Select Committee on Transport Minutes of Evidence


3. Supplementary memorandum submitted by the Highways Agency in relation to Question 20

20.   Regarding cost overruns on major road schemes, Mr Robertson told us in the evidence session that much of the increases could be explained by inflation and the failure to include some VAT. For each scheme that was listed in the Department for Transport's answer to Tom Brake MP on 19 December 2005, could you please provide figures showing what proportion of the overspend is due to these causes and what reasons exist for any remaining amounts?

  1.  The attached list of schemes expands on the answer given on 19 December 2005 to Tom Brake MP, which provided data for all current road schemes in the Targeted Programme of Improvements (TPI) on the expected costs when schemes received Ministerial approval for entry to the TPI (TPI entry) and the latest agreed budget cost.

  2.  Since April 2003 the TPI entry, cost has been reported on the basis of full projected outturn—making allowance for identified risks, inflation up to scheme completion, non-recoverable VAT and for "optimism bias" in line with revised Treasury guidance[1] issued in April 2003. Before then, only net scheme costs, exclusive of VAT, projected inflation and "optimism bias" were reported at TPI entry. The answer to Tom Brake MP explained that the greater part of the increase in estimated cost was due to that change in methodology.

  3.  The latest Ministerially agreed budget costs in Tables 1 and 2 represent the latest approved estimated costs of the schemes. However, the TPI is subject to significant external cost pressures, including rising energy prices, which have driven cost inflation above the retail price index in the road construction industry. We have measures in hand to drive down costs and improve estimating and budgeting, including working closely with the supply chain, details of which we have already provided to the Committee in our response to Question 21. We are also developing and revising scheme estimates to take a more realistic view of the likely final cost of projects to be fed into updated programme costs. The cost forecasts are being finalised as part of the Regional Funding Allocation exercise. We shall write again to the Committee when those revised estimates are finalised.

  4.  The Agency has carried out further analysis to show the original cost estimate at TPI entry, adjusted to represent the revised approach to estimating. The Agency has also reviewed a sample of seven schemes to identify in more detail the reasons for cost escalation. The National Audit Office (NAO) has worked with the Agency in compiling and validating the data in this Memorandum.

  5.  The answer to Tom Brake MP stated that for some schemes, the estimated costs on TPI entry were not directly comparable with the latest approved budget cost because of changes in the way that estimates have been prepared since 2003. Table 1 lists schemes which entered the TPI before April 2003 that have yet to be completed and provides TPI entry cost estimates and adjusted entry costs that are now directly comparable with the latest agreed budget cost (ie the cost that was most recently approved by Ministers). The remaining differences represent increases in forecast costs due to reasons other than the revised approach to estimating. Table 2 lists schemes that entered the TPI after April 2003, for which the TPI entry cost and latest agreed budget cost are on a comparable basis and for which no adjustment has therefore been necessary. In addition to the schemes listed in Tables 1 and 2, the Agency has completed 30 schemes under the TPI which are not included in the analysis.

  6.  Table 1 shows that, prior to the adjustments to the estimates, the TPI entry cost for schemes which entered the TPI before April 2003 and which have yet to be completed was £1,682 million. This compared with the latest agreed budget costs of £3,217 million, an increase of £1,535 million or 91% over the original estimates. Our analysis shows that the revised approach to estimating increased the TPI entry costs of these schemes, from £1,682 million to £2,695 million. Thus £1,013 million or 66% of the total cost increase of £1,535 million is explained by the revised approach to estimating costs. The remaining £522 million or 34% of the increase is explained by other factors.

  7.  Table 2 shows that the latest agreed budget costs for most schemes which entered the TPI after April 2003 have not changed compared to the estimated costs at entry.

  8.  We took a sample of seven schemes in order to examine in more detail the main reasons for the latest cost estimates being greater than the estimates on entry to the TPI, other than the differences explained by the revised approach to estimating. Our analysis shows that the most significant area of increases is related to those affecting the works (construction) costs (66% of the total cost increase), which is made up as follows:

    —  change in preliminaries costs, which cover site set up, staff costs, large plant, insurance and so on—22%;

    —  inadequate early estimate and increased scope—20%;

    —  additional risk/contingency allowance—15%;

    —  inflation due to slippage/higher inflation rate—4%; and

    —  third party, statutory and other requirements (landfill tax, archaeology etc)—5%

  9.  Preparation and supervision costs have also increased, accounting for some 7% of the total increase, due to:

    —  change of scope and investing more in design through the early contractor involvement form of contracts to reduce overall costs—5%; and

    —  omissions (including historic spend) and underestimates—2%.

  10.  There have also been increases in land and compensation costs (20%), made up as follows:

    —  revised estimates due to changes in land values and the addition of risk/contingency and statutory interest—16%; and

    —  increased landtake—4%.

  11.  Increases due to statutory undertakers' works accounted for 7%:

    —  better understanding of the work required/inadequate early estimate—4%; and

    —  increased scope—3%.

  12.  Improved processes introduced by the Agency, following the revised approach to estimating, means that we will have this level of detail available for all schemes as they go through the approval processes. We are currently developing a costs database for our project teams, together with guidance on improving scheme estimates. The level of detail available for the schemes that entered the TPI after 2003 is more comprehensive than for the earlier schemes. That reflects the increased focus on delivery processes, following the creation of the Agency's Major Projects Directorate in May 2003.

  13.  The National Audit Office has worked with the Agency in compiling and validating the data in this Memorandum. The NAO's work involved reviewing:

    —  the methodology for adjusting the initial cost estimates;

    —  the Agency's quality assurance of the adjustment calculations and validating the calculations for a sample of schemes, including those marked (1) in Table 1 where the Agency used a slightly different approach; and

    —  the reasons for cost escalation, using a small sample of eight schemes, selected to represent the range of schemes that form the TPI in terms of value, type of scheme, progress and geographical region. The NAO's sample included four of the seven schemes analysed by the Agency (paragraph 7).

  14.  Based on this work, the NAO has told the Agency it is satisfied with the methodology and its implementation, and that the data in Tables 1 and 2 and the analysis in this Memorandum present the position accurately and reliably. The NAO confirmed that the range of reasons for cost increases identified from the Agency's review of seven schemes reflected the range of reasons for cost increases in the NAO's sample of eight schemes, but notes that the reasons and their extent vary significantly, scheme by scheme.

  15.  The Agency are considering recommendations from the NAO that we should consider annually publishing updated cost estimates and outturns for all the roads schemes within the Targeted Programme of Improvements.

5 April 2006


Table 1

HIGHWAYS AGENCY TARGETTED PROGRAMME OF IMPROVEMENT - SCHEMES THAT ENTERTED TPI PRIOR TO APRIL 2003 AND HAVE NOT YET BEEN COMPLETED


Table 1 - CONTINUED

HIGHWAYS AGENCY TARGETTED PROGRAMME OF IMPROVEMENT - SCHEMES THAT ENTERTED TPI PRIOR TO APRIL 2003 AND HAVE NOT YET BEEN COMPLETED

Table 2

HIGHWAYS AGENCY TARGETED PROGRAMME OF IMPROVEMENT—SCHEMES THAT ENTERED THE PROGRAMME AFTER APRIL 2003 AND HAVE NOT YET BEEN COMPLETED


Scheme

TPI Entry cost
(£m)
Latest
Ministerially
agreed budget cost
(£m)


% Increase


TPI Entry Date


Start of
Works
A14 Ellington—Fen Ditton Improvement 4904900% April 2003SIP
A57/A628 Mottram—Tintwistle Bypass 9010314% April 2003SIP
A45/A46 Tollbar End Improvement57 570%April 2003 SIP
M1 Junction 6a to 10 Widening241 28920%July 2003 March 2006
M1 Junction 10 to 13 Widening382 3820%July 2003 SIP
Al Morpeth to Felton Dualling84 840%July 2003 SIP
Al Adderstone to Belford Dualling14 140%July 2003 SIP
A1/A19/A1068 Seaton Burn Junction30 29-3%July 2003 SIP
A19/A184 Testos Junction Improvement21 210%July 2003 SIP
A505 Dunstable Northern Bypass (A5 to M1) 48480%July 2003 SIP
A421 Bedford to M1 Junction 13171 1710%July 2003 SIP
A21 Tonbridge to Pembury65 650%July 2003 SIP
M40 Junction 15 (Longbridge)57 570%July 2003 SIP
A590 High and Low Newton Bypass22 220%October 2003 SIP
M20 Junction 10A4646 0%November 2003SIP
A30 Carland Cross to Chiverton Cross125 1250%November 2003 SIP
A30 Temple to Higher Carblake   Improvement 41410% November 2003SIP
A27 Southerham to Beddingham   Improvement 19190% March 2004SIP
M1 J21-301,9151,915 0%April 2004SIP
M25 J1b-3 Widening6666 0%April 2004SIP
M25 J5-7 Widening214214 0%April 2004SIP
M25 J16-23496496 0%April 2004SIP
M25 J23-27 Widening419 4190%April 2004 SIP
M25 J27-30 Widening402 4020%April 2004 SIP
A21 Kippings Cross to Lamberhurst Bypass 68680%May 2004 SIP
A23 Handcross to Warninglid Widening41 410%May 2004 SIP
A453 Widening (M1 J24 to A52   Nottingham) 90900% May 2004SIP
M25 Junction 28/A12 Brook Street   Interchange 880% March 2005SIP
M27 J11 to J12 Climbing Lanes27 270%March 2005 SIP
M27J3 to J4 Widening52 520%March 2005 SIP
M1 J30 to J31 Widening135 1350%March 2005 SIP
M1 J31 to J32 Widening20 200%March 2005 SIP
M1 J32 to J34S Widening139 1390%March 2005 SIP
M1 J34N to J37 Widening246 2460%March 2005 SIP
M1 J37 to J39 Widening224 2240%March 2005 SIP
M1 J39 to J42 Widening202 2020%March 2005 SIP
M1 J31 to J32 Northbound Collector/  Distributor 29290% March 2005SIP
M62 J25 to J27 Widening215 2150%March 2005 SIP
M62 J27 to J28 Widening83 830%March 2005 SIP

TOTALS
7,094 7,154March 2005


Notes:

Note 1:  The TPI entry cost adjusted to include optimism bias, VAT and inflation (Table 1, column C) is the TPI entry cost revised so that it is calculated on the same basis as the latest Ministerially approved budget cost (Table 1, column D) as follows:

    —  Making an allowance for non-recoverable VAT on the works cost. The other key elements of scheme costs (preparation and supervision, and land) are for the majority of cases fully VAT recoverable. For schemes marked (1) in Table 1 the cost breakdown between these elements was not available so non-recoverable VAT has been applied to the total cost inclusive of land and preparation and supervision thus marginally overstating the TPI entry cost.

    —  Making an allowance for "optimism bias" as required from April 2003 in the Treasury Green Book on investment appraisal. Optimism bias is the tendency of those appraising a new project, and those engaged in bidding for its operation, to over-estimate the benefits and to under-estimate the costs and the risks associated with delivery. To counter this tendency, scheme cost estimates are expected to include an allowance for optimism bias, set at between 3% and 65% depending on the quality of the risk assessment and the stage and complexity of the scheme. The level of optimism bias decreases as a scheme progresses and has therefore been applied according to the stage of each scheme at TPI entry and the complexity of the scheme (more complex schemes require a higher level of optimism bias).

    —  The TPI entry cost has been adjusted to Quarter 3, 2001 prices using the Road Construction Tender Price Index (based on price rates contained in accepted tenders for public sector road schemes). The latest Ministerially approved budgets are all at Quarter 3, 2001 prices. All estimates are therefore on a common price base.

    —  Inflation has been applied to the TPI entry cost at a rate of 2.5% per year for 2001-02 to 2007-2008 and 2.7% thereafter in line with Treasury guidance. In order to apply inflation the scheme costs were profiled in line with the expected timetable at TPI entry. 10% of the scheme cost was profiled over the preparation years and 90% across the construction years.

Note 2:  The figures included for the two DBFO schemes (Al (M) Ferrybridge to Hookmoor and A249 Iwade to Queenborough Improvement) represent the Financed Capital Cost of the schemes.

Note 3:  SIP denotes that the scheme is in preparation (prior to start of works).





1   http://greenbook.treasury/gov.uk/ Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 27 July 2006