Select Committee on Office of the Deputy Prime Minister: Housing, Planning, Local Government and the Regions Written Evidence


APPENDIX "A"

FIRECONTROL AND FIRELINK

  The Authority acknowledges that the benefits identified by the ODPM in terms of resilience and greater interoperability can improve the safety of personnel and our communities, but contend that these will accrue if and only if, the outcomes suggested by Government are reached. We have several deeply held concerns related to how the projects are developing and the implications for fire authorities in financial, capacity and interim continuity terms.

  It is not surprising that as primary stakeholders, fire authorities have concerns over the successful delivery of these projects and the modernisation agenda in general as failure to do so would indicate an abdication of the statutory duties that not only currently but in the future will continue to fall on individual fire authorities.

  The current concerns of this authority that we wish to draw to the Committee's attention include the following (it should be noted that these concerns have not been assuaged by the previously given responses to repeated enquiries at all levels of the project).

1.   The robustness of the business cases and impacts on our local "value for money" priority

  It is noted that it was intended to provide a regional breakdown of the FiReControl Outline Business Case in the summer of 2005. This has not been forthcoming and there appears to be no intention of providing greater clarity of financial issues at the regional level at this time. The FireLink project has only issued limited financial information on the capital costs of provision of additional equipment beyond the current scope of supply. It is understood that Ministers are currently reviewing revenue implications. Failure to provide sufficient information on both of these projects is causing significant concern as the recent announcement of the two-year settlement for local government (inequitable from the point of Oxfordshire County Council) cannot address these unannounced costs. The lack of timely information with which to plan for the future, whilst government highlights the spectre of Local Authority capping, militates against the successful implementation of both projects.

2.   Increased costs of local project delivery and interim business continuity (including new burdens issues)

  The level of New Burdens funding remains a significant area of concern. It is acknowledged that recent statements have clarified that "net additional expenditure" may be met eg for redundancy but only if all alternatives are exhausted and if the decision is identified as Best Value. However, there remain areas of uncertainty and disagreement. These primarily relate to the costs of ensuring the existing control rooms remain fully functional until cut over to the RCC eg retention schemes for staff and support for interim technical upgrades required due to the extended project timetable and the revenue costs associated with the migration eg training for a wide range of staff due to changes is procedures and new technology. Training costs for are currently limited to ODPM funding a "train the trainer" level not the full costs of training.

  As yet there has been little indication that any new burdens funding is available for the rollout of the FireLink project. It is understood that the project has provided outline guidance of their expectations for resourcing successful local rollout. This authority would welcome clarification of this and other funding issues relating to FireLink.

3.   THE ONGOING FUNDING ARRANGEMENTS AND LOCAL IMPACT OF REVENUE COSTS, ONCE ESTABLISHED

  The headline average saving of 30% claimed by ODPM for FiReControl is considered to be as yet unsubstantiated. Two main issues can be identified, additional costs relating to higher security standards that currently are in place and residual costs of "out of scope" activities remaining in services.

  Recent indications are that the ODPM now believe there are no additional costs relating to the requirement for higher security standards as part of the Critical National Infrastructure. The requirements, although modified, still remain as do their cost. As a result costs shown in the Draft Outline Business Case formerly paid centrally, will be transferred to FRS's (possibly 10% of anticipated rental payable on each building). Such transfers of costs must inevitably have an impact on the headline 30% "saving". This fire authorities position remains that as National resilience is not a fire authority responsibility any additional costs should not be accrued.

  Of greater concern is the ongoing revenue effect of those tasks currently carried out in the Control Room, which will not be transferred in totality by the Regional Control Centre. Such out of scope activities have only recently been investigated fully and fire authorities have recently resubmitted information that indicates the level of current expenditure that cannot be included in the full national / regional business case. The original ODPM outline business case did not fully take account the tasks that would remain with Brigades and thus the basis of the business case must be revisited. The current work, and therefore costs that will still be incurred by fire authorities locally will be further refined once the detailed processes and technology to be used by the Regional control Centre are finalised. This will require a further examination of the business case and again calls into question the headline savings previously claimed.

4.   Legal liabilities, accountabilities and the structure of governance for the Control Centre

  This authority has grave concerns over the undeniable complication of the governance structures at a regional level and the remaining legal liabilities that will continue to fall on individual fire authorities.

  Whilst the consultation on the governance arrangements for the RCC is eagerly awaited, there remains the issue of the transfer of legal liabilities of operational failure at the regional level to the constituent fire authorities who individually appear to have little direct control over the regional entity. There is, as yet, little statutory basis for the regional management board or the local government company limited by guarantee. Clarity of legal responsibilities is essential. In addition the costs for each individual fire authority to establish that the arrangements for all wider corporate governance issues are adequate are currently not identified and sufficient new burdens funding must be forthcoming for these necessary activities.

5.   The effect on fire authority staff of the project, in terms of capacity, retention and continuance

  This fire authority is concerned that the national project has not given sufficient cognisance of the limited capacity available in individual brigades to successfully complete both projects with their inter-related (but as yet) indistinct project timetables.

  While the location of the Regional Control Centre is known, many employment issues remain for the staff involved and uncertainty remains. Staff and managers responsible for the project remain frustrated with the apparent lack of information over employment issues. Several of these may be resolved when the governance issues are addressed allowing an employing entity to be created. Meanwhile the uncertainly is debilitating for staff and adversely affecting morale. Maintaining the current Fire and Rescue service is the Service's key concern and therefore retaining existing staff and their expertise is the greatest challenge in Oxfordshire. Whilst it is acknowledged that the responsibility for maintaining existing control rooms remains with FRA's, staff consider that the national project have little understanding of the impact of delay and uncertainty on them and the authorities ability to continue to provide what is a key statutory duty.

6.   Project Delivery Issues

  The alignment of the FireLink and FiReControl projects is welcomed, particularly as they are closely related and interdependent. Issues of cost transfer between the projects remains a concern, particularly with the relative absence of information due to no full business case for either project before their alignment.

  The adoption of a PRINCE2 project methodology is welcomed, as this should reduce risks to all stakeholders. However, it is apparent that the methodology is not being applied consistently and as a result regional and local teams cannot fully utilise this best practice approach.

  The effect of delay to the project (the national project team has not yet managed to keep to any of its own target dates) is causing difficulty in services due to our inability to plan resourcing arrangements meaningfully. This has effect on the quality of work that can be accomplished in often limited timescales, increases stress on the very staff who are facing potential redundancy and is inefficient in that staff resources provided at the expense of the authority (and not supported by new burdens) could be underutilised.

  Well-planned and executed communications are essential to successful project delivery. Whilst it is accepted that communications will never meet all needs the national project team project has consistently failed to:

    —  Send documents out for meetings in a timely manner;

    —  Circulate documents through the agreed coordinating points of contact in regional teams;

    —  Make clear to regional teams what information can be shared with FRAs;

    —  Set up the ODPM-standard collaborative software that would allow teams within the national project to access key documents, and would make communication with regional teams simpler and more reliable;

  This does affect the ability of the FRAs and regional teams to:

    —  Deliver a considered response to the national project

    —  Accept the results of consultations

    —  Work efficiently to overcome resource issues

FIRELINK—SPECIFIC ISSUES

  The authority is aware that several stakeholders and potential respondents to the select committee are lobbying for the remit of the FireLink project to be extended to accommodate incident ground communications, potentially in support of ICS and CCBRN considerations. This is understandable and as a matter of principal should be seriously considered. However, there are a number of issues that must be fully addressed prior to any decisions made concerning this development which could adversely effect the continued provision and commercial viability of current incident ground (largely UHF based) radio communications. These are:-

    —  The current technical limitations of TETRA based systems in direct mode operation (DMO) and in point-to-point (via the nearest cell base) mode. Current users of the Airwave Service informally advise that coverage and reliability issues are of concern (NOTE the current operation assumptions for FireLink never included "in building' coverage and were based on vehicle mounted systems)

    —  Capacity concerns if the system requires significant cell capacity when working on a point-to-point basis

  The absence (as identified above) of detailed revenue costings for in use charges. Current systems are very cost effective and are based primarily on a cost of ownership arrangement without significant revenue effect. The reliance on an external contractor to provide all communication needs must be questioned until all information is available for fire authorities to undertake a detailed business case.

CONCLUSION

  This authority has deeply held reservations concerning both the FiReContol and FireLink projects and welcomes the select committee's inquiry as a useful mechanism to increase the project transparency and level of understanding of all stakeholders involved.





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 23 March 2006