Select Committee on Transport Minutes of Evidence


Supplementary memorandum submitted by Transport 2000

  At the Select Committee session on 23 November 2005 where we gave oral evidence, a number of points arose and questions asked on which we considered it useful to do some further work. What follows are some supplementary evidence and figures that amplify points made in our original evidence and at the Committee hearing.

1.  INDEX OF PASSENGER KM AND EARNINGS PER PASSENGER KM 1989-2004


Source calculations from British Railways Board Accounts/SRA, DfT and ONS websites.

  Further calculations from the data reveal that the average elasticity from 1989 to 1996 was around -1 and that from 1999 onwards was -0.7. (Compared with -0.5 for the selection of operators cited in our original submission). This implies that there will a greater proportion of journey flows where the elasticity is -1 or better. This means opportunities for operators to lower the average earnings per passenger km and increase both passenger numbers and their total revenue which also would result in modal shift from in certain areas of the country very congested local road networks. There are a number of factors which could have led to the changes in fares elasticity before and after 1997 these are for example;

    (a)  Introduction of fares regulation as the consequence of the 1993 Railways act;

    (b)  The economic upturn;

    (c)  The consequence of abandoning the "fuel duty escalator";

    (d)  The improvement in punctuality cited in our previous additional submission to the Select Committee.

      This additional research strengthens our original case that there is a range of benefits (lower subsidies, reduced congestion and pollution etc) from reducing overall earnings per passenger kilometre. We would suggest to the Committee that they ask operators to what extent they have examined fare elasticity with the flows for which they have pricing control and how they are utilising such information.

    2.  ELASTICITIES MADE EASY

      This section is a worked example of elasticities in practice; we referred to this in our oral evidence.

    PriceElasticity = %changeindemand/%changeinprice

    This gives point elasticity which changes with where you are on demand curve I tend to use average elasticity which after some cute algebra reduces to:

    EA = (Q2 ¸ 1)/(Q2+ Q1)  (P2 ¸ P1)

      where

      Q1 = initial demand

      Q2 = finaldemand

      P1 = initialprice

      P2 = finalprice

      So based on Railway that is selling 100 £1 tickets a day:
    initial price final priceinitial passengers final passengersaverage elasticity change in fare boxchange in pass numbers
    £1.00£0.75 100150¸1.40 13%50%
    £1.00£0.50100 220¸1.1310% 120%
    £1.00£0.50100 200¸1.000% 100%
    £1.00£0.75100 120¸0.64¸10% 20%
    £1.00£1.25100 87¸0.639% ¸13%
    £1.00£0.80100 111¸0.47¸11% 11%
    £1.00£1.20100 92¸0.4610% ¸8%
    £1.00£1.50100 95¸0.1343% ¸5%
    £1.00£0.50100 1000.00¸50% 0%
    £1.00£0.75100 1000.00¸25% 0%
    £1.00£1.25100 1000.0025% 0%
    £1.00£1.50100 1000.0050% 0%
    £1.00£1.50100 1050.1258% 5%
    £1.00£1.25100 1100.4338% 10%
    £1.00£0.75100 800.78¸40% ¸20%
    £1.00£0.50100 501.00¸75% ¸50%
    £1.00£1.50100 1501.00125% 50%
    £1.00£1.25100 1501.8088% 50%


    Worked example

      So given that Northern Trains only receives 20% of its income in fares then it's going on the basis of an elasticity of ¸0.64 that a fare reduction of 25% is going to cost the government an increase of 2.5% in subsidy to achieve a 20% increase in passenger numbers (ie value for money increase of 17%). So if the fares went up by 25% then government subsidy would reduce by 2.25% and value for money reduce by 11%!!!! If the elasticity is around -0.5 then a 20% reduction in fares would increase the subsidy by just under 5% but there would 6% increase in value for money—in contrast a 20% increase in fares would reduce the subsidy by 5% but reduce value for money by 3%.

    The chances are that given the huge number of short journeys on Northern Trains are short then the elasticities are probably nearer or around -1 so it would not cost as much.

    3.  THE IMPACT OF PUNCTUALITY ON THE DEMAND FOR RAIL TRAVEL

    Introduction

    This section has been prepared in response to a question on the impact of punctuality and factors other than fares on the demand for rail travel raised by Mr Clive Efford. It is accepted that a wide range of factors influence rail travel not just fares and reliability factors but also frequencies and timings station cleanness and security amongst many others. For instance, the Institute of Transport Studies at Leeds University has calculated that there is a strong correlation between economic growth and rail travel so that for each 3% growth in GDP corresponds to a 2% growth in rail travel. This paper does not seek to produce a "all singing all dancing" model to predict rail travel, but instead focuses on the impact of punctuality on the demand for rail travel and how it impacts on passengers numbers and journey patterns. Comparable data was readily available for the same sort of analysis that was undertaken in the original paper submitted for evidence. However in order to produce a quicker response the analysis below focuses on each sector (i.e. Long distance, London and the South East and Regional) rather than a selection of individual train operators.

    Figure 1

    Trends in train punctuality 2000—05


  Source calculations from SRA

Figure 1 shows that punctuality has generally improved since 2001 and that it has strong seasonal trends with a low point in quarter 3 (September—December), though the difference between the peaks and troughs is gradually diminishing. Further analysis suggests that the moving average is improving by ½ % per quarter and that if this continues it will be 2010 before a punctuality reaches 90%.

Methodology

Relevant data and statistics was taken from the SRA website for the railway years ending 2001-05, with the year ending 2001 taken as the base year for each set of data. The Microsoft Excel package was used in each case to display the information graphically and calculate correlations and the line of best fit so that the impact of changes in punctuality performance could be calculated The graphs for each set of analysis are shown in Annex 1. R2 (coefficient of determination) is shown for each variable. The value of the gradient for each graph represents 1% increase (negative = decrease) for that variable for a 1% change in punctuality in the base year. For example if in the base year the punctuality was 80% then the gradient is the change for that variable for a 0.8% change in punctuality. Results shown in italics are those derived where the coefficient of determination is so small that it is considered there is no relationship between that variable and punctuality.

LONG DISTANCE OPERATORS

Table 1
Long Distance
Punctuality % passenger km (billionsRevenue (£ billions) passenger journeys (billions)average journey length (km) Earnings per journey
2000-01
69.1 12.11.1090.07 173£15.84
Long DistancePunctuality % passenger kmRevenue passenger journeys average journey length Earnings per journey
2000-01100100 100100100 100
2001-02100107 109106101 96
2002-03102107 11111097 93
2003-04106110 11711695 92
2004-05114111 12012092 95
R20.60 0.740.810.55 0.09
Gradient0.56 1.131.23¸0.83 ¸0.17


Table 1a
passenger km (millions) Revenue (£ millions)passenger journeys (millions) average journey length (km)Earnings per journey
Effect of 1% change in punctuality 98.4518.061.25 ¸2.07¸0.04
as percentage of sector total 2003-040.01% 0.01%0.01%


  Table 1a shows the results of calculations though the changes are small compared with the sector totals the change in revenue is equal to 15% of the total profits of the long distance sector which in 2003-04 was just over £120 million. However in the year 2003-04 an exceptional payment was made by the SRA Virgin Cross Country of £58 million , if this taken into account the total sector profit for the year falls to £62 million and the effect of a 1% change in punctuality is equivalent to 29% of the total sector profits.


LONDON AND THE SOUTH EAST OPERATORS

Table 2
London and South EastPunctuality % passenger km (billionsRevenue (£ billions) passenger journeys (billions)average journey length (km) Earnings per journey
2000-01 actual77.6 19.21.7320.664 29£2.61
London and South EastPunctuality % passenger kmRevenue passenger journeys average journey length Earnings per journey
2000-01100100 100100100 100
2001-02100101 103100101 103
2002-03102103 102102101 100
2003-04104105 104104100 100
2004-05109110 10811398 96
R20.98 0.89.99420.75 0.79
Gradient1.05 0.711.38¸0.30 ¸0.61


Table 2a
passenger km (millions) Revenue (£ millions)passenger journeys (millions) average journey length (km)Earnings per journey
Effect of 1% change in punctuality 259.5215.8511.80 ¸0.11¸0.02
as percentage of sector total 2003-040.01% 0.01%0.01%


  Table 2a shows the results of calculations though the changes are small compared with the sector totals the change in revenue is equal to 16% of the total profits of the long distance sector which in 2003-04 was just under £97 million.


REGIONAL OPERATORS

Table 3
RegionalPunctuality % passenger km (billionsRevenue (£ billions) passenger journeys (billions)average journey length (km) Earnings per journey
2001-01 actual81.7 6.90.5720.223 31£2.57
Punctuality % passenger kmRevenue passenger journeys average journey length Earnings per journey
2000-01100100 100100100 100
2001-0297101 90100102 91
2002-0399100 9098102 91
2003-04101109 96108101 89
2004-05101114 10011599 87
R20.50 0.600.560.57 0.03
Gradient2.38 2.042.82¸0.44 ¸0.44


Table 3a
passenger km (millions) Revenue (£ millions)passenger journeys (millions) average journey length (km)Earnings per journey
Effect of 1% change in punctuality 201.1814.317.70 ¸0.17¸0.01
as percentage of sector total 2003-040.004% 0.004%0.003%


  Table 3a shows the results of calculations though the changes are small compared with the sector totals the change in revenue is equal to 49% of the total profits of the long distance sector which in 2003-04 was just over £29 million. However in the year 2003-04 Gatwick Express as a result in the downturn in air travel made a loss of £3.2 million, if Gatwick Express accounts are removed from the sector accounts the sector profit rises to £32.2 million and a 1% change in punctuality is equivalent to 44.4% of total sector profits.

CONCLUSION

It is clear that for all sectors that punctuality performance affects passenger numbers, though in each of the sectors the proportion of journeys are relatively small. However the potential for changes in revenue do represent significant proportions of overall profits in each sector particularly for regional operators. The consequence of this is that small decreases in punctuality performance can affect profit margins and thus have the potential to lead to pressures for fare increases and or further restrictions on "walk on" fares such as "Savers" or additional subsidy payments from the government, or a combination of all three of these. Conversely small improvements in punctuality can increase profits substantially, which implies that if current trends continue there will be less pressure to increase fares and that as suggested in our previous evidence to the Committee operators could look to either reducing actual fares paid per mile, or lifting restrictions on "walk on" fares or the DfT could seek to encourage modal shift from the car and plane by using this "punctuality windfall" to improve capacity.

Part of the analysis examined the effect of punctuality on average journey length. The results show that in each of the sectors journey lengths would decrease as a result of improved punctuality. However parts of the various Route Utilisation Strategies started by the SRA which in part are attempts to improve punctuality seek to limit the availability of short journey opportunities. In other words one possible outcome of some RUS will be contradictory, our previous evidence to the Committee highlighted the high proportion of journeys that are very short (ie 46% of rail journeys are less than 20 miles). Has the Committee asked Network Rail if they have taken this in consideration in the implementation of any or all of the proposed RUS?

This evidence together with the evidence submitted previously suggests that there is a relationship passenger travel and fare level as well as punctuality. Has the Committee chair rightly pointed out on the 23 November factors that influence the numbers travel by train are numerous it is hoped that the evidence submitted by TRANSPORT 2000 will unravel some of the complexity.



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 19 May 2006