclear power industry is underinsured. The limited insurance
it does have is effectively subsidised by public funds. The nuclear
industry is unable to get commercial insurance cover and governments
have had to step in, taking on the burden instead. This is a substantial,
and largely hidden subsidy to the industry. [251]
In several countries the law sets a maximum liability for
any nuclear facility, regardless of what the real economic, human
and environmental costs of an accident will be. Under the Canadian
Nuclear Liability Act the limit for an installation is CAD$75
million and is underwritten by the federal government. [252]In
the United States, coverage for a "catastrophic nuclear accident"
is set in law under the Price-Anderson Act of 1957 at a much larger
US$9 billion, although this too has been labelled "inadequate".[253]
Arguing for the industry to meet more of its own insurance costs,
Senate Democrat and chair of the Senate's Transportation, Infrastructure
and Nuclear Safety subcommittee Harry Reid said, during negotiations
to renew legislation for the insurance programme, "We cannot
allow nuclear power plants to operate without adequate insurance."
[254]
The 11 September attacks on New York and Washington raised
fears about the vulnerability of nuclear installations to attack.
In response American Nuclear Insurers, which administers the industry's
collective insurance pool, limited the industry individual operator's
liability to $200 million. In the US, such a government-backed
insurance programme for industry is considered unique to nuclear.
To put these figures into context, the Ukraine estimated
in 1998 that, up to that point in time, it had lost between $120
and $130 billion thanks to the Chernobyl disaster over a decade
earlier, whilst neighbouring Belarus estimated its economic loss
at $35 billion. Of course the damage from that one incident spread
much wider and, for example, still affects the hill farmers of
Wales today. [255]Figures
released in 2004 in response to Parliamentary questions by Labour
MP Llew Smith, showed continuing damage to sheep farming in the
UK from the fallout from Chernobyl. [256]In
North Wales restrictions remained at 359 farms covering 53,000
hectares; [257]in west
Cumbria in England, near Sellafield, nine farms were still affected
covering 12,100ha; [258]in
Northern Ireland, in Counties Antrim and Londonderry, 153 farms
covering 8,752ha were still affected; [259]and
in SW and central Scotland, 14 farms covering 16,300ha remained
affected. [260]
In terms of the international communities' ability to respond
to major nuclear accidents, the Chernobyl case is instructive.
A limited plan to manage the contaminated accident site was pulled
together in 1996 known as the International Shelter Project. It
was estimated to cost $758 million, not including the costs of
actual fuel removal or the decommissioning and decontamination
of the site. G7 nations pledged to contribute $300 million towards
the $758 million cost, topped up by a further $37 million from
40 other countries, together making up less than half the total
estimated cost. [261]
The insurance circumstances of the nuclear industry represent
a double subsidy. Firstly installations are underinsured, and
secondly the state ultimately picks up the bill. As the retired
Royal Navy Commander Robert Green, (who navigated nuclear strike
aircraft during two decades of service) observed, "No commercial
insurance company has ever insured either nuclear-powered merchant
ships (which were all economic failures) or electricity generation
plants, because a worst-case accident, like the 1986 Chernobyl
reactor explosion, cannot be ruled out." [262]
The insurance industry's deep antipathy towards the nuclear
sector was underlined by a call in 2003 from Swiss Re for contracts
to be rewritten and laws to be changed to explicitly remove any
exposure of the insurance and reinsurance sector to the nuclear
industry. [263]
4.8 Questions of supply and cutting greenhouse gases
People rarely consider the question of finite resources in
relation to nuclear power but uranium is in limited supply. Given
current nuclear output one estimate from a body representing the
renewables industry suggests that uranium reserves will be depleted
in around four decades. [264]
But even the International Atomic Energy Agency (IAEA), a
UN body that promotes peaceful uses of nuclear power, cites known
conventional, recoverable resources of uranium at 4.6 million
tonnesenough to last only another 85 years at the rate
of use in 2002. It also observes "The period for which resources
are sufficient decreases the more nuclear power is assumed to
grow in the future." [265]
Another question is whether, even with a major building programme,
nuclear power could make much difference in terms of global greenhouse
gas emissions. The IAEA's 2004 review of the sector looked at
two different scenarios. In the first, in which no new nuclear
stations beyond those already planned get built, "Nuclear
power's share of global electricity generation decreases after
2010 to 12% in 2030, compared to 16% in 2002," meaning that
its relative contribution to fighting global warming falls also.
However, ironically, nuclear power's potential relative contribution
to reducing greenhouse emissions is even worse under the IAEA's
more optimistic high-growth scenario.
This is because the model takes account of the fact that
in order to pay for a major nuclear building programme there would
have to be high economic growth, which would still be largely
powered by even faster growth of fossil-fuel use. Hence the conclusion
that under the high nuclear growth scenario "generation steadily
increases by a total of 46% through 2020 and by 70% through 2030",
but, "overall electricity generation increases even faster
than nuclear power, causing nuclear power's share of overall electricity
to decline. By 2030 the nuclear share is down to 11%".[266]
Fast-breeder reactors are meant to solve the problem of limited
uranium supplies, but they require much higher energy "investments".
As the UK Atomic Energy Authority wrote in 1989, "In practice,
it is now not clear how [the use of fast breeders] would be achieved
on an expanded global scale without encountering basic plutonium
shortages, not to mention serious problems with waste disposal,
power plant decommissioning and nuclear weapons proliferation."
[267]
If fuel supply was not a problem there is another one. Margaret
Thatcher as Prime Minister planned 10 new nuclear power stations
and managed only one. In the context of declining global oil and
gas production, to meet unmanaged growth in energy demand, would
require an unfeasibly large programme of new build. According
to one estimate between 2015 and 2040, 1,700 stations would be
required. [268]Add
to that the new demand to provide the energy necessary for the
global economy to grow at 2% beyond 2015, and another 5,000 stations
could be needed. Based on this estimate, over the 25-year period
up to 2040, approximately five new stations would need to open
every week. There would be significant problems in finding suitable
sites outside earthquake zones and where the cooling water would
not harm the marine environment, and where local opposition was
not strong. Given that most stations take ten years to build,
work would have to start almost immediately. [269]
Another estimate comes from the US-based Nuclear Information
and Resource Service (NIRS): to meet the IAEA's high-growth scenario
for nuclear power an average of 115 power stations of 1,000MW
would need to be constructed annually, with a new station opening
approximately every three days. [270]
A report on the Future of Nuclear Power, recently
published by MIT said that to increase nuclear power's share from
17% of world electricity to just 19% by 2050 would mean nearly
trebling nuclear capacity. Between 1,000 and 1,500 large nuclear
plants would have to be built worldwide. [271]
Even a report produced in 2004 by the IAEA to mark the 50th
anniversary of nuclear power conceded that nuclear power could
not stop climate change. In an interview Alan McDonald, an IAEA
energy analyst, admitted that, "Saying that nuclear power
can solve global warming by itself is way over the top."
[272]
4.9 Security
Global reinsurance giant Swiss Re cites three scenarios for
nuclear terrorism in the post 9/11 world: [273]
(1) A radiological dispersal device, otherwise known as
a "dirty bomb".
(2) Attack or sabotage on a nuclear installation.
http://www.dti.gov.uk/energy/nuclear/technology/history.shtml
(downloaded 21 Apr 2005).
Centre for Non-Proliferation Studies (CNS) at:
http://www.nti.org/db/profiles/dprk/nuc/fac/reactors/NKN_F_5mwrct_GO.html
http://www.dti.gov.uk/energy/nuclear/technology/history.shtml
(downloaded 21 April 2005).
http://www.bellona.no/en/energy/nuclear/sellafield/33726.html
(downloaded 20 April 2005).
Nuclear Decommissioning Authority (2004) "Nuclear Decommissioning
Authority publishes its 2005/06 Annual Plan", NDA Communications
Team.
http://www.feasta.org/events/debtconf/sleepwalking4.htmpanel1
(downloaded 6 Apr 05).
(3) An "improvised nuclear device", either taken
from military sources or "home made".
All imply long-term contamination and extremely high costs
in both human and financial terms.
So far, no convincing response has been given to this key
security question, which explains the nervousness of the insurance
industry. There are fears that the degree of new security measures
necessary to address such concerns, could, in themselves, represent
a victory for terrorism and lead to a police state. There is also
the problem of materials "leaking" to supply the market
for state sponsored nuclear proliferation. [274]
One recent estimate put the cost to BNFL of providing security
against terrorism, including armed police, at £50 million
per year. This is roughly the same as the total amount recently
allocated to a new wave and tidal development fund in the UK,
to be spread over several years.7[275]
Chernobyl demonstrated what happens when a reactor core is
penetrated without first having shut down safely. Private nuclear
industry calculations are understood to have shown that the effect
of a plane being flown into the Intermediate Level Waste stores
at Sellafield could result in 3,000 deaths within two days of
the attack. [276]
With the industry arguing the case for their own renaissance
in the context of climate change, there is another, ironic, potential
obstacle. The challenge of finding appropriate sites for new wind
farms is dwarfed by the task of choosing sites for new nuclear
reactors. Given public opposition, a common official fallback
position is to advocate building new reactors at existing nuclear
sites. However, following the sector's much-criticised "dilute
and disperse" approach to waste management, nearly all nuclear
plants are to be found on the coast. But as observed in a newsletter
produced by Defra, "With sea levels rising due to climate
change, this does not seem to be a good location." [277]
4.10 Waste
Britain has over 10,000 tonnes of radioactive waste, set
to increase 25-fold when current nuclear facilities are decommissioned.
Most high and intermediate level waste, around 90%, is in "unconditioned
form", not held in a form suitable for long-term storage.
[278]
The total amount of nuclear waste in the UK, including waste
generated over the next century from existing power stations and
their decommissioning, is 470,000 cubic metres when conditioned
and packagedenough to fill the Royal Albert Hall five times
over. The nuclear waste volumes can be divided as follows:
High level waste2,000 cubic metres.
Intermediate-level waste350,000 cubic metres.
Low-level waste30,000 cubic metres.
Spent fuel10,000 cubic metres.
Plutonium4,300 cubic metres.
Uranium75,000 cubic metres. [279]
On average, people in Britain live only 26 miles from a major
radioactive waste site, including power plants and military bases.
[280]
A recently released consultation document from The Committee
on Radioactive Waste Management (CORWM), based on an investigation
of different options over a period of 18 months, recommended that
waste should be either buried underground or stored temporarily
in facilities above ground in anticipation of better technologies.
No recommendation, however, is forthcoming on where these sites
should be located. 283[281]
The high cost of waste management was a factor in another
controversial government decision to do with the industry. In
order to help meet waste management costs, in late 2004 the UK
Government reversed a 30-year-old policy to not store foreign
intermediate-level nuclear waste on British soil. But where the
new waste from Japan, Germany, Italy, Spain, Sweden and Switzerland
will be stored is unclear. Many observers believe that the current
storage site at Drigg, near Sellafield in Cumbria is nearly full.
[282]
Both sides are calling for a new debate about disposal of
nuclear waste. Along with the question of security and cost, waste
management remains a thorn in the industry's side. For example,
the UK Government faces court action from the European Commission
for safety failures and for having no reliable figure for the
amount of plutonium and uranium contained in waste tanks at Sellafield.
The problem goes to the heart of the technology: murky water in
the tanks and radiation prevent proper inspection of the content
of the holding tanks. When the problem came to light, a national
newspaper commented that, "The European court of justice
could in theory levy unlimited fines on the UK for failing to
comply with Euratom safeguards to prevent diversion of nuclear
material for military purposes." [283]
4.11 Clarity, information and public message management
Shortly after Margaret Thatcher became Prime Minister she
announced a plan to build 10 new nuclear power stations. In spite
of her extraordinary grasp on power in Britain, as mentioned above,
just one was commissioned. With peculiar symmetry, shortly after
Tony Blair was re-elected in 2005, a Whitehall plan was leaked,
appearing to allow for a series of ten new nuclear power stations.
In the event, according to former ministerial advisor Tom Burke,
it turned out to be merely one of numerous options papers produced
"like confetti" for incoming ministers. [284]
But the return of nuclear power to public debate didn't just
happen. It has been carefully engineered. Over the course of the
previous year a range of bodies representing the industry invested
heavily in new staff and capacity to engage in a press and public
affairs. A combination of British Energy, the Nuclear Decommissioning
Agency, the UK Atomic Energy Authority (UKAEA) and the Nuclear
Industry Association used a range of strategies and newly employed
lobbyists to try to revive debate about the industry's prospects.
[285]Even nef was
invited to become part of the process in the build up to the political
party conference season in 2005 by a public relations firm, Grayling
Political Strategy, taken on by the UKAEA. In spite of such efforts,
it seems the most important audience is yet to be convinced. This
year only 15% of the senior management of Britain's energy utilities
expected current reactors to be replaced. [286]
5. THE REAL
COSTS OF
NUCLEAR POWER
AND COMPARISONS
WITH RENEWABLE
OPTIONS
According to the PIU, British Energy (BE) and BNFL estimate
the costs of nuclear generation at between 2.2 and 3.0p/kWh. Having
criticised the over-optimism of many of their assumptions, PIU
proposes a range of 2.2-5.0p/kWh as more realistic, with a narrower
range of 3-4p.
However, this range appears too low, and unrealistically
narrow for new technology that remains untested. Even if the BNFL
and BE assumptions are accepted, the 2.2p/kWh figure is the lowest
estimate for the eighth reactor to be built in a series
of new build, which presupposes the construction of seven previous
reactors at highest cost; and it is based on a 20-year plant lifetime.
Using the PIU's standard assumptions of an 8-15% discount rate
and 15-year plant lifetime, even with an optimistic view of the
reduction in costs between the first and eighth units, BE and
BNFL estimates imply an average cost for all eight reactors between
3.1 and 4.3p/kWh.
However, the PIU highlights reasons beyond vested interests,
to believe that these figures themselves are an under-estimate.
The following adjustments are based on the PIU figures for sensitivity
analysis. However, since these are themselves based on an 11%
cost of capital and a 20-year plant life, they are adjusted by
+/-10% to correct and bring them broadly into line with the standard
PIU assumptions.
First, BE/BNFL estimates of construction costs are below
the lower end of the range of IEA estimates for expected construction
costs of new nuclear capacity in seven OECD countries ($1,518-$2,521/kW).
Based on the PIU's own sensitivity analysis, this suggests an
increase in the upper end of the UK cost scale in excess of 1.1-1.3p/kWh.
The estimated £100-300 million of additional "first-of-a-kind"
costs excluded from the BNFL and BE figures, if spread across
eight reactors, would add up to a further 4% (approximately) to
construction costs, and up to 0.07p/kWh to the overall cost.
It should also be noted that these estimates are based heavily
on "engineering judgements", in which the lower limits
to the costs of producing certain types of structure are directly
estimated. In other words, while the lower end of the range is
a minimum, there is much greater potential for upside risk.
Past experience of nuclear powerparticularly in the
UKsuggests that such risks may be very considerable. Dungeness
B, for example, took 23 years to complete instead of five years,
resulting in a construction period longer than its productive
life, while construction costs were more than 400% above the original
projection. If this were repeated, it would increase the price
per kWh by around 11-12p/Kh. A moderately cautious estimate of
potential time and cost overruns (five years' delay and 50% cost
overrun) would increase the upper end of the cost range by a further
1.5-1.8p/kWh.
Together, these considerations suggest additional costs of
0.1-3.2p/kWh, increasing the cost range to 3.2-7.5p/kWh.
BE/BNFL also assume operating availability substantially
above the IEA's estimate of the current average OECD lifetime
performance (75-80%). Interpreting "substantially" as
a margin of 5-10%, and lowering the assumption to the IEA estimate
would increase all costs (including additional costs based on
the sensitivity analysis) by 5.3-11.1%. This further increases
the range to 3.4-8.3p/kWh.
By comparison, if the industry estimate of 2.5-3.0p/kWh were
under-estimated by the same margin as its 1995 estimate (3.5p/kWh)
compared with the actual cost (6p/kWh), the true range would be
4.3-5.2p/kWh.
5.1 Timing
PIU suggests a planning/construction period in the order
of a decade for each nuclear planta figure that may prove
optimistic in the light of the controversy of planning applications
and past experience of delays in construction. This suggests that
electricity supply would come on-stream no earlier than mid-2015,
even if the planning period began immediately.
However, there are a number of reasons to expect substantial
further delays. Recent official briefings suggest that even an
initial decision to pursue a nuclear option is far from immediately
likely and possibly very far away, if it exists at all. Such an
option has been, and remains highly controversial. Popular opinion
towards nuclear power is roughly equally divided between supporters,
opponents and undecided. [287]An
added complication is the absence of a policy on nuclear waste
disposal, and the finding of the Royal Commission on Energy Policy
that new nuclear construction should not be permitted until this
issue has been resolved to the satisfaction of the scientific
community, and the public at large.
In view of these considerations, it seems unlikely that production
will begin until at least 2020, and possibly well after this.
This has two very important implications. First, it means that
new nuclear capacity cannot contribute significantly, if at all,
to the 20% reduction in carbon emissions required between now
and 2020. Secondly, it means that the relevant cost comparison
is not with the cost of renewable (or non-renewable) energy sources
now, but in around 2020after any cost reductions resulting
from increased economies of scale and learning-curve effects in
the meantime.
In fact, the delay could extend considerably further into
the future. In 1981, the Monopolies and Mergers Commission (now
the Competition Commission), deploring the performance of CEGB
with respect to AGR plants such as Dungeness B drew the following
conclusion:
"Again with hindsight it is clear from the views we have
received that work on the AGRs has been at the frontiers of technology.
The implication of this is that there were many components of
the AGR which could not be fully tested before full-scale operation
began, nor were relationships between the variables in the design
sufficiently understood even to allow simulation of certain potentially
damaging conditions. Nevertheless a full-scale prototype AGR was
not built before proceeding to the programme. It is the CEGB's
policy not to repeat that mistake in the current proposals for
the future nuclear programme."
(Competition Commission, formerly the Monopolies and Mergers
Commission, 1981)
Avoiding this mistake with AP1000 technology might reduce
the risk of construction delays (although construction of Dungeness
B took a further ten years after the completion of Hinkley Point
B). However, it would delay the process by around another ten
years, to 2030 or later.
5.2 Externalities
The PIU explicitly excludes consideration of unpriced externalities.
Taking account of these could add considerably more to the economic
cost of nuclear power, and to its financial cost if mechanisms
were introduced to price them.
For example, there is the question of the insurance of nuclear
installations, explored above. This is a cost borne largely by
the State, which in the UK accepts liability for insurance costs
above £140 million, and is therefore an uncounted subsidy.
Secondly there is the issue that the limits set on insurance liability,
where costs from major nuclear accidents are unlimited, represents
a second subsidy passed onto the environment and wider community.
The nuclear industry assumes that these costs are of minimal value,
in which case the question remains, why should the nuclear industry
not be insured at going market rates, and if the costs really
are minimal why is the industry not prepared to take them on?
The risk of theft of nuclear materials, for example by terrorists,
is also ignored. Given the increased level of perceived risk since
9/11, this is a serious omission. Again, it should be included
in the calculations, and valued at the commercial cost of insurance
against 100% liability for the damage caused. This would add significantly
to costs. Additional security costs for storage and transport
of inputs and waste could also increase costs significantly.
An indication of the existence of such uncompensated externalities
is the public preference for renewable energy over nuclear power,
excluding price effects. Asked by MORI in July 2002 about their
preferences between the two, if the cost of either option were
equal, 72% expressed a preference for renewables, and only 6%
for nuclear (see Figure 1).
Figure 1
PREFERENCES BETWEEN NUCLEAR AND RENEWABLE ENERGY AT EQUAL
PRICES (2002)
Source: MORI (2002)
"Renewable Energy Wins Support From British Public"[288]
5.3 Energy costs and learning curves
A more positive externality arises from learning effectsthe
progressive reduction in costs arising from gaining experience
in production. However, these effects are relatively limited in
the case of nuclear power. While learning effects are typically
in the order of 10-30% for each doubling of cumulative production,
and 5-25% for the energy sector as a whole the figure for nuclear
power is only 5.8%.[289]
There are a number of reasons for this:
Nuclear power stations are large, one-off projects,
which need to be individually designed according to local conditions.
This limits the scope for learning from one case to another, even
where the same technology is used.
The large scale of nuclear power stations means
that relatively few units are built; and the scope for standardisation
of components is more limited than in most other productive sectors
(including energy sub-sectors). The resulting short production
runs for components limits the potential for economies of scale
through increasing production.
As the current cases of Iran and North Korea demonstrate,
the potential for international sharing of learning is limited
by security considerations, and particularly concerns about nuclear
proliferation. Such concerns also limit the potential scope for
use of nuclear power as an alternative to fossil fuel use globally.
The gestation period of construction for a nuclear
power station is very longat best several yearsand
extended still further by an extensive planning and approval process,
necessary for safety reasons. This means that, where lessons are
learned which could reduce production costs, there is a considerable
built-in delay before they can be put into practice.
http://www.antenna.nl/wise/index.html?http://www.antenna.nl/wise/568/5405.html
(downloaded 18 Apr 2005).
www.bellona.no
IAEA (2003) "Guidance for the evaluation of innovative
nuclear reactors and fuel cycles: Report of Phase 1A of the International
Project on Innovative Nuclear Reactors and Fuel Cycles (INPRO)
" IAEA-TECDOC-1362, June. http://www-pub.iaea.org/MTCD/publications/PDF/te_1362_web.pdf
Learning is further delayed by the need for rigorous
safety assessments of any significant changes in technology or
design.
This is a critical issue. The diversification away from fossil
fuels is, by nature, a very long-term process. The implications
of current decisions for the future costs of non-carbon production
are therefore at least as important as the effects on current
energy costs. The relevant consideration, therefore, is not limited
to the immediate effect on energy prices, but the long-term effect
into the indefinite future of producing energy from alternative
non-carbon means.
By contrast, learning effects for renewable technologies
have been found to be much higheraround 18-20% for wind
and PV. This reflects the more conventional nature of the production
process, at least for wind and solar power, which is based on
the production of a much larger number of more standardised units,
with considerable scope both for learning and for economies of
scale.
However, these headline figures seriously understate the
scale of the differences they imply. In the case of renewable
energy sources, if cost falls by 18-20% for every doubling of
cumulative production, it will take an increase in cumulative
production by a factor of around 10 for costs to be halved. In
the case of nuclear energy, with a learning effect of 5.8%, costs
would be halved only when cumulative production had been increased
by a factor more than 3,000. To underline this crucial point,
it means that nuclear power is 300 times less efficient at lowering
its costs compared to renewables.
A further issue arising in comparing nuclear power with renewable
technologies, and particularly micro-renewables, is the relative
maturity of these sectors. Empirical work on learning effects
shows that cost reduction is proportional to the change in cumulative
production. Since nuclear power has been operating on a substantial
scale for half a century, new production increases cumulative
production by a relatively small amount. Thus the 5.8% learning
effect is applied to a relatively small number, limiting cost
reduction still further.
Most renewable technologies (except hydro), have thus far
been much smaller in scaleand microrenewables still more
so. As well as having much greater potential learning effects,
increases in their production are therefore substantially larger
relative to cumulative past production, so that these higher ratios
are also applied to substantially larger numbers. The result is
a much greater benefit in terms of reducing the cost of future
non-carbon energy production.
Thus there are two distinct factors, each of which makes
this consideration much more positive for microrenewables than
for nuclear: first, the nuclear learning curve is shallower than
that for microrenewables; and secondly that nuclear is further
along the curve, which becomes progressively shallower as production
increases (see Figure 2).
In other words, not only would halving nuclear prices require
an increase in cumulative production 300 times as great as that
for wind or PV, but the much greater production to date means
that it would take many times longer to increase cumulative production
by a given factor for nuclear than for renewables.
Even further, increasing the production of microrenewable
capacity by a factor of 10 is more than plausible; it is probable.
Increasing nuclear capacity by a factor 3,000, regardless of strictly
limited supplies of uranium, is highly improbable and more likely
impossible.
Figure 2
LEARNING CURVE AND COST REDUCTIONS FOR NUCLEAR AND RENEWABLE
ENERGY
First it should be noted that the starting point for learning-curve
effects, according to our calculations is that the real cost of
any new nuclear generation will be much higher than the industry-quoted
figures. In Figure 4 the curve marked N represents the cost of
producing electricity from nuclear power at a given level of cumulative
production, and R is the corresponding curve for renewables. R*
and N* show the current combination of cumulative production and
costs in the renewable and nuclear industries respectively. It
will be noted both that the N curve slopes down more slowly than
the R curve (reflecting the smaller learning effect), and that
N* is further along the curve than R*, so that the slope of the
curve is still shallower. The result is that if production of
renewables in a given year is Q, PR reduces the cost of production
substantially; but the same production from the nuclear sector
will reduce cost by a much smaller amount, PN.
Even though our figures show that renewables already generally
represent better value than nuclear on a range of criteria, there
is a still further powerful argument for much greater public investment
into research and development with regard to renewables and microgeneration.
According to analyst Robert Williams, "When new technologies
are introduced into markets, their costs tend to be higher than
the costs of the technologies they would displace. Early investments
are needed to `buy down' the costs of new technologies along their
experience, or learning, curves to levels at which the technologies
can be widely competitive. In principle, a firm introducing a
new technology should consider experience effects when deciding
how much to produce and consequently to `forward-price': that
is, it should initially sell at a loss to gain market share and
thereby maximize profit over the entire production period. In
the real world, however, the benefits of a firm's production experience
spill over to its competitors, so that the producing firm will
forward-price less than the optimal amount from a societal perspective.
That phenomenon provides a powerful rationale for public-sector
support of technology cost buy-downs." [290]
Figure 3
PROJECTED ELECTRICITY GENERATION COST, 2020
Source: PIU Energy Review (2002); DTI/ofgem (2004) Distributed
Generation Coordinating Group, PO2a Working Paper Three: The
Economics Value of Micro Generation, Technical Steering Group
(except nef/nuclearnef estimate)
Even based on the PIU's estimate of 3-4p/kWh for nuclear
power, offshore wind (2-3p/kWh) is at least as cheap, and could
cost as little as half as much; and onshore wind (1.5-2.5p/kWh)
is between 17% and 60% cheaper. Large CHP is also at least 33%
cheaper. The cost range for nuclear energy overlaps with those
for energy crops and mCHP, which may be slightly cheaper, and
with wave power which may be somewhat more expensive. However,
the corrected estimates for nuclear provided above suggest that
it will almost certainly be substantially more expensive than
any form of renewable energy with the exception of photovoltaic
(which remains substantially more expensive in the UK) and possibly
wave power.
Also included in Figure 3 are estimates for the cost of electricity
from microrenewable energy sources. The maximum cost is that estimated
by the Distributed Generation Coordinating Group Technical Steering
Group in November 2004; the minimum assumes cost reductions of
up to 50% by 2020 as a result of learning effects. These figures
suggest that micro-hydro is likely to be one of the lowest cost
sources of electricity in 2020. While the cost reduction assumption
may be over-optimistic in this case, it remains highly competitive
even at the maximum level (ie with no cost reduction).
The estimate cost range for micro-wind power is broadly comparable
with energy crops and the PIU estimates for nuclear power (though
well below our estimates for the latter). MicroPV, however, is
still more expensive than larger scale PV.
Figure 4
COST OF CARBON SAVING, 2020
Source: PIU
Energy Review (2002), Table 6.1 (except nef/nuclearnef
estimate; microwind/hydronef estimates based on P02a Working
Paper Three: The Economic Value of Micro Generation, Technical
Steering Group, DTI/ofgem (2004) Distributed Generation Co-ordinating
Group)
Figure 4 shows the corresponding figures for the cost of
carbon savings, in pounds per tonne (excluding PV). This suggests
that mCHP saves money as well as carbon, as may large-scale CHP,
onshore wind and micro-hydro. Offshore wind and micro-wind power
are in the middle of the range. Nuclear power is near the upper
end of the scale even on the PIU figures, equal with energy crops
at £70-200/tC, and cheaper only than wave power. On our revised
estimate for nuclear, the cost rises to a range broadly corresponding
with that of wave power (£110-430/tC), though still cheaper
than PV (£520-£1,250/tC), and considerably cheaper than
micro-PV (£1,450-£3,200/tC).
Figure 5 illustrates the effects of correcting the various
sources of under-estimation of the maximum cost of nuclear power.
Starting from the BNFL/BE estimate of 3p/kWh, averaging the costs
of the first eight reactors adds 1.3p/kWh, as does substituting
the IEA range for OECD construction costs, while "first-of-a-kind"
(FOAK) costs add about 0.1p/kWh, taking the figure to 5.7p/kWh.
Allowing for delays and cost-overruns could add a further 1.8p/kWh,
and lowering the assumed performance to current levels 0.8p/kWh,
taking the total to 8.3p/kWh177% above the BNFL/BE figure.
Table 2
JOB CREATION IN THE ENERGY PRODUCTION INDUSTRIES
Sector |
Jobsyear/TWh
(fuel production and power generation) |
Petroleum | 260 |
Offshore oil | 265 |
Natural gas | 250 |
Coal | 370 |
Nuclear | 75 |
Wood energy | 733 - 1,067
|
Hydro | 250 |
Mini hydro | 120 |
Wind | 918 - 2,400 |
Bioenergy (ie: sugarcane) | 3,711 - 5,392
|
Source: Goldemberg (2004) [291]
The nuclear industry is highly capital intensive and one
of the least labour intensive methods of energy generation. Due
to technological changes, any new cycle of nuclear power stations
would employ fewer people than existing plants. Renewable energy,
on the other hand, has rich potential for job creation.
The European Commission estimated that the predicted growth
in the renewable energy sector would create nearly one million
(900,000) new jobs by 2020, with at least 15,000 being created
in the UK. [292]
30 September 2005
230
Renew, Issue 155, NATTA, The Network for Alternative
Technology and Technology Assessment. Back
231
Ibid. Back
232
"Close nuclear leak plant for good says Sellafield",
The Observer, 15 May 2005. Back
233
DTI (2003) Nuclear power generation and the UK industry, Back
234
Marquand, R (2004) "North Korea's nukes: advanced, but
hidden", The Christian Science Monitor, 21 December
2004. Back
235
"British Energy planning new nuclear programme", The
Business, 27-28 March 2005. Back
236
Full report at: http://www.piu.gov.uk Back
237
http://www.dti.gov.uk/energy/whitepaper/index.shtml Back
238
DTI (2003) Nuclear power generation and the UK industry, Back
239
Evans A (2003) The Generation Gap, ippr: London. Back
240
"BNFL launches nuclear clean-up business", Bellona,
6 May 2004, Back
241
"UK nuclear industry is allegedly "cheating the market",
18 January 2005 www.bellona.no Back
242
Cabinet Office Performance and Innovation Unit (2002). Back
243
Evans, op cit. Back
244
"British Energy planning new nuclear programme", The
Business, 27-28 March 2005. Back
245
Ibid. Back
246
Cabinet Office Performance and Innovation Unit (2002), op
cit. Back
247
British Energy Planning new nuclear programme, The Business,
27-28 March 2005. Back
248
World Nuclear Association (2004) The Economics of Nuclear
Power, http://www.world-nuclear.org/info/inf02.htm (downloaded
21 April 2005). Back
249
"Best Foot Forward", www.bestfootforward.com/footfaq.html Back
250
Folkers, C. (August 2004), Nuclear power can't stop climate
change, (Nuclear Information and Resource Service, Washington
DC). Back
251
FEASTA, "Curing global crises: Let's treat the disease
and not the symptoms", Back
252
de la Chevrotiere, N. "New insurance subsidies for nuclear
industry", Bruce Centre for energy research and information,
(downloaded 3 March 2005). Back
253
United States Regulatory Commission, Nuclear Insurance and
Disaster Relief Funds-Fact Sheet, (Office of Public Affairs,
Washington DC). Back
254
"US nuclear insurance law faces Senate fight", Reuters,
25 January 2002. Back
255
"Neighbours count cost of Chernobyl disaster", BBC
Online, 26 April 1998. Back
256
Renew, Issue 153 Jan/Feb2005, NATTA, The Network for
Alternative Technology and Technology Assessment. Back
257
Hansard, 10 May 2004, column 98. Back
258
Hansard, 11 May 2004, column 208. Back
259
Hansard, 4 May 2004, column 1410. Back
260
Hansard, 13 May 2004, column 488. Back
261
Fact Sheet on the Accident at the Chernobyl Nuclear Power
Plant, December 2000, US Nuclear Regulatory Commission. Back
262
Green, R D. (2004) "Why the nuclear-powered ship ban must
stay", 17 February 2004, (Disarmament & Security Centre,
Aotearoa/New Zealand). Back
263
Andris, D, Galley, G, Reitsma, S and Walker, R. (2003) Nuclear
risks in property insurance and limitations of insurability, Swiss
Reinsurance Company. Back
264
See: World Council for Renewable Energy at: http://www.world-council-for-renewable-energy.org/ Back
265
Nuclear Technology Review 2004, (International Atomic
Energy Agency, Vienna). Back
266
Ibid. Back
267
Quoted in: FEASTA, "Curing global crises" op cit. Back
268
Ibid. Back
269
Ibid. Back
270
Folkers, op cit. Back
271
Quoted in: Renew, issue 154 Mar/Apr2005 http://eeru.open.ac.uk/natta/renewonline/rol54/13.htm Back
272
Lean, G. (2004) "Nuclear power can't stop climate change",
The Independent on Sunday, 27 June 2004. Back
273
Andris et al, op cit. Back
274
45 FEASTA, "Curing global crises" op cit. Back
275
Renew, issue 154, op cit. Back
276
Evans, op cit. Back
277
"Energy monitor", Renew, quoted in Energy,
resource, environmental and sustainable Management, May/June
2005 (defra, London). Back
278
WISE/NIRS, "UK neglects its `serious and urgent' nuclear
waste problem", 17 May 2002, Back
279
Committee on Radioactive Waste Management (2005) Learning
from the past-Listening for the future. How should the UK manage
radioactive waste? 2nd Consultation Document, CORWM: London. Back
280
BBC News, "Warning on nuclear waste disposal", 4 April
2005, http://news.bbc.co.uk/1/hi/sci/tech/4407421.stm (downloaded
18 April 2005). Back
281
Committee on Radioactive Waste Management (2005) op cit. Back
282
"In policy shift, UK says it will store nuclear waste from
foreign reprocessing customers", 21 December 2004, Back
283
"UK faces court action for nuclear safety failings",
The Guardian, 4 September 2004. Back
284
Burke, T (2005) "Plant life", The Guardian, 18
May 2005. Back
285
Leake, J and Box, D (2005) "The Nuclear charm offensive",
New Statesman, 23 May 2005. Back
286
Burke, op cit. Back
287
See MORI research at: http://www.mori.com/polls/2005/nda.shtml Back
288
MORI (2002) "Renewable Energy Wins Support From British
Public" http://www.mori.com/polls/2002/greenpeace-energy.shtml Back
289
Back
290
Williams, R. H. (2002) Facilitating Widespread Deployment
of Wind and Photovoltaic Technologies (Princeton Environmental
Institute, Princeton University, Princeton, N.J.), citing: Duke,
R and Kammen, D. "The economics of energy market transformation
programs", The Energy Journal, 20:15-64, 1999. http://ist-socrates.berkeley.edu/-kammen/dukekammen.pdf Back
291
Goldemberg, op cit. Back
292
European Commission, Directorate General for Energy, "The
impact of renewables on employment and economic growth (undated)". Back
|