Select Committee on Transport Minutes of Evidence


Memorandum submitted Devon County Council

SUMMARY

  1.  As a Centre of Excellence for Local Transport Delivery and Beacon Authority for Road Safety, we welcome the increased levels of Government investment in local transport funding and strongly suggest that its scope is extended to encompass revenue funding. We feel that LTPs should become part of the warp and weft of national and European transport policy rather than a separate thread.

LOCAL TRANSPORT FUNDING

Have the local transport capital settlements met what was expected and allowed delivery of the planned projects? What have been the impacts on major transport schemes, and smaller schemes? Have the full allocations been spent as planned? How have cost increases been settled?

  2.  The substantial and welcome increase in local transport capital borrowing approvals between 2001-02 and 2005-06 has enabled the implementation of a wide range of integrated transport schemes which would not have previously been affordable. The introduction of the single capital pot has given us more discretion to allocate capital funding to meet our priorities. Our comments on the separate process for funding major transport schemes are set out below.

  3.  Devon County Council has certainly spent its full local Transport Plan allocations and has also supplemented this funding from time to time from its own capital resources.

  4.  Cost increases on integrated transport block schemes have been dealt with through adjustment to the programme within each financial year. However, a significant problem was encountered with a cost increase in the major scheme which Devon had approved in Local Transport Plan 1. Delivery of this scheme was delayed, through no fault of the County Council, by a challenge in the High Court about the actions of the Department's Inspector. The delay resulted in escalation of the scheme cost beyond that which was originally approved, but the Department for Transport were unwilling to meet the full extent of this cost increase; in the end agreement was reached that the County Council would contribute a part of the increase from its own resources.

Is the formulaic funding approach the most suitable method for allocating transport investment? What has been the impact of the performance-related component?

  5.  There is a risk that the formulaic funding approach is seen to be rewarding failure, under-performance or under-achievement, with higher levels of resources being allocated to local transport authorities which are not meeting their targets. This is partly offset by the performance-related component which rewards local transport authorities, like Devon County Council, that have produced well above average LTPs and Annual Progress Reports. The indicative allocations over the five years of the LTP have helped longer-term planning.

Has the balance between revenue funding and capital funding for transport proposals been appropriate? How well have the different funding streams from the Department for Transport and the Office of the Deputy Prime Minister supported local transport projects? Are transport services successful in securing sufficient revenue funding?

  6.  The increase in capital borrowing approvals has not been matched by similar increases in revenue funding: we are capital rich and revenue poor. We would strongly press for highway maintenance, road safety and public transport revenue funding to be allocated through the LTP system. There is a particular concern that despite capital allocations for highway structural maintenance there is a growing backlog of highway repairs, both in Devon and nationally.

  7.  The separate funding streams, eg the rural bus subsidy grant, Rural Bus Challenge, school travel plan bursaries, Cycle Demonstration Towns, have usefully supplemented core LTP funding, for those authorities like Devon which have been able to mount successful bids, but these initiatives can lead to short-termism and difficult decisions have to be made when the term of the grant expires.

How efficient is the bidding and scheme preparation stage? What could be done to avoid local authorities wasting significant resources on preparing and designing transport schemes which do not get approval?

  8.  The Regional Funding Allocations process, which gives clear guidance on those schemes which are regional priorities, should help to avoid abortive expenditure for authorities in preparing major schemes which will not be funded. However, this makes it difficult for authorities to progress significant schemes over £5 million pounds which are of importance locally but are not regionally significant.

  9.  We hope that the current consultation on "Changes to the policy on funding major projects" will improve the process particularly for the reimbursement of preparatory costs.

LOCAL TRANSPORT PLANNING

Were the administrative process and timetable for delivering Local Transport Plans appropriate? How helpful was the guidance from the Department for Transport? How did the second round of Local Transport Plans learn from the first, and how could the process be further improved?

  10.  We have a productive and mutually beneficial working relationship with the Government Office for the South West which has helped the process of LTP preparation. The DfT guidance was clear and comprehensive but the subsequent amendments, re-interpretations and additions have not been helpful or advantageous. The second round of LTPs has been more focussed on meeting targets and objectives and the delivery of value for money.

How well have the Local Transport Plans delivered better access to jobs and services, improved public transport, and reduced problems of congestion, pollution and safety? To what extent has the Government's Transport Strategy fed into the second round Local Transport Plans?

  11.  The second round of LTPs has aimed to achieve the shared central/local priorities for transport. The DfT have not clearly articulated how LTPs are contributing to the modern, efficient and sustainable transport system envisaged in the "Future of Transport" White Paper.

How effective is the Local Transport Plan performance management regime? Do the Annual Progress Reports give the necessary transparency and rigour in assessing performance?

  12.  It is too early to judge the effectiveness of LTPs. The Annual Progress Reports will be replaced by the July 2006 Delivery Reports covering 2001-06 and subsequent bi-annual reporting of progress.

How successful is the balance between infrastructure projects and travel planning initiatives?

  13.  We would welcome an explicit recognition that supporting travel planning which complements investment in infrastructure is a legitimate use of local transport capital.

24 April 2006





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 18 October 2006