Select Committee on Office of the Deputy Prime Minister: Housing, Planning, Local Government and the Regions Minutes of Evidence


Annex A

ODPM CENTRAL EFFICIENCY PROGRAMME



ODPM (C)Target: £620 million by 2007-08, of which at least two thirds will be cashable.
Profile (£m) By Year
Total
(£m)
Targets
Interim
Savings (£m)
—figures yet
to be audited
Comments
ODPM (C) Efficiency Proposals
2005-06
2006-07
2007-08
Savings to date

Administration
8
16.5
25
0.05
Merger of Internal Audit Services with Cabinet Office Audit team successfully completed. Admin funding in the line already reflects savings efficiencies.
Regional Development Agencies
40
80
120
11.9
Plans for achieving savings of £139.5 million (£120 million for ODPM) by 2007-08, were submitted in April 2005 and have been signed off by DTI and OGC. First reports from each of the eight RDAs and the LDA were submitted in October.
Social Housing: New Supply
130
140
160
Housing Corporation (HC) strategy for investment partnering for new affordable housing was launched in August. HC also launched in March an innovative scheme to extend social housing grant to non-registered bodies. By widening the competition for grant, this should encourage better value for money.
Social Housing: RSL spend on capital works
2
30
60
66.4
National change agent now in place to establish network of local procurement consortia to maximise efficiencies throughout the supply chain. £33 million Efficiency Challenge Fund launched to facilitate consortia set up (five consortia have already won funding).
Social Housing: RSL management and maintenance
35
60
80
74.6
ODPM commissioned a review of "systems thinking". Results of pilots testing its application to social housing are encouraging, and the report was launched in September.
Social Housing: RSL spend on commodities
10
30
55
11.5
National collective agent launched last year offering savings through joint procurement of commodity goods and services (telecoms, gas, office supplies etc). It has achieved well over 60% coverage of the RSL sector.
Fire and Rescue Services
25
75
105
Integrated Risk Management Planning is now firmly embedded in all FRAs. The Audit Commission's Fire CPA reports were published at the end of July. CPA improvement planning now underway and providing major opportunity to reinforce efficiency messages and share good practice. Consultation on Annual Efficiency Statements closed on 5 October, subject to which FRAs' first reports should be made on 17 November.
Firelink: Operational Continuity
8
8
10
1.5
Phase 1 work is complete. This replaced high-risk items identified through an initial risk assessment process. As a result of negotiations this work has been completed for £1.5 million less than budget.
Homelessness1
21
58
125
15.7
2005-06 grant allocations have been made to local authorities and other agencies, linking funding more strongly to performance in tackling homelessness. National statistics confirm there have been sustained reductions in new cases of homelessness since the start of 2004 and show no further increase in the number of households in temporary accommodation since September 2004. With these positive changes occurring a year ahead of ODPM's projections we are on track to deliver.
Total (£m)
279
497.5
740
181.7

1  Homelessness: Added to programme in 2005-06 as contingency. New forecast/ target corrects error in data originally supplied so that it is now expressed in cumulative terms.







 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 26 January 2006