Select Committee on Environment, Food and Rural Affairs Minutes of Evidence


Further supplementary memorandum submitted by the Environment Agency

SUPPLEMENTARY MATERIAL

Q337 (transcript): Could you provide a figure for the costs involved in providing planning advice, specifically in relation to the number of planning applications and the potential increase in such applications?

  1.  Total costs associated with the Environment Agency's work in support of planning and development control are currently estimated to be around £8 million per annum. This covers the direct costs of the planning liaison workforce, IS/IT systems development and support, plus management support and overheads.

  2.  The Environment Agency responded to around 65,000 consultations from Local Planning Authorities (LPAs) in 2004, and around 54,000 in 2005. This reflects our focus on "higher risk" consultations (around 65% of workload) in order to free resource to deal with the expected rising workload of Local Development Frameworks.

  3.  We expect the number of higher risk, complex applications to continue to rise so that it becomes an ever-higher percentage of our workload as we reduce lower risk consultations through tools such as standing advice. Current trends indicate a workload of 50,000 per annum (almost all high risk and complex) by 2008. In 2005 we responded to almost 1,500 consultations on new style local plan documents, including sustainability appraisals. We expect this workload to rise steeply as increasing numbers of English LPAs start preparing their Local Development Frameworks under the new system.

  4.  As well as investing in IT, the Agency has recently taken the decision to increase its annual expenditure on planning staff in order to deal with rising complex workload and the expected increase in workload for local (strategic) plans. This will be reviewed as the reduction in strategic plan work, and the increased use of IT systems and e-Planning, allows us to reconsider resource use.

Q350 (transcript): The argument was about taking gravel from one side of a weir and putting it on the other side which might be a good bed for fish spawning, so why did the gravel have to be treated as waste?

  5.  During oral evidence we offered to provide more information on this issue. In the absence of a specific example from witnesses, we are providing some general information on our policy on gravel removal from rivers.

  6.  The Environment Agency has a policy on the removal of gravel from rivers. This states that we are generally against the removal of gravel, other than where specifically allowed for navigation or proven to be essential in specific locations for flood risk management or water supply purposes. We developed this policy to safeguard river geomorphology and channel habitats upon which many birds, invertebrates, plant communities and fish depend. We recognise that historic gravel dredging activities caused a legacy of problems including channel destabilisation, bank erosion, poor water and sediment quality and a consequent reduction in biological diversity. This is also why we would expect any proposal to move gravels within a river to be carefully evaluated to ensure that it is both sustainable and environmentally acceptable over the long term.

  7.  The question of whether gravel removed from a river is defined as waste would depend on the circumstances and the intentions of the person removing it. If the gravel is being sourced for another purpose then it may not be waste, whereas surplus gravel that needs to be discarded would be waste. As we do not know the case in question we are unable to speculate as to what might have been the problem. We do have an obligation to ensure that we provide all sectors with a consistent regulatory approach to definition of waste issues. This is not pursued dogmatically and we act mindful of public interest.

  8.  There are examples in "flashy" rivers (those that experience large and rapid changes in flow) where in-situ gravels become shifted over time and could beneficially be moved within the river to re-create riffles and spawning beds for fish. Under these circumstances the gravel would not be a waste.

Q355 (transcript): Can you provide some commentary on the process of risk assessment in terms of planning and flood protection?

  (Please note that in providing this response we have considered "planning" to mean the Town and Country Land Use Planning system and not the broader catchment planning aspects of flood risk.)

  9.  Planning Policy Guidance Note 25 (PPG25)—Development and Flood Risk, provides current Government guidance on risk assessment in terms of town and country planning and flood protection. PPG25 is currently under review and ODPM are consulting on Draft Planning Policy Statement 25 (PPS25) which strengthens the role of spatial planning in managing and reducing flood risk as well as the process by which flood risk is considered at all stages of planning. Draft PPS25 also strengthens the links between spatial planning, flood risk management planning and emergency planning. Catchment Flood Management Plans and Shoreline Management Plans are seen as providing essential information to and dialogue with the planning sector to deliver cross-organisation sustainable flood management.

  10.  PPG 25 and DRAFT PPS25 emphasise the need to adopt a precautionary approach to the issue of flood risk, avoiding it where possible and managing it elsewhere. The uncertainties inherent in flood prediction are recognised, together with the likely increase in flood risk due to climate change, which introduces even greater uncertainty. PPS25 also encourages Local Authorities to seek opportunities to reallocate existing development to areas of lower risk and utilise opportunities that regeneration and growth provides to reduce risk through making space for water. When allocating land in development plans or deciding applications for development at any particular location, those responsible for the decision are expected to demonstrate that there are no reasonable options available in a lower-risk category.

  11.  Local planning authorities should follow the sequential approach set out in PPG 25 (paragraph 30) as below:

    30.  The Government looks to local planning authorities to apply the risk-based approach to the preparation of development plans and their decisions on development control through a sequential test. Developers seeking sites for housing and other development should also have regard to this test. Accordingly, in drawing up or revising policies in development plans and in considering applications for development in cases where plans do not yet reflect the following, local planning authorities should give priority in allocating or permitting sites for development, in descending order to:

    (i)   areas with little or no potential risk of flooding (annual probability less than 0.1%)—These areas would have no constraints on development other than the need to try to secure that development does not increase run-off from the site to greater than that from the site in its undeveloped or presently developed state;

    (ii)  areas with low potential risk of flooding (annual probability between 0.1% and 1.0% for rivers, 0.1-0.5% for coastal areas) —These areas would be suitable for most development but essential civil infrastructure, such as hospitals, fire stations emergency depots etc, would require guaranteed access in times of emergency due to extreme flooding;

    (iii)   areas with high potential risk of flooding (annual probability greater than 1.0% for rivers, 0.5% for coastal areas), which are already extensively developed—In practice, large parts of these areas are likely be at only low to moderate risk of flooding because they are already adequately defended. These areas will generally be suitable for further residential, commercial and industrial uses, provided there are adequate flood defences, that buildings are designed to resist flooding, that there are suitable warning and evacuation procedures in place and that new development does not add to flood risk downstream. Such areas will generally not be suitable for essential civil emergency infrastructure unless access can be guaranteed in times of flood;

    (iv)   areas with high risk of flooding (annual probability greater than 1.0% for rivers, 0.5% for coastal areas), which are currently undeveloped, including the functional flood plains defined in paragraph 24—These areas are generally not suitable for residential, commercial and industrial uses unless a particular location is essential, eg for navigation and water-based recreation uses and essential transport and utilities infrastructure. Where residential and other uses are permitted they should be provided with adequate flood defences, be designed to resist flooding and suitable warning and evacuation procedures should be in place. Residential uses should generally be limited to job-related accommodation, such as caretakers and operational staff. General-purpose housing or other development comprising residential or institutional accommodation should not normally be permitted. However, exceptions may need to be made where extensive areas of land fall into this category, eg in low-lying parts of eastern England, and in other locations where alternative sites in areas at lower risk are not available. In such areas, further development may be needed to avoid social and economic stagnation or blight, or to allow existing development to be adequately protected. Authorities in these areas should, however, pay particular attention to design and mitigation issues and warning and evacuation arrangements, in full consultation with the Environment Agency, other operating authorities and the emergency services;

    (v)   areas at highest risk from flooding (including those areas behind defences that offer a standard of defence less than 1% for rivers or 0.5% for coastal areas or elsewhere, where there is a significant risk that failure could lead to rapid inundation by fast-flowing water) —These areas may be suitable for recreation, sport, amenity and conservation uses provided adequate warning and evacuation procedures are in place, and for essential transport and utilities infrastructure. Industrial, or commercial development should not normally be allowed. Further residential uses should only be permitted in wholly exceptional circumstances, where no alternative is possible, eg the operational uses noted in (iv) above, and these must be subject to fully suitable mitigation design and warning/evacuation conditions. There should be a general presumption against any extension of general-purpose residential land uses in such areas.

  12.  The new draft PPS25 strengthens the risk based sequential test by adding a new table D2 which considers land use vulnerability. Local Planning Authorities undertaking the sequential test are now steered to allocating land in lower flood risk areas first, and then ensuring that any development planned in areas of flood risk are compatible with that flood risk. Highly vulnerable developments, such as hospitals with A&E, Emergency services which need to operate at times of flood and sheltered accommodation, are "not to be permitted" in flood zone 3, high probability.

  13.  The new Draft PPS25 proposes an exception test as set out below:

  In areas where there are no alternative sites for development in lower risk areas because there are either constraints on those areas or because areas of higher risk are extensive, new development may well be essential to maintain the viability and vitality of the community and deliver sustainable development. The new exception test in PPS25 provides a way of managing flood risk in a transparent and consistent way so that necessary but safe development can go ahead in such areas.

  The exception test can be used where the sequential test has shown that it is not possible for the development to be located in zones of lower probability of flooding or the vulnerability of the proposed use needs further consideration. The exception test should be applied as early in the planning process as possible. In Local Development Documents it can be used to allocate the location of development and for drawing up criteria-based policies against which planning applications can be considered.

  14.  The exception test has four criteria, each of which must be satisfied:

    —  The development must make a positive contribution to sustainable communities;

    —  It is on developable brownfield land where this is available;

    —  A Flood Risk Assessment shows that the residual flood risks are acceptable and manageable within the general level of risk applicable to the area; and

    —  The development makes a positive contribution to reducing or managing flood risk in the area concerned.

  15.  Where development is proposed in a flood risk area (zone 2 and 3) or a development greater than 1ha for flood zone 1 (to take on-board surface water and increasing risk elsewhere), a Flood Risk Assessment (FRA) must be submitted with a planning application to ensure no inappropriate development takes place and that occupants remain safe in times of flood.

  16.  The Environment Agency is a statutory and non-statutory consultee for various elements of the spatial planning process. We are a "Key" consultee for the Regional Spatial Strategy and Local Development Framework processes, along with their associated Sustainability Appraisals. This allows us to ensure all new plans and strategies include appropriate policies on a number of key issues, including Flood Risk.

  17.  In addition, we are a statutory consultee for a number of individual planning applications, dependent on their type and/or location. These are set out in Article 10 of the General Development Procedure Order 1995. At present we are not a statutory consultee for flood risk, although we are a statutory consultee for "development involving the carrying out of works or operations in the bed of or on the banks of a river or stream". Local planning authorities are simply advised in PPG25 to consult us when an application for development raises flood risk issues. Most local authorities do appear to consult us, but there is a danger that we may not always be consulted when there is a flood risk issue. ODPM is at present consulting on a proposal to make us a statutory consultee when development is proposed in areas of flood risk as part of the PPS25 consultation package.

Do you consider the existing mechanisms of evaluating and responding to risk messages to be as good as they should be?

  18.  The principal method of evaluating and responding to risk messages is through the production of an appropriate Flood Risk Assessment (FRA).

  Whilst PPG25 (Appendix F) provides information on what an appropriate FRA should consider, our experience has shown that local authorities and developers constantly seek further guidance from the Environment Agency. ODPM plan to release a Practice Guide in support of the new PPS25 and this document will help provide more information and assistance.

  19.  Unfortunately, four years after the publication of PPG25, large numbers of consultations are still being submitted to local planning authorities (and then the Environment Agency) without an appropriate/satisfactory FRA. This deprives us of important information we need to determine our response to flood risk issues. The lack of a satisfactory FRA accounted for over half (53%) of all Environment Agency sustained objections on flood risk grounds to planning applications in 2004-05. Draft PPS25 however provides greater clarity and stronger policy on FRAs, requiring Regional FRAs and Strategic FRAs as part of Regional Spatial Strategies and Local Development Frameworks, and site-specific FRAs to accompany individual planning applications for development in flood risk areas. In addition ODPM are proposing to introduce a standard planning application form which would require developers to submit an appropriate FRA before a planning application could be registered.

  20.  Some local planning authorities continue to grant planning consents in flood risk areas where the Environment Agency has lodged a formal objection on flood risk grounds. ODPM are currently seeking views on proposals for a standing flooding direction in respect of major developments for which a planning authority proposes to grant permission, despite there being a sustained objection from the Environment Agency on flood risk grounds. If adopted, this standing flooding direction will help ensure appropriate responses to flood risk messages where new development is concerned.

  21.  There is always room for improvement in mechanisms and responses in respect of planning and flood risk. However, the proposed PPS25, together with Government, local authorities, developers and the Environment Agency learning from experience will all contribute to this goal.

ADDITIONAL QUESTIONS

1.   Why have 40% of permits issued to waste operators to meet the IPPC and Landfill Directives been subject to appeal?

  22.  Our records show that around 26% of the landfill permits determined have been subject to appeal. It should be noted that nearly 50% of the total number of landfill appeals were against our refusal to permit. Our revised generic landfill permit will lead to the majority of these operator appeals being largely resolved.

  23.  The landfill sector does have a high appeal rate compared with other sectors brought into IPPC. The transition of long-established landfills into a new style of regulation (PPC), whilst also needing to meet the tougher standards set down by the Landfill Directive was always going to be challenging for all concerned. Many existing sites are either not able to meet the Landfill Directive requirements, or would require prohibitively expensive works and a number have closed as a result. A number of fundamental policy issues arise from the need to implement the Landfill, IPPC and Groundwater Directives at the same time. Some of these will be determined through proceedings in the High Court, others are being resolved through the appeal process. 29 of the 48 appeals against conditions are currently held in abeyance, meaning that we are working with the operator to seek resolution. This does not represent the mass permitting problems alleged by some.

Why have less than half of the applications been issued?

  24.  We did not receive all the applications at the same time. Applications were phased in "tranches" so that we dealt firstly with the higher risk, more complex sites.

  25.  Many of the outstanding applications were received in recent tranches and are therefore still within their determination timescale. We did recognise the challenges that PPC permitting presented to us and the industry, and establishment of our Strategic Permitting Groups has helped to cut the average determination time for landfill applications by 20%. Communication with industry has also improved as the re-permitting process has progressed, which is also assisting in resolving permitting issues more quickly.

What are the current costs to the Agency of this "administrative inefficiency"?

  26.  The grant of a PPC permit is not a simple administrative process. We have to make a detailed technical determination of a site specific landfill proposal that, if approved, will be relevant to that local environment for many decades. Noting this and the landfill sector's difficulties with PPC-style regulation, it is perhaps not surprising that in seeking to discharge our obligations to the environment we sometimes find ourselves at odds with some of the applicants. We have done our best to resolve the conflicts without unnecessary expense, but there remain several fundamental differences of view. These stem primarily from a lack of clarity in the Directives, and it is necessary—and in everyone's best interests—that these are resolved through the formal mechanism of appeals or judicial reviews. We believe that our revised generic landfill permit, developed in light of experience and further understanding from Government, will lead to the majority of operator appeals being largely resolved. We do not accept that this process has been subject to "administrative inefficiency".

2.   The Government is currently consulting on the content of the proposed Home Information Packs. Do you believe a flood report for the property should be included within these Packs?

  27.  Yes. Across England and Wales there are over five million people in two million homes at risk of flooding, yet two-fifths of people are unaware of the threat to their lives and their property. We therefore believe an assessment of the risk of flooding to a property is an essential element of the conveyancing process.

    —  If so, would the Agency charge for providing the relevant data?

  28.  We understand from our discussions with ODPM that Home Information Packs (HIPs) will be provided by a number of commercial organisations. We would charge for the incorporation of our data in these commercial products based on their use of our Intellectual Property.

  29.  As we understand it, the intention is that HIPs will be provided in the form of commercial products tailored to the needs of the vendor, rather than vendors making individual enquiries to owners of specific data sets. It would therefore be unlikely that we would be asked to provide data direct to an end user for the purposes of HIPs.

    —  How does the Agency calculate the charges it makes for providing data? Are individuals and businesses charged the same rates?

  30.  We charge commercial royalties on businesses who re-sell our data. We calculate such charges by reference to market forces and in accordance with the Reuse of Public Sector Information Regulations (ROPSI), the Treasury "Wider Markets" initiative and other relevant competition law.

    —  Where else other than the Agency can this data-if required-be obtained?

  31.  As the statutory body responsible for managing flood risk, we have invested heavily in understanding flood risk and we are recognised as the authoritative source of flood risk information for England and Wales.

  32.  We currently license the data relating to flood risk to many commercial providers of property search products, many of whom we expect to become providers of HIPs. All resellers of our data receive it on equal and transparent terms (in accordance with the RoPSI Regulations and the OPSI's Information Fair Trading Scheme).

  33.  Our flood risk information is also provided to some 500 government, public and not-for profit bodies, including:

    —  Association of British Insurers, and through them to insurance companies

    —  Central Government Departments

    —  Welsh Assembly and Government Offices

    —  Local Authorities for spatial and development planning

    —  Emergency services and emergency planners for planning and responding to floods

  34.  We make our information as widely available as possible so there is a clear and consistent message on flood risk from rivers and the sea in any location across England and Wales, and that message is based upon the best available data.

3.   To what extent is your increasing involvement in policy-making a consequence of having to interpret broadly written and poorly-defined primary legislation?

  35.  We feel that there is much that could be done to codify and define the structure of regulation. We see enormous advantages in developing a simpler, consolidated regulatory framework that will reduce the burdens on both business and ourselves.

  36.  EU environmental legislation is often drafted in "piecemeal" fashion, resulting in incoherence, inconsistency and overlapping requirements. This can lead to primary legislation that is poorly defined. As an example of confusion, even the term "pollution"" is defined differently in different EU Directives.

  37.  This has the effect that EU law is transposed into national legislation in a piecemeal fashion and cannot be easily integrated into existing legislation. Together, this silo approach at EU and national level results in legislation that is piecemeal, overly complex and leads to delayed or ineffective implementation.

  38.  We believe that the EU should adopt a common regulatory code for the environment. A common code could cover such issues as definitions, permitting, consultation periods, and monitoring arrangements. A first step would be to start with Waste legislation. This would reduce the administrative and financial burdens on the public and business, since the legislation would be clearer and easier to understand. It would also make transposition easier for Member States.

  39.  There is much that can be done at a national level too. Again, the norm is for legislation to be developed in separate regulatory silos. The result is a different format each time, with different administrative requirements. A common regulatory framework would avoid this.

  40.  We are now working with Defra on developing a common regulatory framework for two major licensing systems[28] from differing EU directives. We are seeking to extend this to other regimes (and other EU directives) in the future.

  41.  Given the incoherence and inconsistencies in legislation, the EA from time to time fills a policy void as we have to take the regulations, apply them at an operational level and make them fit real life situations. A purely legalistic view cannot do this.

  42.  We think it is time to re-visit the policy/delivery interface with Defra. We would like to see greater delegation to the EA of operational policy and regulatory decisions, for example exemption-making powers. We think this would allow us to reduce inconsistencies across different regimes and increase the effectiveness and responsiveness of the regulatory system. It would also be more transparent to the public and business.

  43.  In the meantime, and based on our regulatory experience, we have put forward numerous specific simplification proposals, as potential regulatory reform orders, to improve specific pieces of legislation.

4.   How satisfied are you that Defra consults you often enough in the initial stages of discussions?

  44.  We are encouraged that there is an increasing commitment from Defra to involve us earlier in the decision-making process. We are seeing improvement.

  45.  Historically, Defra regarded EA as merely technical support and did not engage us in policy discussions. In the past there was a difference in focus between Defra and the EA with Defra's focus sometimes on avoiding infraction.

  46.  This can lead to a compressed timescale to plan for implementation, additional administrative burdens and increased business uncertainty.

  47.  However, as stated above, there is now recognition of the need to bring the EA to the table earlier. There have been two very positive initiatives. Firstly, a programme and project management (PPM) approach has been introduced for developing policy, regulation and negotiating positions. This allows a more systematic involvement of key stakeholders, including the EA at the earlier stages of policy development. Secondly, we have signed a Concordat on EU & international Relations with Defra, which encourages the earlier involvement of the EA in EU decision-making.

  48.  We have already seen the benefits of these approaches, for example, in the work on the revision of the Emissions Trading Directive. In our experience, joint project management has resulted in better working between the EA and Defra; effective joint planning; open communication and a greater focus on deliverables.

  49.  The initial PPM projects have been a good step forward but for it to make a real difference, the discipline of PPM has to be rigorously applied throughout Defra. It is not sufficient for it to be adopted selectively.

5.   The Committee received evidence that suggests the Agency is failing to meet its deadlines for implementation of the Habitats Directive. Why are you failing to meet your targets on creation of saltmarsh and other wetland habitats?

  50.  Our annual flood risk management performance to create saltmarsh and other Biodiversity Action Plan habitats depends on the size and number of schemes being progressed in any particular year. Consequently, there will be years when a major scheme is completed and the target is more than achieved and others when schemes have not yet delivered habitat increase.

  51.  For example, the Paul Holmes Stray managed retreat scheme on the North shore of the Humber estuary in 2003 created 80 hectares of saltmarsh, whilst the Alkborough managed retreat scheme (also on the Humber) will create about 400 hectares of saltmarsh in the next two to three years. There will also be years when schemes which, because of limited opportunities, create only small areas of habitat creation are completed. The result is a "spikey" performance and years when the 200 hectares annual target is missed.

How can this be rectified?

  52.  We recognise that more needs to be done to maximise opportunities and establish a more effective cumulative habitat creation programme. To help with this, we are developing, with English Nature's advice, detailed Regional habitat creation targets. This will mean that habitat creation targets are built into flood risk management programmes at an early stage and responsibility for delivery is firmly delegated to a more local level, within an overall national strategic plan. This should help to improve delivery because up until now there have not been formal local targets to deliver proactively, rather than just opportunistically, the necessary actions.

Should Natural England have direct responsibility for all Habitat Action Plans, with the Agency taking an advisory role where these coincide with flood risk management responsibilities?

  53.  We recognise that the UK Biodiversity Action Plan (UKBAP) process is a complicated one, but giving Natural England direct responsibility for all 45 Habitat Action Plans would not improve performance. This is because delivery would still depend on actions by the operational organisations, which have the biggest influence on specific habitats. The Environment Agency leads on key wetland habitats since we have the biggest influence on the key issues of water quality, quantity and flood risk management. The current arrangement, whereby lead responsibility reflects the influence of operating authorities such as the Environment Agency, increases the chances of action being delivered, because there is a corporate responsibility to deliver a Government target.

6.   Further information on Environment Agency Charging—how the EA responds to requests from business for detailed information on the breakdown of charging, including details of generic and web-based documents and specific responses.

  54.  The Environment Agency provides an extensive range of communications and opportunities to discuss charges in an open and transparent way:

  a.  Consultation document—this provides details of the impact of cost increases on different types of charges, for groups of chargepayers, and breaks down the various elements of any charge increases.

  b.  Leaflets—where there are significant changes to schemes or charges we send out leaflets with bills for annual charges which provide an explanation of the reasons for the changes and a breakdown of the elements which make up any increases (see Annex A)[29].

  c.  Website—we publish detailed information on the principles and processes involved in developing our charging schemes and setting charges, as well as providing details of the charges for each of our schemes. More specifically, regarding the breakdown of our charges:

    —  For our main charging schemes, we publish leaflets that break down the reasons and impact of any charge increases.

    —  We have placed a document on our website entitled "Costs and charges for environmental licences" which describes how we bring charging principles together in order to calculate costs and charges. Charges for Pollution Prevention and Control permits are used as examples (see Annex B)[30].

    http://www.environment-agency.gov.uk/business/444669/?version=1&lang=_e

  d.  Stakeholder fora—we engage with our stakeholders through a number of standing groups (eg EP Charges Review Group) and ad hoc meetings with trade associations (eg ESA) where we respond to requests for information, including on the make up of charges.

  e.  Specific requests—requests received from individuals are usually concerned with the individual's own charges. These are usually channelled through our National Customer Contact Centre phoneline (NCCC), our Finance Departments (Exchequer and Financial Accounting Service (EFAS) or EA Wales Finance) or come direct to the Charges Team, either via stakeholder fora, by e-mail (we advertise a specific e-mail query address in our consultation documents and leaflets) or post.

  Where a query relates to the basis or calculation of the charge, this is usually dealt with by EFAS or EA Wales Finance, with reference to local (Regional) Environment Officers where the query is of a technical nature. Other charging queries, or where the basis of the charge is disputed by the chargepayer and cannot be resolved locally, are referred to the Charges Team in Head Office for a decision and response. This ensures a consistent approach and response to chargepayers.

Examples of recent specific requests

Received through stakeholder groups:

  —  COMAH Charging Review Group—breakdown of the hourly charge out rate, supplied at the meeting on 26 October 2005 (Annex C)

  —  Advisory Committee on Packaging—presentation to committee on 6 October 2005, breaking down the costs and charges for producer responsibility (Annex D)

Received from individual chargepayers/businesses:

  —  Typical query received via the NCCC re the method of charging for disposing of sewage effluent (Annex E)

  See the attached documents for more information (please note that customer details have been removed from the attached response to a typical query).

  We believe we provide transparent information about changes and how they are reached. Regulated industry may not like the final outcome but they are fully involved in the process.

Environment Agency

February 2006


28   The Environmental Permitting Programme is aiming to combine the major licensing regimes of Pollution Prevention & Control (PPC) and Waste Management Licensing. Back

29   Not printed. Available at: http://www.environment-agency.gov.uk/business/444669/587179/504799/508992/?version=1&lang=_e Back

30   Not printed. Available at: http://www.environment-agency.gov.uk/commondata/acrobat/costs_and_charges_1017235.pdf Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 11 May 2006