Select Committee on Transport Written Evidence


APPENDIX 31

Memorandum submitted by the East London Line Group

INTRODUCTION

  This memorandum sets out the East London Line Group's assessment of the relationship between the planned extensions to the East London Line, and the 2012 Olympic Games. We respond to a number of the Transport Committee's questions of 27 July 2005 (see summary below).

IN SUMMARY:

1.   Will the Government's Spending Agreement with the Mayor provide adequate funding to deliver excellent transport for London's 2012 Olympic Games?

  Although the Government's Spending Agreement with the Mayor has allowed progress to be made on the much-needed Phase 1 extension of the East London Line, which will be completed in time for the Games, it did not provide a commitment for Phase 2 of the extensions to be taken forward. Phase 2 will provide a considerable transport capacity increase to the East London area, and could be completed in time for the Olympics if given an early go-ahead. Canonbury will provide a direct interchange between the extended ELL and the North London Line to the Olympic Park. Those arriving at Clapham Junction would be offered another way of accessing the Olympic sites around London and the connection at Highbury would strengthen the link with the main underground system. Without Phase 2 London's potential to deliver "excellent" transport for the Games is impaired.

  We urge the Committee to recommend that the Government and TfL give financial authorisation to Phase 2 of the East London Extensions at the earliest opportunity. Only with this timely commitment will Olympics spectators traveling from South London to the East London venues be able to gain the maximum benefit in improved accessibility brought about by the ELL project.

2.   How will the transport projects needed for the Games fit into an integrated and long term transport plan for London?

  The completion of both phases of the East London Line Extension Project will:

    —  sizeably reduce congestion on the existing rail network, especially on journeys to London Bridge and the Northern Line, and to Waterloo, Victoria and the Thameslink stations;

    —  promote orbital rail services between north, east and south London reducing the need to interchange and thus relieving congestion at the terminal stations in central London;

    —  and, improve accessibility by public transport to key areas that are poorly served, including parts of Docklands, Hackney, Lambeth, Lewisham and Southwark.

  Only on completion of Phase 2 of the East London Line extensions will the full benefits of the project be fully brought to life.

3.   Will the transport legacy be appropriate to the needs of east London in the next two to three decades?

  The full completion of the East London Line Project (phases 1 and 2) will be a catalyst for £10 billion worth of regeneration. The scheme represents a prime example of integrated transport, providing a local, commuter and cross-London service linking with the Underground, main line railways, Docklands Light Rail, Croydon Tramlink and buses. Following completion of Phase 1 and 2 journey times from north and south London to the City, Docklands and Central London will be significantly reduced. Linking areas north and south of the river with transport services into the City will present local residents with new opportunities for employment and assist greatly with regeneration efforts. The route of the northern extension will bring more people who live and work in north-east London within easy reach of the Underground network. The proposed line passes through Hackney, one of the most densely populated boroughs in Britain, where there are currently few rail services and only one Underground station. However, in the coming decades East London will require more than just phase 1 of the East London Line extension to secure its "Olympic Legacy". The completion of Phase 2 will bequeath an orbital train service around inner London that will benefit future generation.

EAST LONDON LINE GROUP'S ASSESSMENT OF THE RELATIONSHIP BETWEEN THE PLANNED EXTENSIONS TO THE EAST LONDON LINE, AND THE 2012 OLYMPIC GAMES

The East London Line Group

  The East London Line Group is a consortium of local authorities, business, regeneration agencies and other interested parties, seeking the earliest go-ahead for the extensions.

Background to the East London Line extensions

  Extensions to the East London Line were planned during the 1990s. Powers were granted in 1997 for a northern extension from Whitechapel towards the North London Line, and in 2001 for extensions south and south west onto the South London national rail network. The project's main promoter is now Transport for London.

  The Government approved Transport for London's (TfL's) business plan for the extensions in 2003. This included services north to Dalston Junction and Highbury & Islington, south to New Cross, Crystal Palace, West Croydon, and south west to Peckham and Clapham Junction. The project was approved because of transport and accessibility benefits to an arc of deprived boroughs in inner London, and because of the project's benefits for major regeneration schemes worth up to £10 billion of investment. A fuller statement on benefits is attached as Annex A.

  Funding for a first phase of the extensions was approved as part of the Government's 5 Year Spending Agreement with the Mayor of London in July 2004. This included work on all the physical extensions to comply with the powers granted, and approval for services to Dalston Junction, Crystal Palace and West Croydon. It excluded final completion of the south west link to Peckham and Clapham Junction, and services to Highbury & Islington.

  At the time, the Mayor of London announced: "It's excellent news that the Government has accepted my proposal that TfL should take over construction of the urgently needed East London Line extension and agreed the borrowing approval we need. The first phase of this project is a big boost for everyone in east and south London who have campaigned for this vital new tube line. It also shows the Government's and my total commitment to London's Olympic bid." (Mayor's press statement 20 July 2004)

Transport demand with the 2012 Olympic Games

  In general, the level of funding directed to TfL transport improvements is intended to provide assurance of adequate capacity plus a margin, during the busiest period of the Olympic Games. This comprises new initiatives, plus projects which were already in the pipeline to improve London's transport.

  TfL's underlying proposition is that travel demand in London is lower in the summer than the winter, particularly in the summer holiday period which is when the Olympic Games are scheduled. Consequently there should be capability overall for London's transport network to absorb the impact of the Games in 2012.

  TfL has modelled demand at the many Olympic Games sites, and planning for spectator and workforce travel is based on 100% use of public transport to access the venues. (The Olympic Family will be using dedicated car, coach and bus facilities.) Rail is forecast to be the dominant public transport mode, with 65-82% of spectator travel at selected locations—78% at the Olympic Park). 78% of spectators are forecast to travel from within London, on any one day.[8] 8

Practical benefits of the East London Line extensions for the 2012 Olympic Games

  The East London Line Group had proposed in 2003 that direct ELL services (planned to terminate at Dalston Junction) could be extended to the Olympic Park site, via a disused railway curve at Dalston onto the North London Line towards Stratford. The planning timescale would have permitted acquisition of powers and its construction. It would have offered particular access benefits for South London, where few areas have direct access to the Olympic Park. There would be a legacy benefit with central Hackney and the Lower Lea Valley linked more closely with other parts of London. However, TfL decided not to take forward the ELLG proposal.

  An initial phase of East London Line extensions to Dalston is nevertheless seen by TfL as contributing importantly to the Olympic Games because:

    —  it is a project which can be guaranteed to be up and running in 2010, well before 2012;

    —  it provides cross-river capacity in inner East and South East London, and via transport interchanges improves the accessibility of numerous Games' locations on both sides of the river; and

    —  it creates a north-south public transport bypass for Central London, with capacity relief for congestion pinch-points such as London Bridge, and a level of resilience if access to parts of Central London was curtailed for any reason.

  The East London Line Group also notes that the ELL extensions create a north-south public transport bypass for the Lower Lea Valley Corridor which includes the Olympic Park and other sites. This again provides capacity relief for congestion pinch-points and a level of resilience if access was restricted for any reason.

  So the East London Line project's relevance to the Olympic Games is now directly linked to:

    —  its cross-river capacity;

    —  its extent within London particularly the benefits of its interchanges.

  Each point is now taken in turn.

Cross-river capacity on the East London Line

  Benefits of the cross-river ELL capacity are dependent on changes between 2005 and 2012:

    —  the actual hourly train capacity offered;

    —  the growth in London public transport demand, including the extended East London Line.

  The 2005 ELL train service has a maximum 2-way capacity of 14,240 passengers per hour with fully loaded trains.[9] 9, [10]10 There is an hourly maximum of 10 London Underground four-car trains in each direction. The basic off-peak service is nine trains per hour. Eight inner London stations are served all week, and a ninth (Shoreditch) at specific times.

  In 2010, maximum two-way capacity will be 18,000 passengers per hour with fully loaded trains.[11] 11 [12]12 The initial phase of ELL extensions expands the railway by over two miles northwards, and over 8 miles southwards, and 20 stations will be served. However TfL only plans to increase the peak train service through the Thames Tunnel by two trains per hour (tph) in each direction, from 10 to 12. The off-peak service will also be 12 tph.

  The East London Line Group recognises that passenger flows to and from the various Olympic Games' sites will be spread over a number of hours, so that the cumulative capacity of the East London Line should be significant providing there is marginal capacity available.

  Contrasting the Phase 1 growth in the total number of stations served (122%) with the relatively limited expansion in hourly line capacity (26%), gives rise to the question of whether TfL's proposals will offer sufficient additional capacity on the ELL to provide real relief during the Olympic Games.

  Most of the stations to be served exist already, though not those in Hackney. So the key external driver will be the change in demography by 2012 in the corridor served by the extended East London Line. Individual boroughs in inner East and South East London are projecting major increases in population and economic activity between 2005 and 2012 [see Annex B], linked to London's overall regeneration and economic growth.

  Overall, the demographic indicators suggest that London's growth alone can swallow up most or all of the extra ELL capacity. Also there will be a strong stimulus to increased usage of the line, because of the extra connectivity created by the extended railway including the cross-river link between North and South London. The East London Line Group therefore considers that the actual capacity available during the Olympic Games, under TfL's current plan, will be much less than is desirable—and less than is possible.

Increasing East London Line capacity

  Because of the constraints at the Phase 1 termini, further extensions in some form are essential to increase the line's practical capacity. TfL advises that the second phase of ELL extensions currently planned, north west to Highbury & Islington and south west to Peckham and Clapham Junction, will enable train frequency to increase to 16 tph in each direction. Transport for London and Network Rail are now analysing options for the orbital cross-London routes, and this work should be complete by 2006, which would allow decisions to be taken on Phase 2 with an adequate timescale before the Olympic Games.

  Subject to the outcome of these cross-London route studies, the East London Line Group supports the early financial authorisation of the Phase 2 extensions, to achieve greater cross-river capacity ahead of the 2012 Olympic Games. Realistically the next opportunity for additional funding approval will be as part of the 2007 Comprehensive Spending Review. Authorisation will also help the early regeneration and economic renewal of the additional catchments served. We ask the Transport Select Committee to recommend this course of action.

  The Group considers that 16 tph is still low compared to the future signalled capacity of the line which will be 24 tph. This is a waste of cross-river rail capacity in London, and, after allowing a margin for robust timetabling, a higher frequency may be possible, up to 20 tph. The table below shows the capacity achieved with different levels of train frequency.

FUTURE HOURLY 2-WAY CAPACITY, BASED ON ELL PROJECT SPECIFICATION:


Year

Trains per hour
Passengers per hour
(2-way)
% capacity change
(2005 = 100%)


2005
10 tph 14,240  (TfL existing)
201012 tph18,000 +26%
2012 if ELL Phase 112 tph 18,000  (TfL planned)+26%
2012 if ELL Phase 216 tph 24,000  (ELLG proposal)+69%
Maximum use of ELL20 tph 30,000  (potential)+111%


EAST LONDON LINE'S EXTENT WITHIN LONDON, INCLUDING INTERCHANGES

  The main Olympic Games' sites near to the East London Line, and interchanges offered in the first phase of ELL extensions, are:


Olympic Games sites
Maximum spectators/sessionELL interchanges


Olympic Park
150,600 (cumulative, all sites) Whitechapel (District/Hammersmith)
Canada Water (Jubilee)
Dalston Junction (by bus)
UEL Docklands13,200 Shadwell (DLR)
ExCeL41,700Shadwell (DLR)
The Dome31,800Canada Water (Jubilee)
Greenwich Arena10,400 Canada Water (Jubilee)
Greenwich Park34,800 New Cross, New Cross Gate, Surrey Quays
(all by bus)



  The quality of a number of these interchanges is imperfect. Canada Water is a modern purpose-built interchange constructed as part of the Jubilee Line extension. Dalston Junction is intended by TfL to have a new bus station interchange. However:

    —  Whitechapel is cramped and dependent on either the London Underground PPP and/or the Crossrail project for a major rebuild.

    —  The interchange between ELL and DLR at Shadwell requires a walk through the street.

    —  Bus interchange arrangements at New Cross, New Cross Gate and Surrey Quays are the traditional style of "head-into-the-street-and-search-for-your-bus-stop".

  The East London Line Group believes that these interchanges should receive specific TfL funding for their upgrade ahead of the Olympic Games, and that the Whitechapel PPP upgrade should be prioritised. This would provide a legacy benefit for generations of Londoners.

  With Phase 2 of the ELL extensions, additional rail interchanges served are:


Interchange
Benefit of interchange for Olympics travel


Highbury & Islington
Access from North London rail via ELL to Olympics sites south of river
CanonburyDirect transfer from main ELL onto North London Line for rail access to Olympic Park entrances at Hackney Wick and Stratford
Peckham RyeConnection from South London rail services onto ELL for Olympic sites in Docklands and Olympic Park, also relief of London Bridge station
Clapham High StreetConnection from Northern Line, relief of London Bridge station
Clapham JunctionConnection from wide catchment of South West London, relief of routes via Central London



  For access to the Olympic Park and other sites, the authorisation of Phase 2 of the ELL extensions would have a particular benefit for South London, which under current proposals has few direct railway links to the Olympic Games

  Overall:

    —  the combination of a higher ELL service frequency, to the Phase 2 service level of 16 trains per hour in each direction;

    —  funding and prioritisation of upgrades for a number of Phase 1 extension interchanges; and

    —  funding of the full ELL Phase 2 extension, with completion before 2012;

  will provide a substantial and important margin of capacity relief for the Olympics, and achieve long-lasting legacy benefits which will be important to the catchments.

12 September 2005

Annex A

BENEFITS OF THE EAST LONDON LINE PROJECT FROM THE EAST LONDON LINE PROJECT WEBSITE, AUGUST 2005

  The project benefits can be summarised as follows:

    —  A catalyst for £10 billionn worth of regeneration.

    —  Patronage will increase by 300% by 2021.

    —  Train frequency to increase by 60% through the central section (this includes the planned Phase 2 services)

    —  Phase 1 will be delivered by June 2010, in good time to support the Olympic bid.

  Transport for London provided an assessment of "The Wider Economic and Social Benefits to London", a report that formed part of the Business Case for the extended East London Line submitted to Government by the Strategic Rail Authority in September 2002. The report looks at how the East London Line Project will support London's growth at the strategic level and how increased accessibility will help facilitate the regeneration of local communities and the greater social inclusion of those in need.

From the Invitation to Prequalify for the East London Line main works contract, June 2005

  2.3.1  The East London Line Project aims to further the Mayor of London's Transport Strategy (www.london.gov.uk/mayor/strategies/transport) by providing better public transport for the growing number of people who live and work in London. Specifically it will:

    —  reduce congestion on the existing rail network, especially on journeys to London Bridge and the Northern Line (via Bank), and to Waterloo, Victoria and the Thameslink stations;

    —  reduce journey times from outer London to Docklands, the City and other parts of inner London;

    —  promote orbital rail services between north, east and south London, reducing the need to interchange and thus relieving congestion at the terminal stations in central London;

    —  improve accessibility by public transport to key areas that are poorly served, including parts of Docklands, Hackney, Lambeth, Lewisham and Southwark;

    —  integrate the London Underground and the network in inner London and link them with other modes of transport including buses and light rail; and

    —  meet the growing demand for railway services, making full use of a valuable river crossing in east London.

  2.3.2  By giving more people the choice to use the railway for their journeys rather than rely on buses or cars, the East London Line Project will relieve congestion on the roads in and around central London, especially the South Circular Road, the roads through Lewisham and the Rotherhithe Tunnel, and the New North Road and Kingsland Road to Aldgate.

  2.3.3  The East London Line Project also has wider socio-economic and environmental objectives, and is intended to:

    —  promote local economic regeneration in areas of significant deprivation, providing enhanced employment opportunities and greater social inclusion; and

    —  improve the environment in the area by improving air quality and reducing emissions of carbon dioxide.

Annex B

PROJECTED CHANGES IN POPULATION AND ECONOMIC ACTIVITY IN THE ELL CATCHMENT

OVERALL GROWTH

  The East London Line and its extensions serve the areas of highest growth projected in the London Plan:

    —  "Of the 600,000 plus new jobs projected for London by 2016, the external forecasts for the London Plan indicate 460,000 being in financial and business services… The figures used in the London Plan…are moderately conservative… the city and its fringes, and Docklands, will continue to be the main growth areas for employment in financial and business services" [GLA, Planning for London's Growth, pp12-13]

    —  The London East sub-region (including the City of London) is forecast in the London Plan to grow from a population of 1,991,000 in 2001 to 2,262,000 in 2016, and with employment growing from 1,087,000 to 1,336,000.

    —  Beyond the City and the Isle of Dogs, the subregion of East London could accommodate a further 56,000 jobs. This reflects the Mayor's priority to see development in the east. Much of that growth, up to 30,000 jobs, could be in Stratford which could develop as a new European business quarter on the Channel Tunnel Rail Link (CTRL). [ London Plan, para 5.10]

HOUSING CAPACITY IN ELL BOROUGHS

  The total capacity estimate for London for the period 2007-08 to 2016-17 is 315,327 new dwellings. The period 2007-08 to 2011-12 is forecast to see nearly 60% of new dwellings built in this period. The east sub region comprises the largest contribution to overall capacity with 46% (145,899 homes). In addition, 73,000 more dwellings are forecast to be built in London in the period 2004-05 to 2006-07. A breakdown for ELL boroughs is shown below, from the London Housing Capacity Study, July 2005. The East London Line Group has added a column below which shows an estimate of population growth in ELL Boroughs, based on 2Ö persons per dwelling:


ELL Phase 1 Boroughs
Total housing capacity
2007-08 to 2016-17
Proposed annual
capacity target
ELLG estimate of
population growth
2005-06 to 2011-12


Hackney
9,952 99517,413
Corporation of London1,720 1702,795
Tower Hamlets31,160 3,11554,513
Southwark16,2791,625 28,438
Lewisham10,8301,080 18,900
Bromley5,235520 9,100
Croydon11,2221,120 19,600
(150,938)
ELL Phase 2 Boroughs
Islington11,2461,125 19,688
Lambeth11,3831,135 19,863
Wandsworth7,676765 13,388
(7 years,
21/2 people/
dwelling)



  The additional two-way hourly capacity of TfL's ELL phase 1 in 2012 is 3,760 passengers. Based on the estimates above, it is plausible to expect strong localised growth originating from the ELL boroughs, that could take up most or all of this capacity by 2012. This is in addition to the ELL's attractiveness for improved north-south communications, which would also be relevant in general to London's expanded population and economic base.

LOCALISED GROWTH

  The catchments closest to the ELL stations will have strong impact on local demand. The following main locations for development are identified in the London Plan in proximity to the ELL route:




Adjacent to the ELL route



Dalston
"major centre"—increase shopping, housing, economic activity


Bishopsgate/South Shoreditch
35 hectares16,000 jobs800 homes
Whitechapel/Aldgate31 hectares 14,000 jobs700 homes
Deptford Creek/Greenwich Riverside72 hectares 5,500 jobs1,000 homes
Croydon town centre is already recognised as London's largest "Metropolitan" centre and one of the capital's two strategic office centres outside central London. It is also recognised as an Opportunity Area:
Croydon town centre78 hectares 5,500 jobs2,000 homes
Peckham, Brixton and Clapham Junction are defined as `major centres' on the ELL phase 2 extension




Near to the ELL route



Isle of Dogs
100 hectares100,000 jobs 3,500 homes
Stratford124 hectares 30,000 jobs4,500 homes
Lower Lea Valley250 hectares 8,500 jobs6,000 homes
Greenwich Peninsula104 hectares 15,000 jobs7,500 homes


CURRENT USE OF INNER LONDON RAIL

  The proportion of journeys made on inner London's Underground, metro, light rail and tram is highlighted by the recent Learning & Skills Council analysis of future population and needs in the London Borough of Tower Hamlets.[13] This highlights the high reliance on rail-based services for travel, with 37.3% of all travel to work in Tower Hamlets being on this mode. Southern Hackney does not yet have its metro, and the East London Line extension will provide that, with stations at Shoreditch High Street, Hoxton, Haggerston and Dalston. Strong demand is expected from these stations, and others in inner East and South East London, in line with Tower Hamlets' experience. Further policy developments in London which favour use of public transport, between 2005 and 2012, would increase demand for rail capacity.






8   London Olympic Games bid documents, Volume 3 Theme 14 Transport. Back

9   LUL "A" stock 4-car units have a capacity of 712 passengers (from technical data on TfL website, 3 August 2005). Back

10   Depending on the number of passengers alighting at intermediate stops and interchanges, more passengers than this would actually be accommodated in an hour. Back

11   East London Line Project, Rolling Stock Prequalification Briefing Document, June 2005. The specification for the new National Rail trains has been set by TfL as a minimum of 750 passengers in each 4-car unit. Back

12   Until a number of platforms are reconstructed, overall train lengths are limited on the ELL tunnel section to about 83 metres, equivalent to 4-car trains. Back

13   see link to: www.lsc.gov.uk/NR/rdonlyres and LSC DraftTowerHamletsStARBoroughProfilev01. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 16 March 2006