WRITTEN QUESTIONS AND ANSWERS
Letter to the Head of the Parliamentary
Relations and Devolution Team, FCO, from the Clerk of the Committee,
dated 8 June 2006
Dear Chris,
I attach a list of questions to which I would
be grateful to receive answers prior to Sir Michael Jay's appearance
before the Committee later this month. If the answers are to feed
into the preparations for the oral evidence session, I will need
them not later than close of play on Thursday 22 June. In the
event that some answers are not ready by that date, it would still
be helpful to receive a response on those that are ready, with
the remainder following as soon as possible thereafter.
In view of this truncated timetable, which is
a result of the late publication of the DAR 2005-06, I have attempted
to reduce the burden on those dealing with the response to these
questions by limiting their number. I will, however, need to write
further on a number of possibly less urgent but nonetheless important
issues, to which we will be seeking a response by the Summer recess.
The Committee also wishes to receive:
A copy, or summary, of the regulatory
reform "simplification plan" [the FCO's submission to
the Committee of 3 October 2005 noted that this was expected by
to be ready in January 2006.]
A copy of the conclusions of the
FCO's Financial Management Review [in the FCO's submission to
the Committee, a "final report" was anticipated in November
2005.]
The results of the formal review
of the Global Opportunities Fund [this was anticipated in the
FCO's submission to the Committee to take place "at the end
of 2005-06".]
Yours,
Steve Priestley
Clerk of the Committee
QUESTIONS ARISING
FROM THE
FCO RESPONSE TO
THE COMMITTEE'S
REPORT
1. In reply to Recommendation 13, the FCO
response states that an internal investigation into the satellite
telephone fraud "is nearing completion". The Committee
wishes to receive a copy of the report of this investigation,
if possible before the oral evidence session on 28 June.
What are the revised procedures that the FCO
has put in place to avoid a recurrence of the Bahrain fraud?
2. In reply to Recommendation 23, the response
publishes the red, amber, green list of FCO activities. Who drew
up the list? Which of the "red" activities does the
FCO agree should be stopped completely? Which of the "amber"
activities does the FCO agree should be curtailed or reviewed?
With specific reference to activities related to the work of Members
of Parliament, under which colour group would the FCO place:
(a) briefing for MPs undertaking their official
Parliamentary duties, including overseas trips with select committees,
CPA delegations or IPU delegations;
(b) briefing for MPs travelling with all-party
Parliamentary groups; and
(c) briefing for MPs acting in their own
capacity?
3. The overall response rate during the
data collection phase of the Collinson Grant review was 89% in
the UK and 93% overseas. What was the response rate (a) among
members of the Senior Management Service and (b) among Board members?
4. The Committee wishes the FCO to reconsider
its response to Recommendation 36 and to release the documents
about the Embassy to the Holy See, referred to in that Recommendation.
QUESTIONS ARISING
FROM THE
DEPARTMENTAL ANNUAL
REPORT 2005-06
5. The March 2006 White Paper (Active Diplomacy
for a changing World, Cm 6762) identified nine new "strategic
international priorities" (p 28), and brigaded under each
of these a number of "specific aims" (pp 52-59). Why
does the DAR not address these new priorities and aims? To what
extent does the FCO expect these to be the basis of any new PSA
targets in the 2007 Spending Review?
What are the FCO's proposals for involving the
Committee in formulating those objectives and targets?
6. In regard to the SR-2002 PSA-4C, the
FCO reports that it has been unable to develop a new tool for
measuring conflict levels (2006 Annual Report, p 137). The Report
notes the "inherent difficulties in measuring potential sources
of future conflict and conflict prevention outcomes" and
that a "final assessment . . . will be made in Spring 2008"
(p 112). What work is the FCO doing to develop a means of being
able to make that assessment of the outcomes of its Conflict Prevention
work in 2008?
7. The SR-2002 PSA on Conflict Prevention
included assessments which used statistics on the number of casualties
and refugees, although most of these were not carried over into
the SR-2004 PSAs. Why do SIPRI/IISS casualty statistics still
form part of the assessment of the situation in Nigeria (2006
Report, p 114), and why not for other conflict areas?
8. SR-2004 PS-A4AK envisages agreement on
EU financing arrangements for 2006-13, with spending at 1% of
EU GDP (2006 Report, p 117). With the UK Presidency having overseen
a budget deal in 2005, why is this PSA still assessed as "amber/on
course" rather than as a (red or green) settled outcome?
Similarly, why is PSA-4AL still amber, when changes
to the CAP were agreed in December 2005 and a commitment secured
for a review of CAP in 2008-09 (which falls after the PSA time-horizon)?
9. SR-2002 PSA-7A1 is assessed as "rednot
met" because there were 99 "functioning democracies"
at the end of the SR-2002 PSA period, compared with the target
of 105 (2006 Report, p 140). The 2005 Autumn Performance Report,
only six months before the end of the PSA period, also assessed
the number to be six short of the target. On what basis did the
APR assess this as "ambergenerally on course"?
What six countries did the FCO expect to become functioning democracies
during that last six months of the PSA period?
Similarly, which four countries did the FCO expect
to achieve impartial judiciaries during the last six months of
the PSA period in order to avoid the PSA-7A3 assessment becoming
red by the time of the Annual Report?
10. What changes took place in the six months
between the 2005 Autumn Performance Report and the 2006 Annual
Report to support an improvement in the assessment for constitutional
reform of the Overseas Territories from "red" to "amber/greenmet/ongoing"
(Annual Report p 152; APR p 52)? Why were the APR and Annual Report
assessments not "red", given that the target related
explicitly to a position that had to be reached by March 2005?
Conversely, what changes in that six month period
supported a revision from "amber" to "red"
for Overseas Territories' environment commitments (SR-2002 PSA-11B)?
Letter to the Clerk of the Committee from
the Head of the Parliamentary Relations and Devolution Team, FCO,
dated 22 June 2006
THE FAC'S
REPORT ON
THE FCO'S
DR 2004-05
Dear Steve,
Thank you for your first letter of 8 June requesting
information in advance of Michael Jay's appearance before the
Committee on 28 June. I have pleasure in providing the information
you requested and for ease of reference I have included our responses
immediately below your questions.
We are working on the additional questions covered
in your second letter of 8 June and we will respond as you requested
before the Summer adjournment.
DOCUMENTS/SUMMARIES/CONCLUSIONS
THAT THE
COMMITTEE WISHES
TO RECEIVE:
A copy, or summary, of the regulatory reform "simplification
plan" [the FCO's submission to the Committee of 3 October
2005 noted that this was expected by to be ready in January 2006.]
As part of the Government's Better Regulation
programme, the first drafts of departmental simplification plans
were submitted to the Better Regulation Executive (BRE) of the
Cabinet Office in January 2006. This was followed by a period
of redrafting in consultation with the BRE. On 5 June 2006, BRE
issued revised guidance to all Departments which makes a further
redraft necessary. The FCO simplification plan is therefore not
ready. We are working to a deadline of November 2006 for clearance
by the Panel for Regulatory Reform (PRA) and for publication of
the final plan. A copy of the plan will be made available to the
FAC as soon as it is agreed by PRA.
As the FCO has little legislation, our simplification
plan is focussed on simpler services to the public (mainly visa
and consular services), and the burdens on our front line consular
and visa staff. As consular and visa services are self financing,
the savings resulting from the plan will accrue to users of our
services, and will be reflected in the level of fees charged to
recover the costs of running the services rather than appear as
cash savings to the FCO.
A copy of the conclusions of the FCO's Financial
Management Review [in the FCO's submission to the Committee, a
"final report" was anticipated in November 2005.]
I attach a summary of the main themes and conclusions
arising from the Financial Management Review conducted with HM
Treasury, which was the document that was distributed to the FCO
Board. A similar review was carried out by the Treasury with all
government departments. These reviews were carried out on the
basis of finding a mutual understanding between the Treasury and
the Department concerned of how financial management could be
improved and were not for publication. A number of committees
have been similarly provided with a summary of the main themes
and recommendations.
The FCO Financial Management Review (FMR) is
part of a cross-government review of financial management announced
at the time of SR 2004. It was carried out using an agreed financial
management framework for all departments, focusing on:
Accountability structures, planning
and budgeting.
Production and use of financial information.
The effectiveness and efficiency
of the finance function.
Relationships with HM Treasury.
The FCO review was carried out from August to
November 2005 by a team consisting of officials from HM Treasury,
the National Audit Office, Food Standards Agency and FCO. It was
a collaborative exercise carried out in consultation with FCO
officials.
The Review concluded that the FCO have
made good progress in improving their ability to manage resources
against objectives and that a large number of further reforms
are in train which have the potential to deliver a step-change
in performance. The Review Team noted that recent improvements
and reforms already underway included:
The FCO's 2003 strategy set out clearly
its strategic priorities and associated PSA targets. The priorities
were well understood and provided a framework for resource allocation.
Policy and resource responsibilities would be aligned from April
2006.
The Board's committee structure and
corporate governance represented best practice with skilled non-executive
Directors playing a leading role.
The Board was receiving a monthly
management information pack that had a high-quality structure,
with the content improving as the Prism Oracle system was implemented.
The commitment to faster closing
of the 2005-06 accounts, aimed at bringing forward the audit completion
date by four months.
Support for the Board's plans to
devolve most pay budgets to DGs from 2007-08.
Evidence of lessons learnt from the
early stages of the Prism programme, of firm Board control of
the remaining global rollout project and of benefits starting
to be delivered.
Recognition of the need to simplify
and standardise many of the FCO's business processes and of steps
being taken to do so.
The report concluded that the key challenge
was to ensure the practical delivery of this high-level vision.
This required leadership and commitment not just to the vision
but also to the significant changes in behaviour and working practices
that would be needed to deliver it.
In terms of areas for improvement, the four
overarching themes for the FCO were:
A stronger, more strategic role for
the Board in financial management and business planning.
Better project management and Board
impetus to work on cross-cutting business change, ICT and efficiency
initiatives.
High quality management information,
appropriate skills and incentives at all levels to improve the
way the FCO is run.
The Board needed to be supported
by a better and stronger finance function with wider reach and
greater weight.
On the first themethe role of the Boardthe
FMR underlined the need for full financial analyses of costed
options, as better quality management information from Prism was
generated and used. The Review supported further work and early
decisions, supported by robust business cases, on "hub and
spoke" options for service delivery currently being piloted
in Italy and Spain and planned for the US.
In relation to driving business change and efficiencies,
the Review highlighted that the Board should intensify efforts
to get full benefits from ICT investments, including Prism and
future projects. It also expressed support for measures to identify
and spread finance and HR process efficiencies across the FCO
network.
The Review also looked at the production and
use of management information. It concluded that there should
be less use of "off line" and instead the global network
of PRISM should be fully exploited. The report noted the importance
of spreading and embedding financial skills throughout the organisation
in line with the rest of Whitehall using the new Professional
Skills for Government framework. Accredited resource management
experience was especially important at senior level.
The final main theme was the role and status
of the finance function within the FCO. The Review recommended
that resource management units should be accountable to the Finance
Director as well as individual Directors General. There were also
recommendations about the role and status of the new Finance Director
who should be a finance professional in line with HMT recommendations.
The report recommended that the FCO carry out
its own review of the finance function.
The FCO is actively pursuing all the Review's
recommendations, in timescales agreed with HM Treasury.
The results of the formal review of the global
opportunities fund [this was anticipated in the FCO's submission
to the committee to take place "at the end of 2005-06".]
The review of the FCO's discretionary programme
budgets, including the Global Opportunities Fund, will shortly
be finalised, and the FCO Board will discuss it on 7 July. We
will share it with you thereafter.
QUESTIONS ARISING
FROM THE
FCO RESPONSE TO
THE COMMITTEE'S
REPORT
1. In reply to Recommendation 13, the FCO
response states that an internal investigation into the satellite
telephone fraud "is nearing completion". The Committee
wishes to receive a copy of the report of this investigation,
if possible before the oral evidence session on 28 June.
The FCO's Financial Compliance Unit report forms
part of the ongoing consideration of disciplinary action and cannot
be released without prejudice but the Comptroller and Auditor
General's formal report on the matter to the House of Commons
will, we understand, be issued shortly.
What are the revised procedures that the FCO has
put in place to avoid a recurrence of the Bahrain fraud?
FCO procedures have been put into place to tighten
our management of the Chevening scheme. We now require all FCO
Chevening Officers to maintain a database of selected scholars
separate to that kept by the British Council. The authority to
administer an award form (Chev 2) has been amended. The FCO Chevening
Officer's signature is now counter-signed by another Diplomatic
Service officer confirming that the expenditure of £20,000
or more can take place. Both officers are now required to initial
all pages of the form. This ensures that no details can be substituted.
The British Council must only administer awards approved on Chev
2 forms. FCO Chevening Officers have been instructed that award
letters must be prepared on headed notepaper by the Post. Details
must be checked with the selection database beforehand. Letters
of congratulation sent by Ambassadors or High Commissioners must
not be sent out until the award letter has been prepared and the
details checked.
2. In reply to Recommendation 23, the response
publishes the red, amber, green list of FCO activities. Who drew
up the list? Which of the "red" activities does the
FCO agree should be stopped completely? Which of the "amber"
activities does the FCO agree should be curtailed or reviewed?
With specific reference to activities related to the work of Members
of Parliament, under which colour group would the FCO place: (a)
briefing for MPs undertaking their official Parliamentary duties,
including overseas trips with select committees, CPA delegations
or IPU delegations; (b) briefing for MPs travelling with all-party
Parliamentary groups; (c) briefing for MPs acting in their own
capacity?
The Red Amber and Green List referred to was
produced by officials inside the FCO during 2004-05. It was intended
to suggest areas that might be stopped or given less priority
by geographical departments in London. The list was seen by Collinson
Grant who calculated the potential savings if the list were implemented
in full. However the Board did not adopt the list and it is not
FCO policy. The FCO does not "classify" activities on
the list according to any colour scheme (Red, Amber, Green).
Activities directly impacting on external stakeholders,
such as the work of Members of Parliament, have continued as usual.
Geographic departments have been free to use the list for internally
focused activities and have stopped a formal requirement for Annual
Reviews, facilitating former ambassador travel/access and devising
programmes for visiting Heads of Post.
Our relationship with Parliament and its Members
is a high priority for the FCO and we always seek to be open and
helpful to Committees, delegations, all party groups and individual
Members. We do not use the red/amber/green classification in the
Collinson Grant report in deciding what briefing to give Members.
Our policy on briefing the different categories of
Members the Committee asks about is as follows:
(a) Briefing for MPs undertaking their
official Parliamentary duties, including overseas trips with select
committees, CPA delegations or IPU delegations
Officials should provide written or oral briefings
when requested by select committees travelling abroad and by outgoing
IPU or CPA delegations.
(b) Briefing for MPs travelling with all-party
Parliamentary groups
Officials should help all-party Parliamentary
groups where practicable. They should be ready to offer unclassified
written briefing and an oral briefing if specifically requested.
(c) Briefing for MPs acting in their own
capacity
Officials should be as helpful as possible in
providing factual oral and written briefings, while being careful
not to compromise their official impartiality. Officials should
judge the resources they are able to allocate to such briefings
in the light of their strategic priorities and the potential benefits
to their objectives of such work.
3. The overall response rate during the data
collection phase of the Collinson Grant review was 89% in the
UK and 93% overseas. What was the response rate (a) among members
of the Senior Management Structure and (b) among Board members?
(a) The data set produced by Collinson Grant
at the end of their review indicates that responses were received
from 85.5 Senior Management Structure (SMS) officers based in
the UK. Details are not available of the total number to whom
forms were sent. Hence it is not possible to give a precise figure
for the SMS response rate, although it was in excess of 80%.
(b) Responses to the Collinson Grant review
were treated anonymously. Hence the dataset that was produced
for the FCO at the end of the review does not allow identification
of individuals, nor does it give details of who did not respond.
This means that Board members cannot be identified.
4. The Committee wishes the FCO to reconsider
its response to Recommendation 36 and to release the documents
about the Embassy to the Holy See, referred to in that Recommendation.
We have re-considered the decision not to release
documents about the Embassy to the Holy See. The reasons given
earlier for declining to release the documents still stand and,
as such, we consider that it remains inappropriate to release
these documents.
QUESTIONS ARISING
FROM THE
DEPARTMENTAL ANNUAL
REPORT 2005-06
5. The March 2006 White Paper (Active Diplomacy
for a changing World, Cm 6762) identified nine new "strategic
international priorities" (p 28), and brigaded under each
of these a number of "specific aims" (pp 52-59). Why
does the DAR not address these new priorities and aims? To what
extent does the FCO expect these to be the basis of any new PSA
targets in the 2007 Spending Review?
What are the FCO's proposals for involving the
Committee in formulating those objectives and targets?
The FCO's Departmental Report is an account
of the FCO's performance from 1 April 2005 to 31 March 2006 and
during the reporting period the FCO was working to its eight Strategic
Priorities identified in the 2003 White Paper. On 28 March 2006
the Foreign Secretary published a new White Paper revising the
strategic international prioritiesActive Diplomacy for
a Changing World (Cm 6762). These will be reported on in next
year's Departmental Report, which covers the period 1 April 2006
to 31 March 2007.
Sir Michael Jay wrote to the Chairman of the
FAC on 12 January 2006 to advise the FAC that the FCO were reviewing
the strategic priorities, and to invite the Committee's views.
We continue to welcome the FAC's interest in the strategic international
priorities, and in particular their announcement that they will
conduct a review of the White Paper to assess its continuing relevance
to a constantly changing international situation.
We expect the 2006 White Paper and the subsequent
announcement of a Strategic Priority on climate change to form
the basis of the 2008-11 PSA (as the 2003 white paper informed
the 2005-08 PSA). The next review of strategy is due in 2008 and
it is possible that any significant changes would be reflected
in our new PSA (the FCO is committed to reviewing the UK's international
priorities (FCO's strategic priorities) every two years to ensure
they remain relevant). We welcome the FAC's interest in and views
on our PSA targets. PSAs are proposed to HMT and we will take
into account any views made. We will start negotiations with HMT
later this year on the 2008-11 PSA.
6. In regard to the SR-2002 PSA-4C, the FCO
reports that it has been unable to develop a new tool for measuring
conflict levels (2006 Annual Report, p 137). The Report notes
the "inherent difficulties in measuring potential sources
of future conflict and conflict prevention outcomes" and
that a "final assessment . . . will be made in Spring 2008"
(p 112). What work is the FCO doing to develop a means of being
able to make that assessment of the outcomes of its Conflict Prevention
work in 2008?
Conflict prevention is a complex area in which
to measure outcomes. The SR02 report underlined the inherent difficulties.
In the light of this experience, and accepting the limitations,
FCO, MoD and DFID, the three Departments who jointly own the Conflict
PSA, decided in agreement with HM Treasury, to report against
the SR04 target using primarily narrative reporting, assessed
against a narrative, rather than a statistical, baseline. To inform
this reporting, the three Departments are drawing on a wide range
of sources, both from within HMG and from international organisations
and NGOs.
Separately, HMG is working with partners in
the framework of the OECD Development Assistance Committee, to
examine how to develop improved methodologies for evaluating the
impact of conflict prevention interventions.
7. The SR-2002 PSA on Conflict Prevention
included assessments which used statistics on the number of casualties
and refugees, although most of these were not carried over into
the SR-2004 PSAs. Why do SIPRI/IISS casualty statistics still
form part of the assessment of the situation in Nigeria (2006
Report, p 114), and why not for other conflict areas?
Given the difficulties in measuring conflict
prevention outcomes in purely statistical terms, FCO, MOD and
DFID, the three Departments who jointly own the Conflict PSA,
decided, in agreement with HMT, to report against the SR04 using
primarily narrative reporting, drawing on a wide range of sources.
But for some of the PSA sub-targets, statistical reports from
SIPRI/IISS continue to be a source of relevant data.
In the specific case of Nigeria, the number
of conflict related deaths was considered a useful indicator of
the effectiveness of Nigeria's local and central government institutions
in mediating in and managing conflict. SIPRI/IISS reports were
used because they were seen as a reliable way of measuring that.
This statistical reporting is accompanied, as the recent FCO Departmental
Report shows, by a broader narrative assessment of political developments
bearing on conflict risk in Nigeria.
8. SR-2004 PS-A4AK envisages agreement on
EU financing arrangements for 2006-13, with spending at 1% of
EU GDP (2006 Report, p 117). With the UK Presidency having overseen
a budget deal in 2005, why is this PSA still assessed as "amber/on
course" rather than as a (red or green) settled outcome?
Similarly, why is PSA-4AL still amber, when changes
to the CAP were agreed in December 2005 and a commitment secured
for a review of CAP in 2008-09 (which falls after the PSA time-horizon)?
The amber rating for SR-2004 PS-A4AK reflects
the fact that whilst significant progress has been made towards
achieving the objective, we will continue to pursue budget discipline,
regional policy reform, and protection of the UK net position
in discussions between now and the end of PSA period. These include
discussions to give effect to the revenue side of the December
agreement (known as the Own Resources Decision), and our preparatory
work for the 2008-09 review of the EU budget.
Similarly, the amber rating for SR-2004 PSA-4AL
reflects the fact that we will continue to make the case for reform
of the Common Agricultural Policy in various fora. These include
discussions about individual CAP regimes (eg reform of the EU
fruit and vegetables regime), discussion in the WTO, in preparation
for the 2008 review of the 2003 CAP reforms, and in preparation
for the 2008-09 budget review.
9. SR-2002 PSA-7A1 is assessed as "rednot
met" because there were 99 "functioning democracies"
at the end of the SR-2002 PSA period, compared with the target
of 105 (2006 Report, p 140). The 2005 Autumn Performance Report,
only six months before the end of the PSA period, also assessed
the number to be six short of the target. On what basis did the
APR assess this as "ambergenerally on course"?
What six countries did the FCO expect to become functioning democracies
during that last six months of the PSA period?
Similarly, which four countries did the FCO expect
to achieve impartial judiciaries during the last six months of
the PSA period in order to avoid the PSA-7A3 assessment becoming
red by the time of the Annual Report?
The Committee correctly notes that these targets
were highly unlikely to be achieved before the end of the PSA
period. The indicator was shown in error as amber. Nonetheless,
the assessments in the Autumn Performance Report were intended
to reflect the fact that there had been real progress made towards
achieving both indicators. The narratives were intended to bring
out the fact that an exclusive focus on the headline target figures
did not capture the positive trends on both targets to which FCO
activity had contributed. For example, under indicator A1 the
APR stated: "While we would not currently expect to achieve
this target, the overall trend over the period of the PSA has
been positive and there has been a significant increase in the
number of countries implementing systems, processes and procedures
widely accepted to be necessary in a fully functioning democracy".
We are grateful to the committee for this opportunity
to correct this error.
10. What changes took place in the six months
between the 2005 Autumn Performance Report and the 2006 Annual
Report to support an improvement in the assessment for constitutional
reform of the Overseas Territories from "red" to "amber/greenmet/ongoing"
(Annual Report p 152; APR p 52)? Why were the APR and Annual Report
assessments not "red", given that the target related
explicitly to a position that had to be reached by March 2005?
Conversely, what changes in that six month period
supported a revision from "amber" to "red"
for Overseas Territories' environment commitments (SR-2002 PSA-11B)?
On the indicator relating to constitutional
reform in the Overseas Territories target, as a result of a typographical
error in the internal guidelines, "amber/green" was
incorrectly included as the traffic light. The correct colouring
should have been "red" because, as the narrative explained,
the target dates could not be met.
The error also affected the colouring of the
traffic lights for the overall assessment of the Overseas Territories
target and the fourth target indicator (on economic development).
Both of these should have been "amber/red" and not "amber/green",
as some of the target/target indicator elements were met but not
others. Again the narrative to which the traffic lights were attached
set out correctly the position in terms of meeting the target/indicators.
The decision on extension of the relevant multilateral
environment agreements to the individual territories rests with
the OT Governments, rather than the UK Government. During the
reporting period, despite earlier hopes, it became clear that
the extension of the Conventions could not be achieved in 2006.
Therefore the traffic light was moved from "amber" to
"red".
We are grateful to the committee for the opportunity
to correct this error.
Yours sincerely,
Chris Stanton
Parliamentary Relations and Devolution Team
Letter to the Head of the Parliamentary
Relations and Devolution Team, FCO, from the Clerk of the Committee,
dated 8 June 2006
Dear Chris,
Further to my letter of earlier today, I am
now able to enclose a list of further questions on matters arising
from the Departmental Annual Report 2005-06, to which the Committee
would appreciate answers before the Summer adjournment. There
is also one question (Q9) for which a longer timeframe may be
appropriate.
Yours,
Steve Priestley
Clerk of the Committee
QUESTIONS ARISING
FROM THE
FCO RESPONSE TO
THE COMMITTEE'S
REPORT
1. According to Table 5 [p 80] of the 2006
Departmental Annual Report, in 2005-06 "information and computer
technology" efficiencies were £2.3 million compared
with a planned figure of £4.7 million. What are the factors
behind this shortfall? To what extent are delays with the Prism
computer system reducing the level of otherwise expected ICT efficiencies,
in each year 2005-06 to 2007-08?
2. In the 2006 Annual Report, two classes
of "Administration" costs show large increases in provision
for 2006-07, compared to that given for 2005-06 in last year's
Departmental Report. The "centrally controlled administration
budget" (£571 million) increase by 20% and "locally
controlled administration costs" (£257 million) by 50%
(Table 15, p 89). To what extent are these increases the result
of changes in the way costs have been brigaded under different
Administration headings, and to what extent do the changes represent
additional cost?
3. The 2006-07 provision for receipts for
visa and other services provided at Consular Offices (2006 Report,
Table 15) shows a 77% increase on 2005-06 given in last year's
Departmental Report. To what extent is the increase attributable
to:
(a) increases in visa applications; and
(b) the restructuring of visa fees?
The budgeted receipts of £254 million are
expected to be less than costs of £285 million (2006 Report,
p 90). To what extent are costs planned to be covered by receipts
in 2006-07 for:
(b) other consular services?
What was the actual coverage of costs under
each of these headings in 2005-06?
The fees charged for visa applications were
restructured in the Consular Fees Order 2005, which came into
force on 1 July 2005. Why did the FCO not undertake a Regulatory
Impact Assessment of the changes (2006 Report, p 82)?
4. The 2005 Departmental Report did not
include details of the "iVisas Biometrics Programme"
(valued at £70 million) because it had not then started (2005
Report, Table 16, footnote 4). Similarly, the 2006-07 capital
projects table (Table 16) in the 2006 Departmental Report does
not include it, although the Report reaffirms the FCO's commitment
to a global roll-out of biometric visas from October 2006 (p 24).
With the project expected to be underway in 2006-07, why does
Table 16 not include details of this project?
What progress has been made to date on the iVisas
Biometrics Programme?
What is the estimated average cost of collecting
and processing biometric data for biometric visas? What proportion
of the £254 million visa/consular service budgeted receipts
and £285 million costs (2006 Report, p 90 and 91) are for
providing biometric visas?
The Committee would like cost and timescale
details for the Visas Biometrics Programme, brigaded under the
same heading used in Table 16.
5. The 2006 Annual Report notes that revenue
from property sales is now fully "recycled" back into
the estate (p 75). Against that background, what are the factors
producing a fall in the value of residential land and buildings
and fixtures and fittings of over £200 million between 2004-05
and 2005-06 (Table 11)?
6. Three estate building projects in Table
16 of the 2006 Annual Report have start dates prior to 2005, but
had not been listed in the previous 2005 ReportColombo,
Sana'a, and Doha. Why were these projects not reported in the
2005 Report?
7. Table 18 of the 2006 Departmental Report
notes the contributions of different government departments to
various UN programmes. To what extent do the figures in Table
19, on non-UN programmes, include contributions made by government
departments other than the FCO?
The Table 19 non-UN programme costs for 2005-06
are £133.5 million (2006 Report, p 101). To what extent does
this reflect a real increase in expenditure from the £26.3
million reported for the previous year in the 2005 Report (Cm
6533, Tables 19 and 20 combined)? How, if at all, do the non-UN
programmes listed in Table 19 of the 2006 Report differ from those
covered in the 2005 Report?
8. SR-2002 PSA-2 on reducing tensions subsumes
individual assessments for a range of regions, many of which are
rolled over into the SR-2004 PSAs. Why were Sri Lanka, Ethiopia/Eritrea,
Ivory Coast and Angolawhich were assessed as "red"dropped
from the SR-2004 PSAs?
SR-2004 PSA-3 on Conflict Prevention includes
the security situation in nine regions/countries, but excludes
India/Pakistan and Sri Lanka which were assessed in the similar
PSA-2 of SR-2002. Why were these two regions left out of the SR-2004
PSA?
Overall, the SR-2004 PSA is assessed as "amber"
("on course"), despite "reds" for three areas.
What would the FCO's assessment have been had the situation in
India/Pakistan and Sri Lanka still been included in the PSA?
9. The Committee wishes to receive a finalised
assessment of the Efficiency Programme performance for 2005-06
(2006 Annual Report, Table 5), once the FCO has been able to complete
its assessment by the Autumn, along with any revision to the planned
savings for 2006-07 and 2007-08 made at that time. The Committee
wants an explanation about the process involved and timescales
needed in estimating and then finalising the efficiency assessments.
If, once the firmer data are available, some classes of efficiency
continue to show a fall in cumulative annual savings (as is currently
the case in regard to "reductions in low priority activity"),
the Committee would wish to have an explanation.
Letter to the Clerk of the Committee from
the Head of the Parliamentary Relations and Devolution Team, FCO,
dated 12 July 2006
FCO DEPARTMENTAL
REPORT 2005-06
Dear Steve,
I have pleasure in providing detailed responses
to the questions you raised in your second letter of 8 June.
Q1. According to Table 5 [p 80] of the 2006
Departmental Annual Report, in 2005-06 "information and computer
technology" efficiencies were £2.3 million compared
with a planned figure of £4.7 million. What are the factors
behind this shortfall? To what extent are delays with the Prism
computer system reducing the level of otherwise expected ICT efficiencies,
in each year 2005-06 to 2007-08?
Answer
The reason for the shortfall in ICT efficiencies
in 2005-06 is that the ICT target set at the beginning of the
implementation period double counted some of the benefits delivered
by Prism which had also been included in other efficiency projects
eg Procurement efficiencies and HR reductions within Corporate
Services.
Efficiencies enabled by Prism in 2005-06 totalled
£4.4 million against a planned outturn figure of £4.7
million set at the beginning of the implementation period. Of
the £4.4 million, £2.3 million is shown in the table
under ICT efficiencies and the remaining £2.1 million appears
under other projects.
The ICT projects are now expected to deliver
£8.2 million of efficiencies in 2007-08 against an initial
planned outturn figure of £24.7 million. This shortfall is
not due to delays in Prism. It is caused by the double counting
in the targets of some Prism benefits and the delay in Future
Firecrest implementation due to additional security requirements.
The FCO has introduced a number of new efficiency
projects to bridge this gap and is confident of meeting its overall
target.
Q2. In the 2006 Annual Report, two classes
of "Administration" costs show large increases in provision
for 2006-07, compared to that given for 2005-06 in last year's
Departmental Report. The "centrally controlled administration
budget" (£571 million) increase by 20% and "locally
controlled administration costs" (£257 million) by 50%
(Table 15, p 89). To what extent are these increases the result
of changes in the way costs have been brigaded under different
Administration headings, and to what extent do the changes represent
additional cost?
Answer
The main reason for the increase in gross expenditure
is the increasing costs of the consular and visa operations, which
are fully funded by income, and the uplift in the FCO's administration
budget in Spending Review 2004.
The differences between the methodology used
in each year account for some of the increases on the individual
lines mentioned. The split in the table dates back to the old
Estimates structure when more expenditure was centralised. For
2006 we therefore categorised the information by budget holder
type to reflect devolution of budgets. The Estates line, for example,
now only includes expenditure for which Estates Directorate hold
the budget and not all estates related expenditure. This has the
effect of increasing the local administration costs in the table.
Locally controlled administration costs have also risen because
of the transfer of £20 million from non-cash to cash to compensate
for the reclassification of furniture from capital to administration.
Q3. The 2006-07 provision for receipts for
visa and other services provided at Consular Offices (2006 Report,
Table 15) shows a 77% increase on 2005-06 given in last year's
Departmental Report. To what extent is the increase attributable
to (a) increases in visa applications and (b) the restructuring
of visa fees?
Answer
The 2005-06 Main Estimate figures took a conservative
view of consular and visa income, and matching expenditure, in
drawing up the Main Estimate to ensure that we did not end up
with an income shortfall leading to an overspend.
Forecasts of activity are regularly reviewed
in the light of actual demand and a final adjustment was made
in the Spring Supplementary to reflect our final expectation of
increased cost and income. The initial income of £144 million
in the Main Estimate was increased to £197 million in the
2005-06 Spring Supplementary. This compares to a forecast income
of £254 million in the 2006-07 Main Estimate.
The increased income over 2005-06 is due to
both continued increase in demand for visas, currently running
at 8% growth per annum, and the rise in both consular and visa
fees implemented on July 2005 to fund initiatives such as biometrics,
control strengthening and increased quality assurance. We will
provide a quantification of the individual impact of these once
the 2005-06 Accounts are finalised.
Q3. Cont. The budgeted receipts of £254
million are expected to be less than costs of £285 million
(2006 Report, p 90). To what extent are costs planned to be covered
by receipts in 2006-07 for (a) visa services and (b) other consular
services?
Answer
The budgeted receipts are less than the forecast
costs because the FCO has £32 million in its baseline allocation
from Treasury to reflect the Consular premium element of passport
fees collected by the UK Passport Service which are paid into
the Consolidated Fund. The FCO's budget will be adjusted by any
change in consular premium collected by the UKPS in the 2006-07
Spring Supplementary. In addition there are some £7 million
of visas issued for which no fee is recovered.
Under Fees and Charges Guidelines, fees have
been set to recover the full economic cost of providing the service.
Q3. Cont. What was the actual coverage of
costs under each of these headings in 2005-06?
Answer
The schedule 5 costs and income for 2005-06
are currently being prepared and are due to be finalised and signed
of by the Permanent Under Secretary in July 2006. We will provide
these figures to the FAC once the 2005-06 Accounts have been finalised.
Q3. Cont. The fees charged for visa applications
were restructured in the Consular Fees Order 2005, which came
into force on 1 July 2005. Why did the FCO not undertake a Regulatory
Impact Assessment of the changes (2006 Report, p 82)?
Answer
Increases in visa fees are not a result of a
new policy proposal needing primary legislation and Cabinet Office
guidance states that Regulatory Impact Assessments are not required
if statutory fees are increased by a predetermined formula. UKvisas
is mandated by HM Treasury to cover the costs of issuing visas
and HM Treasury has agreed the formula used to set fee increases.
Q4. The 2005 Departmental Report did not
include details of the "iVisas Biometrics Programme"
(valued at £70 million) because it had not then started (2005
Report, Table 16, footnote 4). Similarly, the 2006-07 capital
projects table (Table 16) in the 2006 Departmental Report does
not include it, although the Report reaffirms the FCO's commitment
to a global roll-out of biometric visas from October 2006 (p 24).
With the project expected to be underway in 2006-07, why does
Table 16 not include details of this project?
Answer
The Biometrics programme was omitted from Table
16, as the FCO does not have any capital provision for the Biometrics
project in the Main Estimates. However, the Home Office plans
to include a £10 million transfer to the FCO in the Winter
Supplementary Estimate to cover capital expenditure on Biometrics
in 2006-07 and a further transfer is expected to be included in
the Spring Supplementary Estimate, pending Home Office Group Investment
Board consideration of the Full Business Case in November.
Q4. Cont. What progress has been made to
date on the iVisas Biometrics Programme?
Answer
Initial proof of concept pilots in Sri Lanka
and East Africa were set up in 2003-04, with Vietnam, the Netherlands
and the Democratic Republic of Congo added in 2005. The results
of these pilots have been invaluable in informing the design of
the global system. The major difference in the pilots and what
is proposed in the global roll-out is the tranfer mechanism and
the time it takes to match fingerprints against the Home Office
Immigration and Asylum Fingerprint Service database and relay
the results back to our overseas posts.
Since the UKvisas Biometrics Programme was set
up in April 2005, a fast and secure system has been developed,
together with the supporting business process changes. The global
system will ensure accessibility, quick, simple and discreet data
capture from applicants and biometric information matching that
enables responses to be sent back to Posts within 30 minutes of
the applicants' data being entered on the system.
Plans for global roll out are now being finalised
and we are presenting these to Ministers in July. Roll out will
begin in Autumn 2006 and will continue until the end of 2007.
Q4. Cont. What is the estimated average cost
of collecting and processing biometric data for biometric visas?
Answer
We estimate that the average incremental cost
of processing a biometrically enabled visa (as opposed to a non
biometric one) will be between £5-£6. We are undertaking
an activity based costing exercise to further validate this costing.
Q4. Cont. What proportion of the £254
million visa/consular service budgeted receipts and £285
million costs (2006 Report, p 90 and 91) are for providing biometric
visas?
Answer
In agreement with HMT we set worldwide fees
to recover costs. We do not expect to create either a surplus
or a deficit at this time. Under HMT Fees and Charges Guidelines
we are not allowed to cross-subsidise different visas. Under Net
Administration Costing Regime principles, we expect the costs
of providing the service to equal income. Actual costing information
by post for 2005-06 are not yet available to confirm this figure.
This actual data should be available in September 2006.
Total income from global visa fees 2005-06
| £163,361,565 |
Total visa income for the 11 Posts taking part in the biometrics "proof of concept" pilot
| £9,111,815 |
Pilot posts' income as a percentage of global visa fee receipts
| 5.58% |
Q4. Cont. The Committee would like cost and timescale details for the iVisas Biometrics Programme, brigaded under the same heading used in Table 16.
Answer
| |
Long term capital projects 2006-07 (capital costs only)
Project: UKvisas Biometrics Programme: Year started
| 2005 |
Current estimate of completion | End-2007
|
Current estimate of capital cost | *£65.6 million
|
Expenditure in previous year | *£3.2 million
|
Estimated provision 2006-07 |
*£31.8 million |
To be spent in future years |
*£30.6 million |
| |
*As part of an evolving programme and in developing the full business
case we are currently evaluating our costs and looking closely
at projected expenditure.
Q5. The 2006 Annual Report notes that revenue from property
sales is now fully "recycled" back into the estate (p
75). Against that background, what are the factors producing a
fall in the value of residential land and buildings and fixtures
and fittings of over £200 million between 2004-05 and 2005-06
(Table 11)?
Answer
The forecast value of residential land and buildings shown
in the 2005-06 report was not updated during the preparation of
the report, and is therefore incorrect. We regret the error and
apologise for any inconvenience caused. I attach a table (annex
A) showing the provisional figures for 2005-06. The FCO's draft
Resource Accounts 2005-06 show that the value of residential land
and buildings has increased from £554 million at 31 March
2005 to £697 million at 31 March 2006. The change reflects
acquisitions and disposals and changes in property values recorded
in the property revaluation process.
Given the many uncertainties in this area (RICS guidelines
specifically preclude surveyors from providing projections of
future property values) we will base this table on a steady state
assumption in respect of property assets for future years.
Q6. In regard to the SR-2002 PSA-4C, the FCO reports that
it has been unable to develop a new tool for measuring conflict
levels (2006 Annual Report, p 137). The Report notes the "inherent
difficulties in measuring potential sources of future conflict
and conflict prevention outcomes" and that a "final
assessment . . . will be made in Spring 2008" (p 112). What
work is the FCO doing to develop a means of being able to make
that assessment of the outcomes of its Conflict Prevention work
in 2008?
Answer
We covered this question in my reply to you of 22 June.
Q7. Three estate building projects in Table 16 of the
2006 Annual Report have start dates prior to 2005, but had not
been listed in the previous 2005 ReportColombo, Sana'a,
and Doha. Why were these projects not reported in the 2005 Report?
Answer
The start dates prior to 2005 given for the estate building
projects in Colombo, Sana'a and Doha indicate when preliminary
work commenced. These projects were not included in the list of
long term capital projects in the 2005 Annual Report because the
main construction contracts had not been let at the time of publication.
Q8. Table 18 of the 2006 Departmental Report notes the
contributions of different government departments to various UN
programmes. To what extent do the figures in Table 19, on non-UN
programmes, include contributions made by government departments
other than the FCO?
Answer
Table 19 shows UK contributions to non-UN peacekeeping. Peacekeeping
expenditure is funded from the peacekeeping element of the Global
Conflict Prevention Pools. All expenditure in this table is therefore
joint-funded by FCO, DFID and MoD.
Q8. Cont. The Table 19 non-UN programme costs for 2005-06
are £133.5 million (2006 Report, p 101). To what extent does
this reflect a real increase in expenditure from the £26.3
million reported for the previous year in the 2005 Report (Cm
6533, Tables 19 and 20 combined)? How, if at all, do the non-UN
programmes listed in Table 19 of the 2006 Report differ from those
covered in the 2005 Report?
Answer
The 2005 and 2006 tables on non-UN peacekeeping have been
drawn up on different bases. The 2005 table only included International
Tribunals and OSCE peacekeeping activity whereas the 2006 table
shows all non-UN peacekeeping. The attached table (annex B) restates
the 2005 table on the same basis as 2006 using final outturn figures.
Q9a. SR-2002 PSA-2 on reducing tensions subsumes individual
assessments for a range of regions, many of which are rolled over
into the SR-2004 PSAs. Why were Sri Lanka, Ethiopia/Eritrea, Ivory
Coast and Angolawhich were assessed as "red"dropped
from the SR-2004 PSAs?
Q9b. SR-2004 PSA-3 on Conflict Prevention includes
the security situation in nine regions/countries, but excludes
India/Pakistan and Sri Lanka which were assessed in the similar
PSA-2 of SR-2002. Why were these two regions left out of the SR-2004
PSA?
Answer
The Committee correctly notes that the FCO's SR02 PSA target
on Reducing Tension (PSA 2) was rolled forward into a number of
SR-2004 PSA targets, but primarily the Conflict Prevention (PSA
3) target. When the SR04 Public Service Agreement targets were
drafted, the FCO agreed with HM Treasury that it was not practical
to include all individual countries and regions of concern within
the SR04 PSA reporting framework.
When the SR04 Conflict Prevention (PSA 3) target was devised,
the three Departments sharing responsibility for delivery (FCO,
DFID and MoD) agreed with Treasury nine focus countries/regions
as representative of HMG's conflict related priorities. The criteria
for selection was based on:
level of UK government expenditure;
potential for the UK to make a significant contribution;
potential risks of involvement;
UK's key priorities; and
political context within which the UK was working.
India/Pakistan, Sri Lanka, Ethiopia/Eritrea, Ivory Coast
and Angola were assessed under the SR02 Reducing Tension (PSA
2) target. Angola and Sri Lanka were considered under the SR02
Conflict Prevention (PSA 4) target.
Although these countries did not meet the criteria for inclusion
on the representative lists of focus countries/regions, the FCO
continues to work with them. Detailed performance monitoring ceased
against some areas of our work to streamline and focus the SR04
PSA targets more closely with our strategic priorities.
Q9c. Overall, the SR-2004 PSA is assessed as "amber"
("on course"), despite "reds" for three areas.
What would the FCO's assessment have been had the situation in
India/Pakistan and Sri Lanka still been included in the PSA?
Answer
Baseline data, sources of data and indicators of success
were not set for India-Pakistan and Sri Lanka as part of the SR04
Conflict Prevention PSA target, so any assessment would be hypothetical.
However it is likely that, given the situation in India-Pakistan
and Sri Lanka at the time of the assessment (January 2006), the
overall assessment would remain "amberon course".
Q10. The Committee wishes to receive a finalised assessment
of the Efficiency Programme performance for 2005-06 (2006 Annual
Report, Table 5), once the FCO has been able to complete its assessment
by the Autumn, along with any revision to the planned savings
for 2006-07 and 2007-08 made at that time. The Committee wants
an explanation about the process involved and timescales needed
in estimating and then finalising the efficiency assessments.
If, once the firmer data are available, some classes of efficiency
continue to show a fall in cumulative annual savings (as is currently
the case in regard to "reductions in low priority activity"),
the Committee would wish to have an explanation.
Answer
Details of how efficiency gains are measured for each of
the FCO's efficiency projects is provided in the Efficiency Technical
Note, published on the FCO's website (and also attached at annex
C[1]). The timescale required
for reliable figures varies from project to project, but should
be available in the Autumn once reports have been produced from
the audited accounts. In line with the advice in the NAO report
"Progress in improving government efficiency" (February
2006), the FCO is verifying the figures for the efficiency gains
it has achieved to date.
The target and planned outturn figures in table 5 on page
80 of the FCO's Departmental Report are based on the initial efficiency
plan. These are consistent with figures published in the FCO's
Efficiency Technical Note and as such have not changed over time.
These figures are not the current forecasts of what these streams
will deliver. The estimated outturn figures are based on the latest
forecasts. These figures are an estimate of what has been actually
delivered rather than what was initially planned.
The FCO has added savings from additional projects to some
of the workstreams, partly to fill the gap caused by the ICT workstream
not meeting its target (see answer to question 1). The "Reductions
in low priority activity" workstream has two new projects,
namely "Alternative Representation" and "DSI Restructuring"
which were previously contingency projects, and delivered £6.6
million of efficiency savings in 2005-06. Hence the reductions
in low priority activity worksteam as a whole is already in excess
of the 2007-08 target of £4.5 million. This £6.6 million
will continue to be delivered in future years. Efficiency gains
are not recorded unless we are confident that they are sustainable
ie that they can be maintained beyond the SR04 period.
Yours sincerely,
Chris Stanton
Parliamentary Relations and Devolution Team
Annex A: FAC Question 5
Table 11
FOREIGN AND COMMONWEALTH OFFICE CAPITAL EMPLOYED (£
MILLION)
| 2000-01 | 2001-02
| 2002-03 | 2003-04 | 2004-05
| 2005-06 | 2006-07 | 2007-08
|
| Outturn | Outturn
| Outturn | Outturn | Outturn
| Provisional
Outturn | Projected
| Projected |
Assets on balance sheet at end of year
Fixed Assets
Intangible
| | 0 | 2 |
1 | 1 | 0 | 0
| 0 |
Tangible | 1,250 | 1,262
| 1,246 | 1,227 | 1,254
| 1,483 | 1,483 | 1,483
|
of which:
Non-residential land and Buildings
| 495 | 561 | 568
| 478 | 492 | 589
| 589 | 589 |
Residential land and Buildings | 471
| 491 | 471 | 540
| 554 | 696 | 696
| 696 |
Information Technology | 42 |
31 | 46 | 54 | 40
| 42 | 42 | 42 |
Plant and machinery | 12 |
13 | 12 | 14 | 14
| 16 | 16 | 16 |
Vehicles | 13 | 13
| 13 | 25 | 21 |
18 | 18 | 18 |
Antiques & works of art |
| | 20 | 19 |
19 | 20 | 20 | 20
|
Furniture & fittings* | 126
| 103 | 71 | 55
| 43 | 0 | 0 |
0 |
Assets in the course of construction | 91
| 51 | 45 | 43 |
71 | 102 | 102 |
102 |
Wilton Park | |
| | | | 1
| 1 | 1 |
Current Assets | |
| | |
| | | |
Stocks | 12 | 10
| 10 | 8 | 9 |
7 | 7 | 7 |
Debtors | 127 | 149
| 144 | 140 | 226
| 243 | 243 | 243
|
Cash at Bank and in hand 17 |
15 | 72 | 39 | 76
| 130 | 130 | 130
|
Creditors <1 year | -125 |
-83 | -126 | -97 |
-250 | -339 | -339
| -339 |
Creditors >1 year | | 0
| -33 | -32 | -32
| -31 | -31 | -31
|
Provisions | -27 | -30
| -30 | -47 | -66
| -67 | -67 | -67
|
Total Capital Employed |
1,254 | 1,325 | 1,285
| 1,240 | 1,217 |
1,427 | 1,427 | 1,427
|
| | |
| | | |
| |
*With effect from 1 April 2005 Furniture and Fittings have been
reclassified as administration expenditure.
Annex B: FAC Question 8
UK CONTRIBUTIONS TO NON-UN PEACEKEEPING 2004-05
SUB-SAHARAN
AFRICA
| Programme/Activity
| Final Spend 2004-05 |
Assessed Contributions |
| |
Country/Region | |
|
Sudan | AU Mission | 2,240,000
|
Sub-Total | | 2,240,000
|
Functional/Thematic |
| |
Rwanda Trib | ICTR | 4,408,625
|
Sub-Total | | 4,408,625
|
Total Assessed | |
6,648,625 |
Non-Assessed Contributions |
Country/Region | |
|
Sudan | Nuba Mtn Monitors and VMT
| 725,639 |
Sub-Total | | 725,639
|
Functional/Thematic | |
|
Sierra Leone | Special Court
| 2,000,000 |
Sub-Total | | 2,000,000
|
Total Non-Assessed | | 2,725,639
|
Sub-Saharan Africa Total
|
9,374,264 | |
|
| | |
GLOBAL (NON
SUB-SAHARAN
AFRICAN)
| Programme/Activity
| Final Spend 2004-05 |
Assessed Contributions |
| |
Country/Region | |
|
Albania | OSCE | 271,356
|
Bosnia | EUFOR | 0
|
Bosnia | EUMM | 517,000
|
Bosnia | EUPM | 2,485,000
|
Bosnia-Herzegovina | OSCE |
818,350 |
Croatia | OSCE | 510,034
|
Georgia | ESDP | 283,000
|
Georgia | OSCE | 1,305,606
|
Kosovo | OSCE | 2,794,344
|
Macedonia | EUPOL Proxima |
1,426,000 |
Nagorno-Karabakh | OSCE |
73,732 |
Sub-Total | |
10,484,422 |
OSCEFormer Programme Activity
| | |
Armenia | OSCE | 92,966
|
Azerbaijan | OSCE | 108,967
|
Belarus | OSCE | 63,913
|
Estonia Mil Pensions | OSCE
| 9,917 |
FRY (Inc Montenegro) | OSCE
| 470,385 |
Kazakhstan | OSCE | 105,557
|
Kyrgystan | OSCE | 134,861
|
Macedonia | OSCE | 906,264
|
Moldova | OSCE | 104,620
|
Tajikistan | OSCE | 277,168
|
Turkmenistan | OSCE | 77,411
|
Ukraine | OSCE | 74,395
|
Uzbekistan | OSCE | 113,397
|
Sub-Total | | 2,539,821
|
Functional/Thematic |
| |
ICC | Criminal Court | 5,154,495
|
Yugoslavia Tribunal | ICTY |
6,238,756 |
Sub-Total | | 11,393,251
|
Total Assessed | |
24,417,494 |
| | |
| Programme/Activity
| Final Spend 2004-05 |
Non-Assessed Contributions |
| |
Country/Region | |
|
Albania | OSCE | 106,565
|
Bosnia | EUPM | 4,403,630
|
Bosnia | OSCE | 674,151
|
Balkans (Bos/Kos) | PSO |
86,500,000 |
Croatia | OSCE | 246,204
|
ESDP Fact Finding | ESDP |
46,000 |
Georgia | OSCE | 899,975
|
IPU | CivPol Mission Costs |
185,655 |
IPU (DPA tax payments) | CivPol Mission Costs
| 0 |
Iraq-Jordan | CivPol Mission Costs
| 10,774,592 |
Kosovo | OSCE | 1,028,656
|
Macedonia | EUPOL Proxima |
294,579 |
Middle East | Jericho Mon Mission
| 722,072 |
Middle East | EU Mon Group |
0 |
Nagorno-Karabakh | OSCE |
71,693 |
Yugoslavia | EUMM (Other) |
325,572 |
Sub-Total | | 106,279,343
|
OSCEFormer Programme Activity
| | |
Armenia | OSCE | 0
|
Azerbaijan | OSCE | 53,004
|
Belarus | OSCE | 53,835
|
FRY (Inc Montenegro) | OSCE
| 378,653 |
Kyrgystan | OSCE | 64,637
|
Macedonia | OSCE | 714,671
|
Moldova | OSCE | 65,543
|
OSCE Secretariat | OSCE |
289,341 |
Tajikistan | OSCE | 0
|
Turkmenistan | OSCE | 53,112
|
Sub-Total | | 1,672,796
|
Functional/Thematic |
| |
Khmer Rouge Trib | KRT |
500,000 |
Sub-Total | | 500,000
|
Total Non-Assessed |
| 108,452,139 |
TOTAL GLOBAL (NON SUB-SAHARAN AFRICAN)
| 132,869,633 |
TOTAL NON-UN PEACEKEEPING |
| £142,243,897 |
| | |
1
Not reprinted-available at http://www.fco.gov.uk Back
|