Select Committee on Environment, Food and Rural Affairs Minutes of Evidence


Examination of Witnesses (Questions 100-119)

LORD BACH, MR JOHNSTON MCNEILL, MR IAN HEWETT AND MR JOHN O'GORMAN

11 JANUARY 2006

  Q100  David Taylor: It is not a soft cop-out management option just to outsource IT?

  Mr McNeill: No.

  Q101  Lynne Jones: I have got two points. Why have you made hundreds of staff redundant and then you have to employ lots of temporary people and at the same time you said a lot of your remaining staff are having to do a lot of overtime? Secondly, is all the extra work and overtime voluntary?

  Mr McNeill: We have had a clear plan in terms of reducing staff. What we have done is trawl the organisation, in agreement with the trade unions, and given the staff the opportunity to identify whether they wish to leave with a package. A number have applied.

  Q102  Lynne Jones: Should you not have kept them on a bit longer?

  Mr McNeill: I was just going to come to that. What we have done is considered those who have applied. We have been very fortunate that the number who have applied have met our needs, so we are not looking at compulsory redundancy. What we have then had to do is look at the particular skills and experience those staff have. Some staff have left on retirement over this period as well and we cannot stop that happening, they have done their service and they are entitled to go. What we do is look at the particular skills and experience of those staff who are saying, "I would quite like to leave" and where they have skills we think we can use, we have said—for a significant number it is the case—"We cannot afford to let you go until we finish certainly the first round of this scheme" and a number have expectations that by this summer we should then be in a position to release them, but in many cases we still have not committed to that. What we have accepted is that when possible we will release them. We have let other staff go, I accept that, but often in areas not directly related to processing SPS: support services, facilities management, we have let some human resource staff go, things of that nature. There is a consideration of each and every case.

  Q103  Lynne Jones: How many staff have you "let go" as you put it? Are you saying that none of those could have been kept on longer and contributed to the work that is being done by the temporary staff and staff doing overtime?

  Mr Hewett: Can I answer that question? Since the start of the Change Programme 300[10] staff have left the organisation and a further 100, bringing the total to 400, are planned under part of the Change Programme. A significant number of those have been released from the two sites at Crewe and Nottingham which were not part of our Change Programme and, therefore, were not part of the IT development which we are now using to deliver the Single Payment Scheme. Those staff were predominantly there to deal with the farm-based schemes in those geographic regions. I visited both of those offices shortly before their closure to thank the staff for their efforts in dealing with the close down of what we now call legacy farm-based schemes, the bovines and sheep schemes, et cetera. Some staff outside of those two offices have left for the reasons Mr McNeill has already explained as part of that programme in corporate areas or, in a few cases, from some of the other areas. For example, at Reading now the number of frontline operational staff who will be left at Reading at the end of the Change Programme is very small, so consequently some of those staff have disappeared during the course of the programme and perhaps that was what Mr Taylor was referring to.


  Q104 Lynne Jones: I am not sure you have answered my question on overtime being voluntary.

  Mr Hewett: Sorry. In terms of overtime being voluntary, absolutely. We do seek volunteers for overtime on a regular basis but since the advent of bringing agency workers into the organisation, primarily for specific jobs such as data capture and more recently validation, we have tried to target those individuals at specific parts of the day to make best use of the system. We want an early shift, we want a late shift and in some cases we have a double-day shift. Where we give overtime over that, particularly weekend working, we do seek volunteers.

  Q105  Mr Rogerson: On this business of redundancies and, therefore, temporary staff coming in, some of my constituents contacted me in relation to the implementation of this system and one of the frustrations they claim to have had is that the people they speak to do not seem equipped to answer the questions which they have or, indeed, capable of taking on board the corrections they are making in terms of letters they have had that have raised issues. When they have tried to explain those issues and explain the answers in order to move their assessment forward they have had a letter back which has carried on with exactly the same situation as before. Indeed, the Minister and I have exchanged letters. We seem to have the same problems over and over again. Is there an element where some of the temporary staff and so on may have added to your problems in terms of being able to meet the deadlines you have got because issues which could have been settled simply have rolled on and on through repeated exchanges of correspondence?

  Mr Hewett: If I can try and answer that question. First-off, administering the Single Payment Scheme is not like administering previous schemes where we had more like a claims management type approach and I would have one of my processors looking after a particular claim and perhaps liaising with the customer where appropriate. With the Single Payment Scheme and the system that we are implementing it through, the claim goes through a number of stages and a number of different individual members of staff might be involved in processing aspects of that claim. As I have already mentioned to one of your colleagues, we have employed a number of staff on a short-term basis, either agency or casual, to do specific jobs, to capture data, to do certain aspects of validation. We know them in the trade as level one or level two primary or more detailed validation. The primary validation was about errors or omissions, so in certain cases some of our staff would have been on the telephone to customers saying, "There appears to be an issue around certain aspects of your claim, could you explain to us". They would not necessarily know certain other aspects of the process, for example if there was a dual claim or an over-claim, they would not have been trained in that, they would have been trained in looking for errors and omissions in the claim. Perhaps that is part of the issue. The other point is in terms of putting right problems when they are found, certainly we have had issues in relation to land registration. Mr McNeill has already explained the scope and the extent of the land registration changes that we have seen in the last 12-18 months. That came on the back of a two year digitisation exercise and I have to say not all of our customers were very keen to talk to us about that digitisation process at that time. They now are because they want to make sure their Single Payment Scheme and Entry Level Scheme claims are accurate. We are now getting into a situation where we have involved an outsourced supplier and we are fielding calls around some of the work associated with that outsourced supplier. We have also established a Customer Service Centre at Newcastle, and now at Workington, that was introduced just before the Single Payment claims went out, and we might touch on that at some point. We knew there were issues around that in terms of making sure that our staff were fully equipped with knowledge around SPS. That is what we are trying to do. We are trying to make sure that in dealing with the 2006 scheme inquiries we are better placed to handle that by making available technology which allows calls to be filtered out of the call centre into sites where the expertise in processing claims for 2005 took place.

The Committee suspended from 5.03pm to 5.16pm for a division in the House.

  Q106 David Lepper: This is a postscript to what Dan Rogerson was asking about just now. Mr Hewett, you have explained what I think is probably called the task-based system for dealing with claims of rather than one person following the claim through to the very end different people work different aspects of it, and you have explained the reasons for that. This relates to the staffing issue as well. The Country Land and Business Association in their evidence to us talk about what they see as a decline in customer service and they feel the way that manifests itself is the personal contacts which did exist, which they felt were valuable, at regional offices are replaced by voices at distant call centres, as they put it, and the service suffers because of that. I guess collectively you would argue the change is necessary not just because perhaps some of those regional offices are no longer there, I am not sure about that fact,—

  Mr Hewett: They are not.

  Q107  David Lepper:— but because the nature of the system requires a different way of dealing with it. Would that be the argument?

  Mr Hewett: I think that would be absolutely the case in terms of we took the decision as part of the Change Programme to move from a regional-based solution to a national-based operation and the Single Payment Scheme effectively embellishes that, if you like, by moving this from the 11 farm-based subsidy schemes to a single farm-based subsidy scheme which in the first year is predominantly based around historic entitlement and reference data and over time moves into a scheme that is based predominantly around land. We have a Land Registration Unit, we have a Customer Registration Unit, and the functionality that supports that was delivered at the end of 2004 and early 2005. We do still, and did during the application window for 2005, operate a system where our customers can make contact with us at our sites where we are processing, and at the moment we have six sites in operation. Predecessor organisations occupied 11 sites, so you can see there is a downsizing process there. Those contact centres are still there if customers wish to deposit anything with us, however our primary intention is to move to a situation where we have a Customer Call Centre that is capable of dealing with telephone and email inquiries and we hope over time, although this is not yet proven, electronic communications.

  Q108  David Lepper: So the regional office is a thing of the past?

  Mr Hewett: That was part of the Change Programme ethos.

  Q109  Chairman: I want to move on to ask some questions about mapping but, just following on from the last points that we heard about customer service, I am going to leave with you a letter which one of my parliamentary colleagues sent to me from a farmer in Gloucestershire. He sent a detailed log of some 55 contacts or activities between 25 March 2004, when he received from the RPA in Exeter a list of field numbers and sizes in his efforts to get himself properly and accurately registered, to the final event on 5 January this year when he finally received maps from the RPA in Reading and they were still wrong. I do not know whether this is an isolated example, I suspect it is not. I suspect it reflects an awful lot of angst as far as landowners are concerned. It would be helpful to have a detailed response to the issues there on what you have done to prevent this kind of thing happening in the future. As far as the mapping is concerned, one of the things that surprised me in terms of the evidence you have given so far is why you did not anticipate the extra volume of work that occurred. Did you do any kind of sampling exercise on farms to assess right at the beginning some of the practical problems that were encountered? In the context of the people who were new to making a claim, when the policy was determined, was no exercise undertaken to estimate the numbers of new people who would be eligible under the policy which you had agreed?

  Lord Bach: The RPA representatives can answer the factual question about whether exercises were conducted. I think the 40,000 increase in claimants, in other words 50%, did take us by surprise to some extent. Whether it should have or not, I do not know, but I suspect it was rather more than thought. In addition to the number of claimants was the number of changes to be made or additions to be made to the land registration and the mapping that follows from that. There I want to emphasise, if I may, something I said a little earlier. It was not just those who were new claimants who were putting forward changes to their maps, it was those who had claimed for years who were legitimately, in a sense, putting forward land they could now claim for as part of the Single Payment Scheme. As I think Mr McNeill has said on more than one occasion, frankly those people should have mentioned that land when they were claiming for previous subsidies but they did not, and it is human not to sometimes, I accept that. I think the number of existing claimants who put in claims for new land did surprise us.

  Q110  Chairman: Minister, could you answer the question that I asked. The question that I asked was did you, once you had agreed the policy, not go out and visit a few farms and say, "We know roughly the kind of information that will be required, now let us do a little sampling", to get some idea in the real world what kind of problems you would encounter? Did any of that get done?

  Lord Bach: That is a factual question I cannot answer.

  Mr McNeill: In terms of the existing customer base in the summer of 2004, having built the new Land Register and put on the circa 1.6[11] million parcels of land, we sent to each of our known customers, the circa 80,000 customers that we dealt with, a copy of the maps and asked them to let us know whether those maps were right. We realised that it was going to be important for legacy schemes and, indeed, for SPS as it happened to have as good a Rural Land Register as possible. We sent them out and a significant number came back and somewhere between 20,000 and 30,000—I can confirm that in writing—did not respond despite repeated reminders and us chasing them up. What we then found was that at the same time as we had to introduce SPS and once our existing customers became aware that there was going to be an area element to the new Single Payment Scheme we had the new Stewardship Scheme, the Entry Level Scheme, introduced by RDS and in some cases the same customers, in other cases new customers, realised that they would also require land to be mapped to make application for that. That was additional work that resulted from that other scheme being introduced. In terms of the 40,000 customers the answer is no, to my recollection we did not sample.


  Q111 Chairman: That is what I thought you were going to say.

  Mr McNeill: We had an understanding about the possible magnitude of the number of customers but who they were and how much land they might hold we did not know. With the introduction of people who kept horses and so on—

  Q112  Chairman: Very simply, Mr McNeill, you knew the policy but you were flying blind when it came to trying to work out the volume and the volume only became apparent once the paperwork started to come in. In other words, when you started you had not got a clue.

  Mr McNeill: We had a system which at that time we felt was scaleable and we would be able to deal with the volumes if all 40,000 decided to submit IACS 22s.

  Q113  Mr Drew: Could I just check, was the satellite monitoring, which is presumably how you built up the knowledge of the field boundaries, included as part of the software management system so that you could compare the bits that were coming in with the acreages or the hectarages that were being claimed for?

  Mr Hewett: The original Rural Land Register project, which was to map 1.7 million land parcels, on which the old IACS system was based, was derived from Ordnance Survey boundaries. That is comparable and allows us to do remote sensing inspections on a proportion of our customer base. We did that under the old IACS regime for arable claimants and we do so for the Single Payment Scheme. A proportion of the customers who were selected for inspection from the 2005 SPS population were subject to remote sensing checks.

  Q114  Mr Drew: So it was never thought either feasible or sensible that there would be a comprehensive pictorial representation of what people were claiming for?

  Mr Hewett: We were already producing that for our own purposes, if you like, in terms of monitoring, checking from remote sensing inspections.

  Q115  Mr Drew: That is for everyone then, regardless. You say you trial, test some people just to get a feel for how accurate the information is, but—

  Mr Hewett: This is for compliance purposes. We are required under one of the key controls that I mentioned some time earlier, Chairman, to inspect a proportion of our claimant base each year. Some of those inspections are physical inspections on the ground with our inspectors actually measuring the area; other inspections are undertaken by remote sensing, by satellite imagery, et cetera, to check the claimed area against the area found by satellite imagery. We use it for compliance purposes. My colleagues in the Rural Development Service, who are responsible for the administration of the Environmental Stewardship Scheme, take as the basis the land area and they are also very keen to make use of the Rural Land Register data as part of the application pack which then goes to customers and forms part of the agreement for that Environmental Stewardship claim.

  Q116  Mr Rogerson: This is a mapping question but it also relates back to what I was talking about before we had to go to vote on people's experience and the complicated nature perhaps arising from having to speak to a different person each time you contact the Agency. This is a gentleman who was applying under the National Reserve as a new entrant into the industry and he tells me that having completed and returned the information he was required to do, others—the figure he gave me was 18,000, I do not know whether that is true or not in terms of the number of people applying for the National Reserve—a smaller proportion of those had not responded with the details necessary but, because there was no way of telling from your system which were the ones who had responded and who had not, all 18,000 had to be written to again prompting a further response. I imagine that would have generated a lot of confused inquiries from people saying, "I have responded, why have you contacted me, is there something missing?" Has that added to your workload significantly?

  Mr Hewett: I can give you a bit of factual information. The 18,000 National Reserve applications is a correct figure. By the time that we completed the assessment of around half of that number, and the assessments have been undertaken off of our main system and then we load the data on afterwards, we determined that around half were in a category known as "insufficient information to make a judgment". On that basis we decided rather than take the time to trawl through the remainder to find out if a comparable proportion were in that "cannot make an assessment" category we would write to everyone to give them a checklist against which to tell us, "Have you given us all the information on this checklist that is relevant to your case? If so, thanks. If not, please provide that and any further information". Subsequently, we discussed that with stakeholders, who we meet on a regular basis, one of whom is sitting behind me, to explain that if any customer believed that they had already provided the information we did not want it a second time, thank you very much, we just needed confirmation that we were going to get everything we wanted. As a consequence of that process and part of our on-going assessment, a considerable number of applicants have actually withdrawn their application, whether they felt they did not have sufficient information to justify eligibility or for whatever reason they decided to withdraw.

  Q117  Mr Rogerson: Inevitably some, who may not have been contacted through your various consultation means, may well have felt, "Does this apply to me? Have I been sent what I need?" and that would trigger off another round of communications with the Agency?

  Mr Hewett: Absolutely. Our stakeholder representatives cover a significant proportion of the industry now, it would be very helpful to us in selling key messages to their members or customers if they helped us to work with this. They recognise that, unlike previous schemes where we could say, "That claim is eligible, pay it", you are putting everything in the pot and working to some of the lowest common denominators here.

  Q118  Mr Williams: If I understand you correctly, mapping is no longer impeding the processing of the calculation of the entitlement?

  Mr McNeill: My earlier comments were about the fact that we have outsourced the processing of the backlog of IACS 22, the applications to have changes made to land, we have brought in the contractor who built the original database, as I mentioned, and as a consequence there are a number remaining, which I can give you, but it is relatively small and planned to be finished in the very near future. So as such the actual mapping process is not going to interfere with the payments. We have had a concern which perhaps I can touch on, and that is about the accuracy of the maps. We have had some system glitches where the land is available on the screen, as our staff look at the screens and the database, but unfortunately when printed the maps have excluded certain parcels of land, and that is a fix which Accenture are sorting for us and will be put in place shortly, but we are aware of the land and who owns it. Unfortunately, when we have sent out the maps, it appears we have missed something, and that has been the problem. Another issue is that we do send out maps and, indeed, we do get it wrong, but also we find that customers often for the first time for sometime actually look at the map in considerable detail and recognise that perhaps they have missed things themselves and identify additional issues they want to raise with us, which is understandable. So we have those cases and so maps can go to and fro. Yes, we have made errors with it. We closely monitor the quality of both our own staff's performance on this and the contractors' and there is a certain 2%, 3%, quality issue which we have been addressing with the supplier and indeed our own staff. So there will be cases when the maps are wrong, and it is unfortunate, and we are aware it has happened, but we would be pleased if customers could send them back and we will sort it out.

  Q119  Mr Williams: So if it is not the mapping that is the problem in making your payments on time, what is the problem?

  Mr McNeill: As I mentioned earlier, the problem we face is that there are a significant number of outstanding issues which we need to address in regard to a significant number of claims. We have gone through various parts of the process and many parts are well nigh completed—level one validations bar a handful are pretty much complete—so large parts of the process are complete, but we are at the stage where there are a number of issues which we still need to resolve. We are also, as I mentioned earlier, awaiting some additional fixes. These are not released as big pieces of functionality from the supplier, but they are fixes which we think may well address large numbers of these.


10   Note by witness: 299 left by 31 December, 117 in 2006, total 416. Back

11   Note by witness: should be 1.6 million. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 2 May 2006