Service risks
The withdrawal by Octagon's investors of large early
benefits from the project was, in effect, an advance payment of
the profits that Octagon expected to earn over the life of the
contract. It creates a risk that Octagon's investors may not be
so concerned about the quality of Octagon's future service delivery
because the investors have already received a substantial part
of their project benefits which previously depended on service
performance. The Trust, so far, has found Octagon's service to
be very good but these are early days in a contract which now
extends to 2037.[12]
Credit risk on the balance of
the Trust's share of the refinancing gains
In choosing, under guidance from the Department,
to receive its share of the refinancing gains over 35 years the
Trust was accepting the risk that, if the contract were to be
terminated early, it could find it difficult to recover the outstanding
balance of its share of the refinancing gains. The Trust's decision
to receive its gains over 35 years is in contrast to Octagon's
investors' decision to take their refinancing gains immediately
at the time of the refinancing which reduced their risks from
investing in the project. The Department acknowledged that, if
Octagon were to fail financially, the Trust would not be certain
of receiving its share of the refinancing gains whereas there
would have been certainty if it had taken the gains as cash at
the time of the refinancing.[13]
2 C&AG's Report, paras 1-2, 1.2-1.3 Back
3
ibid, Figures 6 and 7a, p8 and Figure 8, p9 Back
4
C&AG's Report, Figure 2, p2, para 1.3; Qq 2-3, 123-126; Ev
20 Back
5
C&AG's Report, Figure 2, p2 and para 1.3 Back
6
Qq 1, 9-10, 14, 23, 123 Back
7
C&AG's Report, Figure 8, p9 and Figure 24, p22; Ev 20, 24;
Qq 60-71 Back
8
Qq 11, 48-49, 77 Back
9
Qq 171-172 Back
10
C&AG's Report, Figure 12, p12; Qq 4-8, 14-17, 34-48 Back
11
C&AG's Report, para 2 and Figure 24, p22; Qq 84-89, 115-116 Back
12
C&AG's Report, Figure 8, p 9; Qq 9, 18-21 Back
13
C&AG's Report, Figure 13, p13; Qq 162-170 Back