Select Committee on Environment, Food and Rural Affairs Written Evidence


Memorandum submitted by Prospect: Environment Agency Branch

EXECUTIVE SUMMARY

    —  There is still a lack of clarity as to where the income from fees and charges on industry is spent.

    —  Prospect is concerned about the high turnover rate among specialist staff eg hydrologists and geoscientists.

    —  The predecessor committee recommended that the Agency reconsider its decision to downgrade its Integrated Pollution Prevention and Control (IPPC) staff: a new threat to this recommendation is planned.

    —  Around a quarter of the Agency's white-collar staff are employed by Head Office. Prospect is worried that the centralisation of control will lead to impoverishment of jobs at the point of delivery.

    —  The BRITE (Better Regulation Improving the Environment) Project appears to have failed but the lack of an honest and open report on the project is preventing the necessary learning.

    —  Much of the Agency's IT provision has been launched without sufficient testing, leading to delays, inefficiencies, additional costs and huge levels of staff frustration.

    —  The Agency's production of guidance, templates and applications for operators appears to be on an exponential growth to the detriment of clarity and succinctness.

    —  Prospect believes that the Agency's approach to health and safety is contrary to the advice on good practice given by the Health and Safety Executive and may not meet the requirements of the Health and Safety at Work etc Act 1974.

    —  The Agency is moving towards a charging scheme that offers incentives to operators for good environmental performance. However, one aspect of its proposals threatens the concept of natural justice.

    —  The increasing use of standard conditions in permits issued under Integrated Pollution Prevention and Control (IPPC) may not meet the Agency's legal obligations to deliver the objectives of the EU Directive and domestic legislation.

1.  INTRODUCTION

  Prospect is one of the recognised trade unions in the Environment Agency. It was formed as a result of a merger between the Institution of Professionals, Managers and Specialist (IPMS) and the Engineers' and Managers' Association (EMA). IPMS submitted written and oral evidence to the Environment Select Committee's 1999-2000 inquiry into the workings of the Agency. Prospect's submission today picks up on the Agency's response and actions following that inquiry's report.

2.  FEES AND CHARGES

  Although the Agency is moving to a risk-based charging scheme for Integrated Pollution Prevention and Control (IPPC) waste and process industry operators the charge rate for the latter is still linked to the old "inspector day rate". This was £1,215 in 1999-2000 and is now £1,305. The rate was based on recovering all overheads associated with the regulatory regime through the field inspector. He was assumed to work 220 days per year spending 60% of his time on chargeable work: some £172,000 per inspector per year. Of this some 38%—£65,500—goes in direct costs of employing front-line staff (gross salaries, national insurance, pension contributions and travel and subsistence). The remainder is split as follows:

  37% (£63,700 per front-line inspector per year) goes on the development of policy, technical advice and supervision of service delivery by Head Office + some centralised service delivery carried out once nationally;

  16% (£27,500 per front-line inspector per year) in regional support—management, accommodation, finance, human resources, legal and administrative services;

  7% (£12,000 per front-line inspector per year) on information technology—personal computer, billing and permit tracking systems.

  The original inspector day rate was based on an average inspector salary of £35,000; today's rate equates to nearly £38,000.

  The Committee might wish to examine where all of this money is spent given that the cost recovery legal provisions and the Agency's Financial Memorandum forbid the cross-subsidisation of activities.

3.  TREATMENT OF SPECIALISTS

  Prospect represents specialist staff in hydrological (water catchment modelling and planning), geoscience (contaminated land, landfill engineering) and civil engineering (flood risk management) posts. In parts of the country where workload for these posts is significant there is difficulty in recruiting and retaining such staff. The Agency's pay system seems to be incapable of rewarding such staff sufficiently despite the use of one-off "loyalty" bonuses.

  Anecdotal evidence suggests that in some areas of the Agency the hydrology expertise is stretched so thinly that some members of teams involved in water abstraction licensing have less than full understanding of the water catchment models (ie the science behind the decision making on how much water may be abstracted without threatening springs, streams and rivers). These models have been developed jointly with the water plc's who are the main abstractors.

  The inability to recruit and retain experienced geoscience staff has led to the situation where existing staff are being denied repeatedly the opportunity to undertake short-term assignments in the Agency's policy and process units. This impoverishes the delivery of eg contaminated land remediation in two ways. Firstly, the field officer is denied exposure to the policy-making milieu that would broaden his appreciation of the bigger picture. Secondly, without field officer input the policy-making lacks the essential "muddy boot" feel —a phrase much used by Ed Gallagher, the previous Chief Executive.

  The problem of recruitment in Flood Risk Management is compounded by the Agency's insistence on candidates being chartered engineers for posts not requiring that level of qualification to do the job.

  The failure to address properly the treatment of specialists threatens the technical resilience of planning and delivery in these areas and the Committee might care to examine the impact this may have on the Agency's ability to protect water resources, land and property at risk of flooding.

4.  INTEGRATED POLLUTION PREVENTION AND CONTROL—DOWNGRADING OF THE PROCESS INDUSTRY SPECIALISTS

  The predecessor committee recommended that the Agency reconsider its decision to downgrade these staff. An uneasy standoff during the last five years is being replaced by a plan to introduce 70 lower-graded officers (see Fees and charges above) to carry out this work over the next three years. These officers are graded in Agency terms as AS4U that in 2005-06 equates to an entry salary of £19,884. This rises to £23,839 after eight years in the job. (NB The Agency's pay structure is designed to move staff up to a market median salary for similar jobs—based on data provided by Hay Consultants—after a maximum eight years in post). The Committee will note that even after eight years experience these staff will be earning a salary of around one third of the sum allocated to the employment of front-line staff and some £14,000 less than the figure used to derive the inspector day rate.

  The Committee might wish to examine whether such a downgrading may threaten the technical resilience of the Agency's delivery of continued environmental improvement from major industry and the high-level outcomes of EU legislation.

5.  CENTRAL COMMAND AND CONTROL AND THE IMPACT ON JOB QUALITY

  Somewhere around 2,500 staff are now employed by Agency Head Office, between them producing some 3,500 pieces of guidance, instruction or template. Apart from the sheer impossibility of following all of these documents field staff are suffering impoverishment in their roles due to the disempowering influence of this central command and control style.

  Example 1. The Agency has sought to develop risk-based regulation through its Environmental Protection Operator and Pollution Risk Appraisal (EPOPRA) scheme and Compliance Assessment Scheme. This is part of its wider modernising regulation agenda (Delivering for the environment—a 21st century approach to regulation). For example in PPC, the EPOPRA score seeks to assess the risk presented by a site and to target regulation according to that risk. This is an admirable principle but the practice is perhaps less admirable. The EPOPRA scheme is unduly complex, and although the Agency has recently modified it to reflect operator performance the impact of this on the total score (and charge) is insignificant especially for large scale and complex sites, where the need for good operational practice is greatest. The compliance assessment scheme is unnecessarily bureaucratic and displays the typical Agency approach of trying to micro-manage Area activities without the ability (or effort) to monitor whether such procedures have been implemented or indeed have been successful. This is not to criticise the basic principles but in this as in most areas of work Agency has failed to recognise that "less is more" ie the approach should be to minimise internal bureaucracy, guidance and procedures involved, not to make these as complex and exhaustive as possible.

  This is of course connected to the issue of training and competence of staff and the balance between employing well trained, experienced staff capable of exercising discretion and employing less well trained and experienced staff who are not so capable and who is consequence need much greater direction.

  The committee may wish to consider whether the Agency is developing its modern regulation in an effective way both in terms of its procedural approach and in terms of staff competencies.

  Example 2. The PPC regime has progressively replaced IPC from 2000. The PPC regime does extend the scope of IPC (by covering energy efficiency, accidents etc) and has a wider application than IPC (farms, the food and drink sector) but PPC closely mirrors IPC in both its technical requirements of operators and its procedural and administrative requirements of both the Agency and Operators. The IPC regime had an excellent record for effective permitting to time and budget and one might have expected Agency to build on this for PPC. The Agency, however, chose not do so but to put in place a team-based approach to permitting. The reason for this seems to have been to make a break for political reasons from the IPC regime. The team-based approach was so ineffective in delivering permits on time that the Agency decided to centralise PPC permit determination into the "strategic permitting group" (SPG). This group has expanded to around 170 staff although this has not been sufficient and in fact much permit determination has been contracted out to contractors. Despite much hard work by staff in SPGs, many of whom are experienced staff with practical experience of regulation, the fact is that

    —  SPG is struggling to meet the internal target of 8 months to determine permits (the statutory target is actually four months and this was routinely achieved in IPC);

    —  The quality of permits in particular from contractors is poor, requiring much corrective work by Agency staff;

    —  It is questionable whether the SPG approach has been cost effective.

    —  In excess of 100 appeals have been lodged against permit conditions

  This is compounded by the fact that most of the complex industries (power stations, iron and steel, chemicals) was previously regulated under IPC with relatively little change required to bring these under PPC. The new entrants are both relatively simple (food and drink) and environmentally less harmful.

  The performance of SPGs in our view arises from the combination of a flawed centralised approach and a failure to adopt a risk based approach to technical issues.

  The committee might wish to examine how effective the SPG has been in practice in terms of permitting to time and cost, and also to examine the quality of the permits issued, including whether conditions in permits are proportionate and risk-based.

6.  FAILURE OF BRITE

  Much was made of the Better Regulation Improving the Environment (BRITE) project for improving communication lines and transferring resource to the front line to cope with new duties. Unfortunately it became, in the words of the Chief Executive, a "disaster we must not repeat". After three and a half years the project delivered negligible additional resource to the field, contributed to the "command and control" problem highlighted above and failed to even mention one of the largest new duties: Integrated Pollution Prevention and Control. It is believed that two reports have been compiled but not released to staff or trade unions.

  Many of the shortcomings of BRITE have been repeated in the Incident and Flood Risk Management (IFRM) Project. In the short term the Project failed to identify and address the impacts of the changes on the Flood Risk Management (FRM) programme in 2005 and 2006. In the longer term it threatens to repeat the "command and control" problems of BRITE. By way of example National Flood Risk Assessment (NaFRA) work is being delivered once nationally to amend the Agency's published flood maps. This is producing work of poor quality that is unrealistic in terms of level of risk in many areas and which disregards the local knowledge and experience of area staff.

  Prospect suggests that the Committee might care to examine the findings of any audit of the BRITE benefits realisation delivery.

  The Committee might also care to ask for a review of the implementation of IFRM.

7.  UNTESTED IT SYSTEMS

  The structured testing of new IT systems is now being taken seriously in the Agency with the in-house appointment of a team to recommend and oversee software and system testing. This is a vast improvement on the situation where the specification and programme of testing were left to individual project managers (sometimes employed under contract) or, incredibly, to the project software suppliers! There is still scope, however, for Project Executives to force the pace of change against expert advice. One such occasion was the switching off of the National Time Recording System more than 12 months prior to the date when its replacement—Oracle Time and Labour (OTL) (part of the larger 1B1S system) was fit for purpose. This led to the loss of 12 months' time recording data that is needed for reconciling expenditure against income from regulatory charges and grant-in-aid.

  The Committee might wish to inquire as to how such reconciliation was effected in the absence of time recording information in 2004-05.

8.  AVAILABILITY AND CLARITY OF GUIDANCE—OVERWHELMED BY PAPER

  The predecessor Committee recommended that the Agency ". . . continue to give priority to the clarity and openness of its regulatory requirements and to seek further ways to improve such clarity and openness.". Since then the Agency has produced an overwhelming quantity of guidance, templates and application forms. In fact the Agency's web site alerts PPC applicants to the fact that the application package is so big each document could take 40 minutes to download from the internet and that they should request the information be sent on compact disc. For example the Fuel and Power sector application form runs to 163 pages; the sector guidance note to 123 pages; the site report (a statement on any contamination of the land under the site) guidance and the EO OPRA scoring sheet similarly-sized. All of this may seem fairly daunting to operators who are new to the regulatory regime but, astonishingly, there are no shortened versions for operators who are merely converting from IPC to PPC. The Agency's centralised permitting function has been treating existing IPC operators as if their activities were new to the Agency. All previous interactions with the Agency (and its predecessors) are invisible: files containing inspection reports, improvement plans completed, details of enforcement action, neighbourhood complaints, independent monitoring reports, incidents and accidents, audit findings—all going back as long ago as 15 years—are ignored. Instead of "bolting on" the additional requirements of PPC—state of the land below the site, noise, waste minimisation etc—to an already-proven, highly successful IPC regime [Introduction to DEFRA's Financial Management and Performance Review (FMPR)] the Agency has chosen to start afresh and charge the full fee.

  The Committee might wish to question whether such an approach meets the spirit of "Better Regulation" and, more recently, Hampton.

9.  HEALTH AND SAFETY

  A paper "Health and Safety—Securing a Step Change" [EA(05)30] was endorsed by Agency's Board on 11 May 2005. This paper states that the Agency needs to give a sharper focus to Health and Safety. It proposes to build on the Health and Safety strategy by a step change programme focussed less on process and more on people. While it is stated that there will continue to be a need to work on policy, process and systems the focus is to be centred on people and their behaviours.

  Focussing on people and their behaviour is a method of improving safety but it is only effective if it leads to an examination for and removal of hazards. In the paper emphasis is placed on campaigns and the use of display boards. The use of poster campaigns has been shown to be of negligible value and is rarely used by safety professionals as their main tool. Indeed emphasising the behaviour of individuals instead of examining management systems has not been considered by safety professionals to be a prime tool in improving safety for some 30 years. It was in late 1960's that the change to examining management systems commenced. Since then it has proved highly successful in those companies where directors and managers consider safety performance as a direct result of their decisions. This principle underpins the basis of the Health and Safety at Work Act 1974, which places the main duty on the employer and emphasises those aspects over which the employer has direct control. These are equipment design, equipment maintenance, procedures, training, and supervision of staff. The Health and Safety Executive have published guidance on the management of health and safety, (HSG65 Successful health and safety management first published 1991). The HSE's approach identifies two factors; immediate causes and underlying causes. The underlying causes are those concerned with management and organisational factors and research by HSE has identified that failings in management systems underlie most accidents. One of the key messages in HSG65 is to recognise that "accidents, ill health and incidents result from failings in management control and are not necessarily the fault of individual employees". It particularly points out that accidents "usually arise from organisational failings that are the responsibility of management".

  The Committee might wish to examine the Agency's approach to securing the health and safety of staff and members of the public.

10.  INCENTIVE CHARGING—EXTRA-JUDICIAL PUNISHMENT ON OPERATORS

  The risk-based charging scheme, based on EPOPRA (Environmental Protection Operator and Pollution Risk Appraisal) scores, is influenced by the number of breaches of permit conditions occurring throughout the fiscal year. As a principle this sounds fine. Where a breach has resulted in a successful prosecution or an improvement or enforcement notice that is uncontested (ie the operator did not exercise his right of appeal or such an appeal was denied) then it would be fair to raise the annual subsistence fee as part of incentive charging. However, most breaches of permit conditions do not result in the type of enforcement action outlined above. They are simply recorded by Agency staff on a computer database linked to the billing system. This means that operators will not have recourse to any independent method for contesting such alleged breaches and hence no chance of influencing any decision to raise the subsistence charge.

  The Committee might care to examine whether such a system squares with the concept of natural justice.

11.  FETTERING DISCRETION IN EXERCISING REGULATORY POWERS

  The Agency is charged with determining applications made under the Pollution Prevention and Control (PPC) Regulations to deliver the obligations under the EU IPPC Directive. The regulations cover new activities (ie new sites), activities not previously regulated under analogous regimes and activities which were subject to the integrated pollution control (IPC) provisions of the Environmental Protection Act 1990. The PPC regulations require that permits contain conditions to deliver all of the objectives of the Directive particularly that all appropriate preventative measures are taken against pollution through application of the best available techniques (BAT). The Agency is issuing permits containing standard conditions that transfer the onus onto the operator of the site to determine BAT for himself in several key aspects. There are two main problems with this approach:

    (a)  the Agency has accepted a fee—in some cases in excess of £100,000—with the application, presumably to carry out a BAT assessment of the operator's activities;

    (b)  there is recent case law that supports strongly the contention that the regulator should carry out the BAT assessment. [R v Daventry (Thornby Farms) and R v Chester City Council (Quinn Glass)]. In both cases the regulator was the local authority but both were working within the same legislation as the Agency.

  The Committee might care to inquire into how the use of standard conditions may conflict with legal requirements.

Prospect: Environment Agency Branch

December 2005


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 11 May 2006