Select Committee on Public Accounts Minutes of Evidence


Supplementary memorandum submitted by the Environment Agency

Questions 19-20 (Mr Richard Bacon): Activity Based Costing

  The Environment Agency has worked to improve its efficiency and effectiveness since its formation. The Agency's inherited financial and human resources (HR) systems inhibited efficiency and provided inadequate financial and human resources management information.

  Spending Review 2002 provided the financial resources to replace the previous ageing systems. The Agency in 2002 developed a business case for replacing the finance and HR systems with an integrated enterprise suite of finance and HR resource systems (known in the Environment Agency as "IBIS"). The implementation was to proceed on a phased basis with the most significant elements of finance functionality being introduced in March 2005. This provided the basis to cost activities and outputs known as Activity Based Costing (ABC).

  The core systems were provided by Oracle with the ABC system provided by another supplier (Prodacapo), due to a gap in Oracle's provision. The following summarises the key areas questioned:

Timing

  The ABC component of the IBIS project lasted 15 months (including the procurement phase) and transitioned to being part of normal business at the end of March 2005. The gap between identifying the requirement for ABC and implementing it was due to the need to first implement IBIS financials which provides the necessary Time Recording and Cost data to create the ABC information.

Cost

  The total cost of the ABC system implementation was £600,000. Pricewaterhouse Coopers were commissioned as external consultancy support for specialist advice on system selection and procurement strategy based on their knowledge of the marketplace, at a cost of around £10,000. Tribal Government Consulting provided an external IT and project management service at a cost of around £307,000.

Status

  Following the gathering of time and cost information from April 2005, managers in the Environment Agency have now received their first set of ABC information. This is providing baseline data from which to analyse improvement opportunities and track benefits from change. Work is underway to identify and realise efficiency benefits in a number of areas. These benefits will be implemented systematically in the next two years and beyond.

Question 23 (Mr Richard Bacon): Streamlining Abstraction Processes

  Streamlining Abstraction Processes is a business process change project that has developed new IT systems which will deliver efficiencies in the core regulatory activity of abstraction licensing and reduce burdens on business.

  The two main strands of this work are business change and IT development. Two consultants are assisting us in these changes, Logica CMG for the business change and Science Systems (SciSys) delivering the generic IT regulatory tool across all of the modernising regulation projects.

  Logica CMC are contracted until February 2006 at a total cost of around £66,000.

  The Environment Agency has awarded SciSys a three-year contract to provide core services in support of the development and enhancement of key regulation systems in England and Wales. £15 million is being budgeted for by the Environment Agency to provide technological enhancements to enable improved and streamlined delivery of regulation processes for delivering the whole of the Modernising Regulation IT infrastructure, to include the SAP project.

  Our business case identified costs of £8.8 million over the three years of the project, with benefits rising to at least £3.5 million per annum following completion and bedding in the of the new processes. We are currently preparing detailed plans for implementation following recent approval to proceed with the project.

Question 33 (Mr Richard Bacon): Asset Management Strategy

  Following a review of the Environment Agency's asset management policies and procedures, the Agency is taking forward a more integrated and strategic approach to Asset Management. This will identify modern asset management techniques to deliver significant efficiencies to the Agency.

  The Environment Agency operates physical assets to the value of £20 billion, and spends some £400-500 million per annum on their renewal, upkeep and maintenance. There is potential for significant savings to be achieved, by looking at the way in which these assets are currently managed, by identifying appropriate standards of maintenance, and by analysing ways of providing such maintenance.

  In developing the strategy we have learnt from the experience of others in successfully introducing asset management in comparable businesses.

  The strategy will be prepared by April 2006 and will demonstrate how more efficient asset management will be developed in the Environment Agency, including ways to deploy staff and reduce costs whilst ensuring an acceptable standard of maintenance of assets. The project is developing a detailed business case for a preferred option setting out the likely benefits, costs and risks.

  To construct the right strategy for the Environment Agency we needed to access skills and experience in our current business practices, recent developments and operating risks. This internal knowledge needed to be complemented with experience of delivering cost savings through the implementation of modern asset management techniques in a similar large, complex organisation.

  The external specialist support is provided by an independent consultant who worked in several operating roles (including Director of Operations) during a 12 year period whilst asset management practices were developed and embedded within Wessex Water.

  The approved budget for the project of developing the asset strategy is £200,000 in direct costs. It is due for completion by the end of March 2006.

  During the past two years we have made improvements in asset management. We now have solid records of asset condition, held in a national database. This work was initially focussed on flood risk management assets and has now been widened to navigation and water resource assets. The improved information of asset condition has helped us to target capital, maintenance and operational funding to best manage risk and optimise whole life costs. We have initiated a substantial programme of improvements to our navigational assets.

Question 69 (Jon Trickett): Cost re-allocation between Flood Risk Management and Water Resources

  We have recalculated 2005-06 standard unit charges for abstraction to show the impact of adjusting for the NAO recommendations which will be taken forward (principally the reallocation of hydrometric costs from water resources to flood risk management).

  It should be noted that a number of important other factors will bear upon the actual unit charges which we will be proposing for 2006-07 (including pay and price inflation, changes in workload, changes in the fixed asset infrastructure affecting cost of capital charges, and other efficiency improvements).

  Nevertheless, the table below isolates the impact of reallocation in line with the NAO Report based on 2005-06 charges rates:
RegionStandard Unit Charges per 1,000 metres cubed 2005-06
ActualAdjustment for Reallocations, etc Revised
££ £
Yorkshire10.03-0.22 9.81
Thames11.91-0.48 11.43
North West11.98-0.49 11.49
Midlands12.7612.76
Southern16.7116.71
Wessex18.34-0.18 18.16
South West18.34-0.18 18.16
Anglian21.72-0.55 21.17
Northumbria23.57-0.22 23.35


  As explained in the NAO Report and reinforced at the PAC hearing, unit abstraction charges are fixed on a regional basis to recover the Environment Agency's water resources costs incurred in the particular regions.

  The variations in regional unit rates reflect the major differences in infrastructure costs and workload, which exists between the regions. For example, the high unit charge in Northumbria is primarily attributable to the section 20 charges for Kielder, while the unit charges in the Anglian region reflects the high cost of capital charges for the supporting infrastructure, including the major Ely—Ouse transfer scheme. The unit charges in Southern, Wessex and South West reflect the higher workload on water resource planning and management in those regions.

  The development of activity based costing and use of benchmarking between regions will help us to isolate the efficiency component from other cost elements in unit charge variations and to inform and drive further efficiency improvements.

Question 75 (Mr Richard Bacon): Sea Defences

  North Norfolk District Council has lead on the production of a second generation Shoreline Management Plan (SMP) covering the area between Kelling Hard and Lowestoft on the Norfolk coast, called the Norfolk SMP. The first SMP for this stretch of coastline was produced in 1996. All of the current SMPs are now due to be reviewed, in line with Defra guidance. The Norfolk SMP was one of three pilot SMPs using the revised Defra guidance.

  Policies set in the first SMP document have not been universally applied. Their initial inclusion was motivated by local politics or public opinion, whether or not the measures were demonstrably economically or physically sustainable. For example, a policy of "hold the line" for Happisburgh could not be sustained by North Norfolk District Council owing to the costs involved and in consequence there has been continued erosion of the coastline. The second generation SMP contains policy options that work towards a long-term vision over three time frames, 0-20 years, 20-50 years and 50-100 years, although there is no evidence that unpopular but sustainable options will be any easier to achieve second time around.

  The proposed short-term policies for the new SMP provide a high degree of protection for existing communities against flooding and erosion. The preferred long-term policies set out in the new plan promote greater sustainability of the shoreline, and one more in keeping with the natural character of the coast. However compliance will be difficult where unpopular choices are made even though the actions to be taken may be some years away.

  Continuing to defend the shoreline in a manner similar to today would produce a significant alteration in the nature of the coast, with large concrete seawall structures and few beaches. This might maximise protection to property and land, but would be both difficult and very expensive to sustain.

  The SMP has been split into four management units. For unit three, Eccles to Great Yarmouth, the preferred policy is minimal intervention. The position of the existing hard defences are preventing the natural movement of sediment and structures will become increasingly difficult to maintain or justify over time as the coastal system retreats. This whole length of coast is reliant upon sediment eroded from the cliffs of North Norfolk for beaches to provide natural defence, which has been supplemented in recent years through beach recharge along the Eccles to Waxham frontage. The reefs at Winterton will defer problems for up to 50 years but it is recognised that beyond that time continuing to apply this measure may become increasingly difficult to sustain. The impacts upon areas further down coast may also be significant, if this position continues to be held long-term, as they will receive no natural sediment, which will deplete beaches and accelerate erosion. The preferred policy for this area is to investigate the potential for change whilst still defending, with a view to longer term set back of defences.

  At the southern end of this section, Great Yarmouth is a location that justifies full protection on economic grounds against erosion or flooding. With the exception of the northern and southern extremities of the town, the beach provides ample protection, provided that sediment supply is maintained. The presently defended areas of Caister and California will continue to be defended for some time. If such a policy continued to be applied into the long-term, there would be a significant impact on sediment supply, potentially interrupting sediment transport to Great Yarmouth. Therefore the longer term Plan should allow for some realignment of the shoreline to take place north of Caister Point to enable improved material movement along this coastline.





 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 9 May 2006