Select Committee on Public Accounts Minutes of Evidence


Supplementary memorandum submitted by the Ministry of Defence

Question 27 (Mr Williams): Clarification of the members of the Acquisition Policy Board.

  The Acquisition Police Board is chaired by the Minister for Defence Procurement and has a total of eight members. It was formed in autumn 2004 in order to bring together issues that had previously been considered by three separate Ministerially-chaired groups, which it replaced. It accordingly provides a clear Department-level focus to direct and drive forward acquisition and industrial policy. The eight members are:

  Minister (Defence Procurement), Vice Chief of the Defence Staff, Permanent Under Secretary of State, 2nd Permanent Under Secretary of State, Chief Scientific Advisor, Chief Defence Logistics, Chief Defence Procurement and Deputy Chief of the Defence Staff (Equipment Capability).

  Between Ministerially chaired meetings, it also meets at official level under the direction of the Permanent Secretary.

Question 70 (Mr Jenkins): Details of the cancelled projects.

  In the past two years the following principal projects have been cancelled:

  ADW—Area Defence Weapon: Cancelled pre-Main Gate due to value for money issues and operational limitations. The capability requirement will be pursued through a new project, Future Counter Mobility Capability (FCMC).

  CARMS—Counter Anti-Radiation Missile Suite: Cancelled during Assessment Phase due to value for money for the project itself. The capability will now be delivered by the ASAR (Automated Software Adaptive Radar) programme.

  MINDER(RP)—Mine Detection, Neutralisation and Route Marking (Route Proving): Cancelled during the Assessment Phase due to the technical solutions not providing adequate military capability.

  LIDEA—Laser Identification Experiment Airborne Technology Demonstration: Cancelled after the submission of final business case due to affordability and value for money issues It is envisaged that the capability requirement will be met via other NEC linked sensors.

  Specifically relating to the MPR:

  MRAV—Multi Role Armoured Vehicle: The MRAV requirement was cancelled as the vehicle is not ideally suited to the type of operations now envisaged under the Strategic Review New Chapter and other developing policy work. This policy, and experience gained in recent military operations around the world, have demonstrated the need for rapid deployability in expeditionary operations, which MRAV cannot meet to the satisfaction of the army and did not form part of the endorsed MRAV requirement. The capability requirement will now be pursued through the Future Rapid Effect System (FRES).

  MR TRIGAT—Medium Range TRIGAT: When the UK signed the MR TRIGAT Memorandum of Understanding in July 1999, indicating our intention to proceed to Industrialisation and Production (I&P), we believed Belgium and the Netherlands would sign the Memorandum of Understanding in a similar timescale. By July 2000 the Memorandum of Understanding signature process had not been completed while the uncertainty and the open ended delay had increased further, this deterioration of the programme's prospects led the UK to decide not to proceed into the Industrialisation and Production phase.

Question 70 (Mr Jenkins): An assessment of the impact on our military capability of the over-run of these projects.

  The aim of the Department's planning process is to ensure that the MoD is able to deliver the optimum military capability possible within the resources available and each year the Equipment Plan delivers within the resources allocated. The forward Equipment Plan is regularly recosted to reflect changes in: technology; policy; ideas about how to deal with a particular threat; changes in the allies' intentions; as well as cost growth. When this process indicates that the cost of the forward equipment programme is greater than the resources available, it is necessary to identify changes to bring demand and resources back in to balance for each of the 10 years of the EP. Changes may include a combination of deferral, descope and reduction in numbers.

  A rigorous internal process prioritises these changes according to their impact on the delivery of future capability; those which have the least impact are recommended to Ministers for implementation. Decisions are not driven by individual project affordability, but rather by how best the whole forward plans can be structured to obtain the best value for money from our resources. CDP commented on the accuracy of our cost-estimating in the past. It is worth noting that in many cases the cost-growth reported by projects reflects the level of uncertainty in initial cost estimates which were made with information available at the time.

  Therefore, the usual impact on military capability of a project overrun is that some existing equipment has to be extended in service and/or the rate at which some future capabilities are introduced is slowed down. This does not mean that the Armed Forces have no capability but rather that we have to introduce new capability at the rate that we can afford. Often this is at the rate that we would have planned, if we had more realistic cost/time estimates when the programme began.

Question 118 (Mr Allan): We still have a gap between `most likely' and `maximum' of £3 billion, amounting to 30% of the cost. It seems odd to me that we have not been able to narrow this down.

  The NAO recognised in its Report of 2000 that the process of training aircrew is complicated and must be viewed as a whole if value for money is to be achieved. UKMFTS is a large change programme, involving partnering with industry, designed to address this point by delivering a fully integrated flying training system to meet the needs of all three services across all aircrew disciplines.

  As I outlined in my evidence to the Committee, the figure of £3 billion reported in MPR2004 reflected the aggregate of potential risks and uncertainties that exist in such large and complex programmes during their early gestation. In this case, the figure covers the full projected life of the training system programme, some 25 years, and not just the acquisition phase. Such uncertainty embraces, inter alia: the types, sophistication and numbers of new or modified aircraft required; the mix of live and synthetic flying training to be adopted; potential transfer of some training from more expensive operational aircraft to designated training aircraft; the need to modernise dome MoD infrastructure; variability of training throughput; and the whole-life cost variability of platform support—particularly where a number of different contender aircraft need to be considered.

  Since the Project Summary Sheet (PPS) for MPR2004 was compiled, work has proceeded apace to mitigate these risks. Following a detailed convergence process with industry, MoD now better understands the level of risk that could be transferred. Detailed technical studies have been undertaken to improve our understanding of how to achieve the right balance of training methods: for example, completion of training needs analyses, studies into live versus synthetic flying. Platform mix, aircrew selection standards, and civilian/military instructor mix. In addition, my people are also researching the market place for aircraft and supporting training technology, thus gaining a better understanding of capabilities and potential costs. Meanwhile, as the Committee may be aware, the impact of the medium term work strands within the MoD has been to reduce our future training requirement for certain aircrew disciplines, and this will impact on the design and cost of the training pipelines within UKMFTS.

  Theses changes will be reported in the PSS for MPR2004 and will be reflected in the Invitation to Negotiate (ITN) that will be issued to the three competing consortia as the next stage in this important programme of work.



 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 13 October 2005