channel tunnel rail link
Department FOR TRANSPORT
MR DAVID ROWLANDS CB and MR MIKE FUHR
LONDON AND CONTINENTAL RAILWAYS
MR ROB HOLDEN
Evidence heard in Public Questions 1 -
94
USE OF THE TRANSCRIPT
1.
|
This is an uncorrected transcript of evidence taken in
public and reported to the House. The transcript has been placed on the internet
on the authority of the Committee, and copies have been made available by the
Vote Office for the use of Members and others.
|
2.
|
Any public use of, or reference to, the contents should
make clear that neither witnesses nor Members have had the opportunity to
correct the record. The transcript is not yet an approved formal record of
these proceedings.
|
3.
|
Members who
receive this for the purpose of correcting questions addressed by them to
witnesses are asked to send corrections to the Committee Assistant.
|
4.
|
Prospective
witnesses may receive this in preparation for any written or oral
evidence they may in due course give to the Committee.
|
Oral Evidence
Taken before the Committee of Public Accounts
on Monday 28 November 2005
Members present
Mr Edward Leigh, in the Chair
Greg Clark
Mr Ian Davidson
Kitty Ussher
Mr Alan Williams
________________
Sir John Bourn KCB, Comptroller and Auditor General,
National Audit Office, gave evidence.
Ms Paula Diggle, Second Treasury Officer of Accounts, HM
Treasury, gave evidence.
REPORT BY THE COMPTROLLER AND AUDITOR GENERAL
PROGRESS ON THE CHANNEL TUNNEL RAIL LINK (HC77)
Memorandum submitted by Department for Transport
Examination of Witnesses
Witnesses: Mr David
Rowlands CB, Permanent Secretary, Mr
Mike Fuhr, Director of Major Projects, Department for Transport, and Mr Rob Holden, Chief Executive, London
and Continental Railways, gave evidence.
Q1 Chairman:
Good afternoon and welcome to the Committee of Public Accounts, where today we
are looking at the Comptroller and Auditor General's Report on Progress in the
Channel Tunnel, which examines progress made in the Channel Tunnel rail links
since the last PAC report on this in March 2002. We welcome back to David Rowlands, the Department's Permanent
Secretary, Rob Holden who is the Executive Chairman of London and Continental
Railways, and Mr Michael Fuhr, who is the Director of Main projects. You are all very welcome. Can I start by asking you, Mr Rowlands, to
look at figure 11 on page 27. You
will see there that the latest Eurostar revenue forecasts are even below the
low case ones for 2001. Is that right?
Mr Rowlands: Yes.
Q2 Chairman: What is the likelihood then, Mr Rowlands, that they will be
revised down again?
Mr Rowlands: We are looking
at the moment at the revenue forecasts to re-forecast when LCR may need to
access the access loan charge arrangements.
I think it is too soon to say that they will be revised down again. We will have a clearer view at the end of
the year.
Q3 Chairman: You do not know. Mr Holden,
can you add anything to that?
Mr Holden: The revenue forecasts are continually being
revised. I think you need to look at
this project though, in terms of more than the revenue forecasts; it is a
combination of issues. Together with
other things that have happened since these forecasts were last produced - and
the Committee reviewed the situation in 2001 - a number of things have happened
which have---
Q4 Chairman: You are not answering the question. What is the likelihood of these forecasts being revised down
again?
Mr Holden: I think the likelihood is that they would be
revised downwards and then reviewed again---
Q5
Chairman: The likelihood is
that they will be revised downwards.
Thank you, that is fine. Mr
Rowlands, can you now please look at page 15 paragraphs 2.5 and 2.7 and please
explain to the Committee why the Government, or rather the taxpayer, has
underwritten every single pound of debt in this project?
Mr Rowlands:
Because
financially it was the most efficient way to structure a project that was in
the private sector. What we ensured was
that we did not underwrite all of the risk associated with the project; much of
that remains with both insurers and with Bechtel, as you have seen from the
NAO's report.
Q6 Chairman The taxpayers are over a barrel
over this, are we not?
Mr Rowlands: No, we are not over a barrel.
Q7 Chairman: Can
you explain why not then?
Mr Rowlands: In the
event that this project significantly overruns in terms of cost, for example a
20% cost overrun, the insurance market is out to the tune of £215 million, and
Bechtel is out to the tune of £100 million, as is well set out in the report.
Q8
Chairman: Let us pursue
these factors further. Can we look at
the access loan charge, which is dealt with on page 34, paragraph 3.29. Can you explain to the Committee,
Mr Rowlands, how much of the access charge loan will be repaid; or is it
going to be just another subsidy from the taxpayer?
Mr Rowlands: As the
report says, the LCR expectation is that they will repay all the amounts they draw
down under the access charge loan arrangements.
Q9 Chairman: Can
you now please look at figure 20 on page 38?
This is an important matter; it is the value-for-money assessment of the
case for going ahead with section 2.
Obviously, the economics of the project depend heavily on assumptions
about regeneration benefits - do you accept that?
Mr Rowlands: Yes.
Q10
Chairman: So can we be confident about the numbers in
this figure?
Mr Rowlands: If you look at the extreme right-hand side
down the bottom, 0.7, that is the calculated benefit cost ratio for the low
case, that is the case which includes a £300 million overrun on the original
target construction costs. It is 0.7,
but that does not include any benefits from domestic services. We believe that once those are included that
that will take it above one. We will be
looking again at this once the project is complete, but bear in mind that at
Stratford, Ebbsfleet, King's Cross and indeed at Eastern Quarry, you have about
100,000 jobs tied to the arrival of this project. From memory, there are 18,000 homes and a lot of retail
developments. It is fair to say that
though this project depends in part upon its regeneration benefits, not just
its transport benefits, those benefits are materialising, as the report sets
out.
Q11
Chairman: So if we look at the early part of this
report at paragraph 6, which you will find on page 1, the NAO states there that
the economic case for the link remains marginal. Do you agree with that?
Mr Rowlands: I agree in the sense that, as we speak, the
regeneration benefits are beginning to go in place. They will start to build out Stratford city in 2006 and King's
Cross in 2007. I do not think any of us,
with hand on heart, can say that that is exactly the regeneration benefits, but
they are there. They are still marginal
but I think they will be less marginal as time passes.
Q12 Chairman: In relation to the cost overrun protection programme you can find on page
32, paragraph 3.21, the report states that both the Department and
the Treasury felt the Department was in a weak position when negotiating the
Cost Overrun Protection Programme and that it was expensive. The obvious question is: why did you go
ahead with it?
Mr Rowlands: We looked at the alternatives. There was a Railtrack alternative, which the
report well sets out, that was even more expensive. You see that in table 17 on page 31. We looked at whether the Department in effect should take all the
risk on cost overrun. As the report
sets out, at the mid-case forecast that would have been, in NPV terms, perhaps
£40 million cheaper, so essentially we had to look and say: "To save £40
million in net present value we take all of the construction risk: is this a
sensible thing to do when we cannot manage those risks?" The conclusion we came to was that it was
better to go with what we genuinely did think was an expensive proposition, but
it was the best proposition we had in front of us.
Q13
Chairman: Do you want to
comment on that, Mr Holden?
Mr Holden: I have nothing to add to what Mr Rowlands says. We believe we put to the Department a
proposal which met their objectives.
Q14
Chairman: The product is going to cost us £5
billion. Is that broadly right?
Mr Rowlands: In finite term prices I should think more
like about 5.8.
Q15
Chairman: Would it have been cheaper just to have done
it as a government project?
Mr Rowlands: It depends
whether you believe the Government would have been able to control the costs,
the timetable and the scope. The last
thing we did, if I am allowed to say so, was the Jubilee Line extension, which
came out 21 months late and £1.4 billion over budget. At least against that yardstick, this project is performing a
great deal better.
Chairman: We have the Auditor General of Bulgaria,
Professor Valeriy Dimitrov, with us.
Welcome.
Q16 Kitty
Ussher: I wanted to probe
the wider potential benefits of this scheme.
Can you look at the second phase.
Why was it decided that that should go ahead, in terms of policy-makers
in your Department?
Mr Rowlands: Remember that this project, when it was
restructured in 1998, was broken into two parts, section 1 and section 2. At that stage, albeit that it was difficult
to properly capture the employment and regeneration benefits, it was decided to
go ahead with the project. When it was
reconstructed in 2001, and particularly going ahead with section 2, when that
was reappraised the case was still there in cost-benefit terms.
Q17
Kitty Ussher: Can you
explain that a bit more? The case was
still there in cost-benefit terms. Do
you mean in terms of recouping your investment purely on passenger numbers, or
on wider considerations?
Mr Rowlands: At the time, as I recollect, even the
international transport benefits were sufficient to justify the case on the
basis of the mid-range forecast. It did
not stand up at the lower end.
Remember, this project was originally conceived not simply for its
transport benefits but for its regeneration benefits as well. Although it was difficult at that stage to
properly to quantify it, I think in my earlier answer I set out some of the
consequences that are beginning to flow and will flow. When we looked at it back in 2001, it was a
combination both of a transport benefits but also of the then more clearly
emerging regeneration benefits.
Q18 Kitty
Ussher: So that we can be completely clear, the
mid-range forecast showed that it was probably a good idea to go ahead
purely on the passenger benefits and the transport benefits although there were
clearly some risks at the lower end.
Mr Rowlands: That is right, yes.
Q19
Kitty Ussher: But you
presumed that there would also be wider positive benefits from economic
generation of jobs, but those were not quantified and no analysis was
done. Is that correct?
Mr Rowlands: Yes, I think that is right, and I think the
report says that this route began life back in 1991 when the then government
rejected BR's so-called southerly approach because it did nothing for the
regeneration of east London; and that is why this route was chosen. That is why you see, for example, the
station at Stratford, to drive redevelopment there.
Q20
Kitty Ussher: Once the link
is complete it will be easier to travel, for example, from my constituency in
Birmingham, in the north-west all the way through to the Continent. Was there any assessment of wider economic
benefits to the UK as a whole?
Mr Rowlands: Not to the wider economic benefits. That is what we will need to look at when we
go back on this project when it is complete and finally assess what the
out-turn costs were and what the benefits are.
Q21 Kitty
Ussher: Obviously I support
any kind of decision that is good for jobs, but do you agree with me that it is
unusual for major government projects to look at the wider jobs impact, and
that there are other areas of government procurement in defence and the NHS
where that is not normally looked at?
Mr Rowlands: If you had asked me that question in 2001 I
would have probably said "yes" but it is not the case in 2005. My Department particularly is moving to
assess transport projects on a wider basis than the traditional, may I say,
rather narrow transport cost-benefit approach.
We now require all projects for example to undertake an economic impact
report - and again the NAO report touches on that. We are doing one, for example for Crossrail which looks at
unemployment and employment consequences for major transport
infrastructure. We are broadening the
basis on which we look at projects now.
Q22
Kitty Usher: Does that mean
you are developing a new methodology to be able to quantify economic benefits
of large projects like this?
Mr Rowlands: The guidance on economic impact I think we
posted on our website and it runs to about 24 pages, so, yes, there is an
emerging methodology for this.
Kitty Usher: Chairman, I look forward therefore to
improved train links to my own constituency as a result of this assessment.
Q23
Greg Clark: Sir John, in cash terms the total support for
the rail link comes to about £5 billion.
Do you believe that that represents value for money, Sir John?
Sir John Bourne: My
view essentially is that the Government launched on this project on the basis
the private sector could do it. That
was the original conception of what "value for money" meant. Since then of course it has become clear
that it cannot be done on that basis, and the taxpayer has been called upon to
stand behind the project to an increasing degree, in circumstances, as we know,
with everything Mr Rowlands has said, where there is still a degree of
uncertainty; and there is also uncertainty about the economic regeneration
benefits which underscored the original cost-benefit analysis. So in terms of what the original conception
of what value for money was, this project does not meet that. That is not to say of course that in their
desire to keep, if I put it this way, the show on the road, it has not been
addressed with a lot of care and thought, in the way that the report brings
out. However, in terms of what was
originally intended, the value for money has not been achieved.
Q24
Greg Clark: Mr Rowlands, in answer to a question from
the Chairman you pointed out that the expected benefit-cost ratio is 0.7
excluding regeneration. Do I take it
that this will go down if, as indicated by Mr Holden, the passenger forecasts
for Eurostar go down?
Mr Rowlands: If nothing else were to be included, you are
right that that number would go down; but, as you say, 0.7 does not include the
regeneration benefits and it does not include
the benefits of domestic -----
Q25 Greg
Clark: Sure, but the standard practice, I
understand, from the Treasury, is that one should not include these benefits,
which are difficult to quantify, so from a position of only 0.7 -----
Mr Rowlands: I am sorry, Mr Clark, my Department's
position now is that we do intend to capture these benefits.
Q26
Greg Clark: I am sorry, I missed that, but the financial
benefits go down from 0.72. Where would
you estimate it might be headed to - 0.5?
Mr Rowlands: I think you are tempting me into an answer I
should not give you. We may have a
clearer idea when we get to the end of the year and we have done some re-
forecasting.
Q27 Greg
Clark: Perhaps you can write to the Committee and
give us the percentage.
Mr Rowlands: I am very happy to do that.
Q28 Greg
Clark: Mr Holden, LCR attributes, on page 34,
paragraph 3.27 of the report, the increase in cost to the effect of
railway-related inflation being greater than assumed in 2001. Is that correct?
Mr Holden: Yes.
Q29 Greg
Clark: What is railway-related inflation at the moment?
Mr Holden: It is very difficult to get a precise
measure on it, but there are two factors we have taken into consideration. One is the fact that indices as measured by
the ONS in the construction industry are running at about twice the level we
previously assumed, but specifically railway inflation, following the events of
Hatfield and the Railtrack - railway administration - costs increased
enormously.
Q30
Greg Clark: I am asking how
much. What is it currently running at?
Mr Holden: In terms of impact on the project we believe
it is in excess of £300 million.
Q31
Greg Clark: No, but as a
rate of inflation your forecast was based, by implication, on a certain rate of
inflation, and it has been greater than that.
Mr Holden: It has doubled from 3% to over 6%.
Q32
Greg Clark: So the rate of inflation is 6% rather than
3%.
Mr Holden: It is in excess of 6%.
Q33
Greg Clark: Why was that not anticipated when the
original assessment was made?
Mr Holden: It is very difficult to anticipate inflation
a great many years into the future. On
section one of the Channel Tunnel rail link, we actually over-estimated the
effects of inflation, and unfortunately in section two we have under-estimated
the rate of inflation. To forecast
specific events, as was the case which happened with Hatfield and the Railtrack
administration, is, I guess, impossible.
Q34
Greg Clark: What are you assuming for the next five
years the rate of railway inflation will be?
Mr Holden: We are assuming basically a continuing level
like we have seen in the last three or five years of between 5% or 6%.
Q35
Greg Clark: Why should that continue when Hatfield is
receding into distant memory?
Mr Holden: I think we are being very prudent at this
point in time so that we do not have a recurrence of the problem we are now
talking about.
Q36 Greg
Clark: Is that the reason for inflation being
higher? Can you explain why Hatfield
has put inflation up; rather than requiring more things to be done? Why should the cost of doing those
things be higher?
Mr Holden: There was a greater demand for a limited
amount of resource, and suppliers in the industry took great advantage of that
inequality of supply and demand, as you would expect and ordinarily see in many
aspects of business.
Q37
Greg Clark: So there are more public funds chasing a
limited number of people who can carry it out?
Mr Holden: This was both private and public funds at
the same time. We were, by the schedule
of CTRL, required to do certain works at a certain time, and therefore we were
of course at a very great disadvantage.
Q38
Greg Clark: Were the
contractors making more in profit?
Presumably people were paying the same rates of pay to the engineers and
the people working on this; or were they just taking more profit?
Mr Holden: I think the rate of profit is the same
generally, because profit is generally calculated on what we call a
de-escalated basis, i.e., without the impact of inflation.
Q39
Greg Clark: So where is all this extra money going? In whose pockets is it ending up?
Mr Holden: In terms of additional costs and in terms of
additional wages for people and in terms of additional cost of materials.
Q40 Greg
Clark: Going forward, do you expect to see that,
presumably as capacity comes on-stream, some of these cost pressures to reduce
- yet you are assuming a continued higher rate of inflation?
Mr Holden: As I say, we are being very prudent now in
terms of our costs for completion of the project. Many aspects of the project are now complete, so we are talking
in a much more limited range of costs which we need to estimate.
Q41
Greg Clark: You are currently re-forecasting the
passenger forecasts, as I understand it.
Who is carrying out that forecast?
Mr Holden: This is the commercial team within the
Eurostar business.
Q42
Greg Clark: Have they contracted any consultants to help
with that?
Mr Holden: They do contract consultants and they do
undertake various market research analysis.
Q43 Greg
Clark: Do you know which firm is doing the
forecast?
Mr Holden: I do not know which firm at this particular
point is doing the work. I know that in
the past LEK have undertaken the work, and Booz Allen have undertaken the work
for the Department for Transport.
Q44
Greg Clark: According to the report, Booz Allen conducted
the work in both 2001 and in 2004, in terms of the projections. Was it sensible to employ the same firm to
project into the future since they got it so disastrously wrong in 2001?
Mr Holden: There is a balance to be taken between
bringing in new people who have very limited knowledge of the business, and
people who do. That judgment has to be
made every time a decision is made.
Q45
Greg Clark: The
consequences of the over-estimation in 2001 were pretty catastrophic. It was not the consultants' fault, then,
that they made that mistake?
Mr Holden: I do not believe it has been catastrophic
because there have been a number of other things that have happened since those
estimates were made, which have kept the economics of the project very much the
same today as they were in 2001, at the time of the first NAO report.
Q46
Greg Clark: Just
in terms of the forecast revenues, if it was not the fault of the consultants,
was it the fault of the Department? Who
misperceived the -----
Mr Rowlands: I think
Booz Allen were forecasting for the Department not for LCR.
Q47
Greg Clark: I am sorry, the question should be put to
you, Mr Rowlands.
Mr Rowlands: It is certainly the case that the forecasts
substantially over-estimated the position today. I think it is the case that even when Booz Allen did the 2001
forecast, which they actually did in 2000, they, and frankly nobody else,
really quite figured out the stunning success of the low-cost airlines. The low-cost airlines did not exist when
this project was put together.
Q48 Greg
Clark: They
did not exist in 2000?
Mr Rowlands: Not with the sort of success that you have
seen in 2005 with an ever-growing range of low-cost destinations; nor could
they foresee 9/11 and the impact that that would have.
Q49
Greg Clark: This
is a firm of strategy consultants who have a feel for the developing trends in
the sector, and you are saying that five years ago they had no inkling that
low-cost air travel was likely to increase.
Mr Rowlands: No, I did not say that. I think I said that they, and nobody else,
quite estimated the stunning success of the low-cost airlines. What it does tell you, and a warning for the
future - and again the NAO has drawn it out - is the difficulty of accurately
forecasting revenues and ridership on very novel major projects. This after all was the only high-speed
railway in the country, and the first new railway line for a hundred
years. Looking back, a lesson that we
will want to draw out is that the next time we look at anything like this we
will want to look a great deal more severely at the downside.
Q50 Greg
Clark: Presumably you are doing
that now. Is Booz Allen conducting the
current review?
Mr Rowlands: I believe they are.
Q51
Greg Clark: They are, for the third time.
Mr Fuhr: They will be conducting the review in due
course.
Q52
Greg Clark: So they have got it wrong twice before. Why are you confident that they are not going
to get it wrong for the third time?
Mr Holden: I am sorry, I think we need to correct an
impression there. The increase in
revenues relative to the introduction of CTR on section one of the Booz Allen
forecast was very much on line. What
they, and everybody else, failed to take into account were the macro events
which have occurred since 2000. As Mr
Rowlands has said, there was 9/11; and there was also a huge impact in this
country through the effects of foot and mouth.
They have taken a long time to recover from. If you put those macro things to one side, which I do not believe
anybody is capable of getting right, the underlying remaining issues - they
have been very close to the mark.
Greg Clark: My
time is up but I think chart 9 speaks for itself in terms of their forecasting
being inaccurate.
Q53 Mr
Davidson: Can I return to this question of the
estimates, and looking at the first set of estimates on page 24, chart 8. So far we have had an explanation that it
was low-cost airlines which apparently could not have been foreseen; 9/11; and,
the one that takes the biscuit, foot and mouth. Basically, the difficulties therefore of this have been caused
partly by foot and mouth. Can you
clarify for me whether or not there are any other factors that you think made
these figures over-optimistic?
Mr Holden: In terms of the current year, 2005, yes, the
events of 7 July in this country. Until
that point we were experiencing a 15% growth in revenues; since that point in
time we have had no growth in revenues over the previous year. These are very significant effects which
take an awful long time to recover from.
Q54 Mr
Davidson: Of course they
are; that is absolutely correct; but a reputable firm like this do not factor
in the impact of any possible cataclysmic event, do they not? They work on the basis that everything will
be hunky-dory and that nothing wrong will ever happen.
Mr Holden: Cataclysmic effects, as you quite rightly
point out, are not factored in on an annual basis; they are factored in
throughout -----
Q55
Mr Davidson: They are not
factored in!
Mr Holden: ----- what is an 86-year project.
Q56 Mr
Davidson: So these sorts of things are factored in. Are there any other cataclysmic events that
you think that they did factor in?
Mr Holden: I do not think anybody can specifically
specify what they are. One generalises
about the impact of -----
Q57 Mr
Davidson: Right. One generalises about cataclysmic events and
one therefore anticipates that something might happen, but why are these
estimates all erring on the one side to make the project more viable rather
than being more mainstream? It seems to
me that the estimates that you are working on are consistently over-optimistic.
Mr Holden: Not for 20043 and 2004. As I said, the uplift from the introduction
of CPR section 1 was exactly as forecast.
Q58
Mr Davidson: So you are quite happy that the 2004
forecasts will be completely in line over a long period and that they will not
turn out to be over-optimistic?
Mr Holden: I am confident that over the 80 odd years
remaining on this franchise, sufficient revenues will be generated to enable
LCR to fulfil its obligations.
Q59 Mr
Davidson: The difficulty
about working over an 80-year time span is that I am not sure the Committee
will be able to call you back at some point! If these estimates turn out to be over-optimistic, what would the
effect on LCR financing and the potential recourse to the taxpayer through the
access charge loan be?
Mr Holden: We will be drawing down on the access charge
loan arrangement, but under the forecast that we have we also envisage being
able to repay any drawings from -----
Q60 Mr
Davidson: I understand you envisage - that is right - but if it does
not turn out as planned, what will the consequences be?
Mr Holden: It clearly depends on how bad the situation
is. It would have to deteriorate quite
considerably before we were in a position where we could not repay any
drawings.
Mr Rowlands: The work we are doing at the moment will
re-forecast, as best it can on a forecast basis, when we expect London and
Continental Railways first to have to draw down under the access charge loan
arrangement. Under the development
agreement, I believe, from memory, that in net present value terms the total
drawing that they can take under that loan agreement is £270 million. If they go beyond £270 million, they will be
in breach of their development agreement.
Q61
Mr Davidson: Then what
happens?
Mr Rowlands: Then the Government has a right, if it so
wishes, I believe, to terminate that agreement.
Q62
Mr Davidson: Then what
happens?
Mr Rowlands: It would all revert to the Government.
Q63
Mr Davidson: It all reverts
to the Government in a situation where it is basically bankrupt! So we have the consolation that if it all
goes wrong and the money cannot be repaid, we get it.
Mr Rowlands: Yes.
Q64 Mr
Davidson: What exactly is the advantage to us of having this asset
that is making such an enormous loss that it cannot repay the money that we
have lent it, coming to us?
Mr Rowlands: We would still get infrastructure costs of
some £5 billion. The British share of
the Eurostar train sets that run the joint service with SNCF and SNCB - it may
come back on the basis that it is not a profit-making enterprise at that point. If it came back in those circumstances I
guess that would be true, although I have to say that much the same can be said
of the existing national railway system.
Q65
Mr Davidson: Is there a
limit to the amount that the Department for Transport are prepared to lend to
LCR?
Mr Rowlands: That is why we have set a cap on the maximum
drawings under the access charge loan agreement.
Q66 Mr
Davidson: There is a limit
and that is it!
Mr Rowlands: As I say, they would be in breach of their
development agreement at that point.
The Government would then have to decide what to do.
Q67 Mr
Davidson: Can we turn to the
question of regeneration benefits. Our
previous recommendations indicated that there should be a "robust appraisal" of
the regeneration benefits. Has
that been done yet?
Mr Rowlands: We cannot do a robust appraisal perhaps in
the sense that you mean until this project is built out and section 2 is
running. We have seen the consequences
in terms of the finalised proposals for King's Cross, Stratford, Ebbsfleet; and
-because it is, although not part of LCR's plans, also Eastern Quarry in Kent,
which ties into Ebbsfleet.
Q68 Mr
Davidson: Is much work on the methodology of that being done at the
moment, or are you waiting until everything is finished before you start that?
Mr Rowlands: No.
As I said to Ms Ussher, we have put out guidance on how to put together
an economic impact report, when looking at the employment consequences of large
and indeed small transport infrastructure projects. It is a non-trivial exercise.
I believe the report being done for Crossrail is not yet finalised, and
it has taken 12 months already and is expensive to produce. We will in effect do this for this project
once it is built out and running.
Q69
Mr Davidson: How will you be
able to separate the boost to areas like east London from this project, as
distinct from the Olympics, or from anything else that is happening?
Mr Rowlands: I should not trespass into whether or not the
Olympics came here because of this project, although it certainly helped at the
margin. It will be a challenge to
disentangle some of the Olympic effects, but that is less so in the case of the
King's Cross railway lands, which have stood there semi-derelict for heaven knows
how long, and only this project has kicked it into life. Ebbsfleet would not exist without this
project, and the Stratford railway lands similarly have stood desolate for
decades. I think there is a real task to
separate it out. There are lessons to
be learnt, and it is a real task to separate out the genuine regeneration
consequence from the background noise, and I cannot give you a defined answer
today. That is one of the challenges
for us when this project completes.
Q70 Mr
Williams: Mr Rowlands, in reply to the Chairman you
said that the Government underwriting all debt was the most efficient way of
funding risk in the private sector. Is
that right?
Mr Rowlands: I think the Chairman had asked what was the
benefit for the Government seemingly underwriting every last penny of this
project. I think I said in reply that
it helped to maintain this project in the private sector, and therefore the
carrying of a substantial degree of risk of cost overrun and proper management
therefore in the private sector.
Q71 Mr
Williams: We have ended up with a situation where inflation
estimates have been grossly under-estimated and inflation being much higher,
and with the revenue being over-estimated; the Government is piggy in the
middle and the taxpayer is going to pick up most of the bill.
Mr Rowlands: I do not believe that I could be wrong that
this project will substantially overspend, but if it does do so then the
Government is not piggy in the middle.
As I said earlier, for a £600 million cost overrun the insurance market
will pick up £215 million and Bechtel will pick up £100 million, so we have
laid off significant risk on to the private sector.
Q72
Mr Williams: What is the
maximum the taxpayer could be at risk for?
Mr Rowlands: Above £600 million, the taxpayers are in for
every last penny because this is a layered arrangement and the bill was up to
£600 million; after that the insurers would have fallen away, but there is no
evidence that this project is going to overrun to the extent of 30% or
40%. We have reached a point where it
is well over 80% complete. The spend to
go is only measured now in hundreds of millions against a total spend of £3
billion or so. I do not think we face
that risk. The challenge is to keep a
grip on it at this stage to get it finally delivered at the best cost we can.
Q73
Mr Williams: How can you say
there is no way? After all, the reason
that the inflation figures were altered was because they had been
over-estimated previously, and that was a relatively short time ago. We are talking about revenues up to
2050. How can you say there is no way
it will exceed that ceiling?
Mr Rowlands: Forgive me, I was talking about the cost of
building this project. This project
will complete with Eurostar inter-service into St Pancras in 2007, so there is
not much more to be spent in terms of simply building the project. The risk beyond that- you are quite right -
relates to performance of Eurostar itself.
That is to do with its passengers and its ridership.
Q74 Mr
Williams: Mr Holden, you made the point about 7 July. You had had 15% growth prior to that but now
there is no growth. Can we look back to
9/11? What was the pattern then, and
how did it change? Did we then suffer a
significant change in revenue as a result of that, and has it recovered; and,
if so, to what extent has it recovered?
In other words, what I am trying to get at is how temporary or permanent
you calculate the impact of 7 July to be.
Mr Holden: The year 2000 was a record year for Eurostar
revenues. The first eight months of
2001 were showing a reasonable increase over 2000. In real terms we are not yet back at those levels, so the
recovery period is very long indeed. Mr
Rowlands referred previously to the low-cost airlines. We find that when people move away, they
have now a greater number of alternatives, so the task of recovery has been
difficult for 2001 and will continue to be so.
Q75
Mr Williams: In terms of
your latest projections, what adjustment have you had to make to them? Could you quantify the adjustment you have
had to make in forward projections as a result of 7 July?
Mr Holden: The increase that we expect from section 2
will be about the same as was previously envisaged, but we are working from a
lower base, which I would say was probably between 15% and 20% lower than we
would have expected without some of these major extraneous events.
Q76 Mr
Williams: Is that short term or long term?
Mr Holden: It takes a long time to recover from that.
Q77
Mr Williams: So 20% is what,
in financial terms, in revenue?
Mr Holden: It is £40 million a year.
Q78
Mr Williams: As you say,
that could be for a very long period ahead.
If it were for ten years, it would be £400 million.
Mr Holden: You would get recovery over that period.
Q79 Mr
Williams: Yes, but recovery is never to the original path, is
it? This is what I am getting at. It is unfair because none of us know what is
going to happen in the future, but the 40 million has now put you on a new
growth path and you have now different lines of anticipated revenues, which are
going for a long period to be £40 million a year or thereabouts out of what you
have estimated. So the £400 million
over ten years, just on the revenue side, makes your £600 million not look as
improbable as you were trying to make it sound, Mr Rowlands.
Mr Holden: One also has
to look at the associated costs with that; so the net impact is considerably
lower than what you would imply from that analysis. Also, as I said to one of the earlier questions, we cannot look
at the revenue forecasts in isolation from other events. In particular, the cost of financing this
project through the changes that took place in 2001 and 2002 have had a
substantial beneficial impact, as the National Audit Office brings out. Those things combined bring you to the
conclusion, which the NAO did, that the expected burden on the taxpayer is
little different than it was in its previous report four years ago.
Mr Rowlands: I think we are talking about slightly
different hundreds of millions of pounds.
I was talking about a potential cost overrun and trying to lay the risk
off on the construction costs of the second section of the high-speed railway
link. That will be done and dusted by
the time we are into 2007. Whatever
that cost is eats into the cash that London & Continental Railways
have. Your £400 million, if that is
what it is, because the revenue line has been depressed, is a problem going
forward, and at that point may impact on the point at which LCR have to access
the access charge loan agreement, and that is the work we have been forecasting
at the moment and what I promised Mr Clark the details of once we have them.
Q80
Mr Williams: The third
imponderable in the calculations, as has been referred to previously, is the
regeneration benefits; but, as Mr Davidson said, by the time the development
work related to preparation for the Olympics is taken into account we are never
really going to be able to arrive at any meaningful figure, are we?
Mr Rowlands: The biggest impact in terms of jobs is at
Ebbsfleet. I do not think the arrival
of the Olympics has any material impact in terms of what happens at Ebbsfleet
and I think it is an irrelevance. It
may be difficult to disentangle Stratford, but I am sure we can. I do not think it will have any impact in
terms of Eastern Quarry in Kent, and I think the impact on King's Cross is
probably limited as well, so I think it is do-able.
Q81 Kitty
Ussher: When you
answered my questions previously you said that you now had a developed economic
methodology for assessing the benefits of transport infrastructure. To clarify, is it that guidance that you
have used in 2001 of the chart on page 20?
Mr Rowlands: No.
Q82 Kitty
Ussher: So since then?
Mr Rowlands: If I had answered your question in 2001 I
would have answered it differently.
Q83
Kitty Ussher: Is it
therefore possible to revisit the cost-benefit analysis done in 2001 using this
new tool that you now have and perhaps coming up with an updated Departmental
assessment of the value for money?
Mr Rowlands: That is what we propose to do. What we propose to do once this second section
is open and you can see what the actual increase in ridership is and you have a
clearer view of what is happening at Stratford, King's Cross and so on, is do a
complete write-up of the project, so we re-visit the costs and the benefits,
and we can finally establish as best you can the out-turn position. We want to re-visit it in terms of lessons
to be learnt for the handling of other projects, some of which the NAO itself
has drawn out in the report. We would
probably want to re‑visit quietly and hide in a drawer in case of FOI
some of the internal Departmental handling of all of this as well because there
are lessons to be learnt.
Q84
Kitty Ussher: That is interesting. When do you propose to do that?
Mr Rowlands: I do not think we can realistically do it - I
think we can start the work - I am speculating now - at the end of 2006 into
2007, but I think it is not until then that you can realistically expect to
produce a rounded analysis of what we finally got.
Q85 Kitty
Ussher: For the record now, you are saying that if you had had the
tools available in 2001 that you have now, your decision on value for money and
cost-benefit analysis may have been slightly different particularly in terms of
the regeneration aspects.
Mr Rowlands: I think the analysis would have been better
developed. I am not saying the decision
would have been different. I think the
better-developed analysis would have supported well the decision that was taken
in 2001.
Q86 Kitty
Ussher: You have mentioned
that you might want to re-visit your Department's handling of the whole
issue. Do you think your Department has
handled it well?
Mr Rowlands: If I am allowed to say so, this is a huge
project and immensely complicated.
There was a sad history of major infrastructure projects in this country
going completely belly-up. This has had
its problems, but I think it has been, in the round, well handled, including if
I may say so by people in my own Department in terms of particularly the
various crises that have riven it, from London and Continental coming in in
1997 asking for another billion pounds from the Government through to - we
rather foolishly thought we had put Railtrack's balance sheet behind the
project at one stage and that disappeared -----
Q87
Chairman: You are getting softer and softer. Can you try and raise the volume?
Mr Rowlands: In the round it has well handled, but there
are lessons to be learnt.
Q88
Mr Davidson: The estimates from Booz Allen Hamilton seem
to have been quite well laid out in the beginning. Was their fee accuracy-related?
Mr Fuhr: No, there was not, and it would be quite difficult to
do that because it would have to be done in retrospect; you would have to see
what the out-turn was and then try to claim back if you thought it was
wrong. The best way to discipline
consultants who do not deliver well is not to employ them again.
Q89 Mr
Davidson: That is an interesting point. Booz Allen Hamilton were wildly out in their first estimates, so
you punished them by giving them another contract; and now, as I understand it,
you have given them a third contract!
Explain to me how the system of penalties works.
Mr Rowlands: If I may say so, the people who were
originally wildly out were called British Rail and SNCF, whose original
forecasts for this railway were hugely bigger than the numbers we are now
looking at. It is true that Booz Allen
have struggled to produce totally accurate forecasts, I think for the reasons
that Mr Holden and I have tried to explain; but it does reflect the difficulty
of forecasting ridership and revenues from brand-new infrastructure where you
have got no analogues to look to.
Again, going back to lessons learnt, next time - and I am sure there
will be some kind of next time - we need to look much more substantially at the
downside risks and what will drive this project under water.
Q90
Mr Davidson: The defence of Booz Allen Hamilton is, first
of all, that somebody else did it worse, which does not seem to me to be
entirely valid; and then they struggled to produce an accurate so-and-so - that
presumably is what you are paying them for, to produce an accurate result. The idea that all this is very difficult and
we should be thankful for anything we get at all does not seem to me to have
the correct rigour applied to it. I do
not entirely accept the point about trying to recover a fee in arrears because
presumably part of the fee could be withheld if necessary in order to see how
accurate they are? Quite clearly, the
estimates here were quite drastically out for somebody who is selling expertise
in forecasting. To get their forecasts
wrong - it would not be so bad if you just picked somebody off the street and
asked them to dissect a chicken and examine the innards - but these people are
actually marketing themselves as being able to forecast the future accurately,
and getting it wrong.
Mr Rowlands: We are satisfied that Booz Allen did the best
professional job they could do at particular points in time. If we did not believe that, we would not
have re-hired them.
Q91
Greg Clark: Mr
Fuhr, I do not know whether you were joking in saying that the best way to
discipline consultants is not to re-hire them if they get it wrong, but they
got it wrong and I do not understand the basis on which they were
re-hired. Did they go through a
competition for the second and third times they were commissioned?
Mr Fuhr: There was originally a competition.
Q92 Greg
Clark: The second and third times?
Mr Fuhr: I cannot tell you from memory whether there was a
competition or whether there was a continuation of the original contract. Any consultant who is producing forecasts
will produce a range, and there will be a view which you have to take within
that range about where the future is likely to pan out.
Q93
Greg Clark: It was below
that.
Mr Fuhr: Some of the forecasts that were produced in 1998,
which were the original CR forecasts, were very substantially higher, based on
original BR and SNCF figures. The
figures that were produced by Booz Allen Hamilton at the time were
substantially below that, but could not take account of some of the market
forces which intervened, like the low-cost airlines and some of the
perturbations which we were talking about earlier.
Greg Clark: I am
concerned, Chairman, in terms of the rigour of processes, when, by
Mr Fuhr's own admission, a consultant gets it wrong, it should at least be
looked at again; and there is no recollection at least that at the
second and third times of re-hiring there was even a competition to look to see
if anyone could make a better case to get it accurate.
Q94 Chairman:
There are further questions we would like to ask about the effect of
the taxpayer-related cost overruns, but I understand you prefer that we ask
those in private.
Mr Rowlands: That would be helpful.
Chairman: Because it is commercially confidential we can
agree to that. We will now move to
private session and I would request all members of the press and public to
leave.