Select Committee on European Scrutiny Thirty-Second Report


16 Remedies in the field of public procurement

(27485)

9138/06

+ ADD 1

COM(06) 195

Draft Directive amending Council Directives 89/665/EEC and 92/13/EEC CEE with regard to improving the effectiveness of review procedures concerning the award of public contracts

Legal baseArticle 95 EC; co-decision; QMV
Document originated4 May 2006
Deposited in Parliament12 May 2006
DepartmentTrade and Industry
Basis of considerationEM of 6 June 2006
Previous Committee ReportNone
To be discussed in CouncilNo date set
Committee's assessmentLegally and politically important
Committee's decisionCleared

Background

16.1 The award of contracts by public authorities has been subject for a considerable time to a regime adopted at EC level. The procurement procedures of utilities (i.e. those entities operating in the water, energy, transport and postal services sectors) were subject to their own particular regime, and the relevant Directives have now been consolidated by Council Directive 2004/17/EC.[53] For contracts awarded by the generality of public authorities separate Directives were adopted in relation to supplies, works and services, but these have now been consolidated by Council Directive 2004/18/EC on the award of public works contracts, public supply contracts and public service contracts.[54]

16.2 The procurement regime is supported by two Directives providing remedies in the event of failures to observe the prescribed procedures. Council Directive 89/665/EEC of 21 December 1989 provides for remedies relating to procedures for the award of public supply and public works contracts[55] and Council Directive 92/13/EEC of 25 February 1992 makes similar provision for remedies relating to procedures for the award of contracts by entities operating in the water, energy, transport and telecommunications sectors.[56]

16.3 Following a consultation of interested parties, the Commission has identified various weaknesses in the current working of the system of remedies, in particular, the difficulty of ensuring that a decision to award a contract may be set aside before the contract itself comes into force. In this regard, the Commission notes the lack of any co-ordinated rules on the time limits which govern the ability to challenge the award of a contract before it is concluded. The Commission notes that the result of signing the contract in question is almost always to make irreversible the effects of a disputed decision to award the contract. The existing remedies for reviewing the award of a contract after it has been concluded are generally limited to the award of damages, but such a remedy does not allow the claimants to ensure that the contract is re-tendered. The Commission also considers that the possibility of an award of damages does not have much deterrent effect on public authorities because of the burden on the claimant to show that he would have had a serious chance of being awarded the contract.

16.4 The Commission refers to Case C-81/98 Alcatel Austria and others v. Bundesministerium für Wissenschaft und Verkehr (judgment of 28 October 1999) in which the ECJ decided that the provisions of 89/665/EEC meant that Member States must ensure that a contracting authority's decision to award a contract to a particular bidder "is in all cases open to review in a procedure whereby an applicant may have that decision set aside … notwithstanding the possibility, once the contract has been concluded, of obtaining an award of damages". The Commission notes that there are inconsistencies in which the case law of the ECJ is applied, and that it is not taken into account in all Member States and even where it is, most countries do not having provisions creating a fully effective "standstill" period (i.e. a period within which the award of the contract may be challenged) for the award of all contracts falling within the EC public procurement regime.

The draft Directive

16.5 The proposal would amend Council Directives 89/665/EEC and 92/13/EEC so as to require an awarding authority to suspend the conclusion of a contract following an award procedure for a minimum period of ten calendar days from the date when bidders are given a reasoned notification of the award decision. In cases where the awarding authority awards a contract directly (i.e. with no prior advertisement or tender procedure) and the value of the contract is above the relevant thresholds in Directives 2004/17/EC and 2004/18/EC the conclusion of the contract must be suspended for a period of ten calendar days from publication of a simplified award notice.

16.6 To counter any attempt to circumvent the suspension period, amendments are proposed which would require the conclusion of a contract within the period to be "considered invalid". However, the amendments also permit Member States to provide that a contract which has been concluded in these circumstances may have certain effects between the parties, or in relation to third parties for a maximum period of six months. The same six-month period of limitation may also be applied in respect of any reference to a review body of the award of a contract.

The Government's view

16.7 In his Explanatory Memorandum of 6 June 2006 the Minister for Trade at the Department of Trade and Industry (Mr Ian McCartney) states that the Government agrees with the Commission's aim of providing effective remedies where the public procurement rules have been breached, that this supports the UK policy of achieving value for money through competition and that this will help UK suppliers have confidence in bidding for contracts in the European Union.

16.8 The Minister informs us that the Commission has discarded the option of providing for the setting up an independent authority in each Member State to tackle the problems it had highlighted, and that the Government agrees with the Commission's analysis that the resources which would be required make this a less attractive option than providing for a standstill period.

16.9 The Minister also explains that, following the ruling of the ECJ in the Alcatel case, the UK has already introduced a 10-day standstill period in its domestic regulations giving effect to Directives 2004/17/EC and 2004/18/EC. The Minister adds that the Government supports the Commission's aim of introducing a harmonised approach across Member States, because of the increased confidence this will give to economic operators in the system for remedies, but that the Government will wish to make sure that the approach set out in the amendments for the standstill period is proportionate to meeting the objective.

Conclusion

16.10 We thank the Minister for his helpful Explanatory Memorandum and we agree with the comments he has made. The proposal appears to us to have been carefully considered by the Commission and is timely and appropriate, and largely reflects existing UK practice. We therefore clear the document.


53   OJ No. L 134, 30.04.2004, p.1. Back

54   OJ No. L 134, 30.04.2004, p.114. Back

55   OJ No. L 395, 30.12.1989, p.33. The Directive has been amended by Council Directive 92/50/EEC of 18 June 1992 to extend its scope to cover public service contracts. Back

56   OJ No. L 76, 23.03.1992, p. 14. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 30 June 2006