Select Committee on Transport Minutes of Evidence


Memorandum submitted by the Association of Greater Manchester Authorities and Greater Manchester Passenger Transport Authority

  This evidence, submitted by the Association of Greater Manchester Authorities (AGMA) and Greater Manchester Passenger Transport Authority (GMPTA), should be read in the context of the current changing environment for local transport funding. The indicative regional funding allocations (RFAs) have highlighted the limited, whilst important, role that Local Transport Plan (LTP) funds can play in delivering future transport infrastructure projects. For example, for the entire North West region, the total RFA for transport investment in 2006-07 will be £115 million. Therefore, AGMA and GMPTA have welcomed the Government's introduction of the new Transport Innovation Fund (TIF) as the main funding resource for major transport interventions, such as our planned expansion of the Greater Manchester Metrolink system.

  Following our receipt last year of TIF "pump-priming" resources from Government, we are now working with DfT officials and other key stakeholders to establish an integrated, corridor-based approach to transport planning in order to secure the deliver of our Integrated Transport Strategy through a series of corridor partnerships. The aim of the partnerships is to integrate transport planning fully with the delivery of a wider set of transport and regeneration outcomes than has historically been the case. All the key stakeholders within a corridor will be involved in agreeing each set of outcomes in return for Government agreement to the provision of TIF funding. We are also investigating new innovative funding options for local transport investment and revised governance systems to support this. It is our intention to complete this work in advance of a full TIF submission in July 2007.

LOCAL TRANSPORT FUNDING

Have the local transport capital settlements met what was expected and allowed delivery of the planned projects? What have been the impacts on major transport schemes, and smaller schemes? Have the full allocations been spent as planned? How have cost increases been settled?

  Funding during the later years of our first LTP exceded indicative amounts given at the start of the process. This is welcome, however, further funding is essential to enable Greater Manchester to address its transport problems properly.

  There were no indicative amounts for major schemes, so settlement amounts cannot be compared with them. Moreover, the tendency to submit bids based on the most optimistic delivery timescales means that it is not instructive to compare bids with settlements.

  In total, minor scheme expenditure levels have been similar to those planned. We have greater concern with regard to Government treatment of major scheme cost increases, which has varied from scheme to scheme. For example, increases on the Manchester and Salford Inner Relief Route were accepted, but the cost increases on the Metrolink expansion project were not.

Is the formulaic funding approach the most suitable method for allocating transport investment? What has been the impact of the performance-related component?

  The formulaic approach to funding is a welcome move away from the previous bidding approach, which could sometimes work against cross-boundary cooperation with competing neighbouring LTPs. However, as with all formulaic systems the devil is in the detail—which LTPs benefit or lose out depends upon the weightings applied to the different components of the formula. In terms of the allocations received by Greater Manchester, the allocation process has been fair, and produced a reasonable result.

  However, the Greater Manchester authorities remain concerned about the extent to which the DfT evaluation of major scheme bids reflects the wider regeneration or social inclusion agendas. There is a potential mismatch here with Government policy aspirations for regional economic regeneration and the renaissance of our major city regions. Appraisal criteria need to include a suitable assessment of, and weighting towards, a scheme's regeneration impact if we are not to risk jeopardising the sustainability of recent regional economic growth. DfT's consideration of this under the Transport Innovation Fund's productivity strand is welcome. We would urge a similar approach be maintained across all major transport funding mechanisms.

  The performance related component resulted in GM authorities receiving a 5% reduction in funding in the December 2005 settlement, despite achieving a score of 78 out of 100.  The performance related approach as adopted only allows for a small number of authorities to be excellent and hence rewarded. This is because all of the funding was included in the indicative allocations for local authorities; therefore in order to reward some authorities, others will have to lose money to make it available. Thus the thresholds have to move to enable a few authorities to be rewarded. This is counter-productive as it can lead to authorities improving performance yet being penalised, which was the case in Greater Manchester. The system should be trying to encourage all local authorities to become excellent.

Do local authorities have adequate powers to raise resources to fund local transport infrastructure? What other powers could be useful?

  Local authorities outside London are hindered by their inability to raise resources for local public transport schemes through innovative means. This is in contrast to the situation in London where the Mayor, with a much greater range of powers, has been able to provide a far more integrated system, which in turn has seen continued increases in public transport patronage.

  We would encourage Government to develop new mechanisms that will enable local authorities to raise resources to support investment in local transport schemes, which they have identified as being essential for the sustainable economic growth of their areas. The Greater Manchester authorities have engaged enthusiastically with the current Lyons Inquiry into Local Government to assist in the consideration of options for identifying new funding opportunities for local infrastructure developments. In addition, we have put forward a case for the adoption of prudential borrowing arrangements to support our Metrolink expansion plans, which is being developed further through our ongoing discussions with DfT.

Has the balance between revenue funding and capital funding for transport proposals been appropriate? How well have the different funding streams from the Department for Transport and the Office of the Deputy Prime Minister supported local transport projects? Are transport services successful in securing sufficient revenue funding?

  Census 2001 shows that in Greater Manchester, some 33% of households do not have direct access to car. In a number of circumstances, the most effective transport solution to the social exclusion that can result from this requires ongoing revenue support for a local bus service rather than a one-off capital expenditure. Local authorities' and PTAs' limited access to revenue resources, coupled with the inability to utilise LTP resources for revenue activities, means that it is not always possible to deliver integrated transport for those who need it most.

  The deregulated bus networks outside London have resulted in bus companies focussing on the profitable, often main arterial, daytime routes to the detriment of neighbourhood routes and evening services that are essential in social inclusion terms. The costs of providing subsidised services in such areas has increased significantly over the years as the commercial network has reduced in scale. Limited PTA budgets mean that the level of coverage, particularly in the evenings and weekends, has reduced over the years. This has not only contributed to social exclusion, but has also been accompanied by reduced bus patronage and increased car travel, and hence increased traffic congestion. PTA budgets are limited to the resources that constituent District Councils can afford to provide when considering against other services, which are often afforded a higher priority. This can be exacerbated by the precept system, which has been retained for police and fire/rescue services, but has not been extended to PTAs since 1990.

  Therefore, the balance between capital and revenue remains a significant problem in a number of areas. With the current system, it is much easier to build new infrastructure than maintain it; it is also difficult to fund complementary measures to infrastructure (for example provision of travel planning advice, bus services, and marketing). Implementation of local transport schemes has meant a growing burden of revenue demands which are not properly linked in the financial system—for example, maintenance and renewal of white lining, signing and surface colouring on Quality Bus Corridor and road safety schemes.

How efficient is the bidding and scheme preparation stage? What could be done to avoid local authorities wasting significant resources on preparing and designing transport schemes which do not get approval?

  During the early stages of LTP1, when more money was available, the bidding and preparation stage yielded good returns for LTP authorities; however, since resources for major schemes have become tighter, LTP authorities are having to gamble on designing schemes with limited prospect of them being funded. Whilst the Regional Funding Allocation exercise has been helpful in providing an identified level of likely resources available to a region, we remain concerned that the NWRA is not able to effectively reflect the economic importance of the Greater Manchester and Merseyside city regions in coming up with a prioritised list of interventions. We also note that this process carries no guarantee of funding, since Government still issues the final approvals. Moreover, we would suggest that there is a spatial mis-match between local transport planning at the sub-regional level and spending prioritisation at the regional level. We believe that the devolution of decision-making arrangements to city regions, in parallel with the funding arrangements discussed earlier in this evidence, would make for a more effective, outcomes-driven process.

  It would be difficult to stop local authorities continuing to prepare and design major transport schemes, as the LTP is only one of a number of potential funding sources and it is prudent to have a number of schemes ready in preparation should additional funding become available. However, we would encourage DfT to ensure greater certainty for major schemes with "programme entry" status so that the further expense incurred in full scheme development is not wasted.

LOCAL TRANSPORT PLANNING

Were the administrative process and timetable for delivering Local Transport Plans appropriate? How helpful was the guidance from the Department for Transport? How did the second round of Local Transport Plans learn from the first, and how could the process be further improved?

  The process could be made much easier for local authorities by central government providing timely advice. The provision of advice three months or less prior to submission has been problematic, as by this stage documents are already into approval processes and hence have limited scope for change. Guidance could also usefully clarify how documents can be made shorter, yet still provide all the information required by DfT. Despite this, guidance has evolved to give a much clearer indication of how—in theory at least—the Plan will actually be scored.

  One weakness in the LTP process is that there are a number of indicators which DfT set as mandatory and against which the LTP will be assessed and resources allocated, yet over which the LTP has very limited influence. For example bus patronage is affected by the actions of the private bus companies (such as fare setting and punctuality) far more than via the LTP. Indeed, over the lifetime of LTP1, it has been noticeable that Government has moved away from qualitative assessments to a much greater concentration of targets, in the apparent belief that LTPs can deliver them. As noted above, this is not always the case.

  Hence, target setting can pose a significant challenge in achieving an appropriate balance between ambition and realism. This is increasingly difficult given that authorities' funding allocations are linked both to the extent to which they have shown ambition for the future and to performance against previous years' targets. We do not believe that, as yet, DfT guidance provides enough assistance and clarity in this regard.

  The system still remains a very prescriptive approach and differs substantially from other disciplines where central government sets broad policy and direction and then leaves local government to determine the best way of delivering national policy. For example in spatial planning, government issues a series of planning statements of national policy and then leaves it to the regional and local levels to develop the detail to reflect local circumstances and need, whilst still retaining the power to call in plans that are contrary to national policy. DfT tends to adopt a micro-management approach to LTPs and major schemes requiring ever increasing amounts of detail to be provided. The latest guidance on major schemes, for example, states that:

    —  In order to obtain Full Approval authorities will need to provide a further update on the five aspects of their original bid, including a revised scheme appraisal. Authorities are asked to provide full details of the selected bidder's offer together with any conditions that apply (including the firm and final offer if post tender negotiations have taken place). In certain cases the Department may additionally request a copy of the selected supplier's bid document, details of other bids received, or the authority's tender evaluation documentation. As part of the delivery aspect, an updated risk register and project plan with milestones should be provided. The Department will require details of the evaluation and monitoring proposed by the authority at this stage if not before. Full Approval will be given when the Department is satisfied:

    —  that the costs of the scheme are reasonably secured and that the authority has taken adequate steps to protect itself from the risk of increased costs;

    —  that the balance of risks and liabilities is satisfactory, is clearly understood and offers adequate protection for the public sector against potential increases in costs; and

    —  that adequate contract management arrangements are in place to ensure delivery to timetable and budget, including the necessary resource for contract management within the authority.

    —  The Department states that it will make every effort to complete its consideration of bids for full approval before the expiry of tender prices but cannot guarantee it.

  An approach similar to that adopted by ODPM on planning would help to improve the process.

How well have the Local Transport Plans delivered better access to jobs and services, improved public transport, and reduced problems of congestion, pollution and safety? To what extent has the Government's Transport Strategy fed into the second round Local Transport Plans?

  Whilst several of the above factors have not been explicitly part of the LTP1 monitoring regime, a number of proxy measures can be referred to, which demonstrate that the increased funding under the LTP process has contributed to improvement. These factors are a focus for LTP2 and our economic and transport models indicate a positive effect of LTP2.  By way of an example, with regard to congestion, our LTP1 strategy to enhance access to major town and city centres has resulted in less congestion for journeys to Greater Manchester's Regional Centre than there would have been without the investment we have put into public transport. In contrast, there has been growth on the local motorway system, over which we have no effective control and where there have been limited policy interventions.

How effective is the Local Transport Plan performance management regime? Do the Annual Progress Reports give the necessary transparency and rigour in assessing performance?

  To date, the LTP performance management regime has not been as strong as it could be as there was no direct linkage between performance and the financial settlement. In addition, the "core" indicators have not always reflected the breadth of Greater Manchester's top priorities. However, the December 2005 settlement did make that explicit linkage which has focussed attention on delivery of the targets and the revised suite of targets does come closer to reflecting local priorities—although a greater focus on regeneration linkages is needed to complete this challenge.

  The lack of clarity over the scale of ambition needed for targets has been referred to earlier in this evidence. A good example is that of the Greater Manchester bus patronage target, which was revised upward on DfT advice after encouraging early progress, but then performance fell back, leading to a missed target. It would have been preferable for the target to have been left unchanged to reflect the longer-term nature of such performance trends. Future Delivery Reports need to ensure that authorities strengthen their internal links between PI reporting and subsequent actions by providing detailed guidance on scoring methodologies in advance of the assessment process.

  Greater Manchester feels that there is insufficient acknowledgement of the complexities that Metropolitan areas face in producing LTPs and APRs, which could be said to put them at a disadvantage compared with a single unitary authority. It simply is not possible to provide the detail of analysis for each part of Greater Manchester within an LTP in the way that it is for a unitary authority with between 100,000 and 200,000 inhabitants. The transparency of the impacts of transport investment is therefore compromised. There is also a failure by Government to acknowledge the time lag between implementation and outcomes.

  As with all performance indicators, there is an ultimate distortion of investment from the original intentions, simply to achieve a specified target. For example, improvement of BV165 (puffin crossings replacing pelicans) will divert funds away from providing new crossings in locations of need.

How successful is the balance between infrastructure projects and travel planning initiatives?

  In-keeping with Government policy, the Greater Manchester authorities are committed to employing softer, travel change measures alongside infrastructure projects to encourage modal shift. Indeed, as has been referred to above, many infrastructure projects require associated promotional activity to maximise their impacts. During LTP1, non-LTP funding money was made specifically available (via a bidding process) for Workplace Travel Plans and School Travel Plan Bursary posts (and more recently School Travel Advisers). However no other LTP funds have been made specifically available for any of the other "Smarter Choices" measures.

  Over the duration of LTP1, confusion has remained over the ability of authorities to utilise LTP resources for mainstream "Smarter Choices" measures. This matter has not been clarified by LTP2 guidance. We believe that it is essential for authorities to be able to call upon LTP resources to support travel-planning initiatives, so as to support infrastructure investment and to properly reflect the prominence of this activity in Government policy. Therefore, we would recommend DfT to clarify the guidance on the extent to which LTP resources can be utilised for "Smarter Choices" initiatives over the lifetime of LTP2.

April 2006





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 18 October 2006