Select Committee on Transport Minutes of Evidence


Memorandum submitted by the Greater Manchester Passenger Transport Executive

INTRODUCTION

  This submission by GMPTE is made in response to the invitation from the Transport Committee to submit written evidence on issues relating to local transport funding.

  A separate written submission is being made on behalf of the 10 district councils of Greater Manchester and GMPTA by the Association of Greater Manchester Authorities (AGMA) on the whole range of Local Transport Planning and Funding issues to be considered at the inquiry. In addition a submission by PTEG is being made behalf of all six English PTEs, Transport for London and Strathclyde Partnership for Transport which again deals with all the issues raised for consideration in the Inquiry.

  This specific GMPTE submission is complementary to the ones from AGMA and PTEG and will focus on the following issue:

How efficient is the bidding and scheme preparation stage? What could be done to avoid local authorities wasting significant resources on preparing and designing transport schemes that do not get approval?

  The evidence will include current examples of schemes being promoted by GMPTE.

EVIDENCE

  Since the introduction of the Local Transport Plan (LTP) process under the 1998 Transport White Paper and 2000 Transport Act the funding mechanism for local transport capital projects has worked to encourage local authorities to try and secure resources for major schemes for a number of reasons. These are listed below:

    —  The LTP funding changes which include guidance on future year indicative settlement levels is welcomed as this enables greater certainty in planning the use of those resources made available for minor works, through block allocation.

    —  This national bidding approach has encouraged local authorities to "travel hopefully" and bid for major schemes, particularly ones which represent good value for money in BCR terms, because in any one year competition around the country for nationally available DfT resources might be low or other bid schemes not represent such good value for money. Thus undertaking the expenditure necessary to submit an Annex E, required to enable a scheme to be considered for first stage progression, has often been considered a risk worth taking. Typically GMPTE would need to spend £150,000 to £200,000 in the development of a bus station/interchange scheme to the level of detail necessary for an Annex E submission (eg Rochdale Interchange Annex E—July 2004).

    —  The recent move towards seeking views from regions on their transport priorities within a given level of Regional Funding Allocation has been helpful in that it has necessitated Regional Assemblies to only bring forward a recommended list of schemes that can be afforded within the region.

  However, despite the welcome strategic intentions of the LTP process discussed above, the bidding process for major schemes has continued to be an annual lottery as local authorities bid to secure resources nationally from DfT. Moreover, the lack of clarity regarding the extent to which the advice of the region will be a determining factor in which schemes the DfT will be recommending for Ministerial approval continues to encourage local authorities to submit additional major scheme bids to those being recommended by the region.

  GMPTE also has concerns regarding the level of expenditure needed to progress major scheme bids through to full approval status. These relate to both the degree of certainty that full approval can be expected for schemes that secure provisional approval, or as it is now known, programme entry status and the level of costs the promoting authority must incur in order to develop schemes through to full approval stage. In more detail the issues are:

    —  In our view once a scheme has achieved programme entry status there should be a presumption it will be funded unless cost escalation causes this to be reviewed. Currently securing programme entry status is seen as just the first hurdle to be overcome. The recent DfT consultation document on "Changes to the Policy on Funding Major Projects" is seen as helpful here in that it starts to address concerns regarding the process of scheme development once programme entry status has been achieved.

    —  From our experience there is still a sense of the promoting authority being on a "sales pitch" when discussing schemes with the DfT until full approval status is awarded. GMPTE feels it would be advantageous to develop a greater sense of partnership working and shared ownership between promoting authorities and DfT once major bid schemes have secured programme entry status. In this way it is likely that a culture of "no surprises" will emerge to the benefit of both the DfT and the promoting authority. One option might be for DfT to have individual officers nominated as project sponsors for specific schemes. Whilst it is recognised that such a move could have staff resource implications for DfT we believe there would be efficiency benefits arising from the speedier delivery of major schemes.

    —  It is accepted that it is in both the DfT and the promoting authority's interest to secure more reliable cost estimates at programme entry stage. It is not clear whether, to achieve this greater cost certainty, DfT will require that detailed design be undertaken before conditional approval is sought. If so, such expenditure would represent both a cost to be met by the promoting authority and, in the absence of any certainty of achieving programme entry, be a significant risk to the promoting authority.

    —  By way of a local example, to undertake the detailed design for the Rochdale Interchange scheme (full scheme cost estimated at £11.5 million) to a level needed for contract documents would, in our view, involve expenditure in the order of £700,000. The alternative would be for GMPTE to limit design work to a detailed specification and then procure the scheme as a design and build contract. However, we feel that this approach would not be as advantageous for either GMPTE or DfT for two reasons. Firstly, we believe that such an approach would give us less control over all design matters, This would weaken our ability to safeguard the high quality of passenger facilities to be provided as it is likely that the appointed design and build contractor would seek to dilute such aspirations in an attempt to minimise expenditure. Secondly, it is likely that additional costs, in respect of risk, would be included by the appointed contractor for the undertaking of a design and build contract.

  Delays in progressing schemes can also occur for reasons not within the control of the promoting authority. In the example of the Leigh-Salford-Manchester busway, see below, these delays have primarily arisen from the legal powers process. The impact on the cost of the scheme has been significant and GMPTE consider that the DfT should fully recognise such cost escalations caused by inflationary effects.

    —  The Leigh—Salford—Manchester busway scheme secured provisional approval in December 2000. The scheme costs were estimated to be in the order of £26 million at 1998 prices. Provisional approval was needed before the scheme could be progressed through a Transport and Works Act powers application. At that time a 1998 price base enabled an economic appraisal to be undertaken (also valuing benefits in 1998 prices) sufficient to show the scheme represented good value for money.

    —  Following that provisional approval in December 2000 the scheme was developed in more detail for public inquiry procedures. Despite our best endeavours to simplify the powers process and hold a single public inquiry to deal with all the powers (Transport and Works Act, Road Traffic Regulation Act, Planning permissions) this approach was not accepted and separate inquiries had to be held. GMPTE submitted a Transport and Works Act application in January 2002 and a public inquiry was held in September 2002. An interim decision letter was issued by the Secretary of State in October 2003 which required some additional evidence to be submitted, this included further Great Crested Newt surveys that, given the newts were then in hibernation, could not then be undertaken until early June 2004. The additional evidence was submitted in Autumn 2004 and a decision letter from the Secretary of State granting TWA powers was issued in August 2005. An updated Annex E was submitted to the DfT in July 2004. At this stage the scheme cost had risen to £42.3 million (at 2004 prices) in part reflecting six years of construction industry price inflation but also reflecting changes in design from the July 2000 submission arising from the TWA public inquiry.

    —  The DfT have confirmed that the scheme still retains a provisional approval but for £26 million as approved in December 2000. During this time GMPTE have had to fund all development and legal costs from block allocation resources in order to progress the scheme to a stage whereby a bid for conditional funding approval could be made. To date some £4.3 million has been spent on the scheme but with no certainty that it will progress to conditional approval. However, without incurring that level of expenditure it would not have been possible for any progress to be made on the scheme.

  There is a concern that the DfT evaluation of major scheme bids has historically been too focused on the transport benefits of the scheme and places insufficient emphasis on regeneration or social inclusion agendas. This is of particular concern in major metropolitan areas, which are the economic engines charged with leading the regeneration of our regions. It is our contention that a lack of recognition of the impact that major infrastructure investment can have in this regard could risk jeopardising the sustainability of the economic renaissance that the Greater Manchester city region has achieved over recent years. It is therefore, welcome that DfT has begun to address this shortcoming through the introduction of a productivity strand to the Transport Innovation Fund. However, we would assert that a similar discipline should be maintained across all major transport scheme funding streams.

    —  The linkage with regeneration is particularly important as in a number of cases transport infrastructure is seen as a catalyst to other inward investment. This can place constraints on the timing of such schemes that may not be totally within the control of the promoting authority but can be unfortunate if delays in securing the transport scheme frustrate the delivery of other regeneration initiatives. In addition the re-use and/or clearance of urban brownfield sites can add to scheme costs. Such additional costs might not be recoverable from any development gain and unless other sources of funding from, for example ERDF or SRB sources, can be utilised these additional costs would serve to reduce the overall benefit: cost ratio of the scheme. For example in the case of the proposed Rochdale Interchange scheme demolition, site clearance and other site remediation works are estimated to cost £2.3 million for which SRB support of £1.5 million is being sought.

    —  The GMPTE major scheme bid for funding Yellow School Buses is based on achieving both traditional transport benefits, through modal shift from car to bus for home to school trips thereby assisting in reducing congestion and minimising environmental damage. However, it is also intended to address wider education objectives by making journeys to and from school safer and more secure, reducing social exclusion and anti-social behaviour and delivering improved education by providing a quality service to deliver students to school ready to take full advantage of learning opportunities.

SUMMARY AND CONCLUSION

  This evidence deals with the issue regarding the efficiency in the bidding and scheme preparation stage of major schemes.

The key points it raises are:

  The Local Transport Plan funding mechanism for major schemes has encouraged promoting authorities to submit bids given that these schemes were subject to central DfT annual resource allocation and decision making. This has tended to promote a sense of major schemes being an annual national competition which you have to be part of in order to "win". There is a lack of clarity over how the Regional Funding Allocation process will change this.

  There needs to be greater certainty that once major schemes secure programme entry status then the presumption should be that those schemes progress to full funding approval unless there is a significant change of scheme attributes or cost. A greater sense of partnership and shared ownership of schemes once programme entry has been secured is proposed.

  The DfT should work with promoting authorities to reduce delays to scheme progress that arise through reasons not within the control of the promoting authority. The particular case of the delays arising from the Transport and Works Act procedures for the Leigh-Salford-Manchester busway scheme was used to illustrate this.

  Finally, concerns are raised that the DfT evaluation of major scheme bids has historically been too focused on the transport benefits of the scheme and places insufficient emphasis on regeneration or social inclusion agendas. This must be addressed if transport investment is not to become an "end" in itself, and so as to ensure that the recent regional economic growth is to be sustained.

25 April 2006





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 29 October 2006