Select Committee on Transport Written Evidence


APPENDIX 1

Memorandum submitted by Tube Lines

1.  ABOUT TUBE LINES

  1.1.  Tube Lines is responsible for maintaining and upgrading the infrastructure on the Jubilee, Northern and Piccadilly Lines, under a 30 year partnership with London Underground, which commenced on 31 December 2002.

  1.2.  Tube Lines is responsible for 320 km of track, 251 trains, 100 stations, 2,395 bridges and structures, 71 lifts, 227 escalators and 2 passenger travellators.

2.  JUBILEE LINE

  2.1.  The Jubilee Line is one of the 10 lines which will serve the main Olympic sites at Stratford. The Line will also link Stratford with other venues at the Dome, Regent's Park, Lord's and elsewhere. Tube Lines is undertaking a major upgrade of the Jubilee Line, which will be completed well in advance of 2012.

  2.2.  The first part of the upgrade will be completed over Christmas 2005, when an extra carriage will be added to every Jubilee Line train. In addition, four brand new trains will be added to the Line in early 2006.

  2.3.  The second part of the upgrade is the installation of a brand new signalling system. This is due for introduction in 2009, and work is progressing ahead of schedule.

  2.4.  The extra carriages and trains and the signalling upgrade will provide over 40% extra capacity on the Line and will enable over 30 trains per hour to run, up from 24 at present. Average journey times will be reduced by about 18%.

  2.5.  These upgrades are contained within the PPP contract and would have been completed even if the Olympic bid had been unsuccessful. Funding has been in place since Tube Lines' inception and the completion of the project does not require the diversion of funds from other sources.

3.  NORTHERN LINE

  3.1.  The Northern Line is an important transport artery to South London and certain parts of North London. Spectators will be able to use the Northern Line to travel from these areas and interchange to one of the lines directly serving the Olympic sites.

  3.2.  Tube Lines is undertaking a major upgrade of the Northern Line, again in advance of 2012. The signalling system will be replaced to provide a 30% increase in capacity and allow over 25 trains per hour to run on each branch in central London. Average journey times will be reduced by about 18%.

  3.3.  This upgrade is scheduled for completion in 2011 and work is currently ahead of schedule.

4.  CONCLUSION4.1.  Tube Lines is on track to deliver on its obligations to upgrade the Jubilee and Northern Lines in 2009 and 2011 respectively, which will provide an important boost to transport to and from the Olympic Games.

  4.2.  These upgrades would have been delivered whether or not the Bid was successful: therefore the awarding of the Games to London has no implication in terms of timing or demand for additional funding.

4 August 2005





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 16 March 2006