Select Committee on Environment, Food and Rural Affairs Minutes of Evidence


Memorandum submitted by the Association of British Insurers

SUMMARY

  1.  The Environment Agency, and the Government more widely, has made good progress in the last few years in improving the effectiveness of flood management. Many of the factors enabling insurers to remain on cover for as many customers as possible are now being addressed. Key achievements include:

    —  Remaining on track to reduce flood risk for 80,000 households for the period April 2003-06 and contributing to the new target to improve the standard of protection for 100,000 households for the period April 2005-08.

    —  Streamlining flood defence committee structures and moving towards national procedures for the allocation of funding, removing the postcode lottery.

    —  Developing improved and accessible flood risk data for use by the public and by planners, insurers and lenders, with plans for further progress.

    —  Successful trialling of innovative, temporary and demountable flood defences to serve communities where conventional defences are not feasible.

    —  Transfer to the Agency of approximately 40% of ordinary watercourses representing greatest risk, with plans for completion by April 2006.

    —  Recognition that the Agency should take a strategic overview of all types of flooding, with important pilots on integrating urban drainage and sewage issues within catchment planning, and grant aid for householder action.

    —  Action to improve and extend flood warning systems, including the requirement to opt out.

  2.  Building on these successes, ABI believes that the Agency should now:

    —  Ensure that the flood defence database is complete and up-to-date, and medium term plans for investment are clear and accessible. (Urgent).

    —  Ensure procedures deliver maximum efficiency and effectiveness and clarify how savings will be used to cover inflationary costs over the 2004 spending review period. (Urgent).

    —  Ensure that its skills base is deployed to greatest effect, especially engineering staff, and that future needs are addressed.

    —  Work to achieve more effective action by the emergency services and by flood warning recipients once a flood is expected, to ensure life safety and that flood damages, including threats to the wider community, are minimised.

  3.  In addition, Government should enable the Agency to be more effective by:

    —  Strengthening the Agency's role in advising on planning decisions in flood risk areas in order to avoid increased flood risk through inappropriate development.

    —  Increasing investment levels by at least £30 million year on year in real terms, so that national flood risk is reduced despite growing risks from climate change and aging assets, together with improved measures of the overall effectiveness of spending.

DETAILED COMMENTARY ON THE WORK OF THE ENVIRONMENT AGENCY IN MANAGING FLOOD RISK

  4.  The Association of British Insurers (ABI) is the trade association for insurance companies operating in the UK. It represents over 400 members who, between them, account for over 94% of the general insurance business of UK insurance companies.

  5.  The insurance industry has a long history of close working with the Environment Agency and its predecessor, the National Rivers Authority. Over a decade ago the NRA and ABI collaborated in mapping the state of coastal defences and assessing the risk of failure or overtopping together with the resulting areas affected by coastal flooding. The events of Autumn 2000, which led to insurance claims exceeding £1billion, brought about a further strengthening of these ties as insurers sought action from Government that would enable insurance to continue to operate cost effectively in all areas of the UK, avoiding withdrawal with the resultant social and economic costs.

  6.  The ABI identified seven key areas for action, all of which impinge to some degree on the Environment Agency and its operations in England and Wales. These are:

    —  Greater and sustained investment in flood defences.

    —  Administrative streamlining.

    —  Improved land use planning.

    —  Better flood risk communication.

    —  Improved flood warning and emergency planning.

    —  Integrated land drainage planning, particularly in urban areas.

    —  Addressing chronic sewage flooding.

  7.  To date ABI members, who provide 95% of household insurance and 90% of commercial insurance in the UK, have been able to stay on cover for nearly all customers in most locations. Premiums and conditions will reflect the risk.

  8.  This paper sets out the ABI's views on the extent to which the Agency has been successful in addressing each of these critical concerns and identifies further action needed to ensure insurance remains sustainable in areas with high flood risk.

FLOOD DEFENCE INVESTMENT

  9.  Insurers were concerned that much of the damage sustained in the floods of 2000 was due to chronic under-investment in the defence system over many years. The ABI therefore welcomed the step change in investment announced in the 2002 spending review, enabling the Agency to put in place a more realistic programme to deliver better flood protection in England and, through consequential funding allocations to the Devolved Administrations, in Wales.

  10.  Over the period covered by the 2002 spending review, the Government's commitments on investment have been exceeded to date and Defra advises that it expects that the cumulative target at the end of the period will be exceeded. The ABI looks to the Agency to ensure that this investment is used to greatest effect through improved capital planning and rigorous assessment processes in allocating funding between new investment and maintenance programmes. We expect the Agency's reports to Parliament to enable a thorough scrutiny of the effectiveness of these processes.

  11.  Insurers are concerned that holding flood management expenditure at £564 million per annum in real terms will not, in the long term, be sufficient to meet the increased challenges that climate change and aging flood (especially coastal) defences bring. The ABI welcomes the Stern Review into the economics of climate change, announced by the Government on 13 October 2005. We expect the comprehensive spending review in 2007 to take account of the growing body of evidence on the significantly increased flood risks in future, estimated by the Foresight study on "Future Flooding" (2004) to at least double to £2 billion per annum, and possibly rise twenty-fold. This study calculated the need for an additional £30 million year on year (that is, cumulative) increases in investment to deal with climate related risks alone. The ABI is investigating the full future funding needs to contribute further to the evidence base, but consider it essential that, as a starting point, Foresight's findings should be reflected in Defra and the Agency's settlements with effect from 2007-08, in real terms. Without this rising investment we do not see how the Agency can deliver its remit in future.

Table 1

FLOOD MANAGEMENT EXPENDITURE (£ MILLION)
2003-042004-05 2005-062006-07 2007-08
Total Provision419478 570a570a570a
Total Spent432479
Made up of:
Defra "traditional" support for projects 125133169b 169b169b
Block grant to Environment Agency0 271330330 330
Local authorities and internal drainage boards 295c65c63 6363
Defra other expenditure10d 10d8d8d 8d
a  Includes some £6 million not included in the original SR2002 allocation.

b  Includes £15 million for "traditional" support and £5 million for EA block grant from Government to make good previously-expected income from new funding streams.

c  In addition local authorities used council tax to pay levies to Environment Agency that exceed ODPM support (an additional £21.2 million in 2003-04 and £14.4 million in 2004-05).

d  Including contribution to Ministry of Defence for Storm Tide Forecasting Service.


  12.  The ABI welcomed the Agency's innovative trials of both demountable and temporary flood defences in the Severn valley, enabling protection to be offered to communities where conventional engineered solutions are not feasible. In particular, insurers consider these measures invaluable in providing consistent standards of defence within communities where individual flood cells would otherwise receive markedly differing protection due to variations in cost:benefit returns. The ABI strongly supports the risk-based approach to decision making adopted by Defra and the Agency but recognises that communities, particularly small market towns, need coherent strategies if they are to remain vibrant and sustain local economic development.

  13.  Future developments should include more widespread adoption of these approaches, together with grant aiding of individual property protection measures (due to be trialled in 2006), so that small communities, and other properties in high risk areas difficult to defend, can also benefit from taxpayer investment in flood management. In taking these policies forward there needs to be a clear vision of the respective roles of the Agency and of local authorities in delivering and deploying these risk management measures. We would welcome a public debate, engaging all affected stakeholders, on these issues.

EFFICIENCY SAVINGS

  14.  In the 2004 spending review the Government gave commitments to sustain the level of investment at 2005-06 levels in real terms by recycling Environment Agency efficiency savings. These savings were to be used to cover inflationary increases in expected staff and construction costs over the period. In its latest Corporate Plan (2005-08), the Agency has set out an efficiency programme to deliver £15 million in savings each year through reducing the cost of decision-making, overheads and through better procurement methods. The Agency now needs to clarify how these efficiency savings will be monitored and used.

HOUSES PROTECTED

  15.  Defra predicts that the investment programme will deliver additional protection to at least 80,000 properties in England by March 2006, in line with its commitments (Table 2). Insurers are pleased that the Agency is currently on track to make a substantial contribution to achieving this target.

Table 2

PROPERTIES BENEFITING FROM IMPROVED FLOOD PROTECTION


Year
Households benefiting from improved
flood protection
Environment Agency contribution


2003-04
20,000 17,000
2004-0533,80030,000
2005-06 (estimate)40,000 30,000


TOTAL
93,800 77,000


  16.  Going forward, the Government plans to improve the standard of protection for at least 100,000 households during the period covered by the 2004 spending review. As the chief operating authority under the new funding arrangements, the Agency will continue to have a crucial role in delivering protection to 33,000 houses within this target. Insurers believe that some of the more innovative approaches described above will need to be more widely adopted if further progress is to be sustained in delivering greater protection to largely unprotected properties in future.

  17.  Insurers would like to see careful monitoring of the movement of properties between different risk bands (low, moderate, and significant) and the development of an appropriate target to ensure the correct balance between providing new defences for essentially undefended properties and enhancing defence standards for areas of high aggregation where the number of people, properties and extent of the local, regional or national economy affected by a flood would be substantial. This would strengthen the new output and performance measures for flood management, and associated targets, which will achieve the greater transparency and accountability the ABI sought in pressing for a strong role for the Agency in leading flood management operations.

ADMINISTRATIVE STREAMLINING

  18.  Funding problems prior to the 2002 spending review were exacerbated by complex funding and decision mechanisms, so that scarce resources could not be used to greatest effect. There was little transparency or accountability. Insurers welcomed the move to allocate the majority of flood management expenditure directly to the Agency by way of block grant, reducing bureaucracy and ensuring greater accountability.

  19.  The establishment of single tier regional flood defence committees from 1 April 2005 has reduced bureaucracy, enabling efficiency savings. Similar rationalisation of processes, introducing national (rather than regional) procedures and effective management information systems to enable better scrutiny, improving accountability and allowing appraisal of flood management strategies, should be pursued further. Once the Agency has established these improved systems, we believe Defra should devolve all decisions on flood schemes to the Agency, limiting Defra's oversight to audit functions.

  20.  Likewise the Agency, which on flood management issues is an executive agency of government, should leave policymaking to Defra and concentrate on policy delivery. The Agency's engineering expertise should be focused on delivering benefits on the ground. We understand that the Agency has been working closely with the Institute of Civil Engineers to ensure that additional trained personnel are available as the flood investment programme expands. More such resource will be needed as the challenges of climate change and aging assets are tackled, necessitating increased investment programmes in future. The ABI considers that historic swings in funding have undermined the development of engineering capacity in the UK, both public and private sector, and that sustained investment profiles, together with adequate national training strategies, are needed to avoid similar problems in the future.

  21.  The Agency's regional management tier should be concerned wholly with delivery, not strategy, and resources should be deployed according to a central strategy setting out current flood management priorities rather than perpetuating historic allocations through bottom up bids.

TRANSFER OF CRITICAL WATERCOURSES FROM LOCAL AUTHORITIES

  22.  Work on transferring responsibility for those watercourses representing the greatest flood risk—the so-called critical ordinary watercourses (COWs)—to the Agency is making slower progress than insurers had hoped (Table 3). We understand this is in part due to the need to negotiate the transfer of associated resources on an individual basis. Insurers are concerned that, since the inadequate management of flood risk seen on some of these watercourses in the past was often due to a lack of resources being devoted to the issue, this may have been an unnecessary distraction. We look forward to completion of the process by April 2006.

  23.  It is important that these flood sources, which often appear deceptively benign, are brought within the catchment management processes that only the Agency can co-ordinate. This should also enable better mapping and communication of local flood risks and avoid confusion over insurability, enabling local housing markets to function properly.

Table 3

PROGRESS ON TRANSFER OF COWs


Phase
Number of authorities1 Number of COW lengths


Achieved by 31 October 2004
     55   225
Achieved by 1 April 2005     97    464
To be achieved by 1 April 2006   137 1,062


1 Includes all operating authorities, not just local authorities.

DEVELOPMENT CONTROL AND PLANNING

  24.  The introduction of Planning Policy Guidance 25 on flood risk and development in 2001 by the Office of the Deputy Prime Minister (then Department of the Environment, Transport and the Regions) was a welcome step forward, mirroring stronger planning guidance already in place in Scotland (and since enhanced further).

  25.  After an initial improvement in responding to Agency objections (baseline 2001-02), performance now appears to be plateauing. In the last three years, local authorities approved around one fifth (or a total of around 1,000 cases) of all planning applications despite the Agency sustaining its objection (Table 4). Since planning authorities are not obliged currently to seek the Agency's advice, nor report back whether this advice has been heeded, the actual situation may be much worse. The Agency estimates it may be consulted on less than 60% of applications at risk of flooding. Not all planning decisions where the Agency has objected are reported back, although this proportion is said to have improved from around 40% in 2002-03.

Table 4

RESPONSES TO ENVIRONMENT AGENCY ADVICE ON PLANNING APPLICATIONS ON FLOOD RISK GROUNDS




2001-02 2002-03 2003-04


Number of planning applications requiring consideration by EA on flood risk grounds
24,138 20,452 22,067
Total EA objections made on flood risk grounds 2,500 4,523 5,077
Sustained objections on flood risk grounds (where outcome is known) 758 1,047 1,437
Proportion of applications going ahead against sustained objection 37% 21% 23%
Major developments going ahead contrary to EA advice 50 22 21



  26. Insurers would like to see PPG25 strengthened by:

    —  Making the Environment Agency a statutory consultee.

    —  Providing for the Secretary of State to call in applications that a local authority approves despite a sustained objection from the Agency.

    —  Clarifying the sequential test, using land at lowest flood risk first.

    —  Strengthening the requirement to include consideration of climate change impacts.

  27.  However the Agency will need to ensure that it can respond in a timely manner to the increased demand for advice that these measures would generate. The total number of planning applications requiring consideration by the Environment Agency on flood risk grounds has fallen significantly recently due to the adoption of national "standing advice", enabling local authorities to respond directly to planning applications for "lower risk" developments without case by case consultations. The Agency focuses on higher risk applications such as major developments. Insurers are concerned that this approach may lead to cumulative undermining of policy through inappropriate decisions on numerous small developments. Accordingly we support this risk-based approach provided:

    —  High quality strategic flood risk assessments are in place;

    —  Strategic planning frameworks steer designated development zones, sufficient to accommodate the major part of local and regional housing targets, away from areas identified in these assessments as being at flood risk; and

    —  National monitoring and reporting of the results of these "fast-tracked" decisions is in place, to ensure that the Agency's standing advice is being complied with.

  28.  In its initial response to the "Making Space For Water" consultation in March 2005, the Government announced its plans to review existing Planning Policy Guidance for flood risk areas (PPG25) and indicated that it was minded to give the Agency statutory consultee status. We are keen to see this and the other measures set out above put in place as soon as possible.

FLOOD RISK DATA

  29.  The Agency has made good progress in communicating flood risk through delivery of its flood mapping strategy.

  30.  Better catchment-wide modelling of flood risk, the inclusion of the effects of flood defence measures and other features (such as railway embankments) and upgrading of the website resource available to the public has ensured improved, more relevant flood risk information is accessible to all. Likewise insurers welcome the provision of the extreme flood outline to planning authorities, showing the extent of the floodplain facing 0.1% probability of flooding in current climatic conditions. We note that the planning guidance issued by the National Assembly for Wales requires planners to take account of future flood risk levels, incorporating climate change effects, and urge the Agency to provide similar information to planning authorities in England.

  31.  Insurers and lenders were provided with outputs from the National Flood Risk Assessment (NaFRA) modelling tool in October 2004. The quality of some information was questionable and no flood probability data was available for around 400,000 properties in flood risk areas. Improved data were provided in February 2005, but 260,000 properties still had no assigned flood probability. We hope that further improvements in modelling will enable these shortcomings to be addressed in the very near future, and that these improvements will also be reflected in the publicly available maps.

  32.  An essential part of this modelling, and other analyses underpinning strategic flood investment decisions, is a clear understanding of the standard and state of repair of existing flood defences and the areas they protect. At present the National Flood and Coastal Defence Database remains incomplete, although further information is available locally. It is essential that this central resource is completed and readily available to all stakeholders as a matter of urgency. In the future, medium term investment plans should also be made much more accessible, so that all stakeholders can ascertain relatively easily which areas will benefit from schemes in the future, the standards of protection these areas will benefit from and when the schemes will be complete.

FLOOD WARNING AND CONTINGENCY PLANNING

  33.  The Agency has a strategy in place to extend the flood warning system where sufficient warning can be given, although full delivery is some way off (the target is 78% of properties by 2008). This will not only make the service more widely available, and through a more extensive range of media, but will operate on an "opt out", rather than opt in basis. According to the Agency, currently only about 60% of those living in flood risk areas say they are aware of the risk, and of these only 60% have any pre-determined plans on action needed in the event of a flood. Insurers regard the inclusion of flood risk status in Home Information Packs as an essential step in ensuring better understanding and support Agency efforts to secure agreement from ODPM that this information should be required. Innovative approaches to engage the public in personal contingency planning are also needed.

  34.  The Agency is compiling a register of catchments where the potential speed, depth and velocity of flooding would cause extreme risk to life, a measure insurers fully support. Events such as the flooding in Carlisle on 8-9 January 2005 demonstrated the need for all first responders to such emergencies to have pre-agreed evacuation plans, including the identification of vulnerable people needing special assistance or medical support. Whilst it is for Defra to take the lead in amending its Lead Department Plan, we look to the Agency as the operational body to work with all emergency partners in improving capability and preparedness to deal with flooding emergencies.

  35.  The Civil Contingencies Act came into force in April 2005. The insurance industry is working with Government, including the Agency, to assist in effective responses beyond the initial emergency phase. The ABI welcomes this collaborative approach.

LAND DRAINAGE AND SEWER FLOODING

  36.  The ABI welcomes the inclusion of a more integrated approach to land management in the Government's strategy for flood risk management, set out in "Making Space for Water", and proposals for significant funding (£2 million) of studies in 2006 to develop integrated drainage partnerships.

  37.  Insurers welcome the leading role the Agency is taking in developing a strategic overview across all types of flood risk in urban areas. Given the Foresight study's estimate that the number of people at risk from flash flooding in urban areas could increase by up to 700,000 by the end of the century it is vital that decisions on infrastructure, which have a long legacy, take a holistic approach based on future flood risk. Integrated drainage pilots will help assess the underlying causes of flooding in urban areas, so that cost-effective solutions can be identified in each case. The Agency, together with Defra, should ensure that there is a clear mechanism set up to roll out the findings of these pilots.

  38.   Whilst sewage flooding is primarily a responsibility of the sewage undertakers, it is important that the Agency ensures urban drainage plans fully integrate sewer system needs and address problems arising from combined sewers and unprotected outfalls (from treatment plants) into watercourses.

Association of British Insurers

December 2005





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 11 May 2006