Select Committee on Transport Written Evidence


APPENDIX 23

Memorandum submitted by the Corporation of London, City Remembrancer's Office

INTRODUCTION

  1.  The Corporation of London supports the Olympic movement and welcomes the opportunity to work with the Olympic Delivery Authority (ODA) to ensure that the 2012 Olympics are a success. The Games will provide the opportunity to bring much needed regeneration to east London and improve London's status as a world class City which people will want to visit and where they will want to do business. The Corporation is particularly concerned to ensure that the Games fulfil their potential to act as a catalyst and deliver legacy improvements, especially in east London. In order to ensure the success of the Games, however, and to maximise the legacy benefits, it is important that the Olympic Transport Plan does not adopt a narrow geographical or time perspective but considers the Games in the context of London's wider transport requirements. The paragraphs below set out the Corporation's views on the issues it considers should be addressed in planning the transport infrastructure for the Games.

THE OLYMPIC TRANSPORT PLAN

  2.  The Olympic Transport Plan (OTP) should cover a much broader time period than simply the duration of the Games because, in addition to demand generated by the events, the expanded transport system should be designed to sustain the expected extra demands resulting from London's natural growth. It is important therefore that the final OTP reflects the projected future needs of the central and eastern parts of London. The OTP will need to establish both what work is required to fulfil the operational needs of the Olympics and also how this work will contribute to planning for London's growth as set out in the Mayor of London's London Plan.

  3.  The investment that is injected into London to promote the Games should not, however, be at the expense of the existing planned projects and capital schemes within the Mayor's Transport Plan. Where possible, any removal of capacity from the existing transport network should be avoided. This may be mooted under the guise of preparation for the Games but would result in severe inconvenience to London commuters who will still need to use the network in the lead in period before, and during the Games. Any unnecessary removal of capacity prior to the Games will impact upon London's ability to function properly and accommodate the projected growth in its population.

  4.  Public transport provision is vital for the City of London to operate. With a work force of over 310,000 people, and 86% of them arriving by public transport[2]2, a reliable transport network feeding the central business zone is fundamental. Consequently, predictions of employment growth need to be taken into consideration when planning the construction of the Olympic sites and transport network. In addition, the economy of the country relies heavily on financial and business services and cannot risk the existing transport network being inoperable for any extended period due to construction works. A properly scheduled programme of improvement works that minimises disruption should therefore be an essential component of the OTP.

CROSSRAIL

  5.  The Corporation believes that the large infrastructure schemes, such as Crossrail and Thameslink 2000 (discussed in more detail below), which have been developed over many years and are awaiting the allocation of funding, should not be delayed or deferred as a result of the Olympics. These schemes still need to be progressed urgently as they provide additional capacity in key areas of London that are unlikely to benefit directly from the Games. The City and central London as a whole need the benefits of a properly constructed Crossrail scheme to meet demand generated by the predicted growth in employment. The GLA have reported a projected employment figure in the City of London in 2016 of 397,000 people[3]3. This is an approximate 22% increase in the number of employees working in the City. At present the current workforce predominantly relies on public transport to access the City. The Corporation would not expect this travel demand pattern to change unless public transport capacity did not grow to meet the needs of the consumer. A consequence of such a situation would be the suppression of economic activity and job growth.

  6.  Securing funding for these schemes at an early stage would demonstrate commitment to improving the current rail transport network. Without early delivery of these much needed schemes to provide significant new capacity to meet the economic needs of London and its commuter belt, there is a risk of business being lost to overseas competitors with lower office rental costs and cheaper, less crowded transport services. London's competitive advantage must be upheld.

  7.  The private sector is also keen to see the concept of Crossrail progressed and has agreed to the principle of considering a precept on the business rates to help fund the scheme. It cannot also be expected to have a similar large financial role in underwriting the transport plan for the Olympics. The Olympics are a national event and benefits from the Games will not be confined to London. The benefits and costs should be properly shared across the whole of the UK.

  8.  The Corporation understands no significant engineering resource or significant logistical conflict in taking Crossrail forward for its currently planned completion in 2013. The current programme of works suggests that the major tunnelling activities and allied temporary rail sidings for spoil removal at the eastern portal near Stratford will have been completed in advance of the pre-Olympic construction projects. Consequently, only fitting-out and commissioning works for the railway, which will mainly be underground within central London, would coincide with the Olympics work. Typically projects of the scale of Crossrail would be undertaken by consortia of international construction firms drawing their skilled staff and equipment from a very broad base. In terms of construction traffic the Environmental Statement for Crossrail envisages, at peak times, a daily volume of around 200 lorry movements at two City locations. This level of activity can reasonably be absorbed without causing issues on the City's street network. Commercial building redevelopment has always been intense within the City—the most intense being 700,000m2 starting in 1988 and 327,000 m2 under construction now—which often create well in excess of 1,000 lorries per day. The level of construction lorry traffic is comparable to that Crossrail will generate and, using careful management has not proved to be a material issue in terms of traffic congestion. Further, the Games could provide an opportunity for Crossrail to be built with a new focus, with the potential for a partial phased opening of the line, for example to the east of Liverpool Street, which could significantly aid the OTP.

THAMESLINK 2000

  9.  Thameslink 2000 would improve the only north—south mainline rail line across London by enhancing services that run from Bedford to Brighton directly through central London and so increasing capacity across the network. As part of the Channel Tunnel Rail Link (CTRL) works at Kings Cross, Thameslink services were suspended through the central core from September 2004 to allow the construction of a new box under the CTRL site at St Pancras to house a new improved Thameslink Midland Road station. A lack of funding has resulted in the new station lying incomplete and dormant while Thameslink services continue to use the old station at Kings Cross Thameslink. The Corporation believes that fitting out of the Thameslink station box at St Pancras is essential for the success of the OTP. It is likely that Thameslink services will be in great demand by visitors to the Capital throughout the Games as the service links both Gatwick and Luton airports to central London. If the new station were to become operational, there would be a much improved interchange between Thameslink services and the planned high speed Javelin service to Stratford. It would also provide relief to the congested Northern line by aiding the dispersal of international rail passengers both north and south of Kings Cross without the forced need to use the underground system.

CHANNEL TUNNEL RAIL LINK

  10.  The Corporation is keen to ensure normal surface links for international travel continue to function fully and propose that Waterloo International is reopened during the Olympic period so that "non Olympic" international Eurostar passengers can be diverted away from the busy Kings Cross area thus reducing the demand for non-Games related onwards travel from that location.

UNDERGROUND IMPROVEMENTS

  11.  The Corporation would prefer not to have, extended periods of closures on the underground network, as has previously been suggested, in order for the Public Private Partnership (PPP) infrastructure works to be completed unless these become absolutely vital to meet the 2012 deadlines. The current timetable allows for this work to be done without the need for extended closures, providing that there is no slippage in the programme and the contractors apply adequate resources. Metronet's programme for station upgrades has already slipped which suggests that the PPP works need to be managed in a more robust manner so that the infrastructure and rolling stock upgrades are completed to meet the Olympic timescale.

  12.  The Corporation would not advocate any changes to the existing PPP arrangements. In the City's experience, previous closures of both the East London line and Northern line for extended time periods to enable works to be carried out did not deliver results, leaving passengers plagued by faults and requiring additional closures for further remedial work. The cause of this appears to have been failures in the oversight and management of these works.

  13.  The Corporation strongly supports the focus of 2012 for completion of the London Underground capacity enhancements and refurbishment work. The DLR enhancement programme and the East London line extension are also welcomed. These projects need to continue as previously planned and retain the existing allocated funding. Each transport scheme with current funding is supported by a justified economic case. If the decision is taken to transfer these funds to Olympics projects, there should be a guarantee that the funding will be replaced within in a specific time period. Furthermore, the boroughs must be fully consulted on any such proposals.

OTHER PUBLIC TRANSPORT SCHEMES

  14.  Other transport schemes that the Corporation believes could usefully be included in the Olympic Transport Plan include:-

    —  Phase 2 of the East London line extensions. This would complete the scheme and provide connections to other Olympic venues;

    —  Continuation of the DLR enhancement programme;

    —  National Rail station upgrades (especially around the Olympic venues to cater for accessibility issues); and

    —  8 tracking of the bottleneck into/out of Liverpool Street station which would provide greater capacity. Currently the tracks on the approach to the Liverpool Street station narrow to 6 and cause a bottleneck. There is an opportunity to place an additional 2 lines in from Bethnal Green which would relieve the strain and increase the operational capacity at Liverpool Street.

  Each of the above schemes would enhance Olympic services by ensuring greater resilience and improvements to the current public transport network. This would contribute to a valuable legacy, encourage further regeneration and provide some of the necessary infrastructure for the expansion of London to the east.

OLYMPIC ROAD NETWORK

  15.  Central London's key roads are currently running close to operational capacity during weekday peak periods. The proper allocation of this road space, therefore, involves the balancing of a number of issues and the ODA's proposed powers to remove road space for exclusive Olympic usage will need full agreement from stakeholders. It is vital the Corporation is consulted at an early stage before the creation of the Olympic Road Network (ORN) as it will have "traffic transfer" effects on the rest of the City's roads and on the ability to maintain frontage servicing. Changes will have to be communicated to and agreed with the businesses along the route so that their needs can be met without impairing the functioning of the Games. The impact of the operational hours of the ORN also needs to be discussed with the affected boroughs at an early stage in order to allow boroughs sufficient time to make contingency plans for general traffic. It will be important that there is an early decision as to whether the central London congestion charge will operate during the Games, taking into account the effect this will have on the ORN and the roads outside the zone.

FREIGHT

  16.  The Corporation believes that the planned movement of freight during the Olympic period should be taken into consideration within the OTP. Freight supply to London is important to the UK's economy and therefore should not be compromised during the Games. A robust plan, especially for lines such as the North London line which will be heavily used during the Games, is essential.

COACH PARKING

  17.  There is a need to identify suitable on and off street parking facilities for all the additional coaches and buses that will be used to facilitate the Games. Garaging and coach parking facilities in London are already extremely limited. The OTP should therefore tackle this issue at an early opportunity. Assuming an increase in tourism after the Games, as has been shown in other Olympic cities, retention of some facilities is likely to be welcomed by the coach tourism industry but it will need to form part of a wider London policy towards coach provision.

TOURISM

  18.  The main focus of the OTP appears to be improving services to Stratford and linking the Olympic site to the existing transport corridors. The plan should, however, also consider how London's transport system will cope with the expected large number of visitors who may also wish to visit restaurants, entertainment and tourist attractions elsewhere during their visit to London. The Cross River Partnership, in collaboration with TfL, has developed a tram scheme for Central London, called the Cross River Tram, which links Kings Cross to Waterloo where the service divides to serve Peckham and Brixton. This scheme would greatly assist the movement of people across Central London and would aid with the expected post Games increase in tourism. The scheme would also provide transport access from more deprived areas to central London for job opportunities. The continued development of the scheme should not be delayed because of funds being transferred to the Olympics and it would be regrettable if funding for implementation post Games was not identified for this beneficial scheme. The Corporation is also in the process of considering the feasibility of an extension to the proposed Cross River Tram which would connect Battersea to the City via the Elephant and Castle and then travel on into Hackney. The initial modelling work for the extension is encouraging.

HOME WORKING

  19.  One aspect the ODA may wish to explore in the OTP is the possibility of seeking a reduction in the impact of normal weekday business activities to help relieve pressure on the network during crucial periods of the Games. The Corporation will encourage City businesses to work with the ODA to find ways of achieving this. In the Olympic bid document it states that "travel demand is consistently down as much as 20%" in August[4]4 and it is suggested that would release capacity on the network to be used by visitors to the Games. This spare capacity may not arise, however, if businesses continue to operate at their full capacity during the Games and London workers decide that they will remain in London to attend the Olympics rather than taking their usual holidays at this time. In addition, our on-going measurements of road traffic in the City have shown that in August, typically, the levels are down only 2% from the yearly average.

AIR QUALITY

  20.  The OTP should include a section on London's air quality. It seems that the underlying thinking in the Olympic bid was to move the majority of competitors by road transport, hence the need for the ORN. A statement as to how emissions are to be controlled in respect of the increased use of buses, coaches and taxis for both competitors and spectators, especially in central London, needs to be set out at an early stage. Poor air quality during the Games could prove embarrassing to London, particularly if this was thought to affect athletes' performance.

SECURITY

  21.  Given the increased global terrorist threat and high profile nature of the Games security is an issue that needs to be explored fully with the Corporation, boroughs and the Metropolitan and City police at an early stage of the planning process. Liaison with transport providers should form part of the security plan considering the impact on public order and traveller safety of the large numbers of people arriving at and departing from the Olympic sites during events. The Corporation recognises that there are many factors that determine the timetable of events, however one potential solution would be to set the phasing of the starting and finishing times so as not to overcrowd the network or the Capital's streets.

CONCLUSIONS

  22.  The Corporation supports the Olympics and believes it is a great honour for London to host the Games. The Corporation looks forward to working with the Olympic Delivery Authority to progress the projects and works needed to host the Games. In order to ensure that the Games are a complete success for spectators and competitors alike the Olympic Delivery Authority will need to work closely with the London boroughs and the Corporation on issues of transport, security and construction.

  23.  The Olympic Games create an inflexible deadline for construction, so it is important that bureaucracy is streamlined to ensure that all of the projects are completed on time and to budget. It is also important that other transport improvement projects in London, which may not be directly associated with the Games, continue to be progressed in order to support the predicted population and employment growth.

  24.  The Corporation does not believe it would be appropriate to transfer funding from those London transport projects which are not classed as essential for the Olympics. Schemes which have yet to secure funding and powers, such as Crossrail and Thameslink 2000, should continue to be progressed, as London is relying on these large schemes to relieve existing overcrowding and provide additional capacity on the network. The Corporation believes it is vital that the OTP considers the legacy issue and provides London with a world class transport system able to sustain the projected growth of our world class city.

September 2005






2   2001 Census. Back

3   GLA Economics-Current Issue Note 4, May 2005. Back

4   4Olympic Bid Volume 3, Theme 14, page 99. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 16 March 2006