Select Committee on Public Accounts Fiftieth Report


1  Enhancing programme and project management of defence acquisition

1. In 2004-05 following two years of large forecast cost increases, the Department took steps to bring its Equipment Plan under control and to deal with continuing cost increases on some individual projects. For the projects in the Major Projects Report, forecast costs were reduced by some £700 million mainly by cutting equipment capability or numbers.[5] Given previous poor performance in controlling the costs of the projects in the Major Projects Report, reductions were inevitable. The Department said that it had only undertaken these cuts after taking a serious look at what capability it needed in the light of the current threat and had identified the least damaging solutions.[6] In some cases, the threat in certain areas had declined, for example, the submarine threat, and in others fewer weapons were needed as the Department was purchasing fewer planes, ships and helicopters.[7]

2. We have previously recommended that the Department be willing to trade off capability to manage cost increases and to ensure more timely delivery of individual projects.[8] This trade-off should not result in the delivery of a level of capability insufficient to meet the needs of the Armed Forces, but should mean that project teams do not continue to pursue incremental refinements at unplanned expense in cost and time. The best time to make major trade-offs is in the assessment phase when decisions have yet to be reached as to how best to deliver the required capability and substantial funding has not yet been committed.[9] But it is important to retain some scope to trade capability later to bring projects back on track when things go wrong.

3. As projects come forward for approval at the end of the assessment phase, the Department is now defining a threshold level of capability representing the minimum acceptable level below which the equipment would not be worth buying. It also agrees an objective level of capability, representing the full capability it would wish to have. These measures, together with the cost and time ranges approved by the Department, define the envelope within which trade-offs may be made between cost, time and performance. This information is shared with the contractor.[10]

4. Meeting either the threshold or objective levels will not necessarily deliver the required capability to the front-line. As currently defined, these levels only cover technical aspects of performance and not the quantity of weapons or platforms required. For example, although the Meteor missile is currently forecast to achieve 100% of its Key User Requirements, a recent £55 million cut in the numbers of missiles procured is not taken into consideration when measuring overall capability.[11] Consequently, a project could meet all requirements, but not meet the operational needs of the frontline because the available numbers of weapons are too low.

5. The Department has decided to collaborate with France on the Demonstration Phase of the Future Carrier project, and under the terms of the agreement, France will meet a third of the Carrier's demonstration costs already borne by the Department.[12] This contribution will include payments of £55 million, with approximately an additional £45 million at the end of the Demonstration Phase if France decides to remain with the project into the Manufacturing Phase. This collaboration should generate economies of scale benefits for the United Kingdom but consequential risks to the in-service date for the Future Carrier will need to be managed.[13] France has no joint control over the Demonstration Phase of the Future Carrier,[14] and the intended economies arising from collaborating with France are to be driven by industry, not Governments. Industry demonstrated its ability to produce such economies of scale on the shared technology used to meet the Storm Shadow/Scalp cruise missile requirement for the United Kingdom and France, respectively.[15]

6. Previous European collaborative projects, such as the Typhoon aircraft, have been beset by a lack of management direction and problems created by the agreement that the share of work given to the industry in each partner country be in proportion to the intended equipment buy, rather than being allocated to those contractors providing the best value for money. Conversely, projects involving the United States of America have a dominant partner, but British control over these projects is more limited.[16] For example, the Department would prefer that the United States of America commissioned a second engine for the Joint Strike Fighter which would involve British industry in its development and is making its views known.[17]


5   C&AG's Report, para 1.3 Back

6   Q 5  Back

7   Q 32 Back

8   3rd Report from the Committee of Public Accounts, Ministry of Defence: Major Projects Report 2004 (HC 410, Session 2005-06) Recommendation 5, p4 Back

9   Q 29 Back

10   Q 30 Back

11   C&AG's Report, p25 Back

12   Q 18 Back

13   Q 21 Back

14   Q 14 Back

15   Q 20 Back

16   Q 43 Back

17   Qq 26-28 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 27 June 2006