Select Committee on Public Accounts Sixth Report


4  Overcoming the challenges to delivering the 2010 target

18. The Department designed the Renewables Obligation to facilitate the rapid expansion of renewable generation required by the 2010 target. It decided that the Obligation should provide a single level of public support to all technologies, independent of their costs or maturity. The scheme therefore encourages generators to develop the most economic sites first. These sites tend to utilise the mature renewable technologies where risks are better understood and costs have already been reduced.[33]

19. By 2010, the mature renewable technologies are unlikely to account for more than 5% of electricity supplied in Great Britain and thus, on their own, will not deliver the 10% target. The Department has therefore introduced capital grants programmes to help industry develop offshore wind and biomass sites as these are generally not commercially viable under the single level of support provided by the Renewables Obligation. The grants are intended to help developers gain experience and confidence of these technologies, and thus help them reduce generation costs for future projects. The first rounds of grants, for which £170 million has been made available by the Department and the National Lottery fund, have so far had mixed success. These grants have helped the completion of two fully operational offshore wind sites, with 10 others at varying stages of development, but they have produced no significant increase in energy production from biomass.[34]

20. Since the 1990s the development of some renewables sites, in particular, onshore wind sites, has been delayed or halted due to difficulties in getting planning permission. The success rate of applications for onshore wind sites has varied substantially between English regions (Figure 4). The Department has, therefore, worked with the Office of the Deputy Prime Minister to reduce the barriers faced by renewable generators in getting planning permission and, in 2004, a new planning statement was issued. The statement seeks to get a more consistent approach to planning and thus increase the proportion of applications for renewable sites which are approved by requiring local planning authorities to take account of national interests and regional targets for increasing renewable generation, as well as local environmental, economic and social impacts. Consequently some applications which would previously have been refused are now likely to be passed.[35] The statement increases the chances of hitting the 2010 target, but only by reducing local communities' influence on the planning process. Figure 4: Rate of planning approval for onshore wind farms in each of the English Regions from 1999 to 2003

Note: West Midlands has been excluded as no applications were made in the period

Source: British Wind Energy Association

21. The Department has worked with Ofgem to provide incentives for the owners of the electricity grid to upgrade it so that it can transmit and distribute renewable electricity from where it is produced, often at remote sites, to where it is consumed. The total cost of projects to upgrade the grid, which typically require planning approval, is uncertain. The Department estimated in 2003 that the costs of improving the transmission network, so that the 2010 target could be achieved, could be between £1.1 billion to £1.3 billion, with a further £400 million to £600 million needed for the distribution network.[36] These costs will be passed on to consumers through higher prices and are in addition to the costs of the Renewables Obligation.[37]


33   Q 83 Back

34   C&AG's Report, paras 2.29-2.31; Q 99  Back

35   Qq 39-40 Back

36   Renewables Innovation Review, Department for Trade and Industry, February 2004  Back

37   C&AG's Report, para 3.2 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2005
Prepared 15 September 2005