Select Committee on Public Accounts Forty-First Report


3  Protecting taxpayers' interests

11. The transfer from CSE to SET safeguarded the passenger rail service, with services improving following the transfer of the franchise, although this had been due mainly to improvements in Network Rail's performance. Uncertainty remains as to whether termination was the most cost-effective option for the taxpayer. The transfer of the franchise involved considerable effort and costs amounting to some £6.4 million, including £557,000 to provide incentives to some managers to remain with the operation. The SRA also provided subsidies to SET of some £22 million more than those CSE had agreed. The SRA nevertheless considered that it had paid SET an appropriate amount.[14]

12. The SRA's costs for investigating the difficulties with CSE's franchise, monitoring CSE's compliance with the deed of amendment and the termination included consultants' fees of £4.6 million. The SRA had employed consultants because it did not have the necessary resources in-house to deal with the volume of work and the complex issues that arose. It had sought extra assurance by engaging two different firms to carry reviews with some duplication of work to compare their findings and recommendations. The SRA put this in the context of the scale of the task to transfer a business with 4,000 employees, £450 million turnover and 300,000 passengers a day. It nevertheless accepted that in a similar future situation it would spend less on consultancy.[15]

13. The SRA had spent £300,000 on rebranding trains and staff uniforms from CSE to SET which was necessary in their view to demonstrate to passengers and staff that there had been a change. The Department considered this was not an unreasonable cost for the size of the fleet of trains involved. The new franchise agreement with GoVia does not specifically mention rebranding of rolling stock or uniforms, and GoVia had indicated that service delivery was a more important priority for them. Rebranding of stations was required within three years of the franchise term and would most likely be undertaken as part of general maintenance rather than as a specific activity.[16]

14. The SRA recovered from CSE £2.8 million of the £6.4 million costs it had incurred in the termination of the franchise (Figure 3). Under the terms of the franchise agreement, the SRA had a contractual right to deduct from CSE's £19.5 million Performance Bond[17] its losses, liabilities, costs and expenses incurred as a consequence of CSE's failure to comply with its obligations. The SRA obtained independent legal advice on which costs associated with the termination of the franchise it could recover from CSE. It did not, however, test the advice given by its internal legal advisers that it had no contractual right to recover £2 million spent on consultancy and external advisers in the lead up to the termination decision.

15. The SRA considered that there were significant financial and operational risks of CSE's holding company becoming insolvent if all the costs were recovered. The SRA feared that insolvency could trigger Rolling Stock Leasing Companies (ROSCOs) to terminate CSE's leases and claim significant sums in compensation for early termination, putting the continued availability of the rolling stock at risk. However, in practice, in October 2003 the SRA entered into agreements with the relevant ROSCOs under Section 54 of the Railways Act 1993 prior to completion of the franchise exit negotiations with CSE. The Section 54 agreements provided the ROSCOs with certainty over the future leasing of their rolling stock and removed their right to seek termination payments from CSE. At that point, therefore, there was therefore no potential liability for lease termination payments which could have pushed CSE into insolvency.[18]Figure 3: Costs which the SRA had or may have had a right to recover from CSE under the franchise agreement
SRA costs recovered from CSE SRA costs not recovered from CSE that the SRA appeared to have a contractual right to pursue SRA costs not recovered from CSE where the SRA's contractual right to pursue cost recovery was not independently tested
Nature of cost £'000 Nature of cost £'000 Nature of costs £'000
Consultancy costs incurred by the SRA in connection with the decision to terminate the franchise 2,600 Rebranding costs associated with creating South Eastern Trains (SET) and its holding company, SET (Holdings), including new staff uniforms (£274,000) and IT costs (£326,000) 600 Fees for consultancy reviews of CSE's financial difficulties and the extent of CSE's compliance with the deed of amendment 2,000
Media costs associated with the SRA's announcement of the termination 106 Retention payments to key CSE staff 557
The cost of Network Rail carrying out a dilapidations survey of CSE's franchised stations on behalf of, and paid by, the SRA 98 SRA staff time spent managing the termination (based upon the SRA's estimate of the additional work involved) 500
2,804 1,657 2,000


Source: National Audit Office summary of SRA information

16. The SRA had a generic contingency plan to enable it to take over a franchise should a train operating company, for whatever reason, be unable to continue running train services. The CSE case showed that the SRA could terminate a franchise and carry out its role as operator of last resort, protecting passengers' interests. The handover had been achieved with the vast majority of staff, including the new Managing Director appointed by CSE, transferring over to SET and rolling stock maintenance contracts and purchase agreements for new trains continued on SET's behalf by CSE. The handover went well. Some deterioration in CSE's operational performance occurred during the handover period but overall passenger satisfaction increased. SET improved the financial management procedures inherited from CSE, including financial forecasting, and addressed a backlog of station painting and cleaning work.[19]


14   Qq 15, 55, 82, 108, 114 Back

15   Q 101 Back

16   Qq 58, 60; Ev 15 Back

17   A TOC's holding company must take out a Performance Bond with an insurance company to guarantee that the TOC will comply with its franchise agreement obligations. In the event of default, the SRA could retain some, or all, of the Bond. Back

18   Qq 7, 16-18 Back

19   Qq 103, 113, 115-117; C&AG's Report, paras 2.24, 4.5-4.6 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 11 May 2006