Select Committee on Public Accounts Second Special Report


Appendix: The BBC's response


1. During the course of the White City 2 project additional costs were identified which added over £60 million to the total cost, an increase of 29%. The whole life costs of projects should be assessed, and made available to BBC Governors, before projects proceed.

The original investment agreed by the Governors related to the construction costs of the White City 2 development. The BBC welcomes recognition by the NAO that the construction and basic fit out was delivered within the budget and timescales approved by the Governors.

The £60m, referred to by the PAC, was not part of the construction project and £40m related to specialist broadcast technology equipment, including edit suites and playout facilities. This cost was known about at the time of the original investment case. It was specifically budgeted and agreed by a separate legal entity, BBC Broadcast Ltd (now Red-Bee Media).

The BBC accepts the PAC's recommendation that total project costs should be included in the original investment case and have taken steps to seek to ensure that furniture, fit out and staff move costs are included in all cases presented to Governors for approval. Nevertheless in a dynamic changing broadcast operational environment it is unlikely to be possible to envisage all the possible uses to which a building will be put by the BBC over its life.

2. Even after signing the contract with Land Securities Trillium, the BBC made 300 variations to the White City 2 scheme. The BBC should better integrate design and construction, as recommended by the Office of Government Commerce, to reduce the risk of design changes after contracts have been let. Introducing variations after deals have been signed inevitably heightens the risk of cost increases.

The BBC accepts the PAC's suggestion to follow recommendations by the Office of Government Commerce when entering into such contracts.

However, in this instance, out of the 300 contract variations, 129 were simple confirmation of designs at no extra cost to the BBC. The NAO's report acknowledges that most of the variations were to finalise the detailed design and provisional sums rather than involving significant changes to the agreed design. According to our cost consultant, the number of variations and the total value of them is well below the norm for a project of this size and complexity. There was an allowance in the project budget for contract variations, and therefore the 300 variations did not result in any extra cost to the BBC or in delays in completing the building.

3. The BBC sublet space to BBC Broadcast Limited, a commercial subsidiary, for rent lower than the cost to the BBC. Licence fee money should not be used to subsidise the BBC's commercial subsidiaries. The rent charged for sublet buildings should meet the BBC's costs or match the market rate if this is higher. As well as recovering its current costs, the BBC should also recoup previous undercharging from individual subsidiaries.

The BBC does not use the licence fee to subsidise the BBC's commercial activities.

The basis of the rental charge to BBCB was reviewed and updated in spring 2005 by the BBC's Fair Trading Team. The BBC achieved a full recovery of costs under the original unitary charge basis and continues to achieve a full recovery under the current arrangements.

4. Because of the way the project was financed, the BBC did not know whether the return to the private sector shareholders was within the limit specified in the contract, and the BBC was unlikely to secure a share of any refinancing benefits. The principle has been accepted that the public sector should share in gains that arise when projects are refinanced. Public bodies should recognise that obtaining refinancing benefits, and identifying returns to the private sector, is more straightforward where financing is linked directly to the project in question.

The National Audit Office report states that the partnership with Land Securities Trillium was unlikely to achieve refinancing benefits for the BBC. However, as the report was being finalised, the BBC did re-structure the lease, achieving a saving to the BBC of £63m in today's money. In a competitive tender exercise, the decision to appoint Insight (LST) was based on the fact that over the life of the deal, this contractor offered the lowest price to the BBC. In addition to the £63m savings the BBC achieved, LST produced cash benefits to the BBC of £33m over the first four years of the partnership.

5. The BBC's plans to cut staff and move others to Manchester increase the risk of space and technical capacity at White City 2 being under-utilised. While the BBC expects the new buildings to be fully used, its focus should not be exclusively on White City 2 but on achieving the most cost-effective solution to its accommodation needs, taking account of the whole of its estate. The BBC should not hold on to property which it does not need or which cannot be used cost-effectively.

The precise details of accommodation requirements in the future will be at least partially dependant on the progress of the BBC's own cost savings initiatives and the outcome of the discussions with HM Government on the level of the licence fee in the next Charter period from January 2007. Nevertheless, even assuming the move to Manchester goes ahead the London premises are expected to be significantly rationalised with concentration of activity into 3 sites of which the new development on the White City site is key.

6. More than two years after the Energy Centre was completed, the space for a combined heat and power installation is not being used, and the BBC is paying for the empty space. This space, together with vacant office space in the Energy Centre, has cost around £1 million a year, and the BBC should put the unused space to productive use as soon as possible.

The empty space for the combined heat and power plant comprises 2,335 sq ft or 1% of the total project and will be fully utilised when the final phase of the site is bought on stream. The vacant office space is currently a shell and core building and fit-out for occupancy commences this year.

7. The BBC did not follow public sector good practice in several important respects on this project. There is guidance from the Treasury and the Office of Government Commerce on estimating whole life costs, monitoring returns to the private sector, obtaining refinancing benefits, and integrating design and construction. The BBC would benefit from drawing on this guidance.

The BBC welcomes the PAC's recommendations and will endeavour to incorporate this guidance in future projects, where practicable.

8. The Comptroller and Auditor General's work is providing fresh insights about the BBC's use of public money, but is being done under arrangements which end in 2006. The Comptroller and Auditor General should have a continuing role beyond 2006, which should include full access rights enabling him to identify and select subjects for examination.

The BBC welcomes the work of the Comptroller and Auditor General and the NAO. The Communications Act, agreed by all parties at the time, has been successful and has provided the BBC with many valuable lessons learnt.

BBC believes that this arrangement best balances parliamentary scrutiny of licence fee expenditure with the editorial independence of the BBC and should be maintained. The BBC is therefore working with the Comptroller and Auditor General to ensure a similar agreement is reached for a continuing relationship post 2006.




 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 13 June 2006