Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 20 - 39)

MONDAY 7 NOVEMBER 2005

BBC

  Q20  Mr Williams: What about the others? They would have had costs. This is one of the most fundamental flaws which we have pointed out time and time and time again to the Ministry of Defence and to various Departments: you avoid making design changes mid-contract.

  Mr Smith: Yes, but it would be absolutely wrong to characterise these as design changes, especially with the implication that they were expensive design changes, which were unbudgeted. Of the 300 contract variations, 129 carried no extra cost whatsoever since they were simply confirmations of details or information which were in the original contract.

  Q21  Mr Williams: They were so simple that the National Audit Office tells us that contract variations process turned out to be time consuming and overly complicated. Perhaps you did not notice that.

  Mr Smith: That is not the same thing as saying that the contract variations were undue or somehow wrong or somehow led to increased costs, because they did not.

  Q22  Mr Williams: Let us move on then to the financial side. We are told that the bid also included a provision to restrict the return to shareholders to 30%. That is correct, is it? Yes or no.

  Mr Smith: Yes.

  Q23  Mr Williams: In previous PFI projects, 16% has been seen to be a more than healthy return on a safe project and yet here, you are conceding 30%. This is not just extravagant in the context of what is an ultra safe project, it is actually almost usurious, in that it would give re-financing in just over three years. That is venture capital spending, is it not?

  Mr Smith: There is no suggestion in the Report that our partner got a 30% return. It talks about putting an absolute cap on the amount of return they could get. A big difference; a very big difference.

  Q24  Mr Williams: So what is the percentage?

  Mr Smith: We would need to work it out precisely.

  Q25  Mr Williams: I would have thought you would do that, would you not? Since it is known that 16% is the going rate for such projects, surely you know the figure?

  Mr Smith: Let us talk about the re-financing. This is a £321 million re-financing where I think Land Securities' profit was £23 million out of £321 million. So that gives a feel for what the actual return was and the Report puts a ceiling on it, but it does not give an actual return of the 30%.

  Q26  Mr Williams: But you should be able to tell us what the rate of return is.

  Mr Smith: I have just told you: £23 million on £321 million.

  Q27  Mr Williams: That is over the whole lifetime? C&AG, do you agree with those figures?

  Sir John Bourn: Yes we do.

  Q28  Mr Williams: But what about the 30%, how did that enter into the deal?

  Sir John Bourn: It entered into it as the possibility that might have been achieved.

  Q29  Mr Williams: Which would have been unsatisfactory from the licence payers' point of view, would it not?

  Sir John Bourn: It certainly would have been higher than the generality of PFI projects.

  Q30  Mr Williams: Is that not a rather modest assessment of higher? It is considerably higher.

  Sir John Bourn: Yes, it was considerably higher.

  Q31  Mr Williams: Nearly double, and yet they were willing to contemplate it. So much do they care for looking after their licence payers' money—

  Mr Smith: I am sorry to interrupt, but I need to argue about this because it is just not right. Forgive me, Chairman, but I do feel the need to make sure the Committee is clear about this. This is a point in the Report which is comparing the bid from Land Securities Trillium with the bid from the other organisation. We have already explored at the start of the meeting why the Land Securities bid overall was better. It is also describing a situation where there was an absolute cap on the return that Land Securities could earn versus the bid from the other company, where there was less clarity about what the absolute return was. Irrespective of that provision, separately, as the Report says elsewhere, a very specific price was agreed with Land Securities for the building of the building. In the re-financing of that building recently, £321 million, their return was agreed at £23 million. So that tells you what the actual return was. It is just not right to say that because there was an absolute ceiling on it of 30% that was the return that they were getting. They were not.

  Q32  Mr Williams: It is unbelievable that you even contemplated it. Why did the figure arise? If it arose, it was something you were obviously willing to consider. Let us move on, because we are time limited; let us move on to the next point. One of the consequences of not having done the design section properly, particularly in relation to the company which was going to carry out the construction, is that you build an energy centre which takes up a substantial amount of space. You then decide you cannot afford to go ahead with the project of using that energy centre, so that space now remains unused and to some extent is unusable in any practical sense, is it not?

  Mr Peat: May I just give a first response on that? The first point to note is that at the time of the initial construction there were proposals for the use of these buildings by BBC Broadcast, which would have involved much greater use of energy, in which context the energy centre would have been well utilised. That changed over the construction period. Subsequently, when occupation began it was not entirely clear where we were going next on the White City area and therefore the capability to produce a combined heat and power plant or whatever has been retained for the next few months to determine whether it is needed in the new context which now arises.

  Q33  Mr Williams: But as a result of this failure to design the project properly in relation to your need, you now have extensive basement areas and large places for plant and machinery, which cannot be used at the moment, or are not being used at the moment, and that also means that a lower proportion of the building can be used for office space than would be the case in a typical office development. That is a fact, is it not?

  Mr Thompson: No. That figure I quoted, the figure of 6.5% of vacant space across the site, includes the energy centre.

  Q34  Mr Williams: So what is the space being used for?

  Mr Smith: Car parking. It is a car park.

  Q35  Mr Williams: I see. That is a very high rate of return on your investment, is it not?

  Mr Smith: It is very important to have it in an area where there are not any car parks.

  Q36  Mr Williams: But it was not intended to be a car park.

  Mr Smith: Yes, of course it was intended to be a car park.

  Q37  Mr Williams: If you needed a car park, why did you not have one designed in in the first place?

  Mr Smith: We did.

  Mr Peat: There are two elements. One is the basement, which was designed for car parking. The other is the other space, which was the energy centre, part of which, we accept, is unutilised. It may be used for additional office accommodation when we know the future better but at the moment we are waiting to see what is needed, given what happens next on the overall site. As I said earlier, at the time of the initial design, the energy centre would have been needed in the context of BBC Broadcast and that requirement changed during the construction process.

  Q38  Mr Williams: May I say, Chairman, in conclusion, that I hope when we draw up our Report that we will include in it a recommendation to the Chancellor or whoever is the appropriate person, that this is a clear case which vindicates our claim that the National Audit Office should have full access, because the BBC does not seem to be capable of controlling its finances adequately itself.

  Mr Peat: May I just make one further comment? As the Report states, the project was completed on budget and on time; indeed one of the three buildings was completed ahead of time and none of them was late. It is flexible in delivery of value for money, slightly above average cost because of the requirement for additional flexibility, it has won awards, it is environmentally friendly and it is much enjoyed by the staff; they very much appreciate it. I do not think it is all negative.

  Q39  Mr Williams: Despite the fact that attention had been drawn previously to the need to provide for shares in re-financing, you did not make an initial arrangement to have re-financing. You then made a purchase in order to get access to some of the re-financing benefits, but you would almost certainly have had to pay a premium price, because they were expecting the high rates of interest.

  Mr Peat: I do not think that is right, with respect. At the initial time, it was not possible to go down the route we have now gone down.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 14 February 2006