Select Committee on Transport Written Evidence


APPENDIX 8

Memorandum submitted by South Yorkshire LTP Partnership

SUMMARY

  This response represents the collective view of the four district councils in South Yorkshire and the Passenger Transport Executive. Under the requirements of the Transport Act 2000 these authorities must jointly prepare and deliver their Local Transport Plan as a single document for the South Yorkshire Metropolitan Area.

  We believe that, although the LTP has brought certain benefits not least in terms of greater certainty of funding, it remains largely marginal in terms of how it helps us address the scale of the transport challenges we are still facing in South Yorkshire. These challenges must be addressed if we are to secure the economic transformation of the sub-region after many years of industrial decline.

  Particular areas of frustration relating to the DfT's current focus on congestion as a driver for future public investment in transport include:

    —  the inefficiencies of the major scheme bidding process;

    —  the resistance by DfT to recognise improvement in performance if targets have not been met; and

    —  the lack of connection between capital and revenue funding.

LOCAL TRANSPORT FUNDING

Have the local transport capital settlements met what was expected and allowed delivery of the planned projects? What have been the impacts on major transport schemes, and smaller schemes? Have the full allocations been spent as planned? How have cost increases been settled?

  On the whole, although an improvement on previous funding levels, local transport capital settlements have not delivered what was expected. In South Yorkshire our targets for the first LTP have, in the main, not been met. Projects of a more complex nature have proved difficult to deliver within the reporting timescales of APRs. Cost escalations of smaller schemes are met by re-allocating resources from elsewhere in the LTP programme. Major scheme cost increases have been handled through submissions to DfT for extra resources. Full allocations are spent each year but not necessarily on programmed projects.

  The first LTPs were written as bidding documents. There was, however, little if any guidance as to what level of bidding was appropriate. The 10 Year Plan for Transport generated an enthusiasm and belief amongst transport professionals and delivery agencies that funding levels would be of an order capable of bringing real change. LTP targets often reflected this and, in South Yorkshire at least, were based upon identified need and in retrospect set at unrealistically ambitious levels. In the event, the actual levels of allocation, although higher than in previous years under the previous Transport Policies and Programme system, were still insufficient to meet the significant challenges facing South Yorkshire as an area undergoing significant social and economic change after years of industrial decline.

  Although LTP settlements have been modest compared with expectations at the start of the LTP process, the move to indicative allocations for integrated transport block allocations at least provided an opportunity to increase the degree of certainty in programme planning for smaller schemes. In general, South Yorkshire has generally spent its full allocation in each year of the LTP. However this has not always been wholly in line with planned programmes. The DfT's "use it or lose it" approach to annualised LTP capital settlements has resulted each year in some expenditure, deemed to be at risk of not being spent in-year because of delays in the implementation process, being switched to other less complex, less contentious and less effective (in terms of meeting LTP objectives) measures. Transport delivery would benefit from a more relaxed approach towards these annualised settlements.

  The £5 million threshold identifying whether a scheme is a major one or not is too low and has been set at this level for over a decade. It also effects a "definition by cost" rather than what the scheme seeks to achieve. Too many projects of relatively local impact therefore are brought into the DfT's remit for assessment. The introduction of the Regional prioritisation process, as well as adding a further layer of complexity, involves schemes of mostly local impact having to be assessed against criteria concerning regional significance. The opportunities afforded by Transport Innovation Fund to facilitate additional major projects capable of meeting national productivity criteria are significant, but the South Yorkshire partners' view is that to achieve economic transformation here a programme, as opposed to a project-based, approach is needed.

Is the formulaic funding approach the most suitable method for allocating transport investment? What has been the impact of the performance-related component?

  The South Yorkshire partners generally welcomed the formulaic approach to allocating the Integrated Transport block and agreed with the basis of the formula set out in the DfT consultation of July 2005 being an adequate reflection of the pressures related to the transport shared priorities. We expressed some concern at the time that the highest weighting used for the formula, the public transport component, was based only on current patronage data and did not, therefore, recognise efforts to secure "modal shift" and the extent to which potential and new passengers should contribute to this component. This point did not appear to be acknowledged. Also, our preference to phase in the formula over three years (as opposed to five) was not accepted, resulting in a small adverse effect on South Yorkshire's total settlement figure over the plan period of LTP2.

  Although South Yorkshire's actual allocations over the first LTP period have been higher than the indicative amount, this has been the result of supplementary bids being awarded in respect of Objective 1 related projects rather than because of performance related reward funding. South Yorkshire, in recovering from a weak rating for its APR in December 2003, has not had its improved performance recognised in subsequent years' IT allocations as, despite achieving higher scores in December 2004 and December 2005, its relative performance compared to other LTP areas placed it in either the "average" or "fair" band.

  The December 2005 settlement was particularly disappointing for the South Yorkshire partners as, despite bringing our LTP performance up by 17 percentage points to 75% on the previous year, we were still classed only as "fair" and attracted a 5% reduction in our indicative allocation for 2006-07. The assessment of our provisional LTP as "promising" attracted no performance bonus. We feel there is a degree of perversity in that poor performance based upon an unfavourable assessment of performance is rewarded with less funding which contributes to poorer performance. Penalties for non-delivery of certain projects awaiting DfT decisions before they can move forward are particularly galling.

  In addition, our most recent supplementary funding allocation for Objective 1 related projects was significantly lower than the figure bid for as needed to deliver on existing commitments. It has also been negatively affected by the adverse impact of receiving only a "fair" rating for overall LTP performance in 2004-05. In our view, the balance between allocating resources according to need against recognising improving performance is not achieved. The reward system appears not to favour LTPs being delivered in challenging social and economic environments and where delivery must be achieved in co-production as part of a metropolitan area partnership context.

Do Local Authorities have adequate powers to raise resources to fund local transport infrastructure? What other powers would be helpful?

  We believe, strongly, that local authorities do not have adequate powers to raise resources locally for the level of transport involvement necessary to support economic transformation. As a result, the level of transport investment in South Yorkshire, to date, has only been sufficient to aid economic recovery at the margins. We believe a much more focussed effort is needed if transport is not to remain a major barrier to economic transformation. Changes in the institutional and financial arrangements are needed if we are to deliver the types of transport project that can deliver transformational change in South Yorkshire. In South Yorkshire and the wider Sheffield City region the opportunities to improve transport's role include:

    —  recognition by Government departments of the economic impacts of transport investment;

    —  freedom and flexibility to plan and make decisions locally;

    —  local powers to vire between funding streams; and

    —  establishing the Sheffield City region as a Pathfinder City Region on Government initiatives.

  In addition, we believe that the most effective approach to tackling transport barriers to economic transformation would be to develop a locally based programme of transport improvements, resourced from the "national productivity" strand of the Transport Innovation Fund.

Has the balance between revenue funding and capital funding for transport proposals been appropriate? How well have the different funding streams from the Department for Transport and the Office of the Deputy Prime Minister supported local transport projects? Are transport services successful in securing sufficient revenue funding?

  There is a lack of connection between capital and revenue funding, although both are critical to the successful implementation of our transport strategy.

  The LTP system has provided welcome additional capital resources on levels previously allocated under the TPP and Package approach. Revenue funding however has remained largely at a standstill. As new assets are provided the revenue costs of maintaining them need to be addressed through existing budgets. More significant however has been the revenue consequence of supporting a greater number of marginal bus services as operators reduce or remove services considered to be unprofitable. A standstill revenue budget has made it increasingly difficult for the South Yorkshire partners to support such services and develop schemes and projects, even though they are vital to maintaining access to jobs and services for remote or disadvantaged communities and in reducing the numbers of car trips. The imminent demise of rural bus challenge funding will compound these difficulties and create further stress on rural access to jobs and services in a number of South Yorkshire locations.

How efficient is the bidding and scheme preparation stage? What could be done to avoid local authorities wasting significant resources on preparing and designing transport schemes which do not get approval?

  The current bidding process for major schemes is not efficient. Too much time, effort and resource is needed to prepare schemes which may or may not be viewed favourably by DfT. Schemes we believe meet criteria can be delayed (as DfT request more information not originally required). Increasing the £5 million threshold for major schemes or, more significantly, giving more powers to local authorities to raise funds for local transport investment, would avoid the wastage of effort.

  In addition, DfT has passed more of the risks associated with scheme preparation on to local authorities as scheme promoters as a deliberate policy. Whilst this may have the beneficial impact of reducing the number of purely speculative major scheme submissions, the effect has also been to reduce the preparedness of local authorities to commit resources to working on projects that are costly yet could deliver significant benefits in terms of LTP targets. The current DfT consultation on its draft guidance for major scheme funding seems to increase the share of risk carried by local authorities by also seeking a 10% local contribution to all major scheme costs.

  Consultation processes at the local level, often the result of statutory processes, can have a delaying effect on scheme implementation. Although it is entirely right that local communities should have a say in the way schemes that will impact on them are designed and delivered, the current process throws up the following problems:

    —  To cover the costs of scheme preparation a project needs to have first been programmed by the local authority. This means the scheme could change, and its costs increase, as a result of issues or changes identified during consultation.

    —  Once a scheme is programmed DfT's reporting requirements expect to see an output delivered against expenditure during the programme year. In some cases a scheme may take several years to complete but DfT still expects to see an output whenever any expenditure is recorded.

  These problems could be reduced if DfT amended its reporting requirements to recognise that the timescales of some projects span several financial years, and allow work to be progressed on design before "starting the clock" running from when the delivery of outputs must be reported.

  In addition, bidding for "challenge" funding is particularly onerous in terms of staff resources etc.

LOCAL TRANSPORT PLANNING

Were the administrative process and timetable for delivering Local Transport Plans appropriate? How helpful was the guidance from the Department for Transport? How did the second round LTPs learn from the first, and how could the process be further improved?

  The LTP and APR processes represent a significant improvement on previous transport planning processes. They have brought an opportunity to consider transport in its wider context, allow all modes to be considered and provide a framework for more sensible debate about how transport can support wider policy objectives. However, they are highly labour intensive, expensive in terms of staff time and resources, and impose an additional layer of bureaucracy and accountability on top of other auditing and inspection regimes. In an area such as South Yorkshire, recovering from economic decline and looking to transform its economy still further, the LTP is only of marginal significance in delivering what the partners agree is necessary. On this basis the LTP and its reporting requirements are seen as requiring a disproportionate level of attention to be paid to a regime that delivers only a fraction of the investment needed.

  In future, less onerous reporting requirements, a focus on outcomes as opposed to outputs and how resources have been spent would relieve the administrative burden and free up more time and resources to delivering projects. The opportunity to develop a unified reporting framework as part of Local Area Agreements should be taken, although this may require DfT to adopt a less hands-on approach to performance monitoring of local authorities programmes.

  DfT guidance is sometimes received too late for LTP partners to assess and accommodate it, particularly in an area such as South Yorkshire where the statutory requirement to deliver a joint plan involves complex Partnership approval processes that can be time critical. The particular issues of delivery in a metropolitan area where councils and their PTEs must prepare and deliver joint plans, do not always appear to be taken into account within the guidance. There have been incidences of some guidance being unclear or even contradictory, such as in relation to accessibility planning indicators and targets for LTP2. Guidance in relation to setting Congestion targets has been tardy and reliant on untested data and collection methods. Indeed, we are still waiting for the guidance on reviewing and setting speed limits and certain aspects of the use of safety cameras.

How well have the Local Transport Plans delivered better access to jobs and services, improved public transport, and reduced problems of congestion, pollution and safety? To what extent has the Government's Transport Strategy fed into the second round Local Transport Plans?

  Although the South Yorkshire partners have embraced the transport shared priorities that form the basis of the Government's Transport Strategy, and have written their second LTP with a specific focus on how we can address the challenges we face in each, the bigger issue in South Yorkshire at present is how economic transformation can be secured and how transport investment can harness the potential of existing or future opportunities. In this respect therefore the limited funding potential of the LTP and its relatively short term time horizon means that it is viewed here more as a local interpretation of national policy priorities than a means by which the partners can express their particular and ambitious vision for transport.

  Apart from accessibility planning, the focus on shared priorities means that the LTP must address how we deal with the negative impacts of transport, rather than adopting a more positive planning process that incentivises economic and social regeneration and growth.

How effective is the Local Transport Plan performance management regime? Do the Annual Progress Reports give the necessary transparency and rigour in assessing performance?

  The annual reporting process has had the effect of compounding initial errors made when we set unrealistically high targets. It fails to acknowledge upward trends. The Partners in South Yorkshire could have reset their LTP targets but decided to stick with the original set in order to build a clearer picture of progress over the Plan period. The effect of this decision however was the subsequent annual criticism of non-achievement, even where targets were only just missed.

  In setting LTP2 targets at a more realistic level we have learned the lessons of LTP1 of not being overly ambitious and setting ourselves up to fail. We wait with interest to learn if our LTP2 will now be assessed as not being ambitious enough.

  It is our understanding that at present the APR system will not be applied to LTP2, so we await further guidance from the DfT on how they will expect us to report progress. In the meantime, SY has its own performance management regime in place to ensure that progress is maintained.

How successful is the balance between infrastructure projects and travel planning initiatives?

  The considerable potential of "softer" measures to deliver significant changes in people's travel behaviours is not reflected in the capital focus of LTP funding. Although some infrastructure improvements can support travel planning initiatives in some locations, the majority of travel planning activity is revenue based. With pressures on revenue budgets as intense as they are, the full potential of travel planning is difficult to realise.

CONCLUSION

  Recognition by Government that local authorities need more powers to raise resources locally would go some way to relieving some of the inefficiencies and frustrations inherent in the current LTP system. A move towards a single, unified reporting framework as part of Local Area Agreements may bring some efficiencies also in local performance management and help align DfT priorities with other policy areas. At present, the intensive annual reporting process is geared too heavily towards DfT's specific reporting requirements. A move in LTP2 to outcomes-based reporting on a bi-annual basis may bring some benefits, but the DfT guidance needs to be timely and avoid contradictions arising from different parts of the organisation giving different advice.

  More importantly for South Yorkshire, however, would be a move by DfT and other Government departments to recognise the emerging and strengthening city regional governance arrangements which will require greater freedoms and flexibility to plan and make decisions locally.

25 April 2006





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 29 October 2006