Select Committee on Public Accounts Fiftieth Report


2  The impact of older projects on overall acquisition performance

7. The Department blames its overall poor performance on the older projects which remain in the Equipment Plan and Major Projects Reports for many years, the so called toxic legacy.[18] Previous cost and time overruns on these older projects do continue to impact on the overall forecast time and cost budgets. But only current performance on these projects features in the in­year cost and time variations reported on in the Major Projects Report. The Department argued that the challenge with the older projects is to deal retrospectively with poor contracts and inappropriate levels of financial exposure.[19] It regarded the Astute submarine; Nimrod MRA4 aircraft; Type 45 Destroyer and Typhoon as particularly difficult projects.[20] Figure 1 illustrates the problems on Astute, Nimrod MRA4 and Type 45 projects and what the Department has done to rectify them:
Figure 1: Cost and time histories of the Astute submarine, Nimrod MRA4 aircraft and Type 45 destroyers.[21]Astute submarine

Nimrod MRA4 Aircraft


Type 45 destroyers


Source: National Audit Office

8. As Figure 1 illustrates, the Department has experienced great difficulties on the Nimrod MRA4 aircraft project. As reported in the Major Projects Report 2003,[22] the Nimrod was forecast to be delayed a further 3½ years and cost a further £540 million in-year. The Department recognised the problems and restructured its contract with BAE Systems and introduced improved project management. But still Nimrod continues to slip and to cost more money.

9. Eight of the more recent projects are forecast to be delivered on or less than their budgeted costs. Time overruns forecast in-year are concentrated on four more recent projects and Nimrod, leaving other projects in the Major Projects Report forecasting no additional in-year delays.[23] The Department has now had many years to sort out the problems on older projects and in some cases has put them on new contractual footings.

10. Historically, the in-service date of a project was set as the delivery to the front-line of a particular piece of defence equipment. For example, the in-service date for Typhoon was measured by the delivery of the first aircraft to the Royal Air Force, which was achieved in June 2003. This date did not represent delivery the start of operational capability, however, since supporting elements such as training and logistics had still to be delivered. The aircraft is not yet available operationally to the Royal Air Force. The elements needed to provide operational capability are called 'Lines of Development', and include infrastructure, logistics, organisation, personnel and training as well as the equipment itself.

11. Although the Department has made considerable progress in addressing inconsistencies in setting credible In-Service Dates for projects, the term is not always applied consistently, nor does it always represent real delivery of defence capability. More recent projects in the Major Projects Report have in-service dates that do relate to the delivery of defence capability to the front line. For example, the in-service date for Precision Guided Bomb provides for a stated number of weapons and suitably modified aircraft; trained personnel and support equipment; as well as the necessary flight test programme clearances to permit the capability to be used on operations.[24]

12. More consistency is required, however, across the individual capabilities listed in the Major Projects Report. Some projects, such as Nimrod MRA4, still focus on the delivery of pieces of equipment, even though there was the opportunity to change this when the in-service date was modified in February 2003. In some cases, the Department has modified in-service dates to better reflect the delivery of operationally-available capability. For example, the Airborne Stand-Off Radar system had its in-service date amended to include the operational availability of the system. But not all project in-service dates are expressed in terms of all the Lines of Development necessary to ensure the capability is operationally usable and supportable.[25]


18   Q 39 Back

19   Qq 39, 42 Back

20   Qq 37, 39 Back

21   Q 42; C&AG's Report, Project Summary Sheets, pp 67, 107 Back

22   43rd Report from the Committee of Public Accounts, Ministry of Defence: Major Projects Report 2003 (HC 383 Session 2003-04); Qq 3, 42; C&AG's Report, Ministry of Defence: Major Projects Report 2003 (HC 195, Session 2003-04) paras 3.2-3.23  Back

23   C&AG's Report, Ministry of Defence: Major Projects Reports 2003 (HC 195, Session 2003-04) Figures 4, 6 and Appendix 3 Back

24   C&AG's Report, Project Summary Sheets, p75 Back

25   C&AG's Report, Project Summary Sheets, p93; C&AG's Report, Ministry of Defence: Major Projects Report 2004 (HC 1159, Session 2003-04) Box 1, p12 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 27 June 2006