Select Committee on Transport Written Evidence


APPENDIX 49

London Development Agency Briefing Note on the agreement dated 15 November 2005

  This memorandum is intended as a briefing note for the House of Commons Transport Select Committee on the principal provisions of the Agreement relating to both the delivery of and access to the proposed transport and related infrastructure at Stratford City required for the Olympics.

1.  EXECUTIVE SUMMARY

Summary

The Agreement:

  (a) provides for the transfer of land required for the 2012 Olympics (the "Stratford Lands") to EP;

  (b) preserves the interests of the Stratford City developer (ie LCR and SCDL and referred to together as "SCDP") in their proposed redevelopment of a key development area within the proposed Stratford City development (referred to as "Zone 1"); and

  (c) secures the necessary infrastructure and access rights over Zone 1 required to accommodate the 2012 Olympics.

In summary, the Agreement:

  1.1.1  contains an unconditional commitment that the freehold of the Stratford Lands will be transferred to EP for £1 as soon as practicable and by no later than 16 January 2006;

  1.1.2  enables the LDA to make the Olympics CPO in a manner of co-operation with SCDP;

  1.1.3  provides certainty of delivery for the necessary Olympics infrastructure within, and access rights over Zone 1; and

  1.1.4  requires any scheme implementation proposals put forward by SCDP (pursuant to its existing contractual arrangements with SOST) when SCDP is seeking to drawdown land (and particularly Zone 1) to safeguard the appropriate rights required for the delivery of the Olympics.

2.  KEY COMPONENTS OF THE AGREEMENT

2.1  Robust Olympic CPO

SCDP agrees:

  2.1.1  not to seek judicial review of the LDA's Olympics CPO made on 16 November 2005. SCDP had sought to argue that its land interests and those of SOST (as Crown land) were incapable of being the subject of a CPO; and

  2.1.2  to continue to progress its development proposals for Stratford City.

  Zone 1 is now included within the Olympics CPO but not: the freehold interest in it (as this will be owned by EP); the interests of LCR and SCDL in Zone 1; or any interest in Zone 1 subsequently created by either of them.

  Under existing development arrangements, SOST declares (at the request of LCR) land to be surplus where it is not required for the Channel Tunnel Rail Link ("CTRL"), the proposed extension of the Docklands Light Railway and the operational rail network but only in cases where LCR has an "implementable scheme" for the development or sale of such relevant land which scheme proposals must now safeguard appropriate rights for the land intended for the 2012 Olympic Games.

2.2  Guaranteed delivery of Olympic Infrastructure at Stratford City

  2.2.1  Delivery of Olympic Infrastructure

  Land will be made available under the Agreement on the basis that the delivery of the critical and identified infrastructure and access rights for the Olympics within Zone 1 is secured.

  2.2.2  All owners of Zone 1 to be bound by safeguards to deliver Olympic Infrastructure

  Any owner of Zone 1 or any part of it shall be burdened by the following matters upon acquisition:

  2.2.2.1  if development is implemented on Zone 1 the owner shall also be obliged to design and construct the following "Zone 1 Infrastructure" for the Olympics:

  (a)  the town centre link being the pedestrian bridge link between Zone 1 and Meridian Square;

  (b)  enhancement works to Stratford regional station to address the impact of the Olympics; and

  (c)  any other infrastructure within Zone 1 required for the Olympics and which is referred to in the strategy to be agreed between all relevant parties pursuant to the Stratford and Olympics planning consents and planning agreements;

  2.2.2.2  Step-In Rights in favour of EP and/or the Olympic Delivery Authority ("ODA") to enter upon Zone 1 as necessary (ie in default of SCDP/or the relevant owner of Zone 1) to ensure the Zone 1 Infrastructure is carried out and completed; and

  2.2.2.3  access arrangements required for the use and enjoyment of the Zone 1 Infrastructure once it is constructed.

  2.2.3  Construction Standards for the construction of the Zone 1 Infrastructure

  The Zone 1 Infrastructure works must be:

  2.2.3.1 designed and constructed in a good and workmanlike manner and in accordance with planning law and with SCDL's plans and specifications;

  2.2.3.2 started no later than 30 June 2008 with a projected construction completion date of no later than 30 June 2011; and

  2.2.3.3 designed and constructed by consultants and contractors whose terms of engagement allow the exercise of step-in rights by EP or the ODA and require them to comply with the terms of their engagement in relation to the quality of the relevant service or construction work and the time by which it is to be delivered as referred to above.

  2.2.4  Step-In Rights for EP/ODA to carry out the Zone 1 Infrastructure

  The Step-In Rights are in favour of EP or the ODA and are the safeguard by which the Zone 1 Infrastructure works may be carried out if SCDP (or any other Zone 1 owner) has drawndown Zone 1 and fails to undertake the Zone 1 Infrastructure or, if once commenced, it fails to adequately carry out the Zone 1 Infrastructure works. The Step-In Rights:

  2.2.4.1  arise if EP or the ODA determine that SCDP will not achieve the required quality or timing for delivery of the Zone 1 Infrastructure; and

  2.2.4.2  constitute EP's or the ODA's rights to have a licence to enter and remain on such parts of Zone 1 as may be necessary to procure completion of the relevant Zone 1 Infrastructure.

  EP or the ODA secure further necessary rights to enable delivery of the Olympics by having rights to go on to the Zone 1 land as follows. If by 30 June 2008 any Zone 1 land has not been transferred to LCR and the CTRL works have been completed, EP or the ODA may occupy the relevant part of Zone 1 as licensee for the purposes of constructing the Zone 1 Infrastructure in place of the Stratford City developer. If by 30 June 2008 any Zone 1 land has not been transferred to LCR and the CTRL works have not been completed, then EP or the ODA may still occupy the relevant part of Zone 1 as licensee in order to construct the Zone 1 Infrastructure but in this case EP/ODA shall work together with LCR so that their contractors are granted such access as may be required for the carrying out and completion of their respective works.

2.3  The Olympics Facilitation Agreement ("OFA")—delivery of Olympics infrastructure outside of Zone 1

  The OFA is intended to achieve the overarching delivery of the Stratford City Olympics and is primarily concerned with that part of the Stratford Lands outside of Zone 1 (this is because the Agreement is intended to cover the delivery of the Zone 1 Infrastructure). It is specifically stated that the Olympic Village is to be constructed on the Stratford Lands outside of Zone 1.

  If by 31 March 2006 the Parties have not exchanged the OFA, the LDA may proceed to acquire any interest in the Stratford Lands outside of Zone 1 (other than the freehold in such part of the Stratford Lands as this shall be owned by EP).

3.  CONCLUSION

  The Agreement gives a reasonable mechanism enabling EP/LDA to ensure that either SCDP completes the Zone 1 Infrastructure works in a timely manner or provides the rights for EP/ODA to "step in" and complete the Zone 1 Infrastructure.

21 November 2005

  (1)  The Secretary of State for Transport ("SOST");

  (2)  London and Continental Railways Limited ("LCR");

  (3)  Stratford City Developments Limited ("SCDL");

  (4)  Duelguide Holdings Limited;

  (5)  Stanhope PLC;

  (6)  The Urban Regeneration Agency (English Partnerships) ("EP"); and

  (7)  London Development Agency ("LDA").

4.  OTHER NEGOTIATIONS IN RELATION TO THE OLYMPIC PARK

  Mr. Caborn [holding answer 28 October 2005]: There are 284 businesses (of which 96 are in or adjacent to Marshgate Lane) in the Olympic Park area that the London Development Agency is seeking to engage with individually to understand their relocation requirements and to discuss with them the LDA's offer to acquire their premises by agreement.

  164 of these have appointed advisers in order to start negotiations and the LDA has reached in-principle agreements with 31 businesses, of which 22 have signed Heads of Agreements.

  The majority of the businesses in the Olympic Park area will need to move by mid-2007. However around 53 of the businesses will not be required to relocate until later in the process, as vacant possession of their land is not required until 2009 . . .

  Mr. Caborn [holding answer 28 October 2005]: The businesses or parties with an interest in the land to be acquired under a confirmed Compulsory Purchase Order are compensated under the statutory Compensation Code.

  They receive the market value of their premises or other land interests. In addition they are entitled to the following: a disturbance payment in terms of either the business' relocation or extinguishment, a statutory loss payment can be made to commercial and residential owners/occupiers based on a percentage of market value of their property or interests. They are also paid the reasonable costs of their legal advisors and surveyors. Each party with a compensateable interest is entitled to appoint a chartered surveyor to negotiate the compensation on their behalf with the acquiring authority. Disputes as to the level of compensation payable are referred to the Lands Tribunal.

  If the CPO is confirmed the date of land valuation is either a date the parties agree as appropriate, or the date the acquiring authority takes possession of the land. This will not be before the date on which the Secretary of State for Trade and Industry issues his decision concerning confirmation of the CPO.

  The London Development Agency (LDA) today tackled head-on claims that the relocation process for businesses in the 2012 Olympic Park area is being unfairly conducted.

  The LDA's Executive Director of Regeneration and Development Tony Winterbottom said:

    "It is because the Olympic Games presents such an unrivalled opportunity for some of the most deprived parts of East London that we have been involved in Backing the Bid. The London 2012 Olympic Games will transform the Lower Lea Valley, from Tower Hamlets and Newham up through Hackney to Waltham Forest, and will give local communities the boost they deserve—a legacy of 9,000 new homes, double the jobs in the Olympic zone alone, business opportunities, fantastic new sports venues, new schools—and Europe's largest new urban park in 150 years.

    "More than 80% of the land in the Olympic Park area is already under public control. Now we have won the Games, the obligation is on the LDA to secure the remaining 19% of the land. We have made every effort to engage with all 284 businesses within the zone for the past two years, even though we did not yet know that we would get the Olympic Games and were going above and beyond our obligations in doing so. Since the bid decision we have engaged in dialogue with more and more businesses and have to date reached agreement with a total of 24 businesses.

    Of the remaining businesses, nearly 50% have appointed advisors with a view to commencing negotiations with the LDA. This percentage is increasing by the day.

    "The approach we have taken continues to meet the requirements of the Compensation Code. The LDA has given a clear commitment that no business will be financially worse off as a result of relocation and has already made clear to businesses on the site that we will continue to offer voluntary agreements alongside the CPO process.

    "There are a handful of businesses who have been demanding unjustified amounts of money—multiple times the market value—and seeking to use the leverage of the media to get what they do not believe they could attain by independent arbitration. We have to be fair both to the businesses but we must also protect the tax-payer from speculative exploitation."

  Recent false claims made to the media include:

    —  LDA has insufficient funds to pay for relocating businesses in the Olympic Park area. This is untrue. The LDA does have sufficient funds to do this.

    —  There is an inherent "affordability gap" between existing sites and alternative sites. This is untrue. There is suitable land of comparable value nearby.

    —  That the LDA has offered relocation sites "50 miles away from current sites". This is simply untrue. As London's Development agency, LDA landholdings are within London, where, as a major landowner, has more than enough land to relocate every business if necessary and has offered to do so. The relocation process is "putting at risk 11,000 jobs. In fact the relocation process will more than double the number of jobs in the Olympic Park area alone, from around 5,000 to more than 11,000.

    —  Newham "never wanted the Olympics in the first place". In fact, not only has Newham Council been one of the most enthusiastic backers of the 2012 Bid, and a MORI poll showed that 78% of East End businesses backed the Bid.

    —  That "only one deal has been done': in fact 24 agreements have been reached and many more negotiations are at an advanced stage.

    —  That eviction is "imminent". This is untrue. Two years (Starting in July 2005) has been built into the construction timetable before starting the construction of the Olympic Park to ensure businesses have sufficient time to move to appropriate sites. This should ensure both successful relocation and that the Park can be delivered on time. Businesses that can demonstrate that they will need more than two years to relocate are being handled as special cases.

  The LDA has made clear to all the businesses that it will pay market value for land interests in line with the Compensation Code and these values will be in line with the RICS Appraisal and Valuation Framework. The disturbance payable to businesses will facilitate their relocation to alternative premises. Businesses are free to go to independent arbitration or the Lands Tribunal to settle the matter, if they are unhappy with the values offered.

  The LDA will abide by the decision reached.

  In seeking to help the individual businesses concerned, the LDA has been going above and beyond the requirements of the Compensation Code in offering to negotiate voluntary provisional relocation deals in advance of July 6th and in offering to pay for the necessary legal and surveying fees incurred by businesses wishing to take up the offer. The LDA is continuing to go over and above the requirements of the Compensation Code in offering not only to pay the necessary fees of lawyers and surveyors for the businesses but also in offering to secure alternative sites for the businesses. The LDA process has been independently investigated and commended by the RICS (Royal Institution of Chartered Surveyors).

8 September 2005

PLANNING APPLICATION BOUNDARIES



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 16 March 2006